SlideShare a Scribd company logo
1 of 4
Download to read offline
C:dancerpdf_converterwork179_1433572874.14499442.rtf - 1 -
Dwyer v Kelly (Home Building) [2007] NSWCTTT 442 (1 August
2007)
CONSUMER, TRADER AND TENANCY TRIBUNAL
Home Building Division
APPLICATION NO: HB 07/19956 (formerly numbered 07/20688)
APPLICANT: Pauline Therese Dwyer
RESPONDENT: Geoffrey Kelly
APPEARANCES: Applicant in person
Respondent in person
HEARING: 22 June 2007
APPLICATION: The applicant sought an order that the respondent pay
her a sum between $35,000.00 and $45,000.00.
ORDER
The respondent is to fix, repair and make good, on or before 30 October
2007, in a proper and workmanlike manner, the following items:
1. Complete the internal painting, including eliminating the numerous
defects found by Inspector Meagher.
2. The wall and floor tiling in the ensuite so as to eliminate the sharp
and chipped tiling which creates a hazard to bare feet, as well as
those tiles behind the tap in the laundry which have fallen out.
3. Complete the external painting to eliminate the defects found by
Inspector Meagher, including the paintwork to the verandah beams
and clean all spills and marks caused during painting.
4. Remove all waste timber and debris still left on site, as well as
making good the following damage caused while carrying out
previous rectification work including:
1. Sanding mark on right hand side gutter,
2. Small amount of paint splatter on window of dining room,
3. Small paint marks on carpet in bedrooms 3 and 4, and
4. Small paint mark on render outside window of bedroom 2.
C:dancerpdf_converterwork179_1433572874.14499442.rtf - 2 -
REASONS FOR DECISION
1. The applicant, Pauline Therese Dwyer, a homeowner, and the respondent,
Geoffrey Kelly, a builder, signed a home building contract on 14 December
2004. The contract stipulated that the builder was to erect a single storey
kit house, manufactured by New England Country Homes Pty Limited, at
“Kurrawalla”, “…”, Molong for the sum of $364,844.00.
2. Work commenced shortly thereafter. While the dwelling was being
constructed, several changes were made which eventually increased both
the time for completion and the cost of the work. During December 2005,
the respondent moved into the dwelling. There is some dispute about
whether there was any date for “actual completion” and, if so, what that
date was.
3. At some stage, presumably between December 2005 and July 2006, the
local council issued an Occupation Certificate for the dwelling. In a letter
dated 28 July 2006, the General Manager of the Cabonne Council, GLP
Fleming, noted that the Council had acted in good faith in issuing that
Certificate but that an inspection on 5 June 2006 by the Council’s Manager
Building and Environment revealed there were some deficiencies within
the building.
4. In a letter dated 31 August 2006, Mr Stephen Sadlier, the Managing
Director of New England Country Homes Pty Limited, set out that he
visited the dwelling early in June 2006 and that it was his opinion that the
dwelling was soundly constructed with no visible evidence of structural
weakness. He claimed all the external timbers were properly installed and
securely fastened in accordance with good building practice. However, he
did find that some of the sub-trades had not exercised care in their
workmanship with the result that the overall finish of the dwelling was
disappointing.
5. Shortly after occupying the premises the applicant engaged A. Rendell
and Associates, construction consultants, to inspect the dwelling and
report on any defects considered to be the responsibility of the builder to
make good. Alec J. Rendell wrote a 22 page report on 10 April 2006, and
attached thereto various annexures. Section 7 of his report, being pages
10 – 22, itemises the defects found by Mr. Rendell. These were brought to
Mr Kelly’s attention so that he could make good these flaws.
6. Apparently some of these imperfections were deal with by Mr Kelly but his
failure throughout 2006 to address all the problems set out in the Rendell
report led to other parties becoming involved.
C:dancerpdf_converterwork179_1433572874.14499442.rtf - 3 -
7. One of those was Building Inspector Thomas Meagher of the NSW Office
of Fair Trading who wrote to the applicant on 10 February 2006
concerning her complaint about the work performed by the respondent. A
Complaint Inspection Report, dated 4 September 2006, was issued by Mr
Meagher. Attached to it is a list of 26 items considered by the Inspector to
be items of defective work. The respondent attended the premises and
performed some repair work. There was a site meeting between the
applicant and Inspector Meagher on 28 November 2006, and on 5
December 2006 he issued a Rectification Order that 14 items of defective
work be rectified.
8. Apparently the builder attended the premises and further repairs were
carried out. Another site inspection was held on 11 January 2007 and in a
document headed “Building Inspection Report – Addendum”, dated 9
February 2007, the Inspector listed 4 of the 14 items of the Rectification
Order which had not been completed. The Inspector also noted that the
builder, in carrying out the rectification work, had caused damage in 4
specific and identified instances.
9. The applicant has had the advantage of an inspection by a building
inspector of the Office of Fair Trading. Mr Meagher’s Building Inspection
Report – Addendum of 9 February 2007 sets out four items of work listed
in his Rectification Order that have not been completed and that in
carrying out the rectification work which he had ordered to be done, the
respondent had caused 4 instances of damage. Section “A” of the
applicant’s written submission set out the financial claim against the
respondent amounting to a claim between $35,793.87 and $45,788.87.
The range of the claim depends on which quotation from various
contractors is used to make the calculation.
10.The Building Inspector from the Office of Fair Trading has set out the 4
items of work still to be completed as well as four instances of damage
which have to be made good. These are:
1. Internal painting not completed in a good and workmanlike manner.
2. Wall and floor tiling not completed in a good and workmanlike manner.
3. External painting not completed in a good and workmanlike manner.
4. Waste timber left on site
while the damage caused in carrying out rectification work is listed as:
1, Sanding mark on right hand side gutter
2. Small amount of paint splatter on window of dining room
3. Small paint marks on carpet in bedrooms 3 and 4
4. Small paint mark on render outside window of bedroom 2.
11.The builder should be given the opportunity to make good these
outstanding items. Otherwise, he is on notice that should he fail to
complete the work ordered by the Tribunal, then the applicant can seek to
renew her application and convert the Tribunal’s orders for rectification to
C:dancerpdf_converterwork179_1433572874.14499442.rtf - 4 -
a money order so that she may have the defects repaired by the
tradesmen of her choice at the builder’s cost.
12.Therefore, the orders set out on the first page of these reasons are made.
Bruce Howe
Member
Consumer Trader & Tenancy Tribunal
1 August 2007

