SlideShare a Scribd company logo
© Vattenfall AB
Conceptual Design Study
Kriegers Flak
Windforce 09, 18th june, 2009
Thomas Stalin, Vattenfall Wind Power AB
© Vattenfall AB
2
Vattenfall Wind Power
• Activity in DK, FI, SE, UK, DE, PL
• Appr. 160 employee + x consultants
• VF Target in Europe, 49 TWh wind power
by 2030
• One offshore project will be built per
year in Europe
• Thanet, UK
• Electricity to 10 million households
• 1/3 Nordic 1/3 UK 1/3 Central Europe
© Vattenfall AB
3
Targets for Sweden
• Vattenfall share 8 TWh of 16 TWh to 2016
– 4 TWh onshore
– 4 TWh offshore
• New political target 25 TWh to 2020
– Vattenfalls share even larger!!!!
• Focus in Sweden first be onshore in the forest
• Offshore has high technical risk and high investment cost
• Price for green certificates equal for onshore and offshore
• Vattenfall will first build offshore in the countries where we can
meet profitability, GB and DE
• When turbines have matured and total price for green electricity
has increased we will build offshore in Sweden
– Political process
• Kriegers flak is planned to be built in phases starting 2013
© Vattenfall AB
44
SE 103 wtg
160 MW - 440 GWh
FI 10 wtg
4 MW - 8 GWh
DE 386 wtg
307 MW - 800 GWh
UK 30 wtg
90 MW - 270 GWh
Total: Appr. 560 wtg 600 MW 1.6 TWh
Nordic: Appr. 500 wtg 470 MW 1.3 TWh
1.6 TWh Annual Production
PL 15 wtg
30 MW - 60 GWh
DE 13 wtg
14 MW - 29 GWh
© Vattenfall AB
5
Conceptual Design Study, Kriegers Flak
• Study during 2008
• Budget 700 000 Euro
• Four foundation concepts + ref. monopile
• Presentation 28th February 2008
• Proposals from Intrested parties
• Selected five experts
• Started work April/May
• Three meetings
• Draft report in January 2009
• Final Seminary March 2009
• EOW session KF + Final report
© Vattenfall AB
6
Aim of Project
• Costefficient Foundations for 15 to 45 meter water deepths
– Calculations and drawings
– Installation method and specification of equipment
– Including estimate of fabrication and installation cost
• Reduce the cost = Reduce the risk
– Use the time to investigate the conditions
– Find areas that needs further investigations
• Conceptual design for the tender process
– Good base for estimate of volumes of material and labour
– Detailed drawings and worked through concepts
• Establish contacts to Contractors well in advance of tender
– Good knowledge of the project
• Transfer of knowledge to Vattenfall
– Ability to make conceptual design and estimate cost
• Support the generall knowledge
– Develop concepts for deeper waters
© Vattenfall AB
7
Prehistory
• Year 2003 to 2005 Project development focused on permits and
not on implementations and long term ownership
– Millions on environmental investigation
– Before permit => 100% risk to loose money invested in technical
problem solving
– Long technical lead times when permit ready
=> Work in parallel
• Project development without knowing final cost
• No projects built on deep waters
• STEM Call for Offshore Pilot Studies
• Application in March April 2004
• In May 2005 project sold to Vattenfall
– Long term ownership
• Funds approved by STEM 2005
© Vattenfall AB
8
Background
• Started Design Basis 2007
• Detailed geotechnical investigation 2007
– Geobore S, CPTs, Vibro core
– Analyse first half 2008
• How to utilize time to reduce risk
– While project starts 2013
• How to get lower prices for foundations
– Better information for tendering phase
– Several pre-engineered concepts
– Contractors see possibilities and understand risk
• Optimal time schedule for tendering process
– Adopt time to allow the best solution a chance to win
• Volunteer before tendering in order to get the things done in advance
that should be done but normally first is done after the contract is signed
© Vattenfall AB
9
Consultants
• Ramböll and MTHojgaard
– Jacket
– Ref. Monopile
• ISC and Skanska
– Concrete Tripod
• COWI and Aahrsleff
– Cone Gravity foundation
• Ballast Nedam and MTPiling
– Drilled Concrete Monopile
• Pihl
– Automatic stone bed preparation robot
© Vattenfall AB
10
Rambøll tasks
Two generic turbines of 3.6 MW and 5.0 MW
• Natural Frequency Range
• 3.6 MW 0.27 – 0.30 Hz
• 5.0 MW 0.23 – 0.26 Hz
• Life Time of Foundations 25 Years
Monopiles
• 3.6 MW and 5.0 MW Turbine
• 20-35 m Water Depth
Jacket
• 5.0 MW Turbine
• 35 m Water Depth
Two Concepts to be developed
© Vattenfall AB
11
Monopile Concept for Kriegers Flak
Total Steel Weights
• 3.6 MW 400-750 tons
• 5.0 MW 525-1050 tons
