SlideShare a Scribd company logo
1 of 2
Download to read offline
Vuyk Engineering Rotterdam B.V.
Naval architects, Marine engineers, Consultants
P.O. Box 1, De Linie 7
2900 AA Capelle aan den IJssel
Phone +31 (0)10 450 25 00
Fax +31 (0)10 458 72 45
Email vuyk@vuykrotterdam.com
Website www.vuykrotterdam.com Values are for presentation only
Principal dimensions
before jumboizing
Jumboizing TSHD 'HAM 310'
m
m
m
m
m
m
persons
GT
NT
ton
m³
kn
Capacity
Length overall
Length between perpendiculars
Breadth moulded
Depth moulded
Draught moulded (Summer load line)
Draught moulded ("Dredging draft")
Complement
Gross tonnage
Net tonnage
Deadweight
Hopper capacity
Service speed
In 2000, the Dutch dredging contractor HAM Dredging and Marine Contractors
(nowadays called Van Oord ) ordered the jumboizing of their 8 225 m³ trailing
suction hopper dredger 'HAM 310' ay the yard Singapore Technologies Marine.
It was the first dredger jumboisation project in the shiprepair industry in Singapore.
The project involved the lengthening of the dredger with 29.40 metres, involving
some 1 300 tons steel as well as modification of the jet piping system, dredge
piping, dredge pump motors and self-emptying channels.
138.20
125.00
23.00
11.60
8.68
9.80
46
10 378
3 113
14 695
8 225
15.0
Two trailing suction pipes, diameter
Dredging depth
Two dredging pumps; power during
* trailing suction dredging
* shore discharge
Bow discharge
20 bottom doors with a clear opening size of
Dredging equipment
1 100
32.00
2x 1 400
2x 2 210
1 000
3.88 x 3.45
mm
m
kW
kW
mm
m
VER project 00.222
Vuyk Engineering Rotterdam B.V.
Naval architects, Marine engineers, Consultants
P.O. Box 1, De Linie 7
2900 AA Capelle aan den IJssel
Phone +31 (0)10 450 25 00
Fax +31 (0)10 458 72 45
Email vuyk@vuykrotterdam.com
Website www.vuykrotterdam.com Values are for presentation only
Principal dimensions
after conversion
Jumboizing TSHD 'HAM 310'
167.60
154.31
23.00
11.60
8.70
10.00
46
13 456
4 036
20 059
12 535
15.1
m
m
m
m
m
m
persons
GT
NT
ton
m³
kn
Capacity
Length overall
Length between perpendiculars
Breadth moulded
Depth moulded
Draught moulded (Summer load line)
Draught at reduced freeboard
Complement
Gross tonnage
Net tonnage
Deadweight
Hopper capacity
Service speed
Dredging equipment
VER scope of work First of all VER made a feasibility study on the optimal length for lengthening of the
dredger, which resulted in a length of 29.40 metres, taking into account
longitudinal strength and stability.
In close cooperation with the HAM's technical department, VER worked out a
complete tender package, including technical specification, detail engineering and
strength calculations of the lengthened vessel.
The construction drawings of the mid-body section and coaming extension, the
new jet water system, the new hopper discharge system and the renewal of
dredge and jet pump drives were carried out as well.
An additional 2 000 kW generator set was required for ship's operations.
Two trailing suction pipes; diameter
Dredging depth:
* nominal
* maximum
Two dredging pump, power during:
* trailing suction dredging
* shore discharging
Two jet water pumps
Bow discharge
Bottom doors
1 100
35.00
48.00
2x 2 400
2x 2 400
2x 828
900
24
mm
m
m
kW
kW
kW
mm
VER project 00.222

More Related Content

Similar to 00.222 - TSHD_HAM_310_jumboising.PDF

Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnelsarravindsai
 
ORESUND BRIDGE PPT
ORESUND BRIDGE PPTORESUND BRIDGE PPT
ORESUND BRIDGE PPTsai karthik
 
technical_specification_cs_wave_sentinel
technical_specification_cs_wave_sentineltechnical_specification_cs_wave_sentinel
technical_specification_cs_wave_sentinelTsonko Tsonev
 