More Related Content

What's hot

Resume Wayne Recent
Resume Wayne RecentResume Wayne Recent
Resume Wayne Recent
wayne cullen
 
An introduction to Men in White, Sydney
An introduction to Men in White, SydneyAn introduction to Men in White, Sydney
An introduction to Men in White, Sydney
meninwhite
 
Todd F Burns new resume
Todd F Burns new resumeTodd F Burns new resume
Todd F Burns new resume
Todd Burns
 
67 GARRICK STREET COOLANGATTA s
67 GARRICK STREET COOLANGATTA s67 GARRICK STREET COOLANGATTA s
67 GARRICK STREET COOLANGATTA s
Mike Darwich
 

What's hot (17)

Item # 9 - Award ADA Swimming Pool Renovations
Item # 9 - Award ADA Swimming Pool RenovationsItem # 9 - Award ADA Swimming Pool Renovations
Item # 9 - Award ADA Swimming Pool Renovations
 
C.V. u
C.V. uC.V. u
C.V. u
 
mathys eugene cv
mathys eugene cvmathys eugene cv
mathys eugene cv
 
Resume Wayne Recent
Resume Wayne RecentResume Wayne Recent
Resume Wayne Recent
 
An introduction to Men in White, Sydney
An introduction to Men in White, SydneyAn introduction to Men in White, Sydney
An introduction to Men in White, Sydney
 
An introduction to Men in White, Sydney
An introduction to Men in White, SydneyAn introduction to Men in White, Sydney
An introduction to Men in White, Sydney
 
Untitled(2)
Untitled(2)Untitled(2)
Untitled(2)
 
Binder2
Binder2Binder2
Binder2
 
115 Sansome - Centro
115 Sansome - Centro115 Sansome - Centro
115 Sansome - Centro
 
José eustaquio de almeida
José eustaquio de almeidaJosé eustaquio de almeida
José eustaquio de almeida
 
BIM and the drywall cover up - A case for division 9
BIM and the drywall cover up - A case for division 9 BIM and the drywall cover up - A case for division 9
BIM and the drywall cover up - A case for division 9
 
Todd F Burns new resume
Todd F Burns new resumeTodd F Burns new resume
Todd F Burns new resume
 
