SlideShare a Scribd company logo
Building Value into the
NEPA Process
    Peter W. Havens, CEP
Disclaimer


   The opinions and views expressed
     herein are strictly those of the
     author and presenter. They do not
     express the views or opinions of
     the Department of the Navy.
Introduction
   40 CFR 1500.1 Purpose
(c) Ultimately, of course, it is not better documents but
    better decisions that count. NEPA’s purpose is not
    to generate paperwork – even excellent paperwork
    – but to foster excellent action. The NEPA process
    is intended to help public officials make decisions
    that are based on understanding of environmental
    consequences, and take actions that protect,
    restore, and enhance the environment.
The NEPA Process
   NEPA is a procedural law
    A process described by law and regulation

   The NEPA process is not isolated;
    The process exists because of a proposal for action

   The “enterprise” to which the NEPA process is
    attached extends from “first light” to “implementation”

   Therefore, the NEPA process also extends
    from first light to implementation
The process must generate value

   Value must be generated by a process,
    otherwise the activity is wasteful
   Value is determined by the “customer” or the
    recipient of the product output
   Value accrues when we encourage the
    critical path and eliminate non-value added
    activity
   Waste occurs when we measure the product
    at the end of the process and throw away
    those items that fail to meet specifications
Building value into the NEPA Process
   Value of the NEPA process lies in its value to
    agency decision making

   Improving how the process is conducted will
    generate more value than improving the
    document

   Encouraging the NEPA process critical path
    activities will improve value to the decision
    maker
Decision Making Structure

                           Decision




  Environmental     Technical         Economic    Logistic
     (NEPA)       (Engineering)        (Cost)    (Mission)
Consistency of Scope
   Input to decision making must be based on the
    same scope

   A scope change requires all disciplines to re-
    consider their conclusions

   Consistency of Scope is required to
       Conduct impact assessment
       Develop mitigation
       Prepare the NEPA document
Performance Criteria
   Environmental Performance Criteria
       Culvert openings no smaller than 8 inches
       Avoid jurisdictional wetlands

   Design/engineering solutions
       Culvert constructed with 5, 8-inch PVC pipes
       Move it up the hill

   Performance criteria are required to
       Improve efficiency of communication
       Coordinating with design engineers
       Inform decision makers of environmental constraints
        and opportunities
Programming, Budgeting and Design
for Federal Actions
   Military Construction Program
       Lengthy, actions are identified 4 – 6 years in advance of
        the desired “program year”
       Scope and Program year target may vary
       Purpose and need are relatively stable


   Decision making
       Occurs throughout the programming and budgeting
        process
       Continues through the design process
Programming and Budgeting
   Critical path activities

       Identifying and defining the NEPA Scope
           Need
           Purpose
           Alternatives

       Understanding and responding to significant issues

       Defining and budgeting for mitigation

       Planning for environmental documentation
Design
   Critical path activities

       Understanding and communicating the action scope

       Communicating environmental constraints

       Responding to value engineering changes

       Consulting with agencies

       Considering alternative mitigation measures and permit
        coordination
View of the decision maker
    Mission support

    Responsive, effective and efficient input

    Balanced and considered decision

    Truly representative NEPA documents

    Confidence
Improving the NEPA Process
   Improving the perceived value
       Providing value to decision makers

   Focusing on…
       Consistency of Scope
       Environmental Performance Criteria
   Which leads to…
       Improved decision making

More Related Content

What's hot

Pm project-control-compiled
Pm project-control-compiledPm project-control-compiled
Pm project-control-compiled
Arthur Wilson
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
Imran Jamil
 
PDCA
PDCAPDCA
Monitoring & evaluation presentation
Monitoring & evaluation presentationMonitoring & evaluation presentation
Monitoring & evaluation presentation
slubasi
 
Mutch, David Feb2016
Mutch, David Feb2016Mutch, David Feb2016
Mutch, David Feb2016
David Mutch
 
