An Integer Linear Programming
 Representation for DataCenter
    Power-Aware Management
       -ILP implementation and
               Heuristic design




                    Ioanna Tsalouchidou
                    Arinto Murdopo
                    Josep Subirats


                    Communication Networks Optimization
                     2012
Table of Contents
1.     Introduction .......................................................................................................................................... 4
2.     ILP problem formulation ....................................................................................................................... 5
     2.1.     Problem satement ........................................................................................................................ 5
     2.2.     Scheduling Approach .................................................................................................................... 5
     2.3.     Revenue, Power cost, Migration cost and Quality of Service as factors ...................................... 7
     2.4.     The final Model ............................................................................................................................. 7
3.     Metaheuristic Design .......................................................................................................................... 10
     3.1.     GRASP Overview ......................................................................................................................... 10
     3.2.     GRASP Heuristic Implementation ............................................................................................... 11
     3.3.     Random Job Choosing improvement .......................................................................................... 12
4.     Dataset Generation ............................................................................................................................. 13
     4.1.     Node capacity array generation.................................................................................................. 13
     4.2.     Min/Max job CPU requirement array generation....................................................................... 13
5.     Experiment Result ............................................................................................................................... 14
     5.1.     Experiment Platform and Configuration ..................................................................................... 14
     5.2.     Execution Time............................................................................................................................ 14
     5.3.     GRASP Heuristic Alpha Value ...................................................................................................... 15
     5.4.     GRASP Heuristic Solution Rate Quality ....................................................................................... 18
     5.5.     Maximum Benefit Comparison - CPLEX and GRASP Heuristic .................................................... 19
6.     Conclusions ......................................................................................................................................... 21
7.     Future Work ........................................................................................................................................ 22
     7.1.     Implementation of the Local Search Phase of GRASP ................................................................ 22
     7.2.     Simulations with Multiple Problem Instances ............................................................................ 22
8.     References .......................................................................................................................................... 24




2
Table of Figures
Figure 1: Scheduling problem ....................................................................................................................... 5
Figure 2: Job scheduling ................................................................................................................................ 6
Figure 3: Simple scheduling approach .......................................................................................................... 6
Figure 4: Final scheduling ILP model ............................................................................................................. 8
Figure 5: General GRASP algorithm ............................................................................................................ 10
Figure 6: Job's benefit evaluation ............................................................................................................... 11
Figure 7: Execution time of the CPLEX solution .......................................................................................... 14
Figure 8: Execution time for 100H200J R .................................................................................................... 15
Figure 9: NR GRASP Heuristic results .......................................................................................................... 16
Figure 10: R GRASP Heuristic results .......................................................................................................... 17
Figure 11: Normalized benefit over time for NR GRASP Heuristic.............................................................. 18
Figure 12: Normalized benefit over time for R GRASP Heuristic ................................................................ 19
Figure 13: CPLEX and R/NR GRASP Heuristic results .................................................................................. 20
Figure 14: Possible local search phase approach........................................................................................ 22




3
1. Introduction

This project is based on the paper “An Integer Linear Programming Representation for DataCenter
Power-Aware Management” [1]. This paper describes the problem of the placement of jobs in a data-
centre in order to maximize its benefit, while taking into account the revenue obtained for executing the
jobs, SLA penalization costs, migration costs and energy consumption costs.

In this project, the integer linear problem described in the aforementioned paper has been
implemented using IBM ILOG CPLEX, in order to be able to obtain the optimal solution of different
problem instances. The main contribution of this project has been the implementation of a GRASP
metaheuristic (with two variants) which tries to find a good solution to the same problem in much less
time than the original ILP. The metaheuristic has been implemented using Java, and has been tested and
compared against the results provided by the CPLEX ILP implementation.

The structure of this document is as follows. Section 2 summarizes the problem statement as described
in [1]. In Section 3, an overview of the GRASP heuristic is provided, along with an explanation on the
implemented metaheuristic. Closely related to Section 3, Section 4 explains the dataset generation
procedure, which is used to run the simulations. Performance and quality results of the metaheuristic
are presented in Section 5. Finally, conclusions on the work done are exposed in Section 6, while in
Section 7 the possible improvements which could be made on it are envisioned.




4
2. ILP problem formulation

2.1.   Problem satement

In the proposed paper a data-centre is modelled as a set of physical machines, processors and jobs. For
each element a set of constraints have to be accomplished in order to be coherent with the model.

The solution to the problem comes when we find an optimal way to assign resources (in the paper, just
the number of required CPUs is considered) to jobs keeping in mind the electrical power consumption of
the resources, the migration costs (in case a job has to be moved to another physical machine), the
quality of service penalizations and finally the revenue obtained by running these jobs. In the end, a
positive benefit has to be obtained.

In this direction the above problem was defined as a function that needs to be maximized (the obtained
benefit) with the optimal balance of these four parameters. Moreover, there is a set of conditions and
restrictions that set the jobs on the resources while keeping the solution viable and real.


2.2.   Scheduling Approach

The proposed model uses the benefits of the virtualization technology in order for the data centres to
be able to run several jobs in one or multiple physical machines, to share resources and above all to be
able to migrate jobs from one machine to another. This technology enables the dynamic allocation of
jobs along with consolidation, the scheduling policy that reduces the number of used resources by
allocating the most number of jobs in the least number of machines without trade-off in the QoS or
performance.




                                       Figure 1: Scheduling problem



5
As it is shown in Figure 2, the problem that needs to be solved at each scheduling round is the decision
of which resources will be assigned to each job in order to maximize the overall benefit taking into
consideration the job revenue, the migration costs, the power costs and the tolerable QoS loss.




                                            Figure 2: Job scheduling




For the scheduling process each job is supposed to have determined resource requirements, such as
CPU quota or memory space, in order to run properly. In Figure 3 we can see the constraints of the
problem as they were primarily constructed.




                                      Figure 3: Simple scheduling approach



The scheduling problem is therefore described as a matrix (schedule[Hosts,Jobs]) describing whether a
particular job is allocated into a particular host (schedule[host,job]=1) or not (schedule[host,job]=0). The
“Unique” constraint in this case is restrictive; given that it imposes that all the jobs must be allocated in
order for the solution to be feasible. The “Capacity” constraint imposes that the capacity of each one of
the hosts must not be exceeded.


6
2.3.    Revenue, Power cost, Migration cost and Quality of Service as factors

The next step is the introduction of more constraints that will help us to model the maximization of the
economic benefit. Jobs are translated to money according to the data-centre pricing policy in the Service
Level Agreement (SLA). The Benefit equation is defined as follows: Benefit = Revenue - Costs.

In the next step towards the final model we try to focus on the problem of power cost and consumption
and the way in which we can possibly minimize it. As it is already known, the power curve for a given
host grows logarithmically, which means that in the case of two machines with many processors with
only one active processor, the consumption is much higher than one working machine with two active
processors.

In the following solution we consider that the number of CPUs in a host is a natural value so that the
scheduling will consider separately the processors of a given host. Moreover, the number of active CPUs
in a host must not surpass the maximum number of CPUs that a host has available.

Another handicap that is introduced through consolidation is the migration cost that is defined as the
cost that represents the amount of time wasted in moving a job from a host to another. During this
time, there is no revenue obtained from the execution of the job, and therefore must be subtracted
from the overall benefit.

The final step is to define the Quality of Service as an input to the scheduling problem. The system
allows some degradation in the provided QoS, as specified in the SLA. In order to improve consolidation
and reduce power consumption, QoS can be relaxed introducing at the same time a penalization. This
penalization is specified in Service Level Agreement. Therefore, the schedule can be altered while taking
into consideration these economic consequences.

In order to be able to measure the level of accomplishment of the job goals and the SLA, the authors
define the Health function which in its implementation is a linear function that varies from cpumin to
cpumax. In other words, a CPU assignment of cpumin (depends on each job) means a health of 0
(maximum QoS penalization), which equals to running the job in the minimal conditions, whereas a CPU
assignment of cpumax means a health of 1 (no QoS penalization), which equals to the optimal execution
of the job.




2.4.    The final Model

As a result of all the above steps the final model is obtained as in Figure 4. This is also the final version of
the model that has been implemented in CPLEX.




7
Figure 4: Final scheduling ILP model



The presented ILP is based on the primary model, but incorporates the aspects described in Section 2.3.
Further details about the complete ILP model, the constraints, the variables and the parameters that are
specified in the above formulas are in depth explained in [1]

It is worth mentioning that in the paper, while the problem is formulated, a variable multiplication
appears. This converts the problem into a non-linear problem, which is harder and slower to solve. In
order to solve this problem, the author decomposes the constraint which took care of not exceeding the
maximum CPUs of each physical machine into several constraints (“MaxCPU”, “Capacity”, and


8
“QosAux1-4”). This also introduces the “quota” variable. Refer to *1+ for more details of this
decomposition.

It is also interesting to observe that the author introduced a relaxation in the “Unique” constraint in the
final problem model. In this case, it is not mandatory to schedule all the jobs in order for the solution to
be feasible. Therefore, in this case some jobs might not be scheduled in a scheduling round.




