SlideShare a Scribd company logo
1 of 60
Download to read offline
EDR Insight Webinar: 
Lessons Learned from Phase I Litigation: Case Studies 
December 11, 2014 
Presented by: 
Anthony J. Buonicore, P.E., BCEE, QEP 
CEO, The Buonicore Group 
Past Chairman, ASTM Phase 1 Task Group
Overview 
• Background 
• Case Studies: 
• Case Background 
• Problem 
• Plaintiff’s Contention 
• Defendant’s (EP) Response 
• Result 
• Lessons Learned 
• Final Thoughts
Background 
• The key questions in all five Phase I case studies to be 
discussed are: 
• Was the “standard of care” provided by the EP deficient? 
• How did the EP’s performance compare with “customary practice”? 
• Did the work scope meet the requirements in ASTM E1527? 
• All of the cases were settled (typical) with the settlement kept 
confidential (insurance companies prefer not to establish precedent) 
• Where the cases were complex with numerous claims, only that 
portion of the case believed to be most relevant to Phase I 
consultants will be discussed 
• RULE: If you recognize the case, please do not mention the 
firm or any individual names in the Q&A (so as to not violate 
confidence)
#1: Phase I Update Case
Case Background 
• Paint manufacturing on the site for 40 years 
• Operations ended in the early 1970s 
• Site abandoned and five vacant buildings 
• In 1998, a combined Phase I and Phase II was conducted prior 
to acquisition 
• Phase I followed the ASTM E1527-97 standard 
• Phase II consisted of limited sampling: 
• Installed MWs up-gradient (1) and down-gradient (5) of the former 
industrial building complex 
• Sampled soil (from the borings) and groundwater
Case Background cont’d 
• Phase II results indicated: 
• VOCs and petroleum products in soil and groundwater samples 
below the detection limit 
• Heavy metals in soil below background levels 
• Phase I/II concluded that there were no RECs or serious 
environmental contamination issues associated with the site 
• Property was acquired and partially developed 
• In 2004 the property was put up for sale
Case Background cont’d 
• Property owner provided prospective purchaser with original 
Phase I and Phase II (consultant that performed this work was no 
longer is in business) 
• Prospective purchaser submitted these reports to lender 
• Lender requested that they be updated 
• Prospective purchaser retained a Phase I consultant to “do 
an update acceptable to the lender”
Case Background cont’d 
• Consultant submitted SOW with specific tasks to be 
conducted for the “update” (“update” defined in the SOW as “from 
the time the previous Phase I was conducted to the present”) 
• Update of government records 
• Review of any new uses of the property in the update period for 
potential environmental impact 
• Site reconnaissance 
• Re-sampling groundwater in existing monitoring wells installed on the 
site in previous Phase II investigation 
• Lender indicated that SOW for the update was acceptable 
• SOW executed by consultant and no material environmental issues 
(RECs) identified as occurring in the update period 
• Lender made the loan and the property was acquired
The Problem 
• New owner had plans to remove one of the buildings on the 
property and construct new retail/office space 
• When geotechnical work was conducted, evidence of possible 
soil contamination was observed 
• A new consultant was brought in to investigate and found 
contamination (VOCs, PCBs and petroleum products) above 
state remediation standards in soil located immediately 
adjacent to the building that was going to be removed, and in 
soil under the building 
• Remediation recommended
Plaintiff’s Contention 
• Consultant who did the original update should have known 
that the previous Phase I and Phase II were deficient and the 
conclusions should not have been relied upon 
• Consultant did not meet the standard of care followed by 
environmental professionals performing this type of work 
• Consultant who did the update was sued (the consultant who 
did the original Phase I/II was no longer in business) for 
negligence and harm caused, and sought damages
Defendant’s (EP) Response 
• The conclusions drawn in the initial Phase I and Phase II 
were relied upon (there was no “second guessing”) 
• Client did not ask for a new Phase I/Phase II, only an update 
• Update only covered the period between when the previous 
Phase I/ Phase II was conducted to the present 
• The update SOW was agreed to by the lender and the 
property owner
Defendant’s (EP) Response cont’d 
• The update scope of work was conducted as proposed 
• The E1527 standard does not require the EP to verify 
independently information collected in the course of 
conducting the investigation and allows the EP to rely on 
information provided unless the EP has actual knowledge 
that certain information provided is incorrect or unless it is 
obvious [that the information is incorrect]
Result 
• Case was settled by the insurance company that provides 
the consultant’s E&O insurance
Lessons Learned 
• Updating another consultant’s Phase I can be especially 
difficult and risky (particularly since you often do not have the benefit of 
being able to review all the information collected and without any assurance 
that all reasonably ascertainable information has been collected) 
• Relying on the professional opinion of another EP brings with it 
considerable risk (looking at the same data, different professionals can 
have different opinions and draw different conclusions) 
• If you did not do the previous Phase I, it would be wise to 
refrain from doing an “update” of another consultant’s 
Phase I 
• If, for business reasons, you decide to do an update, consider 
proposing an SOW consistent with effectively re-doing the 
Phase I and charging accordingly
#2: Non-Scope Consideration Case
Case Background 
• A prospective purchaser retained a consulting firm in 1999 to 
conduct a Phase I on a parcel of undeveloped property and 
specifically to identify “recognized environmental conditions” 
• The scope of work conducted followed ASTM E1527-97 
• No evidence of “recognized environmental conditions” was 
identified 
• Property was acquired and development initiated
The Problem 
• During the permitting process, the new property owner was 
advised that: 
• Wetlands existed on the property 
• A wetlands delineation investigation was required 
• Wetlands mitigation would be required 
• The extent of the property’s development would likely be limited 
• The existence of wetlands on the property resulted in 
permitting delays, additional engineering costs, additional 
surveying costs, mitigation costs, construction delays and an 
inability to develop the property as planned
Plaintiff’s Contention 
• Property owner relied on the consultant to advise if there were 
any environmental issues 
• The consultant was aware the property was going to be 
developed and should have known that the presence of wetlands 
could adversely impact this development 
• Had the Phase I consultant exercised reasonable professional 
diligence and identified the presence of wetlands on the property, 
the property would not have been acquired
Plaintiff’s Contention cont’d 
• The Phase I consultant breached the standard of care for the 
conduct of environmental assessments and was negligent in the 
performance of its professional services 
• Property owner was harmed and sought damages that were a 
direct result of the Phase I consultant’s negligence
Defendant’s (EP’s) Response 
• An ASTM E1527-97 Phase I was proposed by the consultant, 
accepted by the client and conducted by the consultant 
• According to the ASTM Phase I standard, wetlands is a non-scope 
consideration and is not included in the SOW unless 
the client specifically indicates otherwise 
• The client did not request that wetlands be included in the SOW 
• The Phase I was directed at identifying RECs which are 
associated with the presence or likely presence of hazardous 
substances or petroleum products on the property – the 
presence of wetlands on the property could not be considered a 
REC
Result 
• Case was settled by the insurance company that provides 
the consultant’s E&O insurance
Lessons Learned 
• Do not assume that a client understands what is or is not 
included in an ASTM Phase I – many clients still perceive the 
Phase I as identifying any environmental conditions that may 
adversely impact a property 
• Include a detailed scope of work based on the ASTM E1527 
standard that makes it clear what an ASTM Phase I includes— 
and does not include
Lessons Learned cont’d 
• Refrain in the SOW from indicating that any non-scope 
environmental condition is excluded, e.g., “asbestos is not 
included” 
• If you say an environmental condition is excluded, but at the same time do 
not specifically exclude every other environmental condition, then all those 