AMP Next Steps
AMP Next StepsAMP Next Steps
AMP Next Steps
gary_scott
 
Possibble Internal Audit Monitoring Areas in Projects
Possibble Internal Audit Monitoring Areas in ProjectsPossibble Internal Audit Monitoring Areas in Projects
Possibble Internal Audit Monitoring Areas in Projects
Patrick Thompson
 
Methods for evaluating project performance
Methods for evaluating project performanceMethods for evaluating project performance
Methods for evaluating project performance
liviu00
 
NQA-1-2012 Changes That Support DOE Nuclear Facility Safety
NQA-1-2012 Changes That Support DOE Nuclear Facility SafetyNQA-1-2012 Changes That Support DOE Nuclear Facility Safety
NQA-1-2012 Changes That Support DOE Nuclear Facility Safety
DanielsonG
 
Wayne Babin_Resume_081715
Wayne Babin_Resume_081715Wayne Babin_Resume_081715
Wayne Babin_Resume_081715
Wayne Babin
 

What's hot (10)

Pm project-control-compiled
Pm project-control-compiledPm project-control-compiled
Pm project-control-compiled
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
PDCA
PDCAPDCA
PDCA
 
Monitoring & evaluation presentation
Monitoring & evaluation presentationMonitoring & evaluation presentation
Monitoring & evaluation presentation
 
Mutch, David Feb2016
Mutch, David Feb2016Mutch, David Feb2016
Mutch, David Feb2016
 
AMP Next Steps
AMP Next StepsAMP Next Steps
AMP Next Steps
 
Possibble Internal Audit Monitoring Areas in Projects
Possibble Internal Audit Monitoring Areas in ProjectsPossibble Internal Audit Monitoring Areas in Projects
Possibble Internal Audit Monitoring Areas in Projects
 
Methods for evaluating project performance
Methods for evaluating project performanceMethods for evaluating project performance
Methods for evaluating project performance
 
NQA-1-2012 Changes That Support DOE Nuclear Facility Safety
NQA-1-2012 Changes That Support DOE Nuclear Facility SafetyNQA-1-2012 Changes That Support DOE Nuclear Facility Safety
NQA-1-2012 Changes That Support DOE Nuclear Facility Safety
 
Wayne Babin_Resume_081715
Wayne Babin_Resume_081715Wayne Babin_Resume_081715
Wayne Babin_Resume_081715
 

Viewers also liked

NEPA BlogCon
NEPA BlogConNEPA BlogCon
NEPA Changes For Local Government
NEPA Changes For Local GovernmentNEPA Changes For Local Government
NEPA Changes For Local Government
videoman77
 
Best Practices for NEPA Compliance and Related Permitting for Projects on In...
Best Practices for NEPA Compliance and Related Permitting for  Projects on In...Best Practices for NEPA Compliance and Related Permitting for  Projects on In...
Best Practices for NEPA Compliance and Related Permitting for Projects on In...
Trihydro Corporation
 
March 2010 - DOE-NEPA Lessons Learned
March 2010 - DOE-NEPA Lessons LearnedMarch 2010 - DOE-NEPA Lessons Learned
March 2010 - DOE-NEPA Lessons Learned
DOE Office of NEPA Policy & Compliance
 
Environmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit IIIEnvironmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit III
GAURAV. H .TANDON
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
School of planning and architecture
 
EPA CAA Email 4.21.03
EPA CAA Email 4.21.03EPA CAA Email 4.21.03
EPA CAA Email 4.21.03
Obama White House
 
Crew documents 020564 - 020611
Crew documents 020564 - 020611Crew documents 020564 - 020611
Crew documents 020564 - 020611
Obama White House
 
Citizens Guide To NEPA
Citizens Guide To NEPACitizens Guide To NEPA
Citizens Guide To NEPA
Obama White House
 
Collaboration In Nepa: A Handbook for Practioners
Collaboration In Nepa: A Handbook for PractionersCollaboration In Nepa: A Handbook for Practioners
Collaboration In Nepa: A Handbook for Practioners
Obama White House
 

