TIME IMPACT ANALYSIS
Itis a method used to determine the extent of impact from
potential delay in the construction process.
It involves inserting additional activities indicating delays or
changes into an updated schedule representing progress up to the
point when a delay event occurred to determine the impact of
those delay activities
3.
3
TYPES OF DELAY
EXCUSABLEDELAYS
It occurs when the affected party is allowed to
claim for a time extension, compensation, or both.
NON-EXCUSABLE DELAYS
These are delays that the contractor or the affected
party needs to bear responsibility for
4.
SAMPLE BASELINE DATADATE SEP 04 2023
DELAY
NON EXCUSABLE
EXCUSABLE
NONCOMPENSABLE
EXCUSABLE
COMPENSABLE
0 112 0 0 0 0
MONTH #
PROJ.
COMPLETION
(days)
DELAY
DURING
PERIOD
COMMENTS
SAMPLE UPDATE 2ndMONTH UPDATE
DATA DATE OCT 30 2023
DELAY (CRICTICAL PATH) DELAY (NON CRITICAL PATH)
NON EXCUSABLE
EXCUSABLE
NONCOMPENSABLE
EXCUSABLE
COMPENSABLE
NON EXCUSABLE
EXCUSABLE
NONCOMPENSABLE
EXCUSABLE
COMPENSABLE
0 112 0 0 0 0 0 0 0
1 133 21 0 0 21 0 0 0 Unforeseen Site Condition
2 133 0 0 0 0 0 0 0
MONTH #
PROJ.
COMPLETION
(days)
DELAY
DURING
PERIOD
COMMENTS
There is no delay
9.
SAMPLE UPDATE 3rdMONTH UPDATE
DATA DATE NOV 27 2023
2 Concurrent Delays:
- Owner initiated design
changes (14 days)
- Contractor left the jobsite
(21 days)
10.
SAMPLE UPDATE
2 ConcurrentDelays:
- Owner initiated design
changes (14 days)
- Contractor left the jobsite
(21 days)
3rd MONTH UPDATE
DATA DATE NOV 27 2023
Therefore, 14 days charged to the owner & 7 days charged to the contractor
11.
SAMPLE UPDATE 4thMONTH UPDATE
DATA DATE DEC 26 2023
The contractor caused a
delay in “ Garage Walls” – a
non-critical activity
12.
SAMPLE UPDATE 4thMONTH UPDATE
DATA DATE DEC 26 2023
The contractor caused a
delay in “ Garage Walls” – a
non-critical activity
As long as the activity has available total float it will not affect the final completion date
13.
SAMPLE UPDATE 5thMONTH UPDATE
DATA DATE JAN 22 2024
The owner caused a 28-days
delay on “Garage Doors”
14.
SAMPLE UPDATE 5thMONTH UPDATE
DATA DATE JAN 22 2024
The owner caused a 28-days
delay on “Garage Doors”
The delay moved the critical path by 7 days. The rest of 21 day-delay was absorbed by the remaining available
float. Then, there will be only 7 days of “excusable compensable delay.”
OVERALL TIME IMPACTANALYSIS REPORT
DELAY (CRICTICAL PATH) DELAY (NON CRITICAL PATH)
NON EXCUSABLE
EXCUSABLE
NONCOMPENSABLE
EXCUSABLE
COMPENSABLE
NON EXCUSABLE
EXCUSABLE
NONCOMPENSABLE
EXCUSABLE
COMPENSABLE
0 112 0 0 0 0 0 0 0
1 133 21 0 0 21 0 0 0 Unforeseen Site Condition
2 133 0 0 0 0 0 0 0
3 154 21 7 0 0 0 0 14
Owner initiated design change;
Contractor left jobsite
4 154 0 0 0 0 0 0 0
5 161 7 0 0 0 0 0 7 Owner revised the Garage Door
6 161 0 0 0 0 0 0 0
MONTH #
PROJ.
COMPLETION
(days)
DELAY
DURING
PERIOD
COMMENTS
49 7 0 21 0 0 21
TOTAL
Excusable & Compensable
Delay (time and cost)
21 days Excavation Delay
14 days Design Change by Owner
07 days Garage Door Revision by Owner
Subtotal 42 days
Non Excusable & Non
Compensable
07 days Subcontractor Replacement Delay
Subtotal 07 days
TOTAL 49 days OVERALL DELAY IMPACT
20.
SAMPLE TIME IMPACTANALYSIS DUE TO COVID-19
LOCKDOWN PERIOD
SCENARIO:
On the 5th Month Schedule Update social distancing was implemented due to COVID 19 breakout
on the project. Consequently, reducing 50% of manpower in the affected remaining activities
Impact Analysis on the Primavera Schedule:
• Secure a Baseline Schedule
• Ensure the schedule is resource & cost loaded
• Update the schedule based on the required Data Date
• Apply required calendar and assign it on the affected remaining activities
21.
SAMPLE TIME IMPACTANALYSIS DUE TO COVID-19
LOCKDOWN PERIOD
28 days delayed due to COVID 50% resource deployment impact
BL Calendar with 10hrs/Day
50% impact on Covid Protocol
28 DAYS
EOT
22.
JAN 8 DD
BaselinePlanned Date Completion: 04-Feb-2022
Current Date Completion: 04-Mar-2022
23.
Current Planned DateCompletion: 04-Mar.2022
Jan. 8
DD
Baseline Planned Date Completion: 04-
Feb.2022
Also Materials & Equipment Resource will be move
parallel in connection with the Labor Resource
28 days
EOT