Pile Penetrations
• 3.6 MW 26-29 m
• 5.0 MW 25-29 m
Pile Diameters
• 3.6 MW 4750-6000 mm
• 5.0 MW 5750-6750 mm
Ice cone at
sea level
Grouted
connection
by mud line
Depending on soil profile
© Vattenfall AB
12
Jacket Concept for Kriegers Flak - Results
Weights
– Jacket – 261 tons
• Piles – 248 tons
• Transition Piece – 700
tons
• Secondary Steel – 24
tons
Geometry
• Foot Print 12 x 12 m
• Interface 10.5 m
• Pile Penetration 42 m
© Vattenfall AB
GRAVITY BASED FOUNDATION, COWI - AARSLEFF
© Vattenfall AB
27/03/2015
Gravity Based Foundation - Conceptual design
14
Concepts alternatives
"Traditional" cone,
Thornton type
Floating caisson,
KIS (Keep It Simple)
Semi floating cone,
Pontoon supported
© Vattenfall AB
27/03/2015
Gravity Based Foundation - Conceptual design
15
Cone foundation properties
Volume of concrete
 Base case solid ice cone:
1320 m³ (3300 t)
 Hollow ice cone:
1170 m³ (2925 t)
 0.2m reduced bottom slab height
1080 m³ (2700 t) (hollow ice cone)
Cost & time implications marginal due to
increased reinforcement
Volume of sand ballast
 1830 m³ (3550 t)
Gravel Bed
 1m thickness (575 m³)
Dredging
 2 m deep (~ 3,000 m³)
-32.0
FOUNDATION
LEVEL
+2.0
-2.0
+3.5
MSL
© Vattenfall AB
16
Concept level Cost Estimate
1 Cone Foundation of 40 in total
EUR excl. VAT
Casting Yard (1 of 40) 175,000
Primary Structures: 1.125,000
Secondary Structures: 85,000
Ballast 40,000
Dredging and deposit: 135,000
Stone works: 470,000
Transport & Installation 350,000
SUM 2,380,000 ~ 480,000 EUR/MW
Assuming normal weather year,
Hs < 0.75 m 140 days Feb. - Nov.
Floating concept: ~ 4,000,000 EUR
Semi floating concept: ~ 3,000,000 EUR
© Vattenfall AB
17
Construction/installation KIS - TOWING
Transport
 Towed to installation site by
tugs
Installation
 Lowered by ballasting , tug
aided positioning
 Stability to be assured during
lowering
© Vattenfall AB
18
Construction/installation
SEMI FLOATING - Transport
Construction
 Completed on land, and immersed in shallow waters (dry dock,
skidding ramp, syncrolift)
Transport
 The GBF picked up by pontoon and transported to site
Installation
 Controlled lowering by hydraulic winches and released when in
place
© Vattenfall AB
19
Concrete Tripod, ISC and Skanska
© Vattenfall AB
20
© Vattenfall AB
21
© Vattenfall AB
22
DRILLED CONCRETE MONOPILE
© Vattenfall AB
23
FABRICATION
Fabrication method conform project
Saudi Arabia Bahrain Causeway (1984):
• Prefab reinforcement cages;
• Casting ring elements;
• Storage and curing ring elements;
• Monopile assembly:
• Aligning ements;
• Grouting element joints;
• Installation post tensioning;
• Grouting post tensioning ducts.
• Finishing works:
• Installation cutting toe;
• Installation injection lines for drillmix;
• Installation pile plugs.
© Vattenfall AB
24
Drilling inside and under monopile:
Inside monopile
• Start drilling process
• Soft upper layers
• Diameter 5300 mm
DESIGN DRILLING EQUIPMENT
Under monopile
• Deeper soil layers
• Extended cutter head
(6700/7100 mm)
© Vattenfall AB
25
INSTALLATION
© Vattenfall AB
26
INSTALLATION
© Vattenfall AB
27
INSTALLATION
© Vattenfall AB
28
INSTALLATION
© Vattenfall AB
29
INSTALLATION
© Vattenfall AB
30
INSTALLATION
© Vattenfall AB
31
INSTALLATION
© Vattenfall AB
32
COST
Total cost per MW as function of amount and turbine type:
© Vattenfall AB
33
© Vattenfall AB
34
© Vattenfall AB
35
© Vattenfall AB
36
© Vattenfall AB
37
© Vattenfall AB
38
Purpose Built Vessel
© Vattenfall AB
39
Catamaran
© Vattenfall AB
40
Lowering
© Vattenfall AB
41
Result
• Based on Geotechnical investigations and measurements on Wind and
Waves we have developed a Design Basis that was used in the project
– First test of design basis
• Individual experts developed the concepts with comments from the others
experts, team-work under competition, sharing of experience. Helge
Gravesen was the project manager
• Worked out five foundation concepts and one seabed preparation robot
• Managed to find some solutions in the range below 500 Euro/kW
• For the coming Tender process we have a good material in form of the five
worked out Conceptual designs
• Vattenfall gained knowledge on volumes, prices and time schedules
• The contractors knows about KF
– the conditions, the potential alternatives and the competition.
• Proved to be possible to create exchange between competitive parties
• Two complete new concepts have been developed
• All participants have enjoyed the process
© Vattenfall AB
Thanks!