9
3. Metaheuristic Design

3.1.    GRASP Overview

The chosen metaheuristic for this project has been the GRASP (Greedy RAndomized Search Procedure)
metaheuristic. This metaheuristic consists in building as many feasible solutions as specified by a
maximum number of iterations (construction phase) and evaluate its benefit using the objective
function. In each of these solutions, a local search evaluation (local search phase) is applied in order to
find better solutions starting from a feasible solution. From all the evaluated solutions, the one with
maximum (when maximizing) or minimum (when minimizing) benefit is selected. This algorithm can be
observed in Figure 5.




                                      Figure 5: General GRASP algorithm



This metaheuristic introduces randomization in the construction phase. This phase starts with an empty
Candidate List (CL) of possible placements for a given job (following the example of our problem). Then
using a greedy function which evaluates the individual benefit incurred by this particular placement, the
CL is filled. From this list, a Restricted Candidate List (RCL) containing the placements whose benefit
accomplishes Equation 1 is built. From the RCL, an element is selected randomly.



                                                 Equation 1


This randomness assures that different solutions will be built each time, although its “amount of
randomness” depends on Alpha. The RCL size depends on Alpha. If Alpha=0, it has a pure deterministic
behaviour as it always selects the best placement (only one element in the RCL). On the other hand, a
value of Alpha=1 has a completely random behaviour (all the combinations are present in the RCL),
given that any combination, regardless of its obtained benefit, can be selected.




10
3.2.    GRASP Heuristic Implementation

In this project, the general GRASP design has been followed. Although the local search phase has not
been implemented, a possible way to do it has been envisioned and is explained in the Future Work
section.

The interesting part of the GRASP design is the Greedy Function. In our case, the algorithm evaluates the
individual benefit of placing each one of the jobs in all of the hosts of the infrastructure. The individual
benefit takes into account the amount of revenue obtained by running a given job, incurred power
consumption costs of the scheduled job, QoS penalties when it’s not given the maximum amount of CPU
it requires and migration costs in case it is moved from one host in the initial schedule to another one in
the new one.

As an initial approach, all the jobs are evaluated in order (first job number 1, then job number 2 and so
on). Given that each job has a minimum and maximum CPU requirements, each placement to a
particular host is evaluated with all the possible CPU assignments. Note that each of these CPU
assignments will provide a different benefit, given that less power will be used but also the incurred SLA
penalty will be different. In case a particular placement is not possible because the destination host
doesn’t have enough free CPUs, an individual benefit of negative infinity is assigned. In this case, this
combination is not included in the Candidate List, because it would greatly modify the threshold which is
used later to build the Reduced Candidate List.




                                       Figure 6: Job's benefit evaluation



11
When all the possible placements of a particular job have been evaluated, the CL is reduced into the RCL
as explained in Section 3.1. Then, one element is picked up randomly, which will be the chosen
combination. As in the general GRASP implementation, the greedy behaviour is introduced when
selecting the adopted combination from the RCL, given that it is a random selection. This combination
specifies the destination host for a particular job, as well as the assigned CPU (which is in the range
between its minimum and maximum required CPU).

When all the jobs have been evaluated and the scheduling matrix has been built, it is returned to the
general GRASP algorithm, along with the global benefit of this particular placement. If the obtained
placement achieves a better benefit than previous placements, it is stored along with its benefit.




3.3.    Random Job Choosing improvement

The first approach considered in this project took each of the jobs to be placed from a list, where the
jobs were always kept in the same order. However, it is clear that the last jobs in the list will have less
possible hosts to be placed and less possible CPU assignments, as some of the hosts may be already full
with other jobs. Therefore, the first jobs in the queue have advantage over the last ones. We will refer
this approach as NR GRASP heuristic in subsequent sections.

Taking this into account, a possible way to fix this is to pick the jobs to be placed from the job list in
random order. Then, even if a job has had disadvantage in an iteration of the GRASP heuristic because it
has been evaluated at the last place, it might be evaluated in the first place in another iteration. We will
refer this second approach as the R GRASP heuristic throughout this document.




12
4. Dataset Generation

4.1.   Node capacity array generation

In order to be able to generate large datasets to perform large simulations, an automatic way to
generate the parameters has been implemented. One of these parameters is the capacity in terms of
number of CPUs of each host. Although the model exposed in the paper only considered up-to-4 CPU
nodes, we have extended the power model in order to cope with up-to-8 CPU nodes in order to obtain
richer results.

The capacity of each node is expressed as an array where each position represents the CPU capacity of
host “i”. It can have a capacity of 1, 2, 4 or 8 CPUs, which is assigned randomly.




4.2.   Min/Max job CPU requirement array generation

As in the CPU capacity array generation, the minimum job CPU requirement is assigned a random value
from 1 to 10. Therefore, each position of the “consMin” array represents the minimum CPU
requirement of job “j”, ranging from 1 to 9. Even though 9 and 10 CPUs are not available in any node, it
was considered that having jobs which can’t be run in the infrastructure and have to be refused was a
more realistic characterization.

Once the minimum CPU consumption array has been computed, the maximum CPU consumption array
is generated. Each job’s maximum CPU requirement is calculated as its minimum CPU requirement plus
an extra 1 or 2 CPUs, chosen randomly.




13
5. Experiment Result

5.1.   Experiment Platform and Configuration

We used same computer to execute our CPLEX and Java heuristic code. It was a Dell Latitude E6410 with
Intel i7 M640 @2.8 GHz CPU, 8 Gigabytes of RAM, and 64-bit Windows 7 Operating System. We used
IBM ILOG CPLEX Optimization Studio 12.4 and our GRASP Java heuristic code was executed on top of
JRE 1.6.0_24-b07 from Oracle.

We simulated the following problem sizes: 5H10J (5-hosts-10-jobs), 15H30J, 20H40J, 30H60J, 40H80J
and 100H200J. For each problem size, we experimented with multiple Alpha ( ) values ranging from 0 to
1, with steps of 0.1 (0, 0.1, 0.2, 0.3 …. 1).

For the heuristic executions, we used multiple iteration configurations as follows: 10, 100, 1000, 10000
and 100000 iterations. We measured different performance aspects of both R and NR heuristic types.
The obtained results are discussed in the following subsections.




5.2.   Execution Time

First of all, we measured the execution time in CPLEX for different problem sizes and compared them. As
expected, CPLEX takes a very long time to complete when the problem size is big. In our case, CPLEX was
able to complete a 20H40J instance in 228 seconds.When the problem size was increased to 30H60J,
CPLEX didn’t finish its execution, even though we let it run for 66 hours. We used the available CPLEX
results to measure the quality of the GRASP heuristic solution. Figure 7 shows the execution time of our
CPLEX solution.




                                Figure 7: Execution time of the CPLEX solution



14
Next, we continued to measure the execution time of the GRASP heuristic. GRASP is able to run for
larger problem sizes. Its execution time strongly depends on the number of iterations and the
configured problem size. We measured the execution time for all of the aforementioned problem sizes
and iteration configurations. In Figure 8, the execution time for the highest problem size of 100H200J is
shown.




                                   Figure 8: Execution time for 100H200J R



The x-axis is displayed in logarithmic scale. In normal scale, the heuristic execution time has a linear
correlation with the number of iterations. It is interesting to observe that the GRASP heuristic performs
much better than CPLEX in terms of execution time. For example, the execution time of the GRASP
heuristic with 100H200J and 100000 iterations is 80 seconds faster compared to CPLEX with 20H40J.

However, the superiority of the GRASP heuristic can not be evaluated only in terms of execution time, it
also has to be taken into account the quality of the obtained solution. Therefore we also need to
measure the performance of our GRASP heuristic in terms of solution quality. This aspect will be
discussed in section 5.5.




5.3.    GRASP Heuristic Alpha Value

In this section, we obtain the optimal Alpha value for the GRASP heuristic. For every problem size and
every iteration, we obtained the diagram depicting the relation between Alpha, Benefit, Number of
Iterations, and type of GRASP heuristic. NR refers to not-random job selection GRASP (NR GRASP
heuristic), and R refers to random job selection GRASP (R GRASP heuristic).




15
Figure 9: NR GRASP Heuristic results



Figure 9 shows the results for the NR GRASP heuristic with four types of problem sizes. Based on these
results, it is shown that maximum benefit will be achieved with low Alpha values (0.1, 0.2, 0.3). We also
can see that the more the number of the iterations, the higher the obtained benefit is. As it was
explained in Section 3.1, a value of Alpha=0 has a completely deterministic behaviour, given that only
the combination with the best benefit is chosen when building the Reduced Candidate List, and
therefore is always the one selected in the end. Note that no randomness is introduced in the job
choosing either, as they are selected always in order. This behaviour can be clearly observed in the
previous figure: regardless of the number of iterations, the obtained benefit is exactly the same.