Project proposal
Project proposalProject proposal
Project proposal
 
House Remodeling Proposal PowerPoint Presentation Slides
House Remodeling Proposal PowerPoint Presentation SlidesHouse Remodeling Proposal PowerPoint Presentation Slides
House Remodeling Proposal PowerPoint Presentation Slides
 
KGC Power point
KGC Power pointKGC Power point
KGC Power point
 
Reconstruction And Remodeling Proposal PowerPoint Presentation Slides
Reconstruction And Remodeling Proposal PowerPoint Presentation SlidesReconstruction And Remodeling Proposal PowerPoint Presentation Slides
Reconstruction And Remodeling Proposal PowerPoint Presentation Slides
 
67 GARRICK STREET COOLANGATTA s
67 GARRICK STREET COOLANGATTA s67 GARRICK STREET COOLANGATTA s
67 GARRICK STREET COOLANGATTA s
 

Viewers also liked

Career opportunties after learning english by akash maurya pca aasthan iset,k...
Career opportunties after learning english by akash maurya pca aasthan iset,k...Career opportunties after learning english by akash maurya pca aasthan iset,k...
Career opportunties after learning english by akash maurya pca aasthan iset,k...
AKASH MAURYA
 
How To Choose Recessed Fixtures
How To Choose Recessed FixturesHow To Choose Recessed Fixtures
How To Choose Recessed Fixtures
IES Light Logic
 

Viewers also liked (13)

Monthly Faiz-e-Aalam-june-2013 2
Monthly Faiz-e-Aalam-june-2013 2Monthly Faiz-e-Aalam-june-2013 2
Monthly Faiz-e-Aalam-june-2013 2
 
Life Of Muhammad saw
Life Of Muhammad saw Life Of Muhammad saw
Life Of Muhammad saw
 
Score of Fifa women's world cup 2015
Score of Fifa women's world cup 2015Score of Fifa women's world cup 2015
Score of Fifa women's world cup 2015
 
مؤتمر بانكوك
مؤتمر بانكوكمؤتمر بانكوك
مؤتمر بانكوك
 
Software security
Software securitySoftware security
Software security
 
The Customer-activated Telecom Provider (global C-suite study 2013)
The Customer-activated Telecom Provider (global C-suite study 2013)The Customer-activated Telecom Provider (global C-suite study 2013)
The Customer-activated Telecom Provider (global C-suite study 2013)
 
Maxim Tsvetkov
Maxim TsvetkovMaxim Tsvetkov
Maxim Tsvetkov
 
Career opportunties after learning english by akash maurya pca aasthan iset,k...
Career opportunties after learning english by akash maurya pca aasthan iset,k...Career opportunties after learning english by akash maurya pca aasthan iset,k...
Career opportunties after learning english by akash maurya pca aasthan iset,k...
 
MALIK
MALIKMALIK
MALIK
 
How To Choose Recessed Fixtures
How To Choose Recessed FixturesHow To Choose Recessed Fixtures
How To Choose Recessed Fixtures
 
De la torre, delia (1)
De la torre, delia (1)De la torre, delia (1)
De la torre, delia (1)
 
Perumahan Murah Karawang
Perumahan Murah KarawangPerumahan Murah Karawang
Perumahan Murah Karawang
 
David Bowie in American Horror Story
David Bowie in American Horror StoryDavid Bowie in American Horror Story
David Bowie in American Horror Story
 

Similar to Dwyer v Kelly (Home Building) [2007] NSWCTTT 442

Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
Alec Rendell [NBPR-2]
 
McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
Alec Rendell [NBPR-2]
 
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Alec Rendell [NBPR-2]
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
Jamal Nelson, CCM
 
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
Alec Rendell [NBPR-2]
 
Pathology assignment
Pathology assignment Pathology assignment
Pathology assignment
Mark Percival
 

Similar to Dwyer v Kelly (Home Building) [2007] NSWCTTT 442 (11)

Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
Gugliemino v Advance Flooring Co P.L (Home Building) [2005] NSWCTTT 162
 
McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
McKenzie v Dean T.as T & D Dean Building [2003] NSWCTTT 386
 
March 2015 presentation to ASBC on slab heave and damages
March 2015 presentation to ASBC on slab heave and damagesMarch 2015 presentation to ASBC on slab heave and damages
March 2015 presentation to ASBC on slab heave and damages
 
Lessons Learned from Phase I Litigation: Case Studies
Lessons Learned from Phase I Litigation: Case StudiesLessons Learned from Phase I Litigation: Case Studies
Lessons Learned from Phase I Litigation: Case Studies
 
