The document provides guidance on preparing Detailed Project Reports (DPRs) for slum redevelopment projects under the Rajiv Awas Yojana (RAY) scheme. It outlines the 10 steps to prepare a DPR, including selecting a slum, surveying the area, assessing deficiencies, integrating social infrastructure, establishing citywide linkages, obtaining approvals, designing the project, estimating costs, and planning implementation. DPRs must cover the "whole slum" and include proposals for housing, basic infrastructure, and social amenities to tackle problems faced by residents.
The general concept of a metropolitan area (MA)1 is that of a core area containing a large population nucleus, together with adjacent communities that have a high degree of economic and social integration with that core. The Federal Office of Management and Budget (OMB)2 designates and defines MAs following a set of official standards.
Urban planning for smart cities - Smart tools for Smart CitiesVivek Pai
Smart Cities are the future of India and the GoI's Vision of a 100 Smart cities is slowly but surely coming into reality. The presenter discusses aspects of Smart cities and using the examples of some key projects and tools used by cities to add to the layers of smartness!
To make ensure all Urban Local Bodies are declared ODF ++ and applying for further highest certification in terms of Sanitation and hygiene. Since Water + is high certification and necessity to get it "No Black and Grey water is flowing in open Environment and discharge water is being treated in respective STP or FSTP.
Planning for Broadway now provides an opportunity to
coordinate transit-supportive land use, affordable housing
policies, transportation connectivity and public realm
design with the rapid transit project.
This webinar was hosted on 20th August, 2015 from 4:00 – 5:00 pm IST and was presented by Vijay Anadkat, Senior Manager, EMBARQ India.
With a view to recast the urban landscape of India and make urban areas more livable and inclusive to drive economic growth in the country, the Government of India recently launched two ambitious projects - Smart City and Atal Mission for Rejuvenation and Urban Transportation (AMRUT). The purpose of AMRUT is to 1) ensure that every household has access to a tap with assured supply of water and a sewerage connection; 2) increase the amenity value of cities by developing greenery and well maintained open spaces; and 3) reduce pollution by switching to public transport or constructing facilities for non-motorized transport. The Mission is being implemented in 500 cities towns with a population of over 1 lakh.
This webinar discussed the current state of urbanization in India, the various propositions suggested by the government as a part of the AMRUT scheme and the feasibility of this project.
Webinar Recording - http://embarqindiahub.org/webinars/atal-mission-rejuvenation-and-urban-transportation-amrut-achievable-or-not
This presentation was given by SPA Bhopal for "Samavesh" - XVl Annual NOSPlan Convention. The Theme of Presentation - "Accessibility in Peri-urban area".
The general concept of a metropolitan area (MA)1 is that of a core area containing a large population nucleus, together with adjacent communities that have a high degree of economic and social integration with that core. The Federal Office of Management and Budget (OMB)2 designates and defines MAs following a set of official standards.
Urban planning for smart cities - Smart tools for Smart CitiesVivek Pai
Smart Cities are the future of India and the GoI's Vision of a 100 Smart cities is slowly but surely coming into reality. The presenter discusses aspects of Smart cities and using the examples of some key projects and tools used by cities to add to the layers of smartness!
To make ensure all Urban Local Bodies are declared ODF ++ and applying for further highest certification in terms of Sanitation and hygiene. Since Water + is high certification and necessity to get it "No Black and Grey water is flowing in open Environment and discharge water is being treated in respective STP or FSTP.
Planning for Broadway now provides an opportunity to
coordinate transit-supportive land use, affordable housing
policies, transportation connectivity and public realm
design with the rapid transit project.
This webinar was hosted on 20th August, 2015 from 4:00 – 5:00 pm IST and was presented by Vijay Anadkat, Senior Manager, EMBARQ India.
With a view to recast the urban landscape of India and make urban areas more livable and inclusive to drive economic growth in the country, the Government of India recently launched two ambitious projects - Smart City and Atal Mission for Rejuvenation and Urban Transportation (AMRUT). The purpose of AMRUT is to 1) ensure that every household has access to a tap with assured supply of water and a sewerage connection; 2) increase the amenity value of cities by developing greenery and well maintained open spaces; and 3) reduce pollution by switching to public transport or constructing facilities for non-motorized transport. The Mission is being implemented in 500 cities towns with a population of over 1 lakh.
This webinar discussed the current state of urbanization in India, the various propositions suggested by the government as a part of the AMRUT scheme and the feasibility of this project.