other environmental conditions not specifically excluded may be presumed 
to be included! 
• You may want to consider using a “such as” clause to clarify that a non-scope 
condition, e.g., asbestos or wetlands or lead-based paint, is not part 
of the SOW: “The SOW meets the requirements of the ASTM E1527-XX 
standard. The ASTM E1527-XX standard includes Section 13, Non-scope 
Considerations such as _________, that are not part of the required ASTM 
SOW unless the client specifically requests otherwise. ”
Lessons Learned cont’d 
• If a non-scope condition has been observed in the site recon, it 
should not be mentioned in the Phase I report – by doing so you 
run the risk of it being perceived as included in your SOW 
• What you might consider doing is contacting your client and 
discussing what you observed, what might be done and what it 
could cost 
• If the client chooses to add this to the SOW, then send the client 
a change order with the cost adder 
• If the client chooses not to do anything for whatever reason, 
business or otherwise, fully document this in the project file 
(not in the report)
#3: Vapor Migration Case
Case Background 
• A property developer wanted to acquire a parcel of vacant land 
and build a development of single family homes 
• A consultant was retained in 2006 to conduct a Phase I 
according to the ASTM E1527-05 standard 
• A former industrial site that used chlorinated solvents was 
identified adjacent and hydraulically cross-gradient from the 
target property 
• Review of the contaminated plume delineation study on this 
former industrial property indicated that the contaminated 
groundwater plume was not on the target property 
• The consultant did not identify any recognized environmental 
conditions on the target property and the property was acquired
The Problem 
• After the first phase of residential development was 
completed and sold, one of the homeowners complained of 
“unusual odors” 
• An indoor air investigation was conducted and identified the 
presence of TCE and PERC in the homes 
• An environmental consultant was retained to investigate, and 
identified the source of the indoor air contaminants as vapors 
volatilizing from the contaminated groundwater plume at the 
adjacent former industrial site 
• Subsequent indoor air investigations revealed a number of 
homes with levels of TCE and/or PERC
The Problem cont’d 
• The developer incurred the cost of installing vapor intrusion 
mitigation systems in all impacted homes 
• Homeowners sued the developer for impact on health and 
property value diminution 
• The developer sued the Phase I consultant for negligence in 
not identifying vapors migrating onto the property from the 
adjacent former industrial site as a REC, and sought 
damages
Plaintiff’s Contention 
• The ASTM Phase I ESA is driven by CERCLA 
• CERCLA does not differentiate by the form of the release 
(solid, liquid or vapor) to the environment, only that the 
release be a hazardous substance 
• TCE and PERC are hazardous substances 
• The CERCLA definition of environment includes the 
subsurface 
• The CERCLA definition of release includes hazardous 
substances “emitting” and “escaping” into the subsurface 
environment 
• Vapor migration is included as a consideration in a Phase I 
• The ASTM REC definition includes “releases into structures 
on the property”
Plaintiff’s Contention cont’d 
• The state where the property was located has a draft vapor 
intrusion guidance document and the consultant should have 
been aware of this 
• The consultant was negligent in the conduct of the Phase I 
by not identifying the potential presence of hazardous vapors 
on the property 
• Had the consultant identified the potential presence of 
hazardous vapors migrating onto the property, the developer 
would not have acquired the property without further 
investigation 
• The consultant’s negligence caused harm to the property 
owner and damages were sought
Defendant’s (EP) Response 
• The ASTM E1527-05 standard does not require a vapor 
migration investigation in the SOW 
• The standard of care and customary practice for conducting 
a Phase I ESA does not include evaluating potential vapor 
migration 
• There is no consensus methodology for evaluating vapor 
migration in a Phase I [non-intrusive type] investigation 
• EPA does not include consideration of the vapor pathway in 
its Hazard Ranking System (HRS) for identifying Superfund 
sites
Result 
• Case was settled by the insurance company that provides 
the consultant’s E&O insurance
Lessons Learned 
• If you conducted Phase Is prior to November 2013 (when the 
ASTM E1527-13 standard was published) and did not consider 
vapor migration in those Phase Is, there is liability risk. 
• It would be prudent to work with your legal counsel to develop a 
strategy to respond to a potential future lawsuit claiming that 
you were negligent .
Lessons Learned cont’d 
• Consider the following in developing a response strategy: 
• Industry consensus on a vapor migration screening methodology 
for Phase Is was not developed and published until 2008 (ASTM 
E2600-08 standard) 
• The ASTM E2600-08 standard included vapor migration as a “non-scope 
consideration” that would be included only at the client’s 
request (under legal pressure that this exclusion was inconsistent with 
CERCLA, E2600 was revised in 2010 to delete vapor as non-scope) 
• The ASTM E1527-13 Phase I standard published in November 
2013 for the first time specifically refers to vapor migration 
• EPA first published a draft vapor intrusion guidance document in 
2002, but only published its final version for public comment in April 
2013 – and still has not published a final document
Lessons Learned cont’d 
• Bottom line: 
• For Phase Is conducted prior to 2002 (when EPA published its 
draft VI guidance), a reasonably strong case can be made for not 
having included vapor migration in your Phase I 
• For Phase Is conducted between 2002 and 2005 (AAI Rule), a 
reasonable case might still be made, but this will likely be 
dependent in large part on whether the state where the property 
is located had published vapor intrusion guidance 
• For Phase Is conducted post-2005 when EPA published its AAI 
Rule, it will be difficult to make a case since EPA in its 
December 30, 2013 AAI Amendment to the Rule clearly stated 
that the 2005 Rule included consideration of vapor migration
#4: Former Tenant Case
Case Background 
• A prospective purchaser of a retail property (shopping 
center) retained an environmental consultant in 2003 to 
conduct a Phase I on the property to identify recognized 
environmental conditions 
• The Phase I SOW complied with the ASTM E1527-00 
standard 
• The Phase I investigation concluded that there was no 
evidence of any RECs 
• The property was acquired
The Problem 
• When refinancing was sought four years later, the bank 
required a new Phase I and used a firm from their “approved” 
list 
• The consultant doing the new Phase I for the bank was not 
the firm that did the original Phase I 
• The consultant identified that a former dry cleaner existed on 
the property and recommended a Phase II investigation 
• The Phase II investigation found PERC contamination in the 
soil and groundwater on the property and remediation was 
required to comply with state cleanup standards 
• The property was not able to be re-financed
Plaintiff’s Contention 
• The existence of a former dry cleaner tenant on the property 
that was not identified in the original Phase I investigation 
conducted prior to the property being acquired 
• This resulted in site investigation costs, remediation costs 
and an inability to refinance the property 
• The firm that performed the original Phase I did inadequate 
historical research and did not follow the standard of care 
applicable to the conduct of Phase Is
Plaintiff’s Contention cont’d 
• It should have been obvious that dry cleaners were often 
tenants at shopping centers (particularly where there were 
large food stores) and that they moved relatively frequently. 
As such, a tighter historical search interval should have been 
established and, moreover, the city directories were available. 
• This caused harm for which damages were being sought 
• The damages sought were directly attributable to negligence 
by the firm performing the original Phase I investigation
Defendant’s (EP) Response 
• The Phase I complied with the ASTM E1527-00 standard 
• The E1527-00 standard states that “review of standard 
historical sources at less than approximately five year 
intervals is not required” 
• Past tenants were identified by the defendant using a city 
directory search at approximately 8-10 year intervals (which 
meets the “not less than five year interval” requirement) 
[The dry cleaner tenant identified by bank’s consultant was a 