Lawsuit versus 1 and 1 Electric and Sami Khosravi
Lawsuit versus 1 and 1 Electric and Sami KhosraviLawsuit versus 1 and 1 Electric and Sami Khosravi
Lawsuit versus 1 and 1 Electric and Sami Khosravi
 
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
Ultra Developments Pty Ltd v Alison Bennett [2014] NSWCATCD 61
 
Lessons Learned from Phase I Litigation: Case Studies
Lessons Learned from Phase I Litigation: Case StudiesLessons Learned from Phase I Litigation: Case Studies
Lessons Learned from Phase I Litigation: Case Studies
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
Tyler & Miller v Rawson Homes P.L (Home Building) [2005] NSWCTTT 153
 
Pathology assignment
Pathology assignment Pathology assignment
Pathology assignment
 
Pre Renovation Handbook
Pre Renovation HandbookPre Renovation Handbook
Pre Renovation Handbook
 

More from Alec Rendell [NBPR-2]

Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
Alec Rendell [NBPR-2]
 
FORDHAM #3 of 3; Fordham v Hobson (Dewsash) (Home.B) [2013] NSWCTTT 590
FORDHAM #3 of 3; Fordham v Hobson (Dewsash) (Home.B) [2013] NSWCTTT 590FORDHAM #3 of 3; Fordham v Hobson (Dewsash) (Home.B) [2013] NSWCTTT 590
FORDHAM #3 of 3; Fordham v Hobson (Dewsash) (Home.B) [2013] NSWCTTT 590
Alec Rendell [NBPR-2]
 
FORDHAM #2 of 3; Fordham v Dewsash PL t.as SP&W.Hobson [2012] NSWDC 109
FORDHAM #2 of 3; Fordham v Dewsash PL t.as SP&W.Hobson [2012] NSWDC 109FORDHAM #2 of 3; Fordham v Dewsash PL t.as SP&W.Hobson [2012] NSWDC 109
FORDHAM #2 of 3; Fordham v Dewsash PL t.as SP&W.Hobson [2012] NSWDC 109
Alec Rendell [NBPR-2]
 
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
Alec Rendell [NBPR-2]
 
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
Alec Rendell [NBPR-2]
 
'Arlie' Private Residence; Lyndhurst NSW
'Arlie' Private Residence; Lyndhurst NSW'Arlie' Private Residence; Lyndhurst NSW
'Arlie' Private Residence; Lyndhurst NSW
Alec Rendell [NBPR-2]
 
Western District H3ealth Fund; Lithgow NSW
Western District H3ealth Fund; Lithgow NSWWestern District H3ealth Fund; Lithgow NSW
Western District H3ealth Fund; Lithgow NSW
Alec Rendell [NBPR-2]
 
Accomodation Block; Jenolan Caves NSW
Accomodation Block; Jenolan Caves NSWAccomodation Block; Jenolan Caves NSW
Accomodation Block; Jenolan Caves NSW
Alec Rendell [NBPR-2]
 

More from Alec Rendell [NBPR-2] (19)

Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
Ultra Developments Pty Ltd v Nagle (Home Building) [2012] NSWCTTT 518
 
FORDHAM #3 of 3; Fordham v Hobson (Dewsash) (Home.B) [2013] NSWCTTT 590
FORDHAM #3 of 3; Fordham v Hobson (Dewsash) (Home.B) [2013] NSWCTTT 590FORDHAM #3 of 3; Fordham v Hobson (Dewsash) (Home.B) [2013] NSWCTTT 590
FORDHAM #3 of 3; Fordham v Hobson (Dewsash) (Home.B) [2013] NSWCTTT 590
 
FORDHAM #2 of 3; Fordham v Dewsash PL t.as SP&W.Hobson [2012] NSWDC 109
FORDHAM #2 of 3; Fordham v Dewsash PL t.as SP&W.Hobson [2012] NSWDC 109FORDHAM #2 of 3; Fordham v Dewsash PL t.as SP&W.Hobson [2012] NSWDC 109
FORDHAM #2 of 3; Fordham v Dewsash PL t.as SP&W.Hobson [2012] NSWDC 109
 
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
FORDHAM #1 of 3; Fordham v Hobson (Home Building) [2011] NSWCTTT 164
 
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
Rich v Fair Trading Administration Corporation [2000] NSWFTT 10
 