Webinar Recording - http://embarqindiahub.org/webinars/atal-mission-rejuvenation-and-urban-transportation-amrut-achievable-or-not
This presentation was given by SPA Bhopal for "Samavesh" - XVl Annual NOSPlan Convention. The Theme of Presentation - "Accessibility in Peri-urban area".
Best Crypto Marketing Ideas to Lead Your Project to SuccessIntelisync
In this comprehensive slideshow presentation, we delve into the intricacies of crypto marketing, offering invaluable insights and strategies to propel your project to success in the dynamic cryptocurrency landscape. From understanding market trends to building a robust brand identity, engaging with influencers, and analyzing performance metrics, we cover all aspects essential for effective marketing in the crypto space.
Also Intelisync, our cutting-edge service designed to streamline and optimize your marketing efforts, leveraging data-driven insights and innovative strategies to drive growth and visibility for your project.
With a data-driven approach, transparent communication, and a commitment to excellence, InteliSync is your trusted partner for driving meaningful impact in the fast-paced world of Web3. Contact us today to learn more and embark on a journey to crypto marketing mastery!
Ready to elevate your Web3 project to new heights? Contact InteliSync now and unleash the full potential of your crypto venture!
What You're Going to Learn
- How These 4 Leaks Force You To Work Longer And Harder in order to grow your income… improve just one of these and the impact could be life changing.
- How to SHUT DOWN the revolving door of Income Stagnation… you know, where new sales come into your magazine while at the same time existing sponsors exit.
- How to transform your magazine business by fixing the 4 “DON’Ts”...
#1 LEADS Don’t Book
#2 PROSPECTS Don’t Show
#3 PROSPECTS Don’t Buy
#4 CLIENTS Don’t Stay
- How to identify which leak to fix first so you get the biggest bang for your income.
- Get actionable strategies you can use right away to improve your bookings, sales and retention.
Explore Sarasota Collection's exquisite and long-lasting dining table sets and chairs in Sarasota. Elevate your dining experience with our high-quality collection!
2. INTRODUCTION
RAJIV AWAS YOJANA
2
RAY envisages two-step implementation strategy i.e.
1. Preparation of Slum free City Plan of Action (SFCPoA) and
2. Preparation of projects for selected slums.
For intervention in the selected slum(s),Detailed Project
Reports ( DPRs) are to be prepared on ‘Whole Slum basis’.
The presentation outlines :
• DPR preparation and submission process
• Types of intervention
• Admissible components
• Steps in DPR preparation
• Suggested contents of DPR
Ministry of Housing and Urban Poverty Alleviation
3. DPR PREPARATION AND SUBMISSION PROCESS
RAJIV AWAS YOJANA
3
• Implementing agencies (States/UTs/ULBs/Parastatals &
Central Govt. Agencies) would be required to prepare DPRs
covering ‘Whole Slum’ on the basis of prioritisation of slums in
SFCPoAs.
• States / UTs have the liberty to submit DPRs for sanction,
pending the preparation of SFCPoAs only in the first year of
launch of the scheme, thereafter implementing agencies are
required to prepare SFCPoA first and then DPR for selected
slum.
• During the pendency of SFCPoA finalisation, cities are
expected to list existing slums in the city & give reasons and
justification for the selection of slum for intervention.
• While selecting slum for preparation of DPR it should be
ensured by State / ULB that the slum dwellers are residing in
the slum for a period of 5 years
Ministry of Housing and Urban Poverty Alleviation
4. DPR PREPARATION AND SUBMISSION PROCESS
RAJIV AWAS YOJANA
4
• DPRs are required to be submitted with the executive
summary, checklists and undertaking by State / ULB
duly filled for facilitating faster approval.
• DPRs are to be submitted to the Ministry by the State
Level Nodal Agency (SLNA) with the approval of the
State Level Sanctioning & Monitoring Committee
(SLSMC) for sanction by a Central Sanctioning and
Monitoring Committee (CSMC).
• DPRs can be submitted to the appraisal agencies also
after making entry in the IPoMS.
Ministry of Housing and Urban Poverty Alleviation
5. TYPE OF INTERVENTIONS
RAJIV AWAS YOJANA
5
Following interventions can be taken up as per requirement of Project:
• In-situ re-development (Housing and Infrastructure )
• In-situ up-gradation (Filling gaps in Housing and Infrastructure)
• Relocation (Housing & infrastructure). Only in unavoidable cases &
after prior consent of slum dwellers.