16
Figure 10: R GRASP Heuristic results



Figure 10 shows the results for the R GRASP heuristic with four types of problem sizes, the same ones
that we used to measure NR GRASP heuristic Alpha value. They show the same trend as NR GRASP
heuristic whereby low Alpha values (0, 0.1, 0.2, 0.3) result in higher benefit compared to other Alpha
values. The number of iterations also determine the quality of the benefit and the higher the iteration,
the higher the obtained benefit value. It is also interesting to note that for high problem sizes (30H60J,
40H80J, 100H200J), the highest value is obtained when Alpha is 0. This result means that early
randomization in picking up jobs to be evaluated is more prevalent in producing better results than
randomization in the selection of candidates from the Restricted Candidate List (whose size depends on
the value of Alpha).

Both NR and R GRASP heuristic therefore obtain better benefits when the Alpha Value is small, typically
between 0 to 0.3, both included.




17
5.4.   GRASP Heuristic Solution Rate Quality

In this section, we analyze how fast our GRASP heuristic algorithm reaches some significant percentages
of the best solution it provides. We define “significant percentages” as more than 90% of the best
solution that can be found using GRASP (sometimes, it reaches the optimal solution).

To perform this analysis, we used the largest problem size configuration (100H200J). For NR GRASP
heuristic, we used an Alpha value of 0.1 and 100000 iterations, while for R GRASP heuristic we used an
Alpha value of 0 and 100000 iterations.




                         Figure 11: Normalized benefit over time for NR GRASP Heuristic



Figure 11 shows the normalized benefit over time for the NR GRASP heuristic. The y-axis is the
normalized benefit, which is the percentage of benefit compared to maximum benefit that can be
obtained in this configuration. Note that since we were not able to use CPLEX to obtain the best benefit
for 100H200J, we used the maximum benefit obtained by NR GRASP heuristic to calculate the
normalized benefit. The x-axis denotes the time in mili-seconds. From the figure, we observe that within
12.377 seconds, our NR GRASP heuristic is able to reach around 99.95% of its maximum benefit.




18
Figure 12: Normalized benefit over time for R GRASP Heuristic



Figure 12 shows the results of the R GRASP heuristic. As in the NR GRASP heuristic results, we used the
maximum benefit obtained by the R GRASP heuristic to calculate the normalized benefit. The R GRASP
heuristic is able to reach 93% of maximum benefit within 0.617 seconds and 97.3% of maximum benefit
within 8.813 seconds.

Both NR and R GRASP heuristics have a very good performance in terms of speed to reach more than
90% of its maximum benefit.




5.5.    Maximum Benefit Comparison - CPLEX and GRASP Heuristic

CPLEX is guaranteed to obtain the optimal result for our problem statements. However, it has a
drawback in its execution time. CPLEX execution time is very long and it is not affordable for big problem
sizes. On the other hand, heuristics in general have smaller execution times but their results should be
compared to those of CPLEX in order to evaluate its quality. Figure 13 shows the comparison between
CPLEX and GRASP heuristic results for multiple problem sizes. It also presents two different instances of
R GRASP heuristics, one with 10000 iterations and the other with 100000 iterations.




19
Figure 13: CPLEX and R/NR GRASP Heuristic results



For the smallest problem size (5H10J), all of them have the same maximum benefit. However, at 10H20J,
we already observe that NR GRASP with 100000 iterations is not able to reach the optimal solution
obtained by CPLEX. But R GRASP with 10000 iterations and 100000 iterations managed to produce
CPLEX’s optimal benefit values. The same trend is observed for 15H30J problem size, but things started
to get interesting in 20H40J where R GRASP with 10000 iterations was not able to produce maximum
value produced by CPLEX. Here we can observe that the number of iterations also affect the maximum
obtained benefit. We also can claim that our R GRASP heuristic produces good results, and its obtained
maximum benefit equals to the CPLEX’s optimal benefit for all the simulations where CPLEX data was
available.

For bigger problem sizes (30H60J, 40H80J, 100H200J) we were not able to obtain CPLEX results due to its
extremely long execution times. We observe that R GRASP heuristic with 100000 iterations produces the
maximum benefit compared to the other configurations of the GRASP heuristic. Execution time of
100000-iteration-R GRASP heuristic is around 5 minutes and it is still reasonable.We could not confirm
whether the resulting value is the optimal benefit value but based on good comparison results with
CPLEX for smaller problem sizes, we are assured that the resulting value is pretty good also. In this case,
we can improve the quality of the solution by increasing the number of iterations if we have enough
time and resources to perform that.




20
6. Conclusions

In this project, we have implemented an ILP problem for data-center job scheduling and management.
We used IBM ILOG CPLEX to solve our ILP model. We also implemented two types of GRASP heuristic to
solve the scheduling problem, they are Non Random Job Selection GRASP (NR GRASP heuristic) and
Random Job Selection GRASP (R GRASP heuristic). During the GRASP heuristic methods implementation,
we found that complex ILP restrictions or constraints can be translated into relatively easy heuristic Java
code.

R GRASP heuristic performs better than NR GRASP heuristic. For four small problem sizes that CPLEX is
able to produce maximum benefit, we found that R GRASP heuristic with 100000 iteration also managed
to obtain CPLEX’s optimal benefit. However, NR GRASP heuristic is only able to produce around 83.5% of
the maximum benefit for 15H30J and 88.11% of the maximum benefit for 10H20J case.

In both GRASP implementation, lower Alpha values produce better results. And interestingly, for R
GRASP heuristic, the best result is obtained when Alpha is 0. We also observe that more iterations will
achieve better results, but the execution time will increase.

Regarding the scalability of the solution, based on our experiment, CPLEX does not really scale well as its
execution time grows exponentially. When we increased the problem sizes, CPLEX was not able to finish
its optimization process although we let it run for 66 hours. On the other hand, GRASP heuristic scales
well. We were able to use it to solve the problem for bigger problem sizes with acceptable times and
solution qualities. With the biggest problem size that CPLEX can run, R GRASP heuristic is still able to find
the same benefit as CPLEX, which is the optimal one.




21
7. Future Work

7.1.   Implementation of the Local Search Phase of GRASP

We could further improve our implementation of the GRASP heuristic by including the Local-Search
phase in our heuristic. One way to implement the Local-Search is to perform benefit comparisons
between the solution obtained by the Greedy Function and a modification of this same solution in which
some jobs are not migrated between nodes. Refer to Figure 14. After the Greedy Function obtains a
New Schedule, we create local search candidate (a neighbour of the obtained solution) where Job 1 and
Job 5 are not migrated with respect to the Old Schedule. We can repeat this process by producing
several local search candidates (neighbours of the original solution) and compare their results with the
original New Schedule obtained by the Greedy Function.




                                Figure 14: Possible local search phase approach




7.2.   Simulations with Multiple Problem Instances

When evaluating the performance and quality of the solutions obtained by the GRASP heuristic, only
one problem instance for each problem size was executed. This means that only one set of parameters



22
(CPUs per host, minimum and maximum CPU requirements per job) was generated to perform the
simulations for each problem size. In order to have a more realistic view of the GRASP performance,
multiple sets of parameters for a given problem size could be generated, and evaluate the performance
of the heuristic for different inputs of the same size.




23
8. References

[1] Josep Ll. Berral, Ricard Gavaldà, Jordi Torres. “An Integer Linear Programming Representation for
DataCenter Power-Aware Management” Research Report number: UPC-LSI-10-21-R, November 2010.




24

More Related Content

What's hot

Scheduling Divisible Jobs to Optimize the Computation and Energy Costs
Scheduling Divisible Jobs to Optimize the Computation and Energy CostsScheduling Divisible Jobs to Optimize the Computation and Energy Costs
Scheduling Divisible Jobs to Optimize the Computation and Energy Costsinventionjournals
 
Distributed Feature Selection for Efficient Economic Big Data Analysis
Distributed Feature Selection for Efficient Economic Big Data AnalysisDistributed Feature Selection for Efficient Economic Big Data Analysis
Distributed Feature Selection for Efficient Economic Big Data AnalysisIRJET Journal
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 
Quality of Service based Task Scheduling Algorithms in Cloud Computing
Quality of Service based Task Scheduling Algorithms in  Cloud Computing  Quality of Service based Task Scheduling Algorithms in  Cloud Computing
Quality of Service based Task Scheduling Algorithms in Cloud Computing IJECEIAES
 
22). smlevel energy eff-dynamictaskschedng
22). smlevel energy eff-dynamictaskschedng22). smlevel energy eff-dynamictaskschedng
22). smlevel energy eff-dynamictaskschedngPoornima_Rajanna
 
Efficient Planning and Offline Routing Approaches for IP Networks
Efficient Planning and Offline Routing Approaches for IP NetworksEfficient Planning and Offline Routing Approaches for IP Networks
Efficient Planning and Offline Routing Approaches for IP NetworksEM Legacy
 
Energy efficient-resource-allocation-in-distributed-computing-systems
Energy efficient-resource-allocation-in-distributed-computing-systemsEnergy efficient-resource-allocation-in-distributed-computing-systems
Energy efficient-resource-allocation-in-distributed-computing-systemsCemal Ardil
 