tenant on the premises within this 8-10 year interval. The 
bank’s Phase I consultant searched city directories more 
frequently (at approximately a three year interval), which is 
beyond what is required to comply with ASTM E1527]
Result 
• Case was settled by the insurance company that provides 
the consultant’s E&O insurance
Lessons Learned 
• For retail properties such as shopping centers or industrial 
tenant properties, knowledge of past tenants is important 
• Sellers typically only have limited information on all past 
tenants 
• Historical city directories can provide insight into past tenants 
• It may make sense to review all available (“reasonably 
ascertainable”) city directories for these types of properties 
[Note: This may be beyond the [interval] requirements of the E1527 
standard; hence, it would be prudent first to discuss this with the client 
(you may even be able to charge for the expansion in the scope of work).]
Lessons Learned cont’d 
• For these types of properties, you should make a special 
request to the client to obtain a list of all past tenants (even 
though this information typically is not available, and if it is available, it 
frequently would only be for a limited period of time) 
• If you are following the E1527 standard for these types of 
properties, then your Phase I should include a limitation that 
the investigation may not identify all past tenants on the 
property (a data gap) and therefore may miss a high risk 
tenant (such as a dry cleaner)
#5: “What is obvious” Case
Case Background 
• A property was about to be foreclosed upon in 2002 and the 
bank authorized a Phase I prior to foreclosure 
• A small industrial tenant located on the site was in the process 
of closing down 
• This industrial tenant assembled small (desk-top) electrostatic 
coating equipment (with a component being a small vapor 
degreaser) and tested them prior to shipping 
• No manufacturing was done on site 
• The operation utilized small quantities of chlorinated solvents in 
testing the machines
Case Background cont’d 
• A Phase I consultant was retained by the bank to do a pre-foreclosure 
Phase I following the ASTM E1527-00 standard 
• The Phase I consultant requested hazardous waste manifests 
from the tenant but none were found in the on-site records 
• Plant personnel during interviews were not able to recall any 
hazardous waste manifests 
• The database company’s search of RCRA records identified no 
hazardous waste generation records for the site 
• The consultant made a request to the state DEP for any 
manifest records and was told there were none for the site
Case Background cont’d 
• The consultant concluded that the site likely was a CESQG 
(where an EPA ID number and manifesting was not a requirement in the 
state) 
• The Phase I consultant recommended a Phase II 
• The Phase II involved the installation of 6 monitoring wells 
around the building exterior 
• No VOCs or PHCs were found in any of the soil or 
groundwater samples 
• The consultant concluded that there was no evidence of 
RECs 
• The bank went ahead with the foreclosure proceedings
Case Background cont’d 
• During the foreclosure proceedings, a prospective purchaser 
appeared on the scene and indicated an interest in acquiring 
the property 
• The prospective purchaser’s lender (different from the bank 
involved in the foreclosure) required a Phase I 
• The prospective purchaser retained the Phase I consultant that 
did the original Phase I for the foreclosing bank 
• The original Phase I (8 months old) was updated following the 
ASTM E1527-00 standard 
• The Phase II conducted for the foreclosing bank was less than 
two months old and not updated
Case Background cont’d 
• The consultant concluded again that there was no evidence of 
RECs and the “environmental risk associated with the site was 
low” 
• The property was acquired and the building subdivided for 
office space
The Problem 
• Five years later, the property owner decided to refinance the 
property and the bank (different from the previous banks) 
requested a Phase I 
• The consultant that was retained conducted the Phase I 
following the ASTM E1527-05 standard 
• The consultant in requesting manifest data from the state for 
the site’s former light industrial operation was now told there 
were manifest records and received copies indicating that the 
site was in fact a LQG (the initial state search made an error 
by searching under an incorrectly spelled address, resulting in 
no manifest records on file at this “incorrect” address)
The Problem cont’d 
• The consultant recommended Phase II sampling both at the 
exterior and in the interior of the building 
• The Phase II found chlorinated solvent contamination below 
the floor of the building at levels that required remediation 
• The property owner was unable to get the refinancing 
completed and was required to investigate the site more 
thoroughly, develop a remediation plan and cleanup the 
property 
• Had the consultant that conducted the initial Phase I and 
Phase II identified the potential presence of hazardous 
substances in the subsurface below the slab, the property 
would not have been acquired
Plaintiff’s Contention 
• The Phase I consultant that conducted the Phase I/II did not 
meet the standard of care and should have known that these 
types of industrial facilities (testing vapor degreasers) require more 
comprehensive investigation, including sampling inside the 
building where the testing took place 
• The consultant should have known the state DEP’s reply was 
inaccurate (it was “obvious”) and conducted further investigation, 
i.e., visited the regulatory offices and conducted the manifest 
record search itself (it is widely known that hazardous waste 
transporters for any size generators typically utilize the manifest 
system) 
• The firm performing the Phase I was negligent and caused harm 
for which damages were sought
Defendant’s Response 
• The interviews of plant personnel indicated: 
• The use of solvents at the plant was minimal 
• No recollection of spills or releases 
• Only minor amounts of waste solvent generated from the testing (1-2 
quarts) 
• No manufacturing was done on site, only assembly and testing 
• State DEP had no manifests for the site (providing support that 
the site was likely a CESQG) 
• Search of the RCRA database by the government records search 
company indicated no hazardous waste generation records at the 
federal level for the site
Defendant’s Response cont’d 
• The ASTM E1527 standard does not require independent 
verification of information received from third parties (including 
government agencies and personnel interviewed) but may rely on 
this information “unless he or she actual knowledge that certain 
information is incorrect or unless it is obvious that certain 
information is incorrect based on other information obtained or 
actually known to the environmental professional” 
• A CESQG is not required in the state to have an EPA ID number 
and is not required to manifest
Result 
• Case was settled by the insurance company that provides 
the consultant’s E&O insurance
Lessons Learned 
• If something does not pass the smell test, it probably is worth 
doing additional investigation 
• If you are relying on certain data for your professional 
opinion, make sure this is made clear in the Phase I report 
• If there are limitations in any of the site assessment activities 
reviewed, such as in this case the fact that there was no 
sampling inside the building below the slab, clearly identify 
this limitation in the Phase I report
Final Thoughts 
1. When you rely on important facts (such as the depth to 
groundwater or the type soil or groundwater flow direction 
from a Phase II investigation), be sure to reference the 
source. 
2. When you rely on important assumptions (such as 
groundwater flow following surface topography, or the soil in 
the subsurface being homogenous), be sure to clearly 
state this. 
3. When you provide your professional opinion, be sure 
always to condition it (e.g., clearly identify what you base it 
on).
Final Thoughts 
4. Be sure to identify in your terms and conditions the limiting 
conditions identified in the ASTM E1527 standard, i.e., the 
investigation is not exhaustive and uncertainty is not 
eliminated. 
5. Describe your scope-of-work clearly and comprehensively 
6. State who can rely on the report (anyone relying on the report 
should be provided the SOW, T&C and Limitations/Assumptions and be 
asked to confirm in writing that these have been reviewed; may also want to 
put a time limitation, e.g., 6 months, on the reliance) 
7. When litigation takes place, a key question will be: 
“Did you clearly say what you will do?” 
And then: 
“ Did you do what you said you would, no more, no less?”
Lessons Learned from Phase I Litigation: Case Studies