Cluster of slums should be preferred to obtain advantages of
integration of connectivity with city wide network of infrastructure
and optimum use of land.
Execution of Project :
Execution of projects should be taken up by ULBs.
Preference may be given for beneficiaries led execution.
In exceptional cases execution can be taken up by Parastatals after
consent of concerned ULB.
Ministry of Housing and Urban Poverty Alleviation
6. ADMISSIBLE COMPONENTS
RAJIV AWAS YOJANA
6
• Housing :
i. New dwelling (single or multi storied) units with 21-27 Sqm carpet
area (CA). (2 rooms, kitchen, bath & toilet).
ii. Rental dwelling units (single or multi storied) with CA 16-20 Sqm
with shared civic infrastructure. ( 21-27 Sqm in exceptional cases)
iii. Incremental : Up-gradation of existing DUs by providing additional
room, kitchen, toilet ( either or all) limited to 21-27 Sqm CA.
• Social Infrastructure :
i. Anganwadi, Pre schools, Child care Centres, Livelihood Centre.
Multi purpose community Centre. Library cum study center,
Training center for computer training with internet provisions
ii. Community toilets, Parks and Play equipment.
iii. Health centres/ sub Centres ( if funds are not available from other
scheme)
Ministry of Housing and Urban Poverty Alleviation
7. ADMISSIBLE COMPONENTS ( Cont..)
RAJIV AWAS YOJANA
7
• Basic civic Infrastructure :
i. Roads ( Internal and approach), Water Supply, Sewerage, Drainage,
Solid Waste Management, Street Lights, Internet cables, Rain Water
Harvesting.
ii. Temporary transit units
iii. Retaining wall, fencing and boundary wall ( in exceptional cases)
iv. Animal pen, cattle/rickshaw/ work shed
v. Site Development i/c leveling & Landscaping
• Convergence with ongoing Schemes of:
i. Health, Education and Social welfare.
ii. Infrastructure Connectivity.
• Other Charges* :
i. O&M cost, up-to 4% of the project cost (One time).
ii. DPR preparation, PM, TPIM, social audit etc.
(*By the Centre and State in the same proportion as the funding pattern)
Ministry of Housing and Urban Poverty Alleviation
8. ADMISSIBLE COMPONENTS ( Cont..)
RAJIV AWAS YOJANA
8
• The upper ceiling of Rs 5 Lakh per DU (i/c cost of civic and social
infrastructure) for cities with population more than 5 lakh and for
North East & Special category States irrespective of population.
• The upper ceiling of Rs 4 Lakh per DU (i/c cost of civic and social
infrastructure) for cities with population less than 5 lakh.
• Cost of civic infrastructure and social amenities per DU should not
exceed 25% of the cost.
Following components are not admissible for GoI funding
• Contingencies as percentage considered in DPR
• Price Escalation and any percentage above SOR
• Tender Premium.
• Departmental Charges of Implementing Agency.
Ministry of Housing and Urban Poverty Alleviation
9. STEPS IN DPR PREPARATION
RAJIV AWAS YOJANA
9
1. Selection of Slum –
i. Cities are expected to list existing slums in the city & give reasons
and justification for the selection of slum for intervention.
ii. DPR is to be prepared for one or more slums based on type of project
suitable to tackle the problem faced by selected slum.
iii. While deciding type of project it is to be ensured that slum dwellers /
communities views are taken into account.
2. Land possession and land use –
It is to be ensured that :
i. The land is in the possession of ULB and free from encroachment.
The land use is residential.
ii. The proposal is on tenable land.
Ministry of Housing and Urban Poverty Alleviation
10. STEPS IN DPR PREPARATION Cont..
RAJIV AWAS YOJANA
10
3. Survey and Mapping of selected slum –
i. Readable Plan ( Scale 1:500) showing physical boundary of
slum, roads, lanes, manhole positions, drains, boundary of
dwelling units, community property (if any), open space,
electric poles, trees, telephone poles etc.
ii. Contour Maps indicating ground slope and direction of
drainage. Survey should extend to existing nallahs / drains to
capture ground and invert elevations.
iii. House type, (such as Kutcha / dilapidated, semi Pucca and
Pucca, etc.) shall be noted giving an identification number.
iv. Infrastructure maps showing existing underground utilities
v. Surrounding area up to a reasonable distance, say 100 m to
depict adjoining road / property and administrative
boundaries.