MOLONG CENTRAL SCHOOL CAPITAL WORKS
MOLONG CENTRAL SCHOOL CAPITAL WORKSMOLONG CENTRAL SCHOOL CAPITAL WORKS
MOLONG CENTRAL SCHOOL CAPITAL WORKS
 
Orphan Rocker; Katoomba
Orphan Rocker; KatoombaOrphan Rocker; Katoomba
Orphan Rocker; Katoomba
 
Coonabarabran Hospital Upgrade
Coonabarabran Hospital Upgrade Coonabarabran Hospital Upgrade
Coonabarabran Hospital Upgrade
 
Gundagai High School
Gundagai High SchoolGundagai High School
Gundagai High School
 
RSL Club; Dubbo NSW
RSL Club; Dubbo NSWRSL Club; Dubbo NSW
RSL Club; Dubbo NSW
 
Katoomba Public School; NSW
Katoomba Public School; NSWKatoomba Public School; NSW
Katoomba Public School; NSW
 
Supa K-Mart; Katoomba. NSW
Supa K-Mart; Katoomba. NSWSupa K-Mart; Katoomba. NSW
Supa K-Mart; Katoomba. NSW
 
Lithgow Tafe; Lithgow. NSW
Lithgow Tafe; Lithgow. NSWLithgow Tafe; Lithgow. NSW
Lithgow Tafe; Lithgow. NSW
 
Calvary Hospital; Wagga Wagga NSW
Calvary Hospital; Wagga Wagga NSWCalvary Hospital; Wagga Wagga NSW
Calvary Hospital; Wagga Wagga NSW
 
Public School; Menindee NSW
Public School; Menindee NSWPublic School; Menindee NSW
Public School; Menindee NSW
 
Band Club Restoration; St Marys NSW
Band Club Restoration; St Marys NSWBand Club Restoration; St Marys NSW
Band Club Restoration; St Marys NSW
 
'Arlie' Private Residence; Lyndhurst NSW
'Arlie' Private Residence; Lyndhurst NSW'Arlie' Private Residence; Lyndhurst NSW
'Arlie' Private Residence; Lyndhurst NSW
 
Western District H3ealth Fund; Lithgow NSW
Western District H3ealth Fund; Lithgow NSWWestern District H3ealth Fund; Lithgow NSW
Western District H3ealth Fund; Lithgow NSW
 
Accomodation Block; Jenolan Caves NSW
Accomodation Block; Jenolan Caves NSWAccomodation Block; Jenolan Caves NSW
Accomodation Block; Jenolan Caves NSW
 