Network reconfiguration to improve reliability indices and efficiency in dist...
Network reconfiguration to improve reliability indices and efficiency in dist...Network reconfiguration to improve reliability indices and efficiency in dist...
Network reconfiguration to improve reliability indices and efficiency in dist...INFOGAIN PUBLICATION
 
Competitive Demand Response Trading in Electricity Markets: Aggregator and En...
Competitive Demand Response Trading in Electricity Markets: Aggregator and En...Competitive Demand Response Trading in Electricity Markets: Aggregator and En...
Competitive Demand Response Trading in Electricity Markets: Aggregator and En...Nur Mohammad
 
A Review on Scheduling in Cloud Computing
A Review on Scheduling in Cloud ComputingA Review on Scheduling in Cloud Computing
A Review on Scheduling in Cloud Computingijujournal
 
IRJET- A Statistical Approach Towards Energy Saving in Cloud Computing
IRJET-  	  A Statistical Approach Towards Energy Saving in Cloud ComputingIRJET-  	  A Statistical Approach Towards Energy Saving in Cloud Computing
IRJET- A Statistical Approach Towards Energy Saving in Cloud ComputingIRJET Journal
 
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit...
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit...A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit...
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit...IJAPEJOURNAL
 
Hybrid Task Scheduling Approach using Gravitational and ACO Search Algorithm
Hybrid Task Scheduling Approach using Gravitational and ACO Search AlgorithmHybrid Task Scheduling Approach using Gravitational and ACO Search Algorithm
Hybrid Task Scheduling Approach using Gravitational and ACO Search AlgorithmIRJET Journal
 
SearsonGP_PLS_PhD_thesis
SearsonGP_PLS_PhD_thesisSearsonGP_PLS_PhD_thesis
SearsonGP_PLS_PhD_thesisDominic Searson
 

What's hot (14)

Scheduling Divisible Jobs to Optimize the Computation and Energy Costs
Scheduling Divisible Jobs to Optimize the Computation and Energy CostsScheduling Divisible Jobs to Optimize the Computation and Energy Costs
Scheduling Divisible Jobs to Optimize the Computation and Energy Costs
 
Distributed Feature Selection for Efficient Economic Big Data Analysis
Distributed Feature Selection for Efficient Economic Big Data AnalysisDistributed Feature Selection for Efficient Economic Big Data Analysis
Distributed Feature Selection for Efficient Economic Big Data Analysis
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
Quality of Service based Task Scheduling Algorithms in Cloud Computing
Quality of Service based Task Scheduling Algorithms in  Cloud Computing  Quality of Service based Task Scheduling Algorithms in  Cloud Computing
Quality of Service based Task Scheduling Algorithms in Cloud Computing
 
22). smlevel energy eff-dynamictaskschedng
22). smlevel energy eff-dynamictaskschedng22). smlevel energy eff-dynamictaskschedng
22). smlevel energy eff-dynamictaskschedng
 
Efficient Planning and Offline Routing Approaches for IP Networks
Efficient Planning and Offline Routing Approaches for IP NetworksEfficient Planning and Offline Routing Approaches for IP Networks
Efficient Planning and Offline Routing Approaches for IP Networks
 
Energy efficient-resource-allocation-in-distributed-computing-systems
Energy efficient-resource-allocation-in-distributed-computing-systemsEnergy efficient-resource-allocation-in-distributed-computing-systems
Energy efficient-resource-allocation-in-distributed-computing-systems
 
Network reconfiguration to improve reliability indices and efficiency in dist...
Network reconfiguration to improve reliability indices and efficiency in dist...Network reconfiguration to improve reliability indices and efficiency in dist...
Network reconfiguration to improve reliability indices and efficiency in dist...
 
Competitive Demand Response Trading in Electricity Markets: Aggregator and En...
Competitive Demand Response Trading in Electricity Markets: Aggregator and En...Competitive Demand Response Trading in Electricity Markets: Aggregator and En...
Competitive Demand Response Trading in Electricity Markets: Aggregator and En...
 
A Review on Scheduling in Cloud Computing
A Review on Scheduling in Cloud ComputingA Review on Scheduling in Cloud Computing
A Review on Scheduling in Cloud Computing
 
IRJET- A Statistical Approach Towards Energy Saving in Cloud Computing
IRJET-  	  A Statistical Approach Towards Energy Saving in Cloud ComputingIRJET-  	  A Statistical Approach Towards Energy Saving in Cloud Computing
IRJET- A Statistical Approach Towards Energy Saving in Cloud Computing
 
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit...
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit...A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit...
A Simple Approach for Optimal Generation Scheduling to Maximize GENCOs Profit...
 
Hybrid Task Scheduling Approach using Gravitational and ACO Search Algorithm
Hybrid Task Scheduling Approach using Gravitational and ACO Search AlgorithmHybrid Task Scheduling Approach using Gravitational and ACO Search Algorithm
Hybrid Task Scheduling Approach using Gravitational and ACO Search Algorithm
 
SearsonGP_PLS_PhD_thesis
SearsonGP_PLS_PhD_thesisSearsonGP_PLS_PhD_thesis
SearsonGP_PLS_PhD_thesis
 

Viewers also liked

климат контроль 2 школа
климат контроль 2 школаклимат контроль 2 школа
климат контроль 2 школаspareworld
 
Kerala honeymoon holiday
Kerala honeymoon holiday Kerala honeymoon holiday
Kerala honeymoon holiday Justeat India
 
Social loafing (1979)
Social loafing (1979)Social loafing (1979)
Social loafing (1979)adamthorpe
 
Integer programming
Integer programmingInteger programming
Integer programmingChan Rizky
 
Integer Programming, Gomory
Integer Programming, GomoryInteger Programming, Gomory
Integer Programming, GomoryAVINASH JURIANI
 
Introduction to Algorithms
Introduction to AlgorithmsIntroduction to Algorithms
Introduction to AlgorithmsVenkatesh Iyer
 
Linear Programming 1
Linear Programming 1Linear Programming 1
Linear Programming 1irsa javed
 

Viewers also liked (10)

климат контроль 2 школа
климат контроль 2 школаклимат контроль 2 школа
климат контроль 2 школа
 
Kerala honeymoon holiday
Kerala honeymoon holiday Kerala honeymoon holiday
Kerala honeymoon holiday
 
Social loafing (1979)
Social loafing (1979)Social loafing (1979)
Social loafing (1979)
 
Integer programming
Integer programmingInteger programming
Integer programming
 
Integer Programming, Gomory
Integer Programming, GomoryInteger Programming, Gomory
Integer Programming, Gomory
 
Integer programming
Integer programmingInteger programming
Integer programming
 
Introduction to Algorithms
Introduction to AlgorithmsIntroduction to Algorithms
Introduction to Algorithms
 
Linear Programming 1
Linear Programming 1Linear Programming 1
Linear Programming 1
 
Linear programming ppt
Linear programming pptLinear programming ppt
Linear programming ppt
 
Linear Programming
Linear ProgrammingLinear Programming
Linear Programming
 

Similar to An Integer Programming Representation for Data Center Power-Aware Management - Report

My "Grain Motion Detection" Project
My "Grain Motion Detection" ProjectMy "Grain Motion Detection" Project
My "Grain Motion Detection" Projectsaveli4
 
bachelors_thesis_stephensen1987
bachelors_thesis_stephensen1987bachelors_thesis_stephensen1987
bachelors_thesis_stephensen1987Hans Jacob Teglbj
 
[Evaldas Taroza - Master thesis] Schema Matching and Automatic Web Data Extra...
[Evaldas Taroza - Master thesis] Schema Matching and Automatic Web Data Extra...[Evaldas Taroza - Master thesis] Schema Matching and Automatic Web Data Extra...
[Evaldas Taroza - Master thesis] Schema Matching and Automatic Web Data Extra...Evaldas Taroza
 
CRM EHP3 landscape guide
CRM EHP3 landscape guide CRM EHP3 landscape guide
CRM EHP3 landscape guide SK Kutty
 
SocioTechnical-systems-sim
SocioTechnical-systems-simSocioTechnical-systems-sim
SocioTechnical-systems-simRub Afonso
 
Potential Solutions Co Existence
Potential Solutions   Co ExistencePotential Solutions   Co Existence
Potential Solutions Co ExistenceRoman Agaev
 
FlavioGiobergia_2016_FinalReport
FlavioGiobergia_2016_FinalReportFlavioGiobergia_2016_FinalReport
FlavioGiobergia_2016_FinalReportFlavio Giobergia
 
Furniture shop management system project report
Furniture shop management system project reportFurniture shop management system project report
Furniture shop management system project reportMaiwandTechnologix
 
ProjectResearchReport2009
ProjectResearchReport2009ProjectResearchReport2009
ProjectResearchReport2009Ibrahim Hejab
 
Hadoop as an extension of DW
Hadoop as an extension of DWHadoop as an extension of DW
Hadoop as an extension of DWSidi yazid
 

Similar to An Integer Programming Representation for Data Center Power-Aware Management - Report (20)

Draft Deliverable : IT Cost Recovery Process Implementation Playbook
Draft Deliverable : IT Cost Recovery Process Implementation PlaybookDraft Deliverable : IT Cost Recovery Process Implementation Playbook
Draft Deliverable : IT Cost Recovery Process Implementation Playbook
 
My "Grain Motion Detection" Project
My "Grain Motion Detection" ProjectMy "Grain Motion Detection" Project
My "Grain Motion Detection" Project
 
CS4099Report
CS4099ReportCS4099Report
CS4099Report
 
bachelors_thesis_stephensen1987
bachelors_thesis_stephensen1987bachelors_thesis_stephensen1987
bachelors_thesis_stephensen1987
 
[Evaldas Taroza - Master thesis] Schema Matching and Automatic Web Data Extra...
[Evaldas Taroza - Master thesis] Schema Matching and Automatic Web Data Extra...[Evaldas Taroza - Master thesis] Schema Matching and Automatic Web Data Extra...
[Evaldas Taroza - Master thesis] Schema Matching and Automatic Web Data Extra...
 