Viewers also liked (10)

NEPA BlogCon
NEPA BlogConNEPA BlogCon
NEPA BlogCon
 
NEPA Changes For Local Government
NEPA Changes For Local GovernmentNEPA Changes For Local Government
NEPA Changes For Local Government
 
Best Practices for NEPA Compliance and Related Permitting for Projects on In...
Best Practices for NEPA Compliance and Related Permitting for  Projects on In...Best Practices for NEPA Compliance and Related Permitting for  Projects on In...
Best Practices for NEPA Compliance and Related Permitting for Projects on In...
 
March 2010 - DOE-NEPA Lessons Learned
March 2010 - DOE-NEPA Lessons LearnedMarch 2010 - DOE-NEPA Lessons Learned
March 2010 - DOE-NEPA Lessons Learned
 
Environmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit IIIEnvironmental Impact Assessment and Environmental Audit- Unit III
Environmental Impact Assessment and Environmental Audit- Unit III
 
Environmental impact assessment (EIA)
Environmental impact assessment (EIA)Environmental impact assessment (EIA)
Environmental impact assessment (EIA)
 
EPA CAA Email 4.21.03
EPA CAA Email 4.21.03EPA CAA Email 4.21.03
EPA CAA Email 4.21.03
 
Crew documents 020564 - 020611
Crew documents 020564 - 020611Crew documents 020564 - 020611
Crew documents 020564 - 020611
 
Citizens Guide To NEPA
Citizens Guide To NEPACitizens Guide To NEPA
Citizens Guide To NEPA
 
Collaboration In Nepa: A Handbook for Practioners
Collaboration In Nepa: A Handbook for PractionersCollaboration In Nepa: A Handbook for Practioners
Collaboration In Nepa: A Handbook for Practioners
 

Similar to Building Value Into The Nepa Process (Aka Why Is This Important)

Integrated Project Management And Solution Delivery Process
Integrated Project Management And Solution Delivery ProcessIntegrated Project Management And Solution Delivery Process
Integrated Project Management And Solution Delivery Process
Alan McSweeney
 
Ed4 P4 Project Integration Management
Ed4 P4 Project Integration ManagementEd4 P4 Project Integration Management
Ed4 P4 Project Integration Management
jonash99
 
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
Kristen Carney
 
E136
E136E136
E136
E136E136
SEA.pptx
SEA.pptxSEA.pptx
SEA.pptx
Quasid
 
EOR Webinar PAS presentation slidesFINAL.pptx
EOR Webinar PAS presentation slidesFINAL.pptxEOR Webinar PAS presentation slidesFINAL.pptx
EOR Webinar PAS presentation slidesFINAL.pptx
PAS_Team
 
GREEN BUILDING ONE STOP SERVICE
GREEN BUILDING  ONE STOP SERVICEGREEN BUILDING  ONE STOP SERVICE
Green Audit for Institutes
Green Audit for InstitutesGreen Audit for Institutes
Green Audit for Institutes
Nilesh Dayalapwar
 
Cp gp day04 session 14 - concept and assessment methodology of gp and compari...
Cp gp day04 session 14 - concept and assessment methodology of gp and compari...Cp gp day04 session 14 - concept and assessment methodology of gp and compari...
Cp gp day04 session 14 - concept and assessment methodology of gp and compari...
zubeditufail
 
Green Studio Handbook - Part 1
Green Studio Handbook - Part 1Green Studio Handbook - Part 1
Green Studio Handbook - Part 1
Galala University
 
Integrated project management and solution delivery process 10082017 dt
Integrated project management and solution delivery process 10082017 dtIntegrated project management and solution delivery process 10082017 dt
Integrated project management and solution delivery process 10082017 dt
Daniel Thuraiappah
 
Value Engineering.ppt
Value Engineering.pptValue Engineering.ppt
Value Engineering.ppt
vinukorekar
 
