SlideShare a Scribd company logo
Alex Larcheveque | ME 009 (Section 025) | May 24, 2015
Universal Cargo Carrier
PAGE 1
Introduction
In class we were assigned to design a new cargo carrier, used commonly for wheelchairs and other
mobility carts. The problem with today’s cargo carrier is that it can only be accessed from one side.
So if there is an obstruction from that one side, the person loading the wheelchair/mobility cart
will have a hard time loading the device. In order to avoid these inconveniences, we will try to
design a cargo carrier that can be accessed from all three sides.
Problem Definition
Create a cargo carrier that can be accessed from all three sides.
The newly designed cargo carrier should follow these design criteria:
 The platform should be 60 x 30 inches. The minimum ramp width shall be 24 inches.
 Max height with cargo: 30 inches
 Max height without cargo: 8 inches
 Ramp angle should not exceed 20° when platform is 18 inches off ground
 Deployed/stored by single person
PAGE 2
Conceptual Designs
Design 1: Foldable Design
PAGE 3
Design 2: Cargo Carrier with Lift
PAGE 4
Design 3: Detachable Ramp Assembly with One Temporary Ramp
PAGE 5
Design Concept Selection
From the decision matrix below, I decided to choose the Detachable Ramp Assembly with One
Temporary Ramp.
PAGE 6
Embodiment Design
As seen in the title page, this was the final design for the cargo carrier.
In the following pages, I will go through each individual part of the assembly and explain what its
function was. In addition, I will show you how I met and exceeded the requirements for this design
project.
PAGE 7
Part 1: Base Piece
The base piece is the main part for the design.
Unique Design Features:
 Hole cutouts that are inserts for the side gates.
 Shafts run across three out of the four sides. The purpose for these are so that they can
attach to the clamps, and will create a temporary ramp. I did not include a shaft for the last
side, because that side would be facing the car’s rear.
 The platform also includes an underbody, in which the temporary ramp can be stored
Requirements Met
 The platform is 60 inches by 30 inches
PAGE 8
Part 2: Side Gates
These parts ensures that the cargo inside will not fall out.
Unique Features:
 Designed with correct length so nothing will fall out
 Have tight tolerances (see engineering drawing for tolerances). This allows them to be
taken out/inserted only when force is used. Think of our design as Legos, but for a different
purpose.
Requirements Met:
 Max height with cargo: 30 inches
 Max height without cargo: 8 inches
My design actually exceeds these expectations. In total, our height will be 6.17 inches all the time
(not including the underbody).
Long Side
Short Side
PAGE 9
Part 3: Claw Attachment
This part creates a temporary attachment to the shafts on the base piece.
Unique Features:
 The cylinder is not fully closed. This allows for easy attachment/removal to the shaft.
 The circular hole on the rear side of the claw allows for a shaft connected to the ramp to
attach easily.
Requirements Met:
 None
PAGE 10
Part 5: Claw Shaft
This part connects the claw and the ramp together.
Unique Features:
 None. It’s a shaft….
Requirements Met:
 None.
PAGE 11
Part 6: Ramp (Part 1)
This ramp will connect to the claw and another ramp. These two half ramps will assemble into
one, and are designed to both store in the underbody.
Unique Features:
 Holes inserts are seen on both sides for shafts to fit.
Requirements Met:
 Width is 24 inches
 Ramp angle should not exceed 20° when platform is 18 inches off ground
My design exceeds the requirements of creating the maximum ramp angle of 20°. The total length
of the ramp is 61.20 inches, which creates a 17.10° angle when 18 inches off the ground.
PAGE 12
Part 7: Ramp (Part 2)
This ramp will touch the ground. On the other end, it will connect to ramp (part 1) through a shaft.
Unique Features:
 Hole inserts on one side of the ramp for shafts to fit.
Requirements:
 Same requirements as Ramp (Part 1)
Side will touch the floor
PAGE 13
Part 8: Ramp Shaft
This part connects ramp (part 1) to ramp (part 2).
Unique Features:
 Again, it’s a shaft….
Requirements Met:
 None.
PAGE 14
Summary/Conclusions/Recommendations
SUMMARY
All in all, I thought that my cargo carrier was successful. It fulfilled, even exceeded, all the
requirements specified and solved the problem: Build a cargo carrier that can be accessed from all
three sides.
There were five requirements I needed to fulfill for my design. They were 1. Dimensions of
platform (60” x 30”) and ramp width (24”) 2. Max height with cargo should not exceed 30” 3. Max
height without cargo should not exceed 8” 4. Ramp angle should not exceed 20 degrees when 18
inches off the ground 5. The ramp should be able to be deployed/stored by a single person.
For the first requirement, I followed exactly what the dimensions stated. I made my
platform 60” x 30” in the sketch, and the same went for the ramp width. The second and third
requirement are always fulfilled, because my maximum height of the cargo carrier is fixed at 6.17”.
My height calculation for the cargo carrier height does not include the underbody storage. This is
because the connection of the cargo carrier and the tailgate of a car would not start at the
underbody, the connection would be placed above the underbody of the cargo carrier. The fourth
requirement is fulfilled by using single trigonometry to find the minimum length my ramp needs to
be. Through sin(20)=(18/x), x needs to be at least 52.62” long. My ramp was 61.20”, creating a more
convenient 17.10 degree angle with the ground. My last requirement is fulfilled by using a Lego-
inspired design. Everything can be attached and taken off using shafts and insert holes.
FTERWARDS
This is not my final design. I would still have to do a few steps after this design to ensure
that my product is ready to be sold. The following are what procedures I would follow after this
project.
First, I would make a few more improvements to my design. One area that I believe needed
the most work done to it were the side gate. I think that my side gates design could have been more
permanent than just being held in by tolerances. Maybe a gate swing out design, with one hole
insert being permanent and the hole free swinging, would have made the gate more ergonomic and
permanent.
Second, I would have to choose what material to make the cargo carrier out of. This
material would need to be strong, because a wheelchair/mobility cart sitting on top of the cargo
carrier would weigh close to 100 pounds. I was curious to see how much stress my bottom piece
could hold, so ran a stress test. I used alloy steel for the material and used 50 psi of force applied to
the top face of the part. The results did were not as good as I expected. I either need to have a
stronger material to use, or I need to make structural supports to increase the integrity of the part.
Lastly, I would make sure I liked the final design. I would then create detailed designs and
choose what tolerances I would use for a manufacturer. The manufacture would make the part, we
would be sold in stores all over the world, and we will see all that money roll in.