More Related Content

Similar to Lessons Learned from Phase I Litigation: Case Studies

Evaluating and Managing Environmental Risk in Business Transactions
Evaluating and Managing Environmental Risk in Business TransactionsEvaluating and Managing Environmental Risk in Business Transactions
Evaluating and Managing Environmental Risk in Business TransactionsQuarles & Brady
 
Vapor Intrusion and Environmental Liability—Learning from Past Mistakes
Vapor Intrusion and Environmental Liability—Learning from Past MistakesVapor Intrusion and Environmental Liability—Learning from Past Mistakes
Vapor Intrusion and Environmental Liability—Learning from Past MistakesEDR
 
Managing claims best practices | 2-10 HBW
Managing claims best practices | 2-10 HBWManaging claims best practices | 2-10 HBW
Managing claims best practices | 2-10 HBWHomeBuyersWarranty
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case studyFreelancelanders
 
Clearing Up the Confusion About the ASTM E 1527-13 Phase I ESA Standard
Clearing Up the Confusion About the ASTM E 1527-13 Phase I ESA StandardClearing Up the Confusion About the ASTM E 1527-13 Phase I ESA Standard
Clearing Up the Confusion About the ASTM E 1527-13 Phase I ESA StandardEDR
 
Three Simple Steps for Full Comliance of EPA's Lead Based Paint RRP Rule
Three Simple Steps for Full Comliance of EPA's Lead Based Paint RRP RuleThree Simple Steps for Full Comliance of EPA's Lead Based Paint RRP Rule
Three Simple Steps for Full Comliance of EPA's Lead Based Paint RRP RuleEnvironmental Innovative Technologies
 
Project ppt riverside condo
Project ppt riverside condoProject ppt riverside condo
Project ppt riverside condoSAIFULLAH MAHMUD
 
Phase I Environmental Site Assessment Training Seminar
Phase I Environmental Site Assessment Training SeminarPhase I Environmental Site Assessment Training Seminar
Phase I Environmental Site Assessment Training SeminarBrandon Trate
 
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442Dwyer v Kelly (Home Building) [2007] NSWCTTT 442
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442Alec Rendell [NBPR-2]
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Capital Needs Assessment Example
Capital Needs Assessment ExampleCapital Needs Assessment Example
Capital Needs Assessment ExampleAdam Hoeksema
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental  & Sustainability EngineerANGELA LOPEZ - CV - Civil, Environmental  & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability EngineerAngela Lopez
 
Sample wind apartment ins val rep
Sample wind apartment ins val repSample wind apartment ins val rep
Sample wind apartment ins val repIndependentgroup
 
May AACE Presentation, FINAL
May AACE Presentation, FINALMay AACE Presentation, FINAL
May AACE Presentation, FINALBrandon Hummel
 
Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9Michael Shellshear
 

Similar to Lessons Learned from Phase I Litigation: Case Studies (20)

Evaluating and Managing Environmental Risk in Business Transactions
Evaluating and Managing Environmental Risk in Business TransactionsEvaluating and Managing Environmental Risk in Business Transactions
Evaluating and Managing Environmental Risk in Business Transactions
 
Vapor Intrusion and Environmental Liability—Learning from Past Mistakes
Vapor Intrusion and Environmental Liability—Learning from Past MistakesVapor Intrusion and Environmental Liability—Learning from Past Mistakes
Vapor Intrusion and Environmental Liability—Learning from Past Mistakes
 
Managing claims best practices | 2-10 HBW
Managing claims best practices | 2-10 HBWManaging claims best practices | 2-10 HBW
Managing claims best practices | 2-10 HBW
 
Surrey education case study
Surrey education case studySurrey education case study
Surrey education case study
 
Clearing Up the Confusion About the ASTM E 1527-13 Phase I ESA Standard
Clearing Up the Confusion About the ASTM E 1527-13 Phase I ESA StandardClearing Up the Confusion About the ASTM E 1527-13 Phase I ESA Standard
Clearing Up the Confusion About the ASTM E 1527-13 Phase I ESA Standard
 
claims management framework
 claims management framework claims management framework
claims management framework
 
Three Simple Steps for Full Comliance of EPA's Lead Based Paint RRP Rule
Three Simple Steps for Full Comliance of EPA's Lead Based Paint RRP RuleThree Simple Steps for Full Comliance of EPA's Lead Based Paint RRP Rule
Three Simple Steps for Full Comliance of EPA's Lead Based Paint RRP Rule
 
Project ppt riverside condo
Project ppt riverside condoProject ppt riverside condo
Project ppt riverside condo
 