FULLTEXT01.pdf
FULLTEXT01.pdfFULLTEXT01.pdf
FULLTEXT01.pdf
 
CRM EHP3 landscape guide
CRM EHP3 landscape guide CRM EHP3 landscape guide
CRM EHP3 landscape guide
 
Milan_thesis.pdf
Milan_thesis.pdfMilan_thesis.pdf
Milan_thesis.pdf
 
thesis-2005-029
thesis-2005-029thesis-2005-029
thesis-2005-029
 
SocioTechnical-systems-sim
SocioTechnical-systems-simSocioTechnical-systems-sim
SocioTechnical-systems-sim
 
Final Report, Group 4
Final Report, Group 4Final Report, Group 4
Final Report, Group 4
 
Potential Solutions Co Existence
Potential Solutions   Co ExistencePotential Solutions   Co Existence
Potential Solutions Co Existence
 
FlavioGiobergia_2016_FinalReport
FlavioGiobergia_2016_FinalReportFlavioGiobergia_2016_FinalReport
FlavioGiobergia_2016_FinalReport
 
ITSM Approach for Clouds
 ITSM Approach for Clouds ITSM Approach for Clouds
ITSM Approach for Clouds
 
Furniture shop management system project report
Furniture shop management system project reportFurniture shop management system project report
Furniture shop management system project report
 
Gildenblatt, Robbie 12-17-12
Gildenblatt, Robbie 12-17-12Gildenblatt, Robbie 12-17-12
Gildenblatt, Robbie 12-17-12
 
ProjectResearchReport2009
ProjectResearchReport2009ProjectResearchReport2009
ProjectResearchReport2009
 
Hadoop as an extension of DW
Hadoop as an extension of DWHadoop as an extension of DW
Hadoop as an extension of DW
 
Bslsg131en 1
Bslsg131en 1Bslsg131en 1
Bslsg131en 1
 
Knapp_Masterarbeit
Knapp_MasterarbeitKnapp_Masterarbeit
Knapp_Masterarbeit
 

More from Arinto Murdopo

Distributed Decision Tree Learning for Mining Big Data Streams
Distributed Decision Tree Learning for Mining Big Data StreamsDistributed Decision Tree Learning for Mining Big Data Streams
Distributed Decision Tree Learning for Mining Big Data StreamsArinto Murdopo
 
Distributed Decision Tree Learning for Mining Big Data Streams
Distributed Decision Tree Learning for Mining Big Data StreamsDistributed Decision Tree Learning for Mining Big Data Streams
Distributed Decision Tree Learning for Mining Big Data StreamsArinto Murdopo
 
Next Generation Hadoop: High Availability for YARN
Next Generation Hadoop: High Availability for YARN Next Generation Hadoop: High Availability for YARN
Next Generation Hadoop: High Availability for YARN Arinto Murdopo
 
High Availability in YARN
High Availability in YARNHigh Availability in YARN
High Availability in YARNArinto Murdopo
 
Distributed Computing - What, why, how..
Distributed Computing - What, why, how..Distributed Computing - What, why, how..
Distributed Computing - What, why, how..Arinto Murdopo
 
An Integer Programming Representation for Data Center Power-Aware Management ...
An Integer Programming Representation for Data Center Power-Aware Management ...An Integer Programming Representation for Data Center Power-Aware Management ...
An Integer Programming Representation for Data Center Power-Aware Management ...Arinto Murdopo
 
Quantum Cryptography and Possible Attacks-slide
Quantum Cryptography and Possible Attacks-slideQuantum Cryptography and Possible Attacks-slide
Quantum Cryptography and Possible Attacks-slideArinto Murdopo
 
Quantum Cryptography and Possible Attacks
Quantum Cryptography and Possible AttacksQuantum Cryptography and Possible Attacks
Quantum Cryptography and Possible AttacksArinto Murdopo
 
Parallelization of Smith-Waterman Algorithm using MPI
Parallelization of Smith-Waterman Algorithm using MPIParallelization of Smith-Waterman Algorithm using MPI
Parallelization of Smith-Waterman Algorithm using MPIArinto Murdopo
 
Megastore - ID2220 Presentation
Megastore - ID2220 PresentationMegastore - ID2220 Presentation
Megastore - ID2220 PresentationArinto Murdopo
 
Flume Event Scalability
Flume Event ScalabilityFlume Event Scalability
Flume Event ScalabilityArinto Murdopo
 
Large Scale Distributed Storage Systems in Volunteer Computing - Slide
Large Scale Distributed Storage Systems in Volunteer Computing - SlideLarge Scale Distributed Storage Systems in Volunteer Computing - Slide
Large Scale Distributed Storage Systems in Volunteer Computing - SlideArinto Murdopo
 
Large-Scale Decentralized Storage Systems for Volunter Computing Systems
Large-Scale Decentralized Storage Systems for Volunter Computing SystemsLarge-Scale Decentralized Storage Systems for Volunter Computing Systems
Large-Scale Decentralized Storage Systems for Volunter Computing SystemsArinto Murdopo
 
Rise of Network Virtualization
Rise of Network VirtualizationRise of Network Virtualization
Rise of Network VirtualizationArinto Murdopo
 
Intelligent Placement of Datacenter for Internet Services
Intelligent Placement of Datacenter for Internet Services Intelligent Placement of Datacenter for Internet Services
Intelligent Placement of Datacenter for Internet Services Arinto Murdopo
 
Architecting a Cloud-Scale Identity Fabric
Architecting a Cloud-Scale Identity FabricArchitecting a Cloud-Scale Identity Fabric
Architecting a Cloud-Scale Identity FabricArinto Murdopo
 
Consistency Tradeoffs in Modern Distributed Database System Design
Consistency Tradeoffs in Modern Distributed Database System DesignConsistency Tradeoffs in Modern Distributed Database System Design
Consistency Tradeoffs in Modern Distributed Database System DesignArinto Murdopo
 
Distributed Storage System for Volunteer Computing
Distributed Storage System for Volunteer ComputingDistributed Storage System for Volunteer Computing
Distributed Storage System for Volunteer ComputingArinto Murdopo
 

More from Arinto Murdopo (20)

Distributed Decision Tree Learning for Mining Big Data Streams
Distributed Decision Tree Learning for Mining Big Data StreamsDistributed Decision Tree Learning for Mining Big Data Streams
Distributed Decision Tree Learning for Mining Big Data Streams
 
Distributed Decision Tree Learning for Mining Big Data Streams
Distributed Decision Tree Learning for Mining Big Data StreamsDistributed Decision Tree Learning for Mining Big Data Streams
Distributed Decision Tree Learning for Mining Big Data Streams
 
Next Generation Hadoop: High Availability for YARN
Next Generation Hadoop: High Availability for YARN Next Generation Hadoop: High Availability for YARN
Next Generation Hadoop: High Availability for YARN
 
High Availability in YARN
High Availability in YARNHigh Availability in YARN
High Availability in YARN
 
Distributed Computing - What, why, how..
Distributed Computing - What, why, how..Distributed Computing - What, why, how..
Distributed Computing - What, why, how..
 
An Integer Programming Representation for Data Center Power-Aware Management ...
An Integer Programming Representation for Data Center Power-Aware Management ...An Integer Programming Representation for Data Center Power-Aware Management ...
An Integer Programming Representation for Data Center Power-Aware Management ...
 
