Building Construction Internship
Week 1 Report
Duration: 29th May – 3rd June 2025
Intern: Shiva Raj
Company: S.S. Systems Pvt. Ltd.
Location: Bihar
Site Orientation & Safety Training
• 🔹 Briefed on company rules and daily work
schedule
• 🔹 Safety gear issued: Helmet, reflective
jackets, gloves, shoes
• 🔹 Toolbox meetings every morning to discuss
tasks and safety precautions
• 🔹 Learned about hazard zones and emergency
procedures
• 🔹 Importance of PPE (Personal Protective
Equipment) explained
Soil Excavation and Layout Work
• 🔹 Excavation for isolated footing using JCBs
and manual tools
• 🔹 Understood types of soil and their impact on
foundation design
• 🔹 Layout marking done using measuring tapes,
lime powder, and threads
• 🔹 Site level checked using Dumpy Level and
Spirit Level
• 📸 Insert a photo of excavation work or layout
Footing Types & Site Levels
• 🔹 Introduction to types of footings (Isolated,
Combined, Strip)
• 🔹 Studied reinforcement bar placement for
footings
• 🔹 Observed importance of leveling and slope
management
• 🔹 Reinforcement drawing compared with
actual site work
• 📸 Insert image: steel cage for footing or site
Key Learnings of Week 1
• ✅ Gained awareness of construction site
protocols
• ✅ Understood excavation and initial setting out
work
• ✅ Learned basic safety compliance and its
importance
• ✅ Realized how field practice aligns with
classroom theory

Building estimation module for presentation

  • 1.
    Building Construction Internship Week1 Report Duration: 29th May – 3rd June 2025 Intern: Shiva Raj Company: S.S. Systems Pvt. Ltd. Location: Bihar
  • 2.
    Site Orientation &Safety Training • 🔹 Briefed on company rules and daily work schedule • 🔹 Safety gear issued: Helmet, reflective jackets, gloves, shoes • 🔹 Toolbox meetings every morning to discuss tasks and safety precautions • 🔹 Learned about hazard zones and emergency procedures • 🔹 Importance of PPE (Personal Protective Equipment) explained
  • 3.
    Soil Excavation andLayout Work • 🔹 Excavation for isolated footing using JCBs and manual tools • 🔹 Understood types of soil and their impact on foundation design • 🔹 Layout marking done using measuring tapes, lime powder, and threads • 🔹 Site level checked using Dumpy Level and Spirit Level • 📸 Insert a photo of excavation work or layout
  • 4.
    Footing Types &Site Levels • 🔹 Introduction to types of footings (Isolated, Combined, Strip) • 🔹 Studied reinforcement bar placement for footings • 🔹 Observed importance of leveling and slope management • 🔹 Reinforcement drawing compared with actual site work • 📸 Insert image: steel cage for footing or site
  • 5.
    Key Learnings ofWeek 1 • ✅ Gained awareness of construction site protocols • ✅ Understood excavation and initial setting out work • ✅ Learned basic safety compliance and its importance • ✅ Realized how field practice aligns with classroom theory