Deterioration of Concrete
Deterioration of ConcreteDeterioration of Concrete
Deterioration of Concrete
 
Phase I Environmental Site Assessment Training Seminar
Phase I Environmental Site Assessment Training SeminarPhase I Environmental Site Assessment Training Seminar
Phase I Environmental Site Assessment Training Seminar
 
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442Dwyer v Kelly (Home Building) [2007] NSWCTTT 442
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Building Dilapidations International Sample Report with Gauge
Building Dilapidations International Sample Report with GaugeBuilding Dilapidations International Sample Report with Gauge
Building Dilapidations International Sample Report with Gauge
 
Capital Needs Assessment Example
Capital Needs Assessment ExampleCapital Needs Assessment Example
Capital Needs Assessment Example
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental  & Sustainability EngineerANGELA LOPEZ - CV - Civil, Environmental  & Sustainability Engineer
ANGELA LOPEZ - CV - Civil, Environmental & Sustainability Engineer
 
Sample wind apartment ins val rep
Sample wind apartment ins val repSample wind apartment ins val rep
Sample wind apartment ins val rep
 
May AACE Presentation, FINAL
May AACE Presentation, FINALMay AACE Presentation, FINAL
May AACE Presentation, FINAL
 
Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9
 

More from EDR

Measure twice shields
Measure twice   shieldsMeasure twice   shields
Measure twice shieldsEDR
 
Brownfields under trump panel
Brownfields under trump panelBrownfields under trump panel
Brownfields under trump panelEDR
 
How technology is changing opp danielson
How technology is changing opp danielsonHow technology is changing opp danielson
How technology is changing opp danielsonEDR
 
Measure twice van buren
Measure twice   van burenMeasure twice   van buren
Measure twice van burenEDR
 
Covering your bases parson
Covering your bases parsonCovering your bases parson
Covering your bases parsonEDR
 
Covering Your Bases Parson
Covering Your Bases ParsonCovering Your Bases Parson
Covering Your Bases ParsonEDR
 
CRE At A Crossroads Golin
CRE At A Crossroads GolinCRE At A Crossroads Golin
CRE At A Crossroads GolinEDR
 
Covering Your Bases McDonald
Covering Your Bases McDonaldCovering Your Bases McDonald
Covering Your Bases McDonaldEDR
 
Strategic Growth Spiers
Strategic Growth SpiersStrategic Growth Spiers
Strategic Growth SpiersEDR
 
Market Update Rossi
Market Update RossiMarket Update Rossi
Market Update RossiEDR
 
Market Update - Rossi
Market Update - RossiMarket Update - Rossi
Market Update - RossiEDR
 
Market Update - Keene
Market Update - KeeneMarket Update - Keene
Market Update - KeeneEDR
 
Market Update - Allen
Market Update - AllenMarket Update - Allen
Market Update - AllenEDR
 
The World of CRE Finance
The World of CRE FinanceThe World of CRE Finance
The World of CRE FinanceEDR
 
Two Roads Diverged - Conway
Two Roads Diverged - ConwayTwo Roads Diverged - Conway
Two Roads Diverged - ConwayEDR
 
Brownfields Under Trump - Panel
Brownfields Under Trump - PanelBrownfields Under Trump - Panel
Brownfields Under Trump - PanelEDR
 
Brownfields Under Trump - Bartsch
Brownfields Under Trump - BartschBrownfields Under Trump - Bartsch
Brownfields Under Trump - BartschEDR
 
Covering Your Bases - Parson
Covering Your Bases - ParsonCovering Your Bases - Parson
Covering Your Bases - ParsonEDR
 
A Look at Brexit - Mellott
A Look at Brexit - MellottA Look at Brexit - Mellott
A Look at Brexit - MellottEDR
 
EDR REC CREC-HREC Presentation - Boston DDD
EDR REC CREC-HREC Presentation - Boston DDDEDR REC CREC-HREC Presentation - Boston DDD
EDR REC CREC-HREC Presentation - Boston DDDEDR
 

More from EDR (20)

Measure twice shields
Measure twice   shieldsMeasure twice   shields
Measure twice shields
 
Brownfields under trump panel
Brownfields under trump panelBrownfields under trump panel
Brownfields under trump panel
 
How technology is changing opp danielson
How technology is changing opp danielsonHow technology is changing opp danielson
How technology is changing opp danielson
 
Measure twice van buren
Measure twice   van burenMeasure twice   van buren
Measure twice van buren
 
Covering your bases parson
Covering your bases parsonCovering your bases parson
Covering your bases parson
 
Covering Your Bases Parson
Covering Your Bases ParsonCovering Your Bases Parson
Covering Your Bases Parson
 
CRE At A Crossroads Golin
CRE At A Crossroads GolinCRE At A Crossroads Golin
CRE At A Crossroads Golin
 
Covering Your Bases McDonald
Covering Your Bases McDonaldCovering Your Bases McDonald
Covering Your Bases McDonald
 
Strategic Growth Spiers
Strategic Growth SpiersStrategic Growth Spiers
Strategic Growth Spiers
 
Market Update Rossi
Market Update RossiMarket Update Rossi
Market Update Rossi
 
Market Update - Rossi
Market Update - RossiMarket Update - Rossi
Market Update - Rossi
 
Market Update - Keene
Market Update - KeeneMarket Update - Keene
Market Update - Keene
 
Market Update - Allen
Market Update - AllenMarket Update - Allen
Market Update - Allen
 
The World of CRE Finance
The World of CRE FinanceThe World of CRE Finance
The World of CRE Finance
 
Two Roads Diverged - Conway
Two Roads Diverged - ConwayTwo Roads Diverged - Conway
Two Roads Diverged - Conway
 
Brownfields Under Trump - Panel
Brownfields Under Trump - PanelBrownfields Under Trump - Panel
Brownfields Under Trump - Panel
 
Brownfields Under Trump - Bartsch
Brownfields Under Trump - BartschBrownfields Under Trump - Bartsch
Brownfields Under Trump - Bartsch
 
Covering Your Bases - Parson
Covering Your Bases - ParsonCovering Your Bases - Parson
Covering Your Bases - Parson
 
A Look at Brexit - Mellott
A Look at Brexit - MellottA Look at Brexit - Mellott
A Look at Brexit - Mellott
 
EDR REC CREC-HREC Presentation - Boston DDD
EDR REC CREC-HREC Presentation - Boston DDDEDR REC CREC-HREC Presentation - Boston DDD
EDR REC CREC-HREC Presentation - Boston DDD
 