More Related Content

Similar to Cargo Carrier- ME 9 Design Project

Seafarer's Center Parking Lot
Seafarer's Center Parking LotSeafarer's Center Parking Lot
Seafarer's Center Parking LotMaha Al Soufi
 
Wheel Design & Analysis
Wheel Design & AnalysisWheel Design & Analysis
Wheel Design & Analysis
Martin Dirker
 
PhysicsProjectPresentation
PhysicsProjectPresentationPhysicsProjectPresentation
PhysicsProjectPresentationLuis Torres
 
Rice Transporter Robot Project Report
Rice Transporter Robot Project ReportRice Transporter Robot Project Report
Rice Transporter Robot Project ReportKristopher Brown
 
Investigations of Drag and Lift Forces Over the Profiles of Car Using CFD
Investigations of Drag and Lift Forces Over the Profiles of Car Using CFDInvestigations of Drag and Lift Forces Over the Profiles of Car Using CFD
Investigations of Drag and Lift Forces Over the Profiles of Car Using CFD
ijsrd.com
 
Woodworking: The Essentila "all Purpose" workbench
Woodworking: The Essentila "all Purpose" workbenchWoodworking: The Essentila "all Purpose" workbench
Woodworking: The Essentila "all Purpose" workbench
YadeaHerman
 