Quantum Cryptography and Possible Attacks-slide
Quantum Cryptography and Possible Attacks-slideQuantum Cryptography and Possible Attacks-slide
Quantum Cryptography and Possible Attacks-slide
 
Quantum Cryptography and Possible Attacks
Quantum Cryptography and Possible AttacksQuantum Cryptography and Possible Attacks
Quantum Cryptography and Possible Attacks
 
Parallelization of Smith-Waterman Algorithm using MPI
Parallelization of Smith-Waterman Algorithm using MPIParallelization of Smith-Waterman Algorithm using MPI
Parallelization of Smith-Waterman Algorithm using MPI
 
Dremel Paper Review
Dremel Paper ReviewDremel Paper Review
Dremel Paper Review
 
Megastore - ID2220 Presentation
Megastore - ID2220 PresentationMegastore - ID2220 Presentation
Megastore - ID2220 Presentation
 
Flume Event Scalability
Flume Event ScalabilityFlume Event Scalability
Flume Event Scalability
 
Large Scale Distributed Storage Systems in Volunteer Computing - Slide
Large Scale Distributed Storage Systems in Volunteer Computing - SlideLarge Scale Distributed Storage Systems in Volunteer Computing - Slide
Large Scale Distributed Storage Systems in Volunteer Computing - Slide
 
Large-Scale Decentralized Storage Systems for Volunter Computing Systems
Large-Scale Decentralized Storage Systems for Volunter Computing SystemsLarge-Scale Decentralized Storage Systems for Volunter Computing Systems
Large-Scale Decentralized Storage Systems for Volunter Computing Systems
 
Rise of Network Virtualization
Rise of Network VirtualizationRise of Network Virtualization
Rise of Network Virtualization
 
Intelligent Placement of Datacenter for Internet Services
Intelligent Placement of Datacenter for Internet Services Intelligent Placement of Datacenter for Internet Services
Intelligent Placement of Datacenter for Internet Services
 
Architecting a Cloud-Scale Identity Fabric
Architecting a Cloud-Scale Identity FabricArchitecting a Cloud-Scale Identity Fabric
Architecting a Cloud-Scale Identity Fabric
 
Consistency Tradeoffs in Modern Distributed Database System Design
Consistency Tradeoffs in Modern Distributed Database System DesignConsistency Tradeoffs in Modern Distributed Database System Design
Consistency Tradeoffs in Modern Distributed Database System Design
 
Distributed Storage System for Volunteer Computing
Distributed Storage System for Volunteer ComputingDistributed Storage System for Volunteer Computing
Distributed Storage System for Volunteer Computing
 
Apache Flume
Apache FlumeApache Flume
Apache Flume
 

Recently uploaded

URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 

Recently uploaded (20)

URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 

An Integer Programming Representation for Data Center Power-Aware Management - Report