Lessons Learned from Phase I Litigation: Case Studies

  • 1. EDR Insight Webinar: Lessons Learned from Phase I Litigation: Case Studies December 11, 2014 Presented by: Anthony J. Buonicore, P.E., BCEE, QEP CEO, The Buonicore Group Past Chairman, ASTM Phase 1 Task Group
  • 2. Overview • Background • Case Studies: • Case Background • Problem • Plaintiff’s Contention • Defendant’s (EP) Response • Result • Lessons Learned • Final Thoughts
  • 3. Background • The key questions in all five Phase I case studies to be discussed are: • Was the “standard of care” provided by the EP deficient? • How did the EP’s performance compare with “customary practice”? • Did the work scope meet the requirements in ASTM E1527? • All of the cases were settled (typical) with the settlement kept confidential (insurance companies prefer not to establish precedent) • Where the cases were complex with numerous claims, only that portion of the case believed to be most relevant to Phase I consultants will be discussed • RULE: If you recognize the case, please do not mention the firm or any individual names in the Q&A (so as to not violate confidence)
  • 4. #1: Phase I Update Case
  • 5. Case Background • Paint manufacturing on the site for 40 years • Operations ended in the early 1970s • Site abandoned and five vacant buildings • In 1998, a combined Phase I and Phase II was conducted prior to acquisition • Phase I followed the ASTM E1527-97 standard • Phase II consisted of limited sampling: • Installed MWs up-gradient (1) and down-gradient (5) of the former industrial building complex • Sampled soil (from the borings) and groundwater
  • 6. Case Background cont’d • Phase II results indicated: • VOCs and petroleum products in soil and groundwater samples below the detection limit • Heavy metals in soil below background levels • Phase I/II concluded that there were no RECs or serious environmental contamination issues associated with the site • Property was acquired and partially developed • In 2004 the property was put up for sale
  • 7. Case Background cont’d • Property owner provided prospective purchaser with original Phase I and Phase II (consultant that performed this work was no longer is in business) • Prospective purchaser submitted these reports to lender • Lender requested that they be updated • Prospective purchaser retained a Phase I consultant to “do an update acceptable to the lender”
  • 8. Case Background cont’d • Consultant submitted SOW with specific tasks to be conducted for the “update” (“update” defined in the SOW as “from the time the previous Phase I was conducted to the present”) • Update of government records • Review of any new uses of the property in the update period for potential environmental impact • Site reconnaissance • Re-sampling groundwater in existing monitoring wells installed on the site in previous Phase II investigation • Lender indicated that SOW for the update was acceptable • SOW executed by consultant and no material environmental issues (RECs) identified as occurring in the update period • Lender made the loan and the property was acquired
  • 9. The Problem • New owner had plans to remove one of the buildings on the property and construct new retail/office space • When geotechnical work was conducted, evidence of possible soil contamination was observed • A new consultant was brought in to investigate and found contamination (VOCs, PCBs and petroleum products) above state remediation standards in soil located immediately adjacent to the building that was going to be removed, and in soil under the building • Remediation recommended
  • 10. Plaintiff’s Contention • Consultant who did the original update should have known that the previous Phase I and Phase II were deficient and the conclusions should not have been relied upon • Consultant did not meet the standard of care followed by environmental professionals performing this type of work • Consultant who did the update was sued (the consultant who did the original Phase I/II was no longer in business) for negligence and harm caused, and sought damages
  • 11. Defendant’s (EP) Response • The conclusions drawn in the initial Phase I and Phase II were relied upon (there was no “second guessing”) • Client did not ask for a new Phase I/Phase II, only an update • Update only covered the period between when the previous Phase I/ Phase II was conducted to the present • The update SOW was agreed to by the lender and the property owner
  • 12. Defendant’s (EP) Response cont’d • The update scope of work was conducted as proposed • The E1527 standard does not require the EP to verify independently information collected in the course of conducting the investigation and allows the EP to rely on information provided unless the EP has actual knowledge that certain information provided is incorrect or unless it is obvious [that the information is incorrect]
  • 13. Result • Case was settled by the insurance company that provides the consultant’s E&O insurance
  • 14. Lessons Learned • Updating another consultant’s Phase I can be especially difficult and risky (particularly since you often do not have the benefit of being able to review all the information collected and without any assurance that all reasonably ascertainable information has been collected) • Relying on the professional opinion of another EP brings with it considerable risk (looking at the same data, different professionals can have different opinions and draw different conclusions) • If you did not do the previous Phase I, it would be wise to refrain from doing an “update” of another consultant’s Phase I • If, for business reasons, you decide to do an update, consider proposing an SOW consistent with effectively re-doing the Phase I and charging accordingly
  • 16. Case Background • A prospective purchaser retained a consulting firm in 1999 to conduct a Phase I on a parcel of undeveloped property and specifically to identify “recognized environmental conditions” • The scope of work conducted followed ASTM E1527-97 • No evidence of “recognized environmental conditions” was identified • Property was acquired and development initiated
  • 17. The Problem • During the permitting process, the new property owner was advised that: • Wetlands existed on the property • A wetlands delineation investigation was required • Wetlands mitigation would be required • The extent of the property’s development would likely be limited • The existence of wetlands on the property resulted in permitting delays, additional engineering costs, additional surveying costs, mitigation costs, construction delays and an inability to develop the property as planned
  • 18. Plaintiff’s Contention • Property owner relied on the consultant to advise if there were any environmental issues • The consultant was aware the property was going to be developed and should have known that the presence of wetlands could adversely impact this development • Had the Phase I consultant exercised reasonable professional diligence and identified the presence of wetlands on the property, the property would not have been acquired
  • 19. Plaintiff’s Contention cont’d • The Phase I consultant breached the standard of care for the conduct of environmental assessments and was negligent in the performance of its professional services • Property owner was harmed and sought damages that were a direct result of the Phase I consultant’s negligence
  • 20. Defendant’s (EP’s) Response • An ASTM E1527-97 Phase I was proposed by the consultant, accepted by the client and conducted by the consultant • According to the ASTM Phase I standard, wetlands is a non-scope consideration and is not included in the SOW unless the client specifically indicates otherwise • The client did not request that wetlands be included in the SOW • The Phase I was directed at identifying RECs which are associated with the presence or likely presence of hazardous substances or petroleum products on the property – the presence of wetlands on the property could not be considered a REC
  • 21. Result • Case was settled by the insurance company that provides the consultant’s E&O insurance
  • 22. Lessons Learned • Do not assume that a client understands what is or is not included in an ASTM Phase I – many clients still perceive the Phase I as identifying any environmental conditions that may adversely impact a property • Include a detailed scope of work based on the ASTM E1527 standard that makes it clear what an ASTM Phase I includes— and does not include
