Project Start 1JUN11
Project Finish 30MAY12*
Data Date 1JUN11
Plot Date 22MAR11
(c) Primavera Systems, Inc.
Early dates
Late dates
Date ApprovedCheckedRevision
ORIENTAL ENTERPRISES
EID PRAYING & CAR PARK at AL KHEESA
OVER ALL PROGRESS CURVE
AWQ1 Sheet 1 of 1
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
0
1
2
3
4
5
6
7
8
x Thousand
JUN
2011
JUL AUG SEP OCT NOV DEC JAN
2012
FEB MAR APR MAY
96
342
585
461
588
828
969
1105
1005
544 536
324
96
342
571
423
443
585
768
862 867
850
1093
480
EARLY
LATE
Annexure-1C
MONTH
PROJECT NAME: CONSTRUCTION OF EID PRAYING & CAR PARKING AREAS AT AL KHEESA
OVERALL PROGRESS CURVE
0%
2%
4%
6%
8%
10%
12%
14%
16%
MONTHS
Progress(DuringPeriod)
0%
20%
40%
60%
80%
100%
120%
Progress(Cummulative)
Early Plan Month
Late Plan Month
Early Plan Month (cum)
Late Plan Month (cum)
Early Plan Month 1% 5% 8% 6% 8% 11% 13% 15% 14% 7% 7% 4%
Late Plan Month 1% 5% 8% 6% 6% 8% 10% 12% 12% 12% 15% 7%
Early Plan Month (cum) 1% 6% 14% 20% 28% 39% 52% 67% 81% 88% 96% 100%
Late Plan Month (cum) 1% 6% 14% 19% 25% 33% 44% 55% 67% 79% 93% 100%
Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12
Page 1 of 1
Project Start 1JUN11
Project Finish 30MAY12*
Data Date 1JUN11
Plot Date 22MAR11
(c) Primavera Systems, Inc.
Schedule dates
MANPOWER SUMMARY PROFILE
Date ApprovedCheckedRevision
EID PRAYING & CAR PARKING AL KHEESA
ORIENTALS ENTERPRISES
RESOURCE PROFILES
Sheet 1 of 1
0
4
8
12
16
20
24
28
32
36
40
JUN
2011
AUG OCT DEC FEB
2012
APR
Months
PeakMan/Day
CIVIL & SPECIALTY WORKERS
0
1
2
3
4
5
6
7
8
JUN
2011
AUG OCT DEC FEB
2012
APR
Months
PeakMan/Day
PLUMBERS
0
1
2
3
4
5
6
7
8
9
10
11
JUN
2011
AUG OCT DEC FEB
2012
APR
Months
PeakMan/Day
ELECTRICIANS

p3 s-curves

  • 1.
    Project Start 1JUN11 ProjectFinish 30MAY12* Data Date 1JUN11 Plot Date 22MAR11 (c) Primavera Systems, Inc. Early dates Late dates Date ApprovedCheckedRevision ORIENTAL ENTERPRISES EID PRAYING & CAR PARK at AL KHEESA OVER ALL PROGRESS CURVE AWQ1 Sheet 1 of 1 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 0 1 2 3 4 5 6 7 8 x Thousand JUN 2011 JUL AUG SEP OCT NOV DEC JAN 2012 FEB MAR APR MAY 96 342 585 461 588 828 969 1105 1005 544 536 324 96 342 571 423 443 585 768 862 867 850 1093 480 EARLY LATE
  • 2.
    Annexure-1C MONTH PROJECT NAME: CONSTRUCTIONOF EID PRAYING & CAR PARKING AREAS AT AL KHEESA OVERALL PROGRESS CURVE 0% 2% 4% 6% 8% 10% 12% 14% 16% MONTHS Progress(DuringPeriod) 0% 20% 40% 60% 80% 100% 120% Progress(Cummulative) Early Plan Month Late Plan Month Early Plan Month (cum) Late Plan Month (cum) Early Plan Month 1% 5% 8% 6% 8% 11% 13% 15% 14% 7% 7% 4% Late Plan Month 1% 5% 8% 6% 6% 8% 10% 12% 12% 12% 15% 7% Early Plan Month (cum) 1% 6% 14% 20% 28% 39% 52% 67% 81% 88% 96% 100% Late Plan Month (cum) 1% 6% 14% 19% 25% 33% 44% 55% 67% 79% 93% 100% Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Page 1 of 1
  • 3.
    Project Start 1JUN11 ProjectFinish 30MAY12* Data Date 1JUN11 Plot Date 22MAR11 (c) Primavera Systems, Inc. Schedule dates MANPOWER SUMMARY PROFILE Date ApprovedCheckedRevision EID PRAYING & CAR PARKING AL KHEESA ORIENTALS ENTERPRISES RESOURCE PROFILES Sheet 1 of 1 0 4 8 12 16 20 24 28 32 36 40 JUN 2011 AUG OCT DEC FEB 2012 APR Months PeakMan/Day CIVIL & SPECIALTY WORKERS 0 1 2 3 4 5 6 7 8 JUN 2011 AUG OCT DEC FEB 2012 APR Months PeakMan/Day PLUMBERS 0 1 2 3 4 5 6 7 8 9 10 11 JUN 2011 AUG OCT DEC FEB 2012 APR Months PeakMan/Day ELECTRICIANS