Ministry of Housing and Urban Poverty Alleviation
11. STEPS IN DPR PREPARATION Cont..
RAJIV AWAS YOJANA
11
4. Assessment of deficiencies in slums –
Deficiencies are to be assessed in terms of :
i. Housing
ii. Basic civic infrastructure. and
iii. Social amenities ( Community facilities)
Assessment of demand needs to be done to meet the current deficiency and to
bridge the gap between the future and the present demand.
5. Integration of social infrastructure –
The DPR should aim at integrating social infra as under :
i. Education,
ii. Health and
iii. Social security.
Apart from provisions, it is to be ensured that operationalising these facilities is
also taken care of during project preparation and implementation.
Ministry of Housing and Urban Poverty Alleviation
12. STEPS IN DPR PREPARATION Cont..
RAJIV AWAS YOJANA
12
6. Establish linkage with citywide network :
• For all types of projects, in-slum infrastructure requires to be linked
with city-wide infrastructure
• It is to be checked whether the city-wide system is capable to deliver
the increased demand exerted by development of slum and up-
gradation.
7. Statutory Approvals –
Statutory approvals as per bye laws, master plan, fire safety
norms, Environmental clearance etc. as applicable for the project are to
be taken. These type of approvals are only illustrative and may be vary
for different ULBs/Cities .
The stipulations / regulations might undergo change. States / ULBs
are expected to get the clearance / approval from appropriate
authorities as per amended stipulations / regulations.
Ministry of Housing and Urban Poverty Alleviation
13. STEPS IN DPR PREPARATION Cont..
RAJIV AWAS YOJANA
13
8. Preparation of detailed design after assessment of
Demand / Gap
• The Housing design should be done as per National
Building Code, BIS Codes.
• The design of Infrastructure components should be done
as per CPHEEO Manuals, IRC Codes with amendments
and other relevant specifications as applicable.
• The design should be finalised after proper geotechnical
and hydrological investigation
• Conservation of the environment and ecology should be
built into the habitat planning.
• The DPR should include hazard resistant planning and
design, taking into account proper site selection.
Ministry of Housing and Urban Poverty Alleviation
14. STEPS IN DPR PREPARATION Cont..
RAJIV AWAS YOJANA
14
9. Estimate Project Cost –
• The cost estimates have to be worked out on the basis of
Detailed Bill of Quantities ( BOQ), with detailed measurement of
L,B,D/H using applicable current Schedule of Rates (SOR).
• If the applicable SORs relates to a year which is one or more
years prior to ‘current’ year, appropriate cost index may be
applied to update such rates, as approved by competent
authority.
• In addition to permanent works, temporary transit
accommodation cost should be also included in the estimate.
• The DPR shall be submitted duly authenticated and cost
estimates shall be certified by competent technical authority at
ULB and State/UT level.
Ministry of Housing and Urban Poverty Alleviation
15. STEPS IN DPR PREPARATION Cont..
RAJIV AWAS YOJANA
15
10. Implementation and Management arrangements
The arrangement should mention the role of:
• State Level Nodal Agency (SLNA) & State Level Technical Cell (SLTC),
• City Level Mission & City Level Technical Cell (CLTC),
• Project Management Consultants
• Third Party Inspection & Monitoring Agency (TPIMA)
The DPR should provide a time-bound action plan including :
• Tendering, Appointment of Contractors,
• Construction Schedule, Post-construction activities.
• Measurable milestone through IPoMS.
• Quality Assurance and Quality Control
• Project Schedule in the form of Gantt chart
i. Showing monthly targets.
ii. Quarterly Fund requirement.
iii. Schedule of slum-wise Project Delivery
Ministry of Housing and Urban Poverty Alleviation
16. STEPS IN DPR PREPARATION Cont..
RAJIV AWAS YOJANA
16
11. O&M arrangements of the assets –
• O & M cost up-to 4% of the project cost ( One time).
(As per applicable ratio for the city i.e. 50:50 for cities with
population more than 5 lakh, 75:25 for cities with population less
than 5 lakh and 80:20 for cities in NE and special category
States).
• The maintenance fund should be utilised as corpus fund and
placed at the disposal of ULBs to administer involving the
communities.
Ministry of Housing and Urban Poverty Alleviation
17. SUGGESTED CONTENTS OF DPR
RAJIV AWAS YOJANA
17
• Checklist of documents required in the DPR.
