Wylfa Newydd Progress Update Summary
1. 25/05/2018 Page 1
NOT PROTECTIVELY MARKED
NOT PROTECTIVELY MARKEDNOT PROTECTIVELY MARKED
Wylfa Newydd Progress Update
Sasha Davies, Head of Strategic Development Wales
Thursday 17th May 2018
3. 25/05/2018 Page 3
NOT PROTECTIVELY MARKED
NOT PROTECTIVELY MARKED
Corporate overview
• Established in 2009, acquired by Hitachi in
2012
• Created to help meet the need for new,
secure low carbon power
• Making steady progress past milestones for
our lead project, Wylfa Newydd, with Oldbury-
on-Severn to follow
• Will deploy tried and tested Hitachi-GE
ABWRs which have already been built to time
and budget in Japan four times over
• c.£20billion+ investment in the UK - up to
60% of project value could be spent in UK,
creating opportunities for British businesses
• Approximately 370 employees at HQ and
Wylfa Newydd including temporary
contractors, graduates and apprentices
GLOUCESTER HQ
WYLFA NEWYDD
OLDBURY-ON-SEVERN
4. 25/05/2018 Page 4
NOT PROTECTIVELY MARKED
NOT PROTECTIVELY MARKED
The key development questions….
6. 25/05/2018 Page 6
NOT PROTECTIVELY MARKED
NOT PROTECTIVELY MARKED
Development sequence
DEVELOPMENT
SITE LICENCE GRANT
GENERIC DESIGN
ASSESSMENT
DEVELOPMENT CONSENT
ORDER
CONSTRUCTION OPERATION
UNIT 1 COMMERCIALOPERATION
Mid 2020s
ALLAGREEMENTS/PERMISSIONSINPLACE
Final Investment
Decision
MAJOR EARTHWORKS
UNIT 1
FIRST NUCLEAR
CONCRETE
COMMISSIONING
7. 25/05/2018 Page 7
NOT PROTECTIVELY MARKED
NOT PROTECTIVELY MARKED
What are we submitting ?
Development Consent Order for:
The Generating Station
Offsite facilities (MEEG,ECL,AECC)
Associated Developments (Park & Ride, Logistics Centre)
A5025 off-line highways improvements
Marine License:
Cooling water intake & discharge, breakwaters, MOLF, dredging,
marine disposal
Environmental permits for :
Water, emissions / releases
TCPA for:
Online roads A5025
Site Preparation & Clearance
8. 25/05/2018 Page 8
NOT PROTECTIVELY MARKED
NOT PROTECTIVELY MARKED
Recent progress
Continued support from the UK and Japanese
Governments, Welsh Government
UK ABWR successfully completed Generic
Design Assessment
Clearance to buy reactor components
Operational Partners – JAPC and Exelon
Optimisation of plant
Site Licence Company Board established
Submitted Site Licence Application
Apprenticeship programme onto third cohort
£1 million funding for FE Coleg Menai’s (Llangefni,
Anglesey) £15m Engineering facility
Completed 3 Pre Application Public Consultations
Announced Training Services Partnership with Tecnatom
Submitted application for Radioactive Substances
Regulation Environmental Permit to Natural Resources
Wales
Submitted Articles 37 & 41 Euratom permissions
9. 25/05/2018 Page 9
NOT PROTECTIVELY MARKED
NOT PROTECTIVELY MARKED
Developing our ‘social license’ to operate
By engaging effectively with our host community of Anglesey and
wider North Wales region
Minimising/mitigating negative impacts and maximising positive
socio-economic benefits
Being a good neighbour
To protect and enhance Welsh language and culture
Respecting our Wylfa Newydd ‘sense of place’
10. 25/05/2018 Page 10
NOT PROTECTIVELY MARKED
NOT PROTECTIVELY MARKED
Investing in our future local workforce
Growing our local workforce, from schools through to
Higher & Further Education
Schools ‘Futures/Dyfodol’ Education Outreach and STEM
‘Futures/Dyfodol’ STEM programme drives our local
education engagement:
235 events at Primary, Secondary and Higher Education
with c.19,000 pupils reached
Technical & Further Education
Good relationships with key local & regional, national Colleges & Universities
Horizon Engineering apprenticeship scheme / future Construction apprenticeships via supply chain
£2m invested in our own Technical Apprenticeship scheme
21 apprentices, with an additional 12 places open for 2018/19
11. 25/05/2018 Page 11
NOT PROTECTIVELY MARKED
NOT PROTECTIVELY MARKED
Our Supply Chain approach
Supply Chain Charter outlining high level commitment
Maximise opportunities in the locality and north Wales,
wider UK – North Wales/Northern Powerhouse
Create a sustainable supply chain
Promote good performance
Supplier Code of Conduct develops on commitments made
within Supply Chain Charter to help suppliers understand
our expectations
Develop a Wylfa Newydd Supply Chain Portal to increase
accessibility and visibility of opportunities to all tiers in the
Supply Chain
Continue to work with stakeholders on supply chain
readiness and help suppliers understand and prepare for
our requirements
Reviewing our EPC delivery partner contracting structure
Facilitate our Tier 1 partners to have direct early
engagement with suppliers
12. 25/05/2018 Page 12
NOT PROTECTIVELY MARKED
NOT PROTECTIVELY MARKED
Delivery partnership review & achievements
Advanced the design and development of Wylfa Newydd
Complete Site optimisation review
Cost Verification
Generic Design Assessment
Support Development Consent Order