  • 23. Lessons Learned cont’d • Refrain in the SOW from indicating that any non-scope environmental condition is excluded, e.g., “asbestos is not included” • If you say an environmental condition is excluded, but at the same time do not specifically exclude every other environmental condition, then all those other environmental conditions not specifically excluded may be presumed to be included! • You may want to consider using a “such as” clause to clarify that a non-scope condition, e.g., asbestos or wetlands or lead-based paint, is not part of the SOW: “The SOW meets the requirements of the ASTM E1527-XX standard. The ASTM E1527-XX standard includes Section 13, Non-scope Considerations such as _________, that are not part of the required ASTM SOW unless the client specifically requests otherwise. ”
  • 24. Lessons Learned cont’d • If a non-scope condition has been observed in the site recon, it should not be mentioned in the Phase I report – by doing so you run the risk of it being perceived as included in your SOW • What you might consider doing is contacting your client and discussing what you observed, what might be done and what it could cost • If the client chooses to add this to the SOW, then send the client a change order with the cost adder • If the client chooses not to do anything for whatever reason, business or otherwise, fully document this in the project file (not in the report)
  • 26. Case Background • A property developer wanted to acquire a parcel of vacant land and build a development of single family homes • A consultant was retained in 2006 to conduct a Phase I according to the ASTM E1527-05 standard • A former industrial site that used chlorinated solvents was identified adjacent and hydraulically cross-gradient from the target property • Review of the contaminated plume delineation study on this former industrial property indicated that the contaminated groundwater plume was not on the target property • The consultant did not identify any recognized environmental conditions on the target property and the property was acquired
  • 27. The Problem • After the first phase of residential development was completed and sold, one of the homeowners complained of “unusual odors” • An indoor air investigation was conducted and identified the presence of TCE and PERC in the homes • An environmental consultant was retained to investigate, and identified the source of the indoor air contaminants as vapors volatilizing from the contaminated groundwater plume at the adjacent former industrial site • Subsequent indoor air investigations revealed a number of homes with levels of TCE and/or PERC
  • 28. The Problem cont’d • The developer incurred the cost of installing vapor intrusion mitigation systems in all impacted homes • Homeowners sued the developer for impact on health and property value diminution • The developer sued the Phase I consultant for negligence in not identifying vapors migrating onto the property from the adjacent former industrial site as a REC, and sought damages
  • 29. Plaintiff’s Contention • The ASTM Phase I ESA is driven by CERCLA • CERCLA does not differentiate by the form of the release (solid, liquid or vapor) to the environment, only that the release be a hazardous substance • TCE and PERC are hazardous substances • The CERCLA definition of environment includes the subsurface • The CERCLA definition of release includes hazardous substances “emitting” and “escaping” into the subsurface environment • Vapor migration is included as a consideration in a Phase I • The ASTM REC definition includes “releases into structures on the property”
  • 30. Plaintiff’s Contention cont’d • The state where the property was located has a draft vapor intrusion guidance document and the consultant should have been aware of this • The consultant was negligent in the conduct of the Phase I by not identifying the potential presence of hazardous vapors on the property • Had the consultant identified the potential presence of hazardous vapors migrating onto the property, the developer would not have acquired the property without further investigation • The consultant’s negligence caused harm to the property owner and damages were sought
  • 31. Defendant’s (EP) Response • The ASTM E1527-05 standard does not require a vapor migration investigation in the SOW • The standard of care and customary practice for conducting a Phase I ESA does not include evaluating potential vapor migration • There is no consensus methodology for evaluating vapor migration in a Phase I [non-intrusive type] investigation • EPA does not include consideration of the vapor pathway in its Hazard Ranking System (HRS) for identifying Superfund sites
  • 32. Result • Case was settled by the insurance company that provides the consultant’s E&O insurance
  • 33. Lessons Learned • If you conducted Phase Is prior to November 2013 (when the ASTM E1527-13 standard was published) and did not consider vapor migration in those Phase Is, there is liability risk. • It would be prudent to work with your legal counsel to develop a strategy to respond to a potential future lawsuit claiming that you were negligent .
  • 34. Lessons Learned cont’d • Consider the following in developing a response strategy: • Industry consensus on a vapor migration screening methodology for Phase Is was not developed and published until 2008 (ASTM E2600-08 standard) • The ASTM E2600-08 standard included vapor migration as a “non-scope consideration” that would be included only at the client’s request (under legal pressure that this exclusion was inconsistent with CERCLA, E2600 was revised in 2010 to delete vapor as non-scope) • The ASTM E1527-13 Phase I standard published in November 2013 for the first time specifically refers to vapor migration • EPA first published a draft vapor intrusion guidance document in 2002, but only published its final version for public comment in April 2013 – and still has not published a final document
  • 35. Lessons Learned cont’d • Bottom line: • For Phase Is conducted prior to 2002 (when EPA published its draft VI guidance), a reasonably strong case can be made for not having included vapor migration in your Phase I • For Phase Is conducted between 2002 and 2005 (AAI Rule), a reasonable case might still be made, but this will likely be dependent in large part on whether the state where the property is located had published vapor intrusion guidance • For Phase Is conducted post-2005 when EPA published its AAI Rule, it will be difficult to make a case since EPA in its December 30, 2013 AAI Amendment to the Rule clearly stated that the 2005 Rule included consideration of vapor migration
  • 37. Case Background • A prospective purchaser of a retail property (shopping center) retained an environmental consultant in 2003 to conduct a Phase I on the property to identify recognized environmental conditions • The Phase I SOW complied with the ASTM E1527-00 standard • The Phase I investigation concluded that there was no evidence of any RECs • The property was acquired
  • 38. The Problem • When refinancing was sought four years later, the bank required a new Phase I and used a firm from their “approved” list • The consultant doing the new Phase I for the bank was not the firm that did the original Phase I • The consultant identified that a former dry cleaner existed on the property and recommended a Phase II investigation • The Phase II investigation found PERC contamination in the soil and groundwater on the property and remediation was required to comply with state cleanup standards • The property was not able to be re-financed
  • 39. Plaintiff’s Contention • The existence of a former dry cleaner tenant on the property that was not identified in the original Phase I investigation conducted prior to the property being acquired • This resulted in site investigation costs, remediation costs and an inability to refinance the property • The firm that performed the original Phase I did inadequate historical research and did not follow the standard of care applicable to the conduct of Phase Is
  • 40. Plaintiff’s Contention cont’d • It should have been obvious that dry cleaners were often tenants at shopping centers (particularly where there were large food stores) and that they moved relatively frequently. As such, a tighter historical search interval should have been established and, moreover, the city directories were available. • This caused harm for which damages were being sought • The damages sought were directly attributable to negligence by the firm performing the original Phase I investigation
  • 41. Defendant’s (EP) Response • The Phase I complied with the ASTM E1527-00 standard • The E1527-00 standard states that “review of standard historical sources at less than approximately five year intervals is not required” • Past tenants were identified by the defendant using a city directory search at approximately 8-10 year intervals (which meets the “not less than five year interval” requirement) [The dry cleaner tenant identified by bank’s consultant was a tenant on the premises within this 8-10 year interval. The bank’s Phase I consultant searched city directories more frequently (at approximately a three year interval), which is beyond what is required to comply with ASTM E1527]