Matt Baum Design Engineer Portfolio
Matt Baum Design Engineer PortfolioMatt Baum Design Engineer Portfolio
Matt Baum Design Engineer PortfolioMatthew Baum
 
Titan Rover CDR Presentation
Titan Rover CDR PresentationTitan Rover CDR Presentation
Titan Rover CDR Presentation
KristopherKerames
 
Installation Manual Aluminum
Installation Manual AluminumInstallation Manual Aluminum
Installation Manual Aluminum
tmpservices01
 
Installation Manual Aluminum
Installation Manual AluminumInstallation Manual Aluminum
Installation Manual Aluminum
tmpservices01
 
Tire Arm Process Documentation
Tire Arm Process DocumentationTire Arm Process Documentation
Tire Arm Process DocumentationDaniel Bondarenko
 
Steel Staircase Manufacturers
Steel Staircase ManufacturersSteel Staircase Manufacturers
Steel Staircase Manufacturers
tmpservices01
 
Pinion mount
Pinion mountPinion mount
Pinion mount
Andrew Aung
 
4 classic roubo-style-workbench
4 classic roubo-style-workbench4 classic roubo-style-workbench
4 classic roubo-style-workbench
YadeaHerman
 
CO2 Dragster - Design Thinking Process and Manufacturing
CO2 Dragster - Design Thinking Process and Manufacturing CO2 Dragster - Design Thinking Process and Manufacturing
CO2 Dragster - Design Thinking Process and Manufacturing
ahsengineering
 
TMP Services, Inc. has been the largest manufacturer of modular ramps and stairs
TMP Services, Inc. has been the largest manufacturer of modular ramps and stairsTMP Services, Inc. has been the largest manufacturer of modular ramps and stairs
TMP Services, Inc. has been the largest manufacturer of modular ramps and stairs
tmpservices01
 
Les plans pour une caisse à savon
Les plans pour une caisse à savonLes plans pour une caisse à savon
Les plans pour une caisse à savon
Jean-michel Neugate
 

Similar to Cargo Carrier- ME 9 Design Project (20)

railway_plant_layout
railway_plant_layoutrailway_plant_layout
railway_plant_layout
 
Seafarer's Center Parking Lot
Seafarer's Center Parking LotSeafarer's Center Parking Lot
Seafarer's Center Parking Lot
 
Wheel Design & Analysis
Wheel Design & AnalysisWheel Design & Analysis
Wheel Design & Analysis
 
PhysicsProjectPresentation
PhysicsProjectPresentationPhysicsProjectPresentation
PhysicsProjectPresentation
 
Project List
Project ListProject List
Project List
 
Rice Transporter Robot Project Report
Rice Transporter Robot Project ReportRice Transporter Robot Project Report
Rice Transporter Robot Project Report
 
Investigations of Drag and Lift Forces Over the Profiles of Car Using CFD
Investigations of Drag and Lift Forces Over the Profiles of Car Using CFDInvestigations of Drag and Lift Forces Over the Profiles of Car Using CFD
Investigations of Drag and Lift Forces Over the Profiles of Car Using CFD
 
Woodworking: The Essentila "all Purpose" workbench
Woodworking: The Essentila "all Purpose" workbenchWoodworking: The Essentila "all Purpose" workbench
Woodworking: The Essentila "all Purpose" workbench
 
Matt Baum Design Engineer Portfolio
Matt Baum Design Engineer PortfolioMatt Baum Design Engineer Portfolio
Matt Baum Design Engineer Portfolio
 
Titan Rover CDR Presentation
Titan Rover CDR PresentationTitan Rover CDR Presentation
Titan Rover CDR Presentation
 
Installation Manual Aluminum
Installation Manual AluminumInstallation Manual Aluminum
Installation Manual Aluminum
 
Installation Manual Aluminum
Installation Manual AluminumInstallation Manual Aluminum
Installation Manual Aluminum
 