  • 1. 2012 An Integer Linear Programming Representation for DataCenter Power-Aware Management -ILP implementation and Heuristic design Ioanna Tsalouchidou Arinto Murdopo Josep Subirats Communication Networks Optimization 2012
  • 2. Table of Contents 1. Introduction .......................................................................................................................................... 4 2. ILP problem formulation ....................................................................................................................... 5 2.1. Problem satement ........................................................................................................................ 5 2.2. Scheduling Approach .................................................................................................................... 5 2.3. Revenue, Power cost, Migration cost and Quality of Service as factors ...................................... 7 2.4. The final Model ............................................................................................................................. 7 3. Metaheuristic Design .......................................................................................................................... 10 3.1. GRASP Overview ......................................................................................................................... 10 3.2. GRASP Heuristic Implementation ............................................................................................... 11 3.3. Random Job Choosing improvement .......................................................................................... 12 4. Dataset Generation ............................................................................................................................. 13 4.1. Node capacity array generation.................................................................................................. 13 4.2. Min/Max job CPU requirement array generation....................................................................... 13 5. Experiment Result ............................................................................................................................... 14 5.1. Experiment Platform and Configuration ..................................................................................... 14 5.2. Execution Time............................................................................................................................ 14 5.3. GRASP Heuristic Alpha Value ...................................................................................................... 15 5.4. GRASP Heuristic Solution Rate Quality ....................................................................................... 18 5.5. Maximum Benefit Comparison - CPLEX and GRASP Heuristic .................................................... 19 6. Conclusions ......................................................................................................................................... 21 7. Future Work ........................................................................................................................................ 22 7.1. Implementation of the Local Search Phase of GRASP ................................................................ 22 7.2. Simulations with Multiple Problem Instances ............................................................................ 22 8. References .......................................................................................................................................... 24 2
  • 3. Table of Figures Figure 1: Scheduling problem ....................................................................................................................... 5 Figure 2: Job scheduling ................................................................................................................................ 6 Figure 3: Simple scheduling approach .......................................................................................................... 6 Figure 4: Final scheduling ILP model ............................................................................................................. 8 Figure 5: General GRASP algorithm ............................................................................................................ 10 Figure 6: Job's benefit evaluation ............................................................................................................... 11 Figure 7: Execution time of the CPLEX solution .......................................................................................... 14 Figure 8: Execution time for 100H200J R .................................................................................................... 15 Figure 9: NR GRASP Heuristic results .......................................................................................................... 16 Figure 10: R GRASP Heuristic results .......................................................................................................... 17 Figure 11: Normalized benefit over time for NR GRASP Heuristic.............................................................. 18 Figure 12: Normalized benefit over time for R GRASP Heuristic ................................................................ 19 Figure 13: CPLEX and R/NR GRASP Heuristic results .................................................................................. 20 Figure 14: Possible local search phase approach........................................................................................ 22 3
  • 4. 1. Introduction This project is based on the paper “An Integer Linear Programming Representation for DataCenter Power-Aware Management” [1]. This paper describes the problem of the placement of jobs in a data- centre in order to maximize its benefit, while taking into account the revenue obtained for executing the jobs, SLA penalization costs, migration costs and energy consumption costs. In this project, the integer linear problem described in the aforementioned paper has been implemented using IBM ILOG CPLEX, in order to be able to obtain the optimal solution of different problem instances. The main contribution of this project has been the implementation of a GRASP metaheuristic (with two variants) which tries to find a good solution to the same problem in much less time than the original ILP. The metaheuristic has been implemented using Java, and has been tested and compared against the results provided by the CPLEX ILP implementation. The structure of this document is as follows. Section 2 summarizes the problem statement as described in [1]. In Section 3, an overview of the GRASP heuristic is provided, along with an explanation on the implemented metaheuristic. Closely related to Section 3, Section 4 explains the dataset generation procedure, which is used to run the simulations. Performance and quality results of the metaheuristic are presented in Section 5. Finally, conclusions on the work done are exposed in Section 6, while in Section 7 the possible improvements which could be made on it are envisioned. 4
  • 5. 2. ILP problem formulation 2.1. Problem satement In the proposed paper a data-centre is modelled as a set of physical machines, processors and jobs. For each element a set of constraints have to be accomplished in order to be coherent with the model. The solution to the problem comes when we find an optimal way to assign resources (in the paper, just the number of required CPUs is considered) to jobs keeping in mind the electrical power consumption of the resources, the migration costs (in case a job has to be moved to another physical machine), the quality of service penalizations and finally the revenue obtained by running these jobs. In the end, a positive benefit has to be obtained. In this direction the above problem was defined as a function that needs to be maximized (the obtained benefit) with the optimal balance of these four parameters. Moreover, there is a set of conditions and restrictions that set the jobs on the resources while keeping the solution viable and real. 2.2. Scheduling Approach The proposed model uses the benefits of the virtualization technology in order for the data centres to be able to run several jobs in one or multiple physical machines, to share resources and above all to be able to migrate jobs from one machine to another. This technology enables the dynamic allocation of jobs along with consolidation, the scheduling policy that reduces the number of used resources by allocating the most number of jobs in the least number of machines without trade-off in the QoS or performance. Figure 1: Scheduling problem 5
  • 6. As it is shown in Figure 2, the problem that needs to be solved at each scheduling round is the decision of which resources will be assigned to each job in order to maximize the overall benefit taking into consideration the job revenue, the migration costs, the power costs and the tolerable QoS loss. Figure 2: Job scheduling For the scheduling process each job is supposed to have determined resource requirements, such as CPU quota or memory space, in order to run properly. In Figure 3 we can see the constraints of the problem as they were primarily constructed. Figure 3: Simple scheduling approach The scheduling problem is therefore described as a matrix (schedule[Hosts,Jobs]) describing whether a particular job is allocated into a particular host (schedule[host,job]=1) or not (schedule[host,job]=0). The “Unique” constraint in this case is restrictive; given that it imposes that all the jobs must be allocated in order for the solution to be feasible. The “Capacity” constraint imposes that the capacity of each one of the hosts must not be exceeded. 6
  • 7. 2.3. Revenue, Power cost, Migration cost and Quality of Service as factors The next step is the introduction of more constraints that will help us to model the maximization of the economic benefit. Jobs are translated to money according to the data-centre pricing policy in the Service Level Agreement (SLA). The Benefit equation is defined as follows: Benefit = Revenue - Costs. In the next step towards the final model we try to focus on the problem of power cost and consumption and the way in which we can possibly minimize it. As it is already known, the power curve for a given host grows logarithmically, which means that in the case of two machines with many processors with only one active processor, the consumption is much higher than one working machine with two active processors. In the following solution we consider that the number of CPUs in a host is a natural value so that the scheduling will consider separately the processors of a given host. Moreover, the number of active CPUs in a host must not surpass the maximum number of CPUs that a host has available. Another handicap that is introduced through consolidation is the migration cost that is defined as the cost that represents the amount of time wasted in moving a job from a host to another. During this time, there is no revenue obtained from the execution of the job, and therefore must be subtracted from the overall benefit. The final step is to define the Quality of Service as an input to the scheduling problem. The system allows some degradation in the provided QoS, as specified in the SLA. In order to improve consolidation and reduce power consumption, QoS can be relaxed introducing at the same time a penalization. This penalization is specified in Service Level Agreement. Therefore, the schedule can be altered while taking into consideration these economic consequences. In order to be able to measure the level of accomplishment of the job goals and the SLA, the authors define the Health function which in its implementation is a linear function that varies from cpumin to cpumax. In other words, a CPU assignment of cpumin (depends on each job) means a health of 0 (maximum QoS penalization), which equals to running the job in the minimal conditions, whereas a CPU assignment of cpumax means a health of 1 (no QoS penalization), which equals to the optimal execution of the job. 2.4. The final Model As a result of all the above steps the final model is obtained as in Figure 4. This is also the final version of the model that has been implemented in CPLEX. 7
  • 8. Figure 4: Final scheduling ILP model The presented ILP is based on the primary model, but incorporates the aspects described in Section 2.3. Further details about the complete ILP model, the constraints, the variables and the parameters that are specified in the above formulas are in depth explained in [1] It is worth mentioning that in the paper, while the problem is formulated, a variable multiplication appears. This converts the problem into a non-linear problem, which is harder and slower to solve. In order to solve this problem, the author decomposes the constraint which took care of not exceeding the maximum CPUs of each physical machine into several constraints (“MaxCPU”, “Capacity”, and 8
  • 9. “QosAux1-4”). This also introduces the “quota” variable. Refer to *1+ for more details of this decomposition. It is also interesting to observe that the author introduced a relaxation in the “Unique” constraint in the final problem model. In this case, it is not mandatory to schedule all the jobs in order for the solution to be feasible. Therefore, in this case some jobs might not be scheduled in a scheduling round. 9
  • 10. 3. Metaheuristic Design 3.1. GRASP Overview The chosen metaheuristic for this project has been the GRASP (Greedy RAndomized Search Procedure) metaheuristic. This metaheuristic consists in building as many feasible solutions as specified by a maximum number of iterations (construction phase) and evaluate its benefit using the objective function. In each of these solutions, a local search evaluation (local search phase) is applied in order to find better solutions starting from a feasible solution. From all the evaluated solutions, the one with maximum (when maximizing) or minimum (when minimizing) benefit is selected. This algorithm can be observed in Figure 5. Figure 5: General GRASP algorithm This metaheuristic introduces randomization in the construction phase. This phase starts with an empty Candidate List (CL) of possible placements for a given job (following the example of our problem). Then using a greedy function which evaluates the individual benefit incurred by this particular placement, the CL is filled. From this list, a Restricted Candidate List (RCL) containing the placements whose benefit accomplishes Equation 1 is built. From the RCL, an element is selected randomly. Equation 1 This randomness assures that different solutions will be built each time, although its “amount of randomness” depends on Alpha. The RCL size depends on Alpha. If Alpha=0, it has a pure deterministic behaviour as it always selects the best placement (only one element in the RCL). On the other hand, a value of Alpha=1 has a completely random behaviour (all the combinations are present in the RCL), given that any combination, regardless of its obtained benefit, can be selected. 10
  • 11. 3.2. GRASP Heuristic Implementation In this project, the general GRASP design has been followed. Although the local search phase has not been implemented, a possible way to do it has been envisioned and is explained in the Future Work section. The interesting part of the GRASP design is the Greedy Function. In our case, the algorithm evaluates the individual benefit of placing each one of the jobs in all of the hosts of the infrastructure. The individual benefit takes into account the amount of revenue obtained by running a given job, incurred power consumption costs of the scheduled job, QoS penalties when it’s not given the maximum amount of CPU it requires and migration costs in case it is moved from one host in the initial schedule to another one in the new one. As an initial approach, all the jobs are evaluated in order (first job number 1, then job number 2 and so on). Given that each job has a minimum and maximum CPU requirements, each placement to a particular host is evaluated with all the possible CPU assignments. Note that each of these CPU assignments will provide a different benefit, given that less power will be used but also the incurred SLA penalty will be different. In case a particular placement is not possible because the destination host doesn’t have enough free CPUs, an individual benefit of negative infinity is assigned. In this case, this combination is not included in the Candidate List, because it would greatly modify the threshold which is used later to build the Reduced Candidate List. Figure 6: Job's benefit evaluation 11