  • 42. Result • Case was settled by the insurance company that provides the consultant’s E&O insurance
  • 43. Lessons Learned • For retail properties such as shopping centers or industrial tenant properties, knowledge of past tenants is important • Sellers typically only have limited information on all past tenants • Historical city directories can provide insight into past tenants • It may make sense to review all available (“reasonably ascertainable”) city directories for these types of properties [Note: This may be beyond the [interval] requirements of the E1527 standard; hence, it would be prudent first to discuss this with the client (you may even be able to charge for the expansion in the scope of work).]
  • 44. Lessons Learned cont’d • For these types of properties, you should make a special request to the client to obtain a list of all past tenants (even though this information typically is not available, and if it is available, it frequently would only be for a limited period of time) • If you are following the E1527 standard for these types of properties, then your Phase I should include a limitation that the investigation may not identify all past tenants on the property (a data gap) and therefore may miss a high risk tenant (such as a dry cleaner)
  • 45. #5: “What is obvious” Case
  • 46. Case Background • A property was about to be foreclosed upon in 2002 and the bank authorized a Phase I prior to foreclosure • A small industrial tenant located on the site was in the process of closing down • This industrial tenant assembled small (desk-top) electrostatic coating equipment (with a component being a small vapor degreaser) and tested them prior to shipping • No manufacturing was done on site • The operation utilized small quantities of chlorinated solvents in testing the machines
  • 47. Case Background cont’d • A Phase I consultant was retained by the bank to do a pre-foreclosure Phase I following the ASTM E1527-00 standard • The Phase I consultant requested hazardous waste manifests from the tenant but none were found in the on-site records • Plant personnel during interviews were not able to recall any hazardous waste manifests • The database company’s search of RCRA records identified no hazardous waste generation records for the site • The consultant made a request to the state DEP for any manifest records and was told there were none for the site
  • 48. Case Background cont’d • The consultant concluded that the site likely was a CESQG (where an EPA ID number and manifesting was not a requirement in the state) • The Phase I consultant recommended a Phase II • The Phase II involved the installation of 6 monitoring wells around the building exterior • No VOCs or PHCs were found in any of the soil or groundwater samples • The consultant concluded that there was no evidence of RECs • The bank went ahead with the foreclosure proceedings
  • 49. Case Background cont’d • During the foreclosure proceedings, a prospective purchaser appeared on the scene and indicated an interest in acquiring the property • The prospective purchaser’s lender (different from the bank involved in the foreclosure) required a Phase I • The prospective purchaser retained the Phase I consultant that did the original Phase I for the foreclosing bank • The original Phase I (8 months old) was updated following the ASTM E1527-00 standard • The Phase II conducted for the foreclosing bank was less than two months old and not updated
  • 50. Case Background cont’d • The consultant concluded again that there was no evidence of RECs and the “environmental risk associated with the site was low” • The property was acquired and the building subdivided for office space
  • 51. The Problem • Five years later, the property owner decided to refinance the property and the bank (different from the previous banks) requested a Phase I • The consultant that was retained conducted the Phase I following the ASTM E1527-05 standard • The consultant in requesting manifest data from the state for the site’s former light industrial operation was now told there were manifest records and received copies indicating that the site was in fact a LQG (the initial state search made an error by searching under an incorrectly spelled address, resulting in no manifest records on file at this “incorrect” address)
  • 52. The Problem cont’d • The consultant recommended Phase II sampling both at the exterior and in the interior of the building • The Phase II found chlorinated solvent contamination below the floor of the building at levels that required remediation • The property owner was unable to get the refinancing completed and was required to investigate the site more thoroughly, develop a remediation plan and cleanup the property • Had the consultant that conducted the initial Phase I and Phase II identified the potential presence of hazardous substances in the subsurface below the slab, the property would not have been acquired
  • 53. Plaintiff’s Contention • The Phase I consultant that conducted the Phase I/II did not meet the standard of care and should have known that these types of industrial facilities (testing vapor degreasers) require more comprehensive investigation, including sampling inside the building where the testing took place • The consultant should have known the state DEP’s reply was inaccurate (it was “obvious”) and conducted further investigation, i.e., visited the regulatory offices and conducted the manifest record search itself (it is widely known that hazardous waste transporters for any size generators typically utilize the manifest system) • The firm performing the Phase I was negligent and caused harm for which damages were sought
  • 54. Defendant’s Response • The interviews of plant personnel indicated: • The use of solvents at the plant was minimal • No recollection of spills or releases • Only minor amounts of waste solvent generated from the testing (1-2 quarts) • No manufacturing was done on site, only assembly and testing • State DEP had no manifests for the site (providing support that the site was likely a CESQG) • Search of the RCRA database by the government records search company indicated no hazardous waste generation records at the federal level for the site
  • 55. Defendant’s Response cont’d • The ASTM E1527 standard does not require independent verification of information received from third parties (including government agencies and personnel interviewed) but may rely on this information “unless he or she actual knowledge that certain information is incorrect or unless it is obvious that certain information is incorrect based on other information obtained or actually known to the environmental professional” • A CESQG is not required in the state to have an EPA ID number and is not required to manifest
  • 56. Result • Case was settled by the insurance company that provides the consultant’s E&O insurance
  • 57. Lessons Learned • If something does not pass the smell test, it probably is worth doing additional investigation • If you are relying on certain data for your professional opinion, make sure this is made clear in the Phase I report • If there are limitations in any of the site assessment activities reviewed, such as in this case the fact that there was no sampling inside the building below the slab, clearly identify this limitation in the Phase I report
  • 58. Final Thoughts 1. When you rely on important facts (such as the depth to groundwater or the type soil or groundwater flow direction from a Phase II investigation), be sure to reference the source. 2. When you rely on important assumptions (such as groundwater flow following surface topography, or the soil in the subsurface being homogenous), be sure to clearly state this. 3. When you provide your professional opinion, be sure always to condition it (e.g., clearly identify what you base it on).
  • 59. Final Thoughts 4. Be sure to identify in your terms and conditions the limiting conditions identified in the ASTM E1527 standard, i.e., the investigation is not exhaustive and uncertainty is not eliminated. 5. Describe your scope-of-work clearly and comprehensively 6. State who can rely on the report (anyone relying on the report should be provided the SOW, T&C and Limitations/Assumptions and be asked to confirm in writing that these have been reviewed; may also want to put a time limitation, e.g., 6 months, on the reliance) 7. When litigation takes place, a key question will be: “Did you clearly say what you will do?” And then: “ Did you do what you said you would, no more, no less?”