Tire Arm Process Documentation
Tire Arm Process DocumentationTire Arm Process Documentation
Tire Arm Process Documentation
 
Steel Staircase Manufacturers
Steel Staircase ManufacturersSteel Staircase Manufacturers
Steel Staircase Manufacturers
 
Pinion mount
Pinion mountPinion mount
Pinion mount
 
4 classic roubo-style-workbench
4 classic roubo-style-workbench4 classic roubo-style-workbench
4 classic roubo-style-workbench
 
CO2 Dragster - Design Thinking Process and Manufacturing
CO2 Dragster - Design Thinking Process and Manufacturing CO2 Dragster - Design Thinking Process and Manufacturing
CO2 Dragster - Design Thinking Process and Manufacturing
 
TMP Services, Inc. has been the largest manufacturer of modular ramps and stairs
TMP Services, Inc. has been the largest manufacturer of modular ramps and stairsTMP Services, Inc. has been the largest manufacturer of modular ramps and stairs
TMP Services, Inc. has been the largest manufacturer of modular ramps and stairs
 
Les plans pour une caisse à savon
Les plans pour une caisse à savonLes plans pour une caisse à savon
Les plans pour une caisse à savon
 
The Crank Slider Crusher
The Crank Slider CrusherThe Crank Slider Crusher
The Crank Slider Crusher
 