03.224 - Stern_trawler_Sandettie_upgrading.PDF
03.224 - Stern_trawler_Sandettie_upgrading.PDF03.224 - Stern_trawler_Sandettie_upgrading.PDF
03.224 - Stern_trawler_Sandettie_upgrading.PDFHans Tompot
 
Curriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eCurriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eJens Classen
 
Conceptual design study Kriegers Flak 090618 redused
Conceptual design study Kriegers Flak 090618 redusedConceptual design study Kriegers Flak 090618 redused
Conceptual design study Kriegers Flak 090618 redusedThomas Stalin
 
KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2Brian Quan (Minh)
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAbi Abagun
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAbi Abagun
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
Scandinavian Rail Development 2013 - Harald Vaagaasar Nikolaisen
Scandinavian Rail Development 2013 - Harald Vaagaasar NikolaisenScandinavian Rail Development 2013 - Harald Vaagaasar Nikolaisen
Scandinavian Rail Development 2013 - Harald Vaagaasar NikolaisenRussell Publishing
 
Bouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationBouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationPierre HUBERT
 
Seikan tunnel - The Longest Underwater Rail Tunnel
Seikan tunnel - The Longest Underwater Rail TunnelSeikan tunnel - The Longest Underwater Rail Tunnel
Seikan tunnel - The Longest Underwater Rail TunnelJuhi Aggarwal
 
Lifting and handling solutions for heavy wind turbine components - Fyns Kran ...
Lifting and handling solutions for heavy wind turbine components - Fyns Kran ...Lifting and handling solutions for heavy wind turbine components - Fyns Kran ...
Lifting and handling solutions for heavy wind turbine components - Fyns Kran ...Fyns Kran Udstyr A/S
 

Similar to 00.222 - TSHD_HAM_310_jumboising.PDF (20)

Immersed tunnels
Immersed tunnelsImmersed tunnels
Immersed tunnels
 
ORESUND BRIDGE PPT
ORESUND BRIDGE PPTORESUND BRIDGE PPT
ORESUND BRIDGE PPT
 
technical_specification_cs_wave_sentinel
technical_specification_cs_wave_sentineltechnical_specification_cs_wave_sentinel
technical_specification_cs_wave_sentinel
 
03.224 - Stern_trawler_Sandettie_upgrading.PDF
03.224 - Stern_trawler_Sandettie_upgrading.PDF03.224 - Stern_trawler_Sandettie_upgrading.PDF
03.224 - Stern_trawler_Sandettie_upgrading.PDF
 
Curriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_eCurriculum Vitae Jens Classen 2015_01_e
Curriculum Vitae Jens Classen 2015_01_e
 
Presentation_eng
Presentation_engPresentation_eng
Presentation_eng
 
Pont oresund
Pont oresundPont oresund
Pont oresund
 
Conceptual design study Kriegers Flak 090618 redused
Conceptual design study Kriegers Flak 090618 redusedConceptual design study Kriegers Flak 090618 redused
Conceptual design study Kriegers Flak 090618 redused
 
KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2KOM Presentation STN-N Conductor_rev 2
KOM Presentation STN-N Conductor_rev 2
 
Transatlantic Tunnel
Transatlantic TunnelTransatlantic Tunnel
Transatlantic Tunnel
 
Basic E&Mcalculations for a coal mining project
Basic E&Mcalculations for a coal mining projectBasic E&Mcalculations for a coal mining project
Basic E&Mcalculations for a coal mining project
 
Submerged tunnel ppt
Submerged tunnel pptSubmerged tunnel ppt
Submerged tunnel ppt
 
Gunther koller
Gunther kollerGunther koller
Gunther koller
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Alp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-sAlp transit euro-t&l-oct13-bro-s
Alp transit euro-t&l-oct13-bro-s
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Scandinavian Rail Development 2013 - Harald Vaagaasar Nikolaisen
Scandinavian Rail Development 2013 - Harald Vaagaasar NikolaisenScandinavian Rail Development 2013 - Harald Vaagaasar Nikolaisen
Scandinavian Rail Development 2013 - Harald Vaagaasar Nikolaisen
 
Bouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate PresentationBouygues Travaux Publics_Corporate Presentation
Bouygues Travaux Publics_Corporate Presentation
 
Seikan tunnel - The Longest Underwater Rail Tunnel
Seikan tunnel - The Longest Underwater Rail TunnelSeikan tunnel - The Longest Underwater Rail Tunnel
Seikan tunnel - The Longest Underwater Rail Tunnel
 
Lifting and handling solutions for heavy wind turbine components - Fyns Kran ...
Lifting and handling solutions for heavy wind turbine components - Fyns Kran ...Lifting and handling solutions for heavy wind turbine components - Fyns Kran ...
Lifting and handling solutions for heavy wind turbine components - Fyns Kran ...
 

00.222 - TSHD_HAM_310_jumboising.PDF

  • 1. Vuyk Engineering Rotterdam B.V. Naval architects, Marine engineers, Consultants P.O. Box 1, De Linie 7 2900 AA Capelle aan den IJssel Phone +31 (0)10 450 25 00 Fax +31 (0)10 458 72 45 Email vuyk@vuykrotterdam.com Website www.vuykrotterdam.com Values are for presentation only Principal dimensions before jumboizing Jumboizing TSHD 'HAM 310' m m m m m m persons GT NT ton m³ kn Capacity Length overall Length between perpendiculars Breadth moulded Depth moulded Draught moulded (Summer load line) Draught moulded ("Dredging draft") Complement Gross tonnage Net tonnage Deadweight Hopper capacity Service speed In 2000, the Dutch dredging contractor HAM Dredging and Marine Contractors (nowadays called Van Oord ) ordered the jumboizing of their 8 225 m³ trailing suction hopper dredger 'HAM 310' ay the yard Singapore Technologies Marine. It was the first dredger jumboisation project in the shiprepair industry in Singapore. The project involved the lengthening of the dredger with 29.40 metres, involving some 1 300 tons steel as well as modification of the jet piping system, dredge piping, dredge pump motors and self-emptying channels. 138.20 125.00 23.00 11.60 8.68 9.80 46 10 378 3 113 14 695 8 225 15.0 Two trailing suction pipes, diameter Dredging depth Two dredging pumps; power during * trailing suction dredging * shore discharge Bow discharge 20 bottom doors with a clear opening size of Dredging equipment 1 100 32.00 2x 1 400 2x 2 210 1 000 3.88 x 3.45 mm m kW kW mm m VER project 00.222
  • 2. Vuyk Engineering Rotterdam B.V. Naval architects, Marine engineers, Consultants P.O. Box 1, De Linie 7 2900 AA Capelle aan den IJssel Phone +31 (0)10 450 25 00 Fax +31 (0)10 458 72 45 Email vuyk@vuykrotterdam.com Website www.vuykrotterdam.com Values are for presentation only Principal dimensions after conversion Jumboizing TSHD 'HAM 310' 167.60 154.31 23.00 11.60 8.70 10.00 46 13 456 4 036 20 059 12 535 15.1 m m m m m m persons GT NT ton m³ kn Capacity Length overall Length between perpendiculars Breadth moulded Depth moulded Draught moulded (Summer load line) Draught at reduced freeboard Complement Gross tonnage Net tonnage Deadweight Hopper capacity Service speed Dredging equipment VER scope of work First of all VER made a feasibility study on the optimal length for lengthening of the dredger, which resulted in a length of 29.40 metres, taking into account longitudinal strength and stability. In close cooperation with the HAM's technical department, VER worked out a complete tender package, including technical specification, detail engineering and strength calculations of the lengthened vessel. The construction drawings of the mid-body section and coaming extension, the new jet water system, the new hopper discharge system and the renewal of dredge and jet pump drives were carried out as well. An additional 2 000 kW generator set was required for ship's operations. Two trailing suction pipes; diameter Dredging depth: * nominal * maximum Two dredging pump, power during: * trailing suction dredging * shore discharging Two jet water pumps Bow discharge Bottom doors 1 100 35.00 48.00 2x 2 400 2x 2 400 2x 828 900 24 mm m m kW kW kW mm VER project 00.222