11 of the following activities are appropriate upon completion of risk response planning EXCEPT: a. The project plan should be updated to reflect any changes to the project schedule, budget or resource assignments. b. A single person should be assigned as the owner of each risk. c. The risk register should be baselined after planning is completed, and should not be updated once the project is in flight. d. The risk register should be updated to reflect the risk response strategies. .