Cargo Carrier- ME 9 Design Project

  • 1. Alex Larcheveque | ME 009 (Section 025) | May 24, 2015 Universal Cargo Carrier
  • 2. PAGE 1 Introduction In class we were assigned to design a new cargo carrier, used commonly for wheelchairs and other mobility carts. The problem with today’s cargo carrier is that it can only be accessed from one side. So if there is an obstruction from that one side, the person loading the wheelchair/mobility cart will have a hard time loading the device. In order to avoid these inconveniences, we will try to design a cargo carrier that can be accessed from all three sides. Problem Definition Create a cargo carrier that can be accessed from all three sides. The newly designed cargo carrier should follow these design criteria:  The platform should be 60 x 30 inches. The minimum ramp width shall be 24 inches.  Max height with cargo: 30 inches  Max height without cargo: 8 inches  Ramp angle should not exceed 20° when platform is 18 inches off ground  Deployed/stored by single person
  • 3. PAGE 2 Conceptual Designs Design 1: Foldable Design
  • 4. PAGE 3 Design 2: Cargo Carrier with Lift
  • 5. PAGE 4 Design 3: Detachable Ramp Assembly with One Temporary Ramp
  • 6. PAGE 5 Design Concept Selection From the decision matrix below, I decided to choose the Detachable Ramp Assembly with One Temporary Ramp.
  • 7. PAGE 6 Embodiment Design As seen in the title page, this was the final design for the cargo carrier. In the following pages, I will go through each individual part of the assembly and explain what its function was. In addition, I will show you how I met and exceeded the requirements for this design project.
  • 8. PAGE 7 Part 1: Base Piece The base piece is the main part for the design. Unique Design Features:  Hole cutouts that are inserts for the side gates.  Shafts run across three out of the four sides. The purpose for these are so that they can attach to the clamps, and will create a temporary ramp. I did not include a shaft for the last side, because that side would be facing the car’s rear.  The platform also includes an underbody, in which the temporary ramp can be stored Requirements Met  The platform is 60 inches by 30 inches
  • 9. PAGE 8 Part 2: Side Gates These parts ensures that the cargo inside will not fall out. Unique Features:  Designed with correct length so nothing will fall out  Have tight tolerances (see engineering drawing for tolerances). This allows them to be taken out/inserted only when force is used. Think of our design as Legos, but for a different purpose. Requirements Met:  Max height with cargo: 30 inches  Max height without cargo: 8 inches My design actually exceeds these expectations. In total, our height will be 6.17 inches all the time (not including the underbody). Long Side Short Side
  • 10. PAGE 9 Part 3: Claw Attachment This part creates a temporary attachment to the shafts on the base piece. Unique Features:  The cylinder is not fully closed. This allows for easy attachment/removal to the shaft.  The circular hole on the rear side of the claw allows for a shaft connected to the ramp to attach easily. Requirements Met:  None
  • 11. PAGE 10 Part 5: Claw Shaft This part connects the claw and the ramp together. Unique Features:  None. It’s a shaft…. Requirements Met:  None.
  • 12. PAGE 11 Part 6: Ramp (Part 1) This ramp will connect to the claw and another ramp. These two half ramps will assemble into one, and are designed to both store in the underbody. Unique Features:  Holes inserts are seen on both sides for shafts to fit. Requirements Met:  Width is 24 inches  Ramp angle should not exceed 20° when platform is 18 inches off ground My design exceeds the requirements of creating the maximum ramp angle of 20°. The total length of the ramp is 61.20 inches, which creates a 17.10° angle when 18 inches off the ground.
  • 13. PAGE 12 Part 7: Ramp (Part 2) This ramp will touch the ground. On the other end, it will connect to ramp (part 1) through a shaft. Unique Features:  Hole inserts on one side of the ramp for shafts to fit. Requirements:  Same requirements as Ramp (Part 1) Side will touch the floor
  • 14. PAGE 13 Part 8: Ramp Shaft This part connects ramp (part 1) to ramp (part 2). Unique Features:  Again, it’s a shaft…. Requirements Met:  None.
  • 15. PAGE 14 Summary/Conclusions/Recommendations SUMMARY All in all, I thought that my cargo carrier was successful. It fulfilled, even exceeded, all the requirements specified and solved the problem: Build a cargo carrier that can be accessed from all three sides. There were five requirements I needed to fulfill for my design. They were 1. Dimensions of platform (60” x 30”) and ramp width (24”) 2. Max height with cargo should not exceed 30” 3. Max height without cargo should not exceed 8” 4. Ramp angle should not exceed 20 degrees when 18 inches off the ground 5. The ramp should be able to be deployed/stored by a single person. For the first requirement, I followed exactly what the dimensions stated. I made my platform 60” x 30” in the sketch, and the same went for the ramp width. The second and third requirement are always fulfilled, because my maximum height of the cargo carrier is fixed at 6.17”. My height calculation for the cargo carrier height does not include the underbody storage. This is because the connection of the cargo carrier and the tailgate of a car would not start at the underbody, the connection would be placed above the underbody of the cargo carrier. The fourth requirement is fulfilled by using single trigonometry to find the minimum length my ramp needs to be. Through sin(20)=(18/x), x needs to be at least 52.62” long. My ramp was 61.20”, creating a more convenient 17.10 degree angle with the ground. My last requirement is fulfilled by using a Lego- inspired design. Everything can be attached and taken off using shafts and insert holes. FTERWARDS This is not my final design. I would still have to do a few steps after this design to ensure that my product is ready to be sold. The following are what procedures I would follow after this project. First, I would make a few more improvements to my design. One area that I believe needed the most work done to it were the side gate. I think that my side gates design could have been more permanent than just being held in by tolerances. Maybe a gate swing out design, with one hole insert being permanent and the hole free swinging, would have made the gate more ergonomic and permanent. Second, I would have to choose what material to make the cargo carrier out of. This material would need to be strong, because a wheelchair/mobility cart sitting on top of the cargo carrier would weigh close to 100 pounds. I was curious to see how much stress my bottom piece could hold, so ran a stress test. I used alloy steel for the material and used 50 psi of force applied to the top face of the part. The results did were not as good as I expected. I either need to have a stronger material to use, or I need to make structural supports to increase the integrity of the part. Lastly, I would make sure I liked the final design. I would then create detailed designs and choose what tolerances I would use for a manufacturer. The manufacture would make the part, we would be sold in stores all over the world, and we will see all that money roll in.