Value addition value engineering presentation
Value addition value engineering presentationValue addition value engineering presentation
Value addition value engineering presentation
vedveersingh4
 
Value _Engineering_ by_ tejas _rajput___
Value _Engineering_ by_ tejas _rajput___Value _Engineering_ by_ tejas _rajput___
Value _Engineering_ by_ tejas _rajput___
TejasRajput29
 
PCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on EvaluationPCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on Evaluation
rexcris
 
projec kickoff presentation template
 projec kickoff presentation template projec kickoff presentation template
projec kickoff presentation template
dadiiskandar4
 
Embedding the ecosystem approach in policy: Problems and Potential
Embedding the ecosystem approach in policy: Problems and Potential Embedding the ecosystem approach in policy: Problems and Potential
Embedding the ecosystem approach in policy: Problems and Potential
ruralfringe
 
Fostering Innovation in Postal Service Environmentally Preferable Shipping Su...
Fostering Innovation in Postal Service Environmentally Preferable Shipping Su...Fostering Innovation in Postal Service Environmentally Preferable Shipping Su...
Fostering Innovation in Postal Service Environmentally Preferable Shipping Su...
Michael R. Barr
 
Environmental management sytems and processes
Environmental management  sytems and processesEnvironmental management  sytems and processes
Environmental management sytems and processes
Rakesh Bhaskar
 

Similar to Building Value Into The Nepa Process (Aka Why Is This Important) (20)

Integrated Project Management And Solution Delivery Process
Integrated Project Management And Solution Delivery ProcessIntegrated Project Management And Solution Delivery Process
Integrated Project Management And Solution Delivery Process
 
Ed4 P4 Project Integration Management
Ed4 P4 Project Integration ManagementEd4 P4 Project Integration Management
Ed4 P4 Project Integration Management
 
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
New TxDOT ENV Processes To Reduce Time to Deliver Projects by 50%
 
E136
E136E136
E136
 
E136
E136E136
E136
 
SEA.pptx
SEA.pptxSEA.pptx
SEA.pptx
 
EOR Webinar PAS presentation slidesFINAL.pptx
EOR Webinar PAS presentation slidesFINAL.pptxEOR Webinar PAS presentation slidesFINAL.pptx
EOR Webinar PAS presentation slidesFINAL.pptx
 
GREEN BUILDING ONE STOP SERVICE
GREEN BUILDING  ONE STOP SERVICEGREEN BUILDING  ONE STOP SERVICE
GREEN BUILDING ONE STOP SERVICE
 
Green Audit for Institutes
Green Audit for InstitutesGreen Audit for Institutes
Green Audit for Institutes
 
Cp gp day04 session 14 - concept and assessment methodology of gp and compari...
Cp gp day04 session 14 - concept and assessment methodology of gp and compari...Cp gp day04 session 14 - concept and assessment methodology of gp and compari...
Cp gp day04 session 14 - concept and assessment methodology of gp and compari...
 
Green Studio Handbook - Part 1
Green Studio Handbook - Part 1Green Studio Handbook - Part 1
Green Studio Handbook - Part 1
 
Integrated project management and solution delivery process 10082017 dt
Integrated project management and solution delivery process 10082017 dtIntegrated project management and solution delivery process 10082017 dt
Integrated project management and solution delivery process 10082017 dt
 
Value Engineering.ppt
Value Engineering.pptValue Engineering.ppt
Value Engineering.ppt
 
Value addition value engineering presentation
Value addition value engineering presentationValue addition value engineering presentation
Value addition value engineering presentation
 
Value _Engineering_ by_ tejas _rajput___
Value _Engineering_ by_ tejas _rajput___Value _Engineering_ by_ tejas _rajput___
Value _Engineering_ by_ tejas _rajput___
 
PCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on EvaluationPCM - Project Cycle Management, Training on Evaluation
PCM - Project Cycle Management, Training on Evaluation
 
projec kickoff presentation template
 projec kickoff presentation template projec kickoff presentation template
projec kickoff presentation template
 
Embedding the ecosystem approach in policy: Problems and Potential
Embedding the ecosystem approach in policy: Problems and Potential Embedding the ecosystem approach in policy: Problems and Potential
Embedding the ecosystem approach in policy: Problems and Potential
 
Fostering Innovation in Postal Service Environmentally Preferable Shipping Su...
Fostering Innovation in Postal Service Environmentally Preferable Shipping Su...Fostering Innovation in Postal Service Environmentally Preferable Shipping Su...
Fostering Innovation in Postal Service Environmentally Preferable Shipping Su...
 