• Administrative and Technical checklist
• Executive Summary
• Introduction
• Salient features of SFCP & its linkage with the project
• Justification of the project ( Prioritisation)
• Project Concept and Scope
• Description of Project and Planning
• Slum Survey
i. Socio economic survey and Livelihood survey( Modified NBO format)
ii. Physical survey ( TSS) ( House footprints and infrastructure details
of the area)
iii. Validation of data by competent authority
iv. Beneficiaries identification through UIDAI.
Ministry of Housing and Urban Poverty Alleviation
18. SUGGESTED CONTENTS OF DPR ( Cont..)
RAJIV AWAS YOJANA
18
• Community Participation
i. Focus Group Discussions,
ii. Beneficiaries consent for relocation, accepting DUs on upper floors in
multistoried building and financial contribution,
iii. Community involvement from planning stage to allotment, O&M plan,
iv. Beneficiaries contribution and mobilization. Photographs of activities.
• Provision of Housing
i. Planning & Design of Single/ Multistoried building. Type/Area/Cost
ii. Disaster Management and Mitigation strategies
iii. Adoption of green technology in the project
• Provision of Community Facilities
• Planning & Design of Anganwadi, Health Centre/sub-Centre, Livelihood
Centre, Multi-purpose Community Centre, Community Park, Community
Toilet, Informal Education Centre, Informal sector Markets etc. as
applicable
• Provision of Urban Infrastructure
• Planning & Design of Roads, Water Supply, Sewerage, Storm Water
Drainage, Solid Waste Management, Rain Water Harvesting and
Streetlights
Ministry of Housing and Urban Poverty Alleviation
19. SUGGESTED CONTENTS OF DPR ( Cont..)
RAJIV AWAS YOJANA
19
• Statutory approvals including Environmental Clearance ( if required)
• Project Cost Estimate using current SOR ( Abstract & Detailed Estimate)
• Project Implementation & Management Framework
i. Institutional Capacity ( Infrastructure, man power etc)
ii. Institutional framework ( Creation of Cells)
iii. Implementation schedule ( Bar Chart )
iv. Quarterly component wise investment schedule vis-a-vis means of finance
(Central/State/ULB/Beneficiaries share)
v. Project Management Set-up
vi. Monitoring mechanism at State/ULB/Community level
vii. Quality Control & Quality Assurance plan
• Operation & Maintenance Plan
i. Mechanism proposed
ii. Fund requirement, creation of corpus fund
Ministry of Housing and Urban Poverty Alleviation
20. SUGGESTED CONTENTS OF DPR ( Cont..)
RAJIV AWAS YOJANA
20
• Financing Arrangement: Component wise financial statement for each
slum indicating cost, Central/State/ULB/Beneficiaries share or/and any
other share. One consolidated statement covering all slums should also be
furnished.
• Drawings –
i. Location Plan(s) of City and Slum(s), Land use map
ii. Physical survey maps, Contour plans
iii. Photographs covering the entire slum and Community participation
iv. Slum/Area layout Plan ( Foot prints of existing / proposed houses
and infrastructure connectivity)
v. On site Infrastructure service plan (water supply, sewerage, roads,
drainage etc.) and linkage with city wide infrastructure ,
vi. Architectural and Structural Drawings of Buildings
vii. L section/ Cross section/ Elevation of Roads, SWD, Sewerage, Water
Supply, Boundary Wall, Retaining Wall etc.
Ministry of Housing and Urban Poverty Alleviation
21. SUGGESTED CONTENTS OF DPR ( Cont..)
RAJIV AWAS YOJANA
21
• Annexures to DPR:
i. List of Beneficiaries
ii. Sample copy of consent of beneficiaries
iii. Sample copy of house holds survey.
iv. Copy of Act/ Legislation for conferment of tenure rights
v. Sample copy of allotment letter indicating ownership / lease rights.
vi. Copy of minutes of SLSMC indicating approval of project.
vii. Copies of MoA signed between ULB/parastatals, State and MoHUPA.
viii. Reforms – Status and Proposals
ix. Undertakings of ULB and SLNA
x. Details of educational and health facilities for scheme
xi. Copies of statutory approvals
xii. Photographs covering existing housing and infrastructure of entire slum
xiii. Photographs of ‘Micro Planning’ with the community
Ministry of Housing and Urban Poverty Alleviation
22. RAJIV AWAS YOJANA
22
Discussion forum on RAY VAARTA available at
www.mhupa-ray.gov.in can be used for queries related
to DPR preparation
Thank You