  • 12. When all the possible placements of a particular job have been evaluated, the CL is reduced into the RCL as explained in Section 3.1. Then, one element is picked up randomly, which will be the chosen combination. As in the general GRASP implementation, the greedy behaviour is introduced when selecting the adopted combination from the RCL, given that it is a random selection. This combination specifies the destination host for a particular job, as well as the assigned CPU (which is in the range between its minimum and maximum required CPU). When all the jobs have been evaluated and the scheduling matrix has been built, it is returned to the general GRASP algorithm, along with the global benefit of this particular placement. If the obtained placement achieves a better benefit than previous placements, it is stored along with its benefit. 3.3. Random Job Choosing improvement The first approach considered in this project took each of the jobs to be placed from a list, where the jobs were always kept in the same order. However, it is clear that the last jobs in the list will have less possible hosts to be placed and less possible CPU assignments, as some of the hosts may be already full with other jobs. Therefore, the first jobs in the queue have advantage over the last ones. We will refer this approach as NR GRASP heuristic in subsequent sections. Taking this into account, a possible way to fix this is to pick the jobs to be placed from the job list in random order. Then, even if a job has had disadvantage in an iteration of the GRASP heuristic because it has been evaluated at the last place, it might be evaluated in the first place in another iteration. We will refer this second approach as the R GRASP heuristic throughout this document. 12
  • 13. 4. Dataset Generation 4.1. Node capacity array generation In order to be able to generate large datasets to perform large simulations, an automatic way to generate the parameters has been implemented. One of these parameters is the capacity in terms of number of CPUs of each host. Although the model exposed in the paper only considered up-to-4 CPU nodes, we have extended the power model in order to cope with up-to-8 CPU nodes in order to obtain richer results. The capacity of each node is expressed as an array where each position represents the CPU capacity of host “i”. It can have a capacity of 1, 2, 4 or 8 CPUs, which is assigned randomly. 4.2. Min/Max job CPU requirement array generation As in the CPU capacity array generation, the minimum job CPU requirement is assigned a random value from 1 to 10. Therefore, each position of the “consMin” array represents the minimum CPU requirement of job “j”, ranging from 1 to 9. Even though 9 and 10 CPUs are not available in any node, it was considered that having jobs which can’t be run in the infrastructure and have to be refused was a more realistic characterization. Once the minimum CPU consumption array has been computed, the maximum CPU consumption array is generated. Each job’s maximum CPU requirement is calculated as its minimum CPU requirement plus an extra 1 or 2 CPUs, chosen randomly. 13
  • 14. 5. Experiment Result 5.1. Experiment Platform and Configuration We used same computer to execute our CPLEX and Java heuristic code. It was a Dell Latitude E6410 with Intel i7 M640 @2.8 GHz CPU, 8 Gigabytes of RAM, and 64-bit Windows 7 Operating System. We used IBM ILOG CPLEX Optimization Studio 12.4 and our GRASP Java heuristic code was executed on top of JRE 1.6.0_24-b07 from Oracle. We simulated the following problem sizes: 5H10J (5-hosts-10-jobs), 15H30J, 20H40J, 30H60J, 40H80J and 100H200J. For each problem size, we experimented with multiple Alpha ( ) values ranging from 0 to 1, with steps of 0.1 (0, 0.1, 0.2, 0.3 …. 1). For the heuristic executions, we used multiple iteration configurations as follows: 10, 100, 1000, 10000 and 100000 iterations. We measured different performance aspects of both R and NR heuristic types. The obtained results are discussed in the following subsections. 5.2. Execution Time First of all, we measured the execution time in CPLEX for different problem sizes and compared them. As expected, CPLEX takes a very long time to complete when the problem size is big. In our case, CPLEX was able to complete a 20H40J instance in 228 seconds.When the problem size was increased to 30H60J, CPLEX didn’t finish its execution, even though we let it run for 66 hours. We used the available CPLEX results to measure the quality of the GRASP heuristic solution. Figure 7 shows the execution time of our CPLEX solution. Figure 7: Execution time of the CPLEX solution 14
  • 15. Next, we continued to measure the execution time of the GRASP heuristic. GRASP is able to run for larger problem sizes. Its execution time strongly depends on the number of iterations and the configured problem size. We measured the execution time for all of the aforementioned problem sizes and iteration configurations. In Figure 8, the execution time for the highest problem size of 100H200J is shown. Figure 8: Execution time for 100H200J R The x-axis is displayed in logarithmic scale. In normal scale, the heuristic execution time has a linear correlation with the number of iterations. It is interesting to observe that the GRASP heuristic performs much better than CPLEX in terms of execution time. For example, the execution time of the GRASP heuristic with 100H200J and 100000 iterations is 80 seconds faster compared to CPLEX with 20H40J. However, the superiority of the GRASP heuristic can not be evaluated only in terms of execution time, it also has to be taken into account the quality of the obtained solution. Therefore we also need to measure the performance of our GRASP heuristic in terms of solution quality. This aspect will be discussed in section 5.5. 5.3. GRASP Heuristic Alpha Value In this section, we obtain the optimal Alpha value for the GRASP heuristic. For every problem size and every iteration, we obtained the diagram depicting the relation between Alpha, Benefit, Number of Iterations, and type of GRASP heuristic. NR refers to not-random job selection GRASP (NR GRASP heuristic), and R refers to random job selection GRASP (R GRASP heuristic). 15
  • 16. Figure 9: NR GRASP Heuristic results Figure 9 shows the results for the NR GRASP heuristic with four types of problem sizes. Based on these results, it is shown that maximum benefit will be achieved with low Alpha values (0.1, 0.2, 0.3). We also can see that the more the number of the iterations, the higher the obtained benefit is. As it was explained in Section 3.1, a value of Alpha=0 has a completely deterministic behaviour, given that only the combination with the best benefit is chosen when building the Reduced Candidate List, and therefore is always the one selected in the end. Note that no randomness is introduced in the job choosing either, as they are selected always in order. This behaviour can be clearly observed in the previous figure: regardless of the number of iterations, the obtained benefit is exactly the same. 16
  • 17. Figure 10: R GRASP Heuristic results Figure 10 shows the results for the R GRASP heuristic with four types of problem sizes, the same ones that we used to measure NR GRASP heuristic Alpha value. They show the same trend as NR GRASP heuristic whereby low Alpha values (0, 0.1, 0.2, 0.3) result in higher benefit compared to other Alpha values. The number of iterations also determine the quality of the benefit and the higher the iteration, the higher the obtained benefit value. It is also interesting to note that for high problem sizes (30H60J, 40H80J, 100H200J), the highest value is obtained when Alpha is 0. This result means that early randomization in picking up jobs to be evaluated is more prevalent in producing better results than randomization in the selection of candidates from the Restricted Candidate List (whose size depends on the value of Alpha). Both NR and R GRASP heuristic therefore obtain better benefits when the Alpha Value is small, typically between 0 to 0.3, both included. 17
  • 18. 5.4. GRASP Heuristic Solution Rate Quality In this section, we analyze how fast our GRASP heuristic algorithm reaches some significant percentages of the best solution it provides. We define “significant percentages” as more than 90% of the best solution that can be found using GRASP (sometimes, it reaches the optimal solution). To perform this analysis, we used the largest problem size configuration (100H200J). For NR GRASP heuristic, we used an Alpha value of 0.1 and 100000 iterations, while for R GRASP heuristic we used an Alpha value of 0 and 100000 iterations. Figure 11: Normalized benefit over time for NR GRASP Heuristic Figure 11 shows the normalized benefit over time for the NR GRASP heuristic. The y-axis is the normalized benefit, which is the percentage of benefit compared to maximum benefit that can be obtained in this configuration. Note that since we were not able to use CPLEX to obtain the best benefit for 100H200J, we used the maximum benefit obtained by NR GRASP heuristic to calculate the normalized benefit. The x-axis denotes the time in mili-seconds. From the figure, we observe that within 12.377 seconds, our NR GRASP heuristic is able to reach around 99.95% of its maximum benefit. 18
  • 19. Figure 12: Normalized benefit over time for R GRASP Heuristic Figure 12 shows the results of the R GRASP heuristic. As in the NR GRASP heuristic results, we used the maximum benefit obtained by the R GRASP heuristic to calculate the normalized benefit. The R GRASP heuristic is able to reach 93% of maximum benefit within 0.617 seconds and 97.3% of maximum benefit within 8.813 seconds. Both NR and R GRASP heuristics have a very good performance in terms of speed to reach more than 90% of its maximum benefit. 5.5. Maximum Benefit Comparison - CPLEX and GRASP Heuristic CPLEX is guaranteed to obtain the optimal result for our problem statements. However, it has a drawback in its execution time. CPLEX execution time is very long and it is not affordable for big problem sizes. On the other hand, heuristics in general have smaller execution times but their results should be compared to those of CPLEX in order to evaluate its quality. Figure 13 shows the comparison between CPLEX and GRASP heuristic results for multiple problem sizes. It also presents two different instances of R GRASP heuristics, one with 10000 iterations and the other with 100000 iterations. 19
  • 20. Figure 13: CPLEX and R/NR GRASP Heuristic results For the smallest problem size (5H10J), all of them have the same maximum benefit. However, at 10H20J, we already observe that NR GRASP with 100000 iterations is not able to reach the optimal solution obtained by CPLEX. But R GRASP with 10000 iterations and 100000 iterations managed to produce CPLEX’s optimal benefit values. The same trend is observed for 15H30J problem size, but things started to get interesting in 20H40J where R GRASP with 10000 iterations was not able to produce maximum value produced by CPLEX. Here we can observe that the number of iterations also affect the maximum obtained benefit. We also can claim that our R GRASP heuristic produces good results, and its obtained maximum benefit equals to the CPLEX’s optimal benefit for all the simulations where CPLEX data was available. For bigger problem sizes (30H60J, 40H80J, 100H200J) we were not able to obtain CPLEX results due to its extremely long execution times. We observe that R GRASP heuristic with 100000 iterations produces the maximum benefit compared to the other configurations of the GRASP heuristic. Execution time of 100000-iteration-R GRASP heuristic is around 5 minutes and it is still reasonable.We could not confirm whether the resulting value is the optimal benefit value but based on good comparison results with CPLEX for smaller problem sizes, we are assured that the resulting value is pretty good also. In this case, we can improve the quality of the solution by increasing the number of iterations if we have enough time and resources to perform that. 20
  • 21. 6. Conclusions In this project, we have implemented an ILP problem for data-center job scheduling and management. We used IBM ILOG CPLEX to solve our ILP model. We also implemented two types of GRASP heuristic to solve the scheduling problem, they are Non Random Job Selection GRASP (NR GRASP heuristic) and Random Job Selection GRASP (R GRASP heuristic). During the GRASP heuristic methods implementation, we found that complex ILP restrictions or constraints can be translated into relatively easy heuristic Java code. R GRASP heuristic performs better than NR GRASP heuristic. For four small problem sizes that CPLEX is able to produce maximum benefit, we found that R GRASP heuristic with 100000 iteration also managed to obtain CPLEX’s optimal benefit. However, NR GRASP heuristic is only able to produce around 83.5% of the maximum benefit for 15H30J and 88.11% of the maximum benefit for 10H20J case. In both GRASP implementation, lower Alpha values produce better results. And interestingly, for R GRASP heuristic, the best result is obtained when Alpha is 0. We also observe that more iterations will achieve better results, but the execution time will increase. Regarding the scalability of the solution, based on our experiment, CPLEX does not really scale well as its execution time grows exponentially. When we increased the problem sizes, CPLEX was not able to finish its optimization process although we let it run for 66 hours. On the other hand, GRASP heuristic scales well. We were able to use it to solve the problem for bigger problem sizes with acceptable times and solution qualities. With the biggest problem size that CPLEX can run, R GRASP heuristic is still able to find the same benefit as CPLEX, which is the optimal one. 21
  • 22. 7. Future Work 7.1. Implementation of the Local Search Phase of GRASP We could further improve our implementation of the GRASP heuristic by including the Local-Search phase in our heuristic. One way to implement the Local-Search is to perform benefit comparisons between the solution obtained by the Greedy Function and a modification of this same solution in which some jobs are not migrated between nodes. Refer to Figure 14. After the Greedy Function obtains a New Schedule, we create local search candidate (a neighbour of the obtained solution) where Job 1 and Job 5 are not migrated with respect to the Old Schedule. We can repeat this process by producing several local search candidates (neighbours of the original solution) and compare their results with the original New Schedule obtained by the Greedy Function. Figure 14: Possible local search phase approach 7.2. Simulations with Multiple Problem Instances When evaluating the performance and quality of the solutions obtained by the GRASP heuristic, only one problem instance for each problem size was executed. This means that only one set of parameters 22
  • 23. (CPUs per host, minimum and maximum CPU requirements per job) was generated to perform the simulations for each problem size. In order to have a more realistic view of the GRASP performance, multiple sets of parameters for a given problem size could be generated, and evaluate the performance of the heuristic for different inputs of the same size. 23
  • 24. 8. References [1] Josep Ll. Berral, Ricard Gavaldà, Jordi Torres. “An Integer Linear Programming Representation for DataCenter Power-Aware Management” Research Report number: UPC-LSI-10-21-R, November 2010. 24