Dwyer v Kelly (Home Building) [2007] NSWCTTT 442

  • 1. C:dancerpdf_converterwork179_1433572874.14499442.rtf - 1 - Dwyer v Kelly (Home Building) [2007] NSWCTTT 442 (1 August 2007) CONSUMER, TRADER AND TENANCY TRIBUNAL Home Building Division APPLICATION NO: HB 07/19956 (formerly numbered 07/20688) APPLICANT: Pauline Therese Dwyer RESPONDENT: Geoffrey Kelly APPEARANCES: Applicant in person Respondent in person HEARING: 22 June 2007 APPLICATION: The applicant sought an order that the respondent pay her a sum between $35,000.00 and $45,000.00. ORDER The respondent is to fix, repair and make good, on or before 30 October 2007, in a proper and workmanlike manner, the following items: 1. Complete the internal painting, including eliminating the numerous defects found by Inspector Meagher. 2. The wall and floor tiling in the ensuite so as to eliminate the sharp and chipped tiling which creates a hazard to bare feet, as well as those tiles behind the tap in the laundry which have fallen out. 3. Complete the external painting to eliminate the defects found by Inspector Meagher, including the paintwork to the verandah beams and clean all spills and marks caused during painting. 4. Remove all waste timber and debris still left on site, as well as making good the following damage caused while carrying out previous rectification work including: 1. Sanding mark on right hand side gutter, 2. Small amount of paint splatter on window of dining room, 3. Small paint marks on carpet in bedrooms 3 and 4, and 4. Small paint mark on render outside window of bedroom 2.
  • 2. C:dancerpdf_converterwork179_1433572874.14499442.rtf - 2 - REASONS FOR DECISION 1. The applicant, Pauline Therese Dwyer, a homeowner, and the respondent, Geoffrey Kelly, a builder, signed a home building contract on 14 December 2004. The contract stipulated that the builder was to erect a single storey kit house, manufactured by New England Country Homes Pty Limited, at “Kurrawalla”, “…”, Molong for the sum of $364,844.00. 2. Work commenced shortly thereafter. While the dwelling was being constructed, several changes were made which eventually increased both the time for completion and the cost of the work. During December 2005, the respondent moved into the dwelling. There is some dispute about whether there was any date for “actual completion” and, if so, what that date was. 3. At some stage, presumably between December 2005 and July 2006, the local council issued an Occupation Certificate for the dwelling. In a letter dated 28 July 2006, the General Manager of the Cabonne Council, GLP Fleming, noted that the Council had acted in good faith in issuing that Certificate but that an inspection on 5 June 2006 by the Council’s Manager Building and Environment revealed there were some deficiencies within the building. 4. In a letter dated 31 August 2006, Mr Stephen Sadlier, the Managing Director of New England Country Homes Pty Limited, set out that he visited the dwelling early in June 2006 and that it was his opinion that the dwelling was soundly constructed with no visible evidence of structural weakness. He claimed all the external timbers were properly installed and securely fastened in accordance with good building practice. However, he did find that some of the sub-trades had not exercised care in their workmanship with the result that the overall finish of the dwelling was disappointing. 5. Shortly after occupying the premises the applicant engaged A. Rendell and Associates, construction consultants, to inspect the dwelling and report on any defects considered to be the responsibility of the builder to make good. Alec J. Rendell wrote a 22 page report on 10 April 2006, and attached thereto various annexures. Section 7 of his report, being pages 10 – 22, itemises the defects found by Mr. Rendell. These were brought to Mr Kelly’s attention so that he could make good these flaws. 6. Apparently some of these imperfections were deal with by Mr Kelly but his failure throughout 2006 to address all the problems set out in the Rendell report led to other parties becoming involved.
  • 3. C:dancerpdf_converterwork179_1433572874.14499442.rtf - 3 - 7. One of those was Building Inspector Thomas Meagher of the NSW Office of Fair Trading who wrote to the applicant on 10 February 2006 concerning her complaint about the work performed by the respondent. A Complaint Inspection Report, dated 4 September 2006, was issued by Mr Meagher. Attached to it is a list of 26 items considered by the Inspector to be items of defective work. The respondent attended the premises and performed some repair work. There was a site meeting between the applicant and Inspector Meagher on 28 November 2006, and on 5 December 2006 he issued a Rectification Order that 14 items of defective work be rectified. 8. Apparently the builder attended the premises and further repairs were carried out. Another site inspection was held on 11 January 2007 and in a document headed “Building Inspection Report – Addendum”, dated 9 February 2007, the Inspector listed 4 of the 14 items of the Rectification Order which had not been completed. The Inspector also noted that the builder, in carrying out the rectification work, had caused damage in 4 specific and identified instances. 9. The applicant has had the advantage of an inspection by a building inspector of the Office of Fair Trading. Mr Meagher’s Building Inspection Report – Addendum of 9 February 2007 sets out four items of work listed in his Rectification Order that have not been completed and that in carrying out the rectification work which he had ordered to be done, the respondent had caused 4 instances of damage. Section “A” of the applicant’s written submission set out the financial claim against the respondent amounting to a claim between $35,793.87 and $45,788.87. The range of the claim depends on which quotation from various contractors is used to make the calculation. 10.The Building Inspector from the Office of Fair Trading has set out the 4 items of work still to be completed as well as four instances of damage which have to be made good. These are: 1. Internal painting not completed in a good and workmanlike manner. 2. Wall and floor tiling not completed in a good and workmanlike manner. 3. External painting not completed in a good and workmanlike manner. 4. Waste timber left on site while the damage caused in carrying out rectification work is listed as: 1, Sanding mark on right hand side gutter 2. Small amount of paint splatter on window of dining room 3. Small paint marks on carpet in bedrooms 3 and 4 4. Small paint mark on render outside window of bedroom 2. 11.The builder should be given the opportunity to make good these outstanding items. Otherwise, he is on notice that should he fail to complete the work ordered by the Tribunal, then the applicant can seek to renew her application and convert the Tribunal’s orders for rectification to
  • 4. C:dancerpdf_converterwork179_1433572874.14499442.rtf - 4 - a money order so that she may have the defects repaired by the tradesmen of her choice at the builder’s cost. 12.Therefore, the orders set out on the first page of these reasons are made. Bruce Howe Member Consumer Trader & Tenancy Tribunal 1 August 2007