Environmental management sytems and processes
Environmental management  sytems and processesEnvironmental management  sytems and processes
Environmental management sytems and processes
 

Building Value Into The Nepa Process (Aka Why Is This Important)

  • 1. Building Value into the NEPA Process Peter W. Havens, CEP
  • 2. Disclaimer The opinions and views expressed herein are strictly those of the author and presenter. They do not express the views or opinions of the Department of the Navy.
  • 3. Introduction  40 CFR 1500.1 Purpose (c) Ultimately, of course, it is not better documents but better decisions that count. NEPA’s purpose is not to generate paperwork – even excellent paperwork – but to foster excellent action. The NEPA process is intended to help public officials make decisions that are based on understanding of environmental consequences, and take actions that protect, restore, and enhance the environment.
  • 4. The NEPA Process  NEPA is a procedural law A process described by law and regulation  The NEPA process is not isolated; The process exists because of a proposal for action  The “enterprise” to which the NEPA process is attached extends from “first light” to “implementation”  Therefore, the NEPA process also extends from first light to implementation
  • 5. The process must generate value  Value must be generated by a process, otherwise the activity is wasteful  Value is determined by the “customer” or the recipient of the product output  Value accrues when we encourage the critical path and eliminate non-value added activity  Waste occurs when we measure the product at the end of the process and throw away those items that fail to meet specifications
  • 6. Building value into the NEPA Process  Value of the NEPA process lies in its value to agency decision making  Improving how the process is conducted will generate more value than improving the document  Encouraging the NEPA process critical path activities will improve value to the decision maker
  • 7. Decision Making Structure Decision Environmental Technical Economic Logistic (NEPA) (Engineering) (Cost) (Mission)
  • 8. Consistency of Scope  Input to decision making must be based on the same scope  A scope change requires all disciplines to re- consider their conclusions  Consistency of Scope is required to  Conduct impact assessment  Develop mitigation  Prepare the NEPA document
  • 9. Performance Criteria  Environmental Performance Criteria  Culvert openings no smaller than 8 inches  Avoid jurisdictional wetlands  Design/engineering solutions  Culvert constructed with 5, 8-inch PVC pipes  Move it up the hill  Performance criteria are required to  Improve efficiency of communication  Coordinating with design engineers  Inform decision makers of environmental constraints and opportunities
  • 10. Programming, Budgeting and Design for Federal Actions  Military Construction Program  Lengthy, actions are identified 4 – 6 years in advance of the desired “program year”  Scope and Program year target may vary  Purpose and need are relatively stable  Decision making  Occurs throughout the programming and budgeting process  Continues through the design process
  • 11. Programming and Budgeting  Critical path activities  Identifying and defining the NEPA Scope  Need  Purpose  Alternatives  Understanding and responding to significant issues  Defining and budgeting for mitigation  Planning for environmental documentation
  • 12. Design  Critical path activities  Understanding and communicating the action scope  Communicating environmental constraints  Responding to value engineering changes  Consulting with agencies  Considering alternative mitigation measures and permit coordination
  • 13. View of the decision maker  Mission support  Responsive, effective and efficient input  Balanced and considered decision  Truly representative NEPA documents  Confidence
  • 14. Improving the NEPA Process  Improving the perceived value  Providing value to decision makers  Focusing on…  Consistency of Scope  Environmental Performance Criteria  Which leads to…  Improved decision making