More Related Content

What's hot

Justifying a GEP Stack Height Taller than the EPA Formula Height
Justifying a GEP Stack Height Taller than the EPA Formula HeightJustifying a GEP Stack Height Taller than the EPA Formula Height
Justifying a GEP Stack Height Taller than the EPA Formula Height
Ron Petersen, PhD, CCM, FASHRAE
 
Heat Tracing Solutions for LNG facilities in Arctic Conditions
Heat Tracing Solutions for LNG facilities in Arctic ConditionsHeat Tracing Solutions for LNG facilities in Arctic Conditions
Heat Tracing Solutions for LNG facilities in Arctic Conditions
Dillen Valerie
 
20160224 smart klub housing leeds v3.0
20160224 smart klub housing leeds v3.020160224 smart klub housing leeds v3.0
20160224 smart klub housing leeds v3.0
smartklubleeds
 
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
Global CCS Institute
 
REHVA: Country reports from benchmark study on European regulations
REHVA: Country reports from benchmark study on European regulationsREHVA: Country reports from benchmark study on European regulations
REHVA: Country reports from benchmark study on European regulations
Sitra / Ekologinen kestävyys
 
CO Removal and Smoke Extraction: Garage Ventilation System Design with CFD
CO Removal and Smoke Extraction: Garage Ventilation System Design with CFDCO Removal and Smoke Extraction: Garage Ventilation System Design with CFD
CO Removal and Smoke Extraction: Garage Ventilation System Design with CFD
SimScale
 
Team IES - 2016 ASHRAE Lowdown Showdown
Team IES - 2016 ASHRAE Lowdown ShowdownTeam IES - 2016 ASHRAE Lowdown Showdown
Team IES - 2016 ASHRAE Lowdown Showdown
IES VE
 
Natural gas and bio methane as fuel for transport h. aouad
Natural gas and bio methane as fuel for transport   h. aouadNatural gas and bio methane as fuel for transport   h. aouad
Natural gas and bio methane as fuel for transport h. aouad
European Commission
 
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
Kevin Perry
 
Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3
Nicholas Naing
 
2016 02-24 smart klub lcc tower blocks + rfk (1)
2016 02-24 smart klub lcc tower blocks + rfk (1)2016 02-24 smart klub lcc tower blocks + rfk (1)
2016 02-24 smart klub lcc tower blocks + rfk (1)
smartklubleeds
 
Benchmarking Regulations on Energy Efficiency of Buildings
Benchmarking Regulations on Energy Efficiency of BuildingsBenchmarking Regulations on Energy Efficiency of Buildings
Benchmarking Regulations on Energy Efficiency of Buildings
Sitra / Ekologinen kestävyys
 
ENERCRET summary
ENERCRET summaryENERCRET summary
ENERCRET summaryMartyn Rose
 

What's hot (13)

Justifying a GEP Stack Height Taller than the EPA Formula Height
Justifying a GEP Stack Height Taller than the EPA Formula HeightJustifying a GEP Stack Height Taller than the EPA Formula Height
Justifying a GEP Stack Height Taller than the EPA Formula Height
 
Heat Tracing Solutions for LNG facilities in Arctic Conditions
Heat Tracing Solutions for LNG facilities in Arctic ConditionsHeat Tracing Solutions for LNG facilities in Arctic Conditions
Heat Tracing Solutions for LNG facilities in Arctic Conditions
 
20160224 smart klub housing leeds v3.0
20160224 smart klub housing leeds v3.020160224 smart klub housing leeds v3.0
20160224 smart klub housing leeds v3.0
 
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
CCS cost estimation methods in the coal, oil and gas sectors - David Butler, ...
 
REHVA: Country reports from benchmark study on European regulations
REHVA: Country reports from benchmark study on European regulationsREHVA: Country reports from benchmark study on European regulations
REHVA: Country reports from benchmark study on European regulations
 
CO Removal and Smoke Extraction: Garage Ventilation System Design with CFD
CO Removal and Smoke Extraction: Garage Ventilation System Design with CFDCO Removal and Smoke Extraction: Garage Ventilation System Design with CFD
CO Removal and Smoke Extraction: Garage Ventilation System Design with CFD
 
Team IES - 2016 ASHRAE Lowdown Showdown
Team IES - 2016 ASHRAE Lowdown ShowdownTeam IES - 2016 ASHRAE Lowdown Showdown
Team IES - 2016 ASHRAE Lowdown Showdown
 
Natural gas and bio methane as fuel for transport h. aouad
Natural gas and bio methane as fuel for transport   h. aouadNatural gas and bio methane as fuel for transport   h. aouad
Natural gas and bio methane as fuel for transport h. aouad
 
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
Andracsek, Robynn, Burns & McDonnell, What Every EHS Staff should Know about ...
 
Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3Mechanical Engineering Seminar 2017_3
Mechanical Engineering Seminar 2017_3
 
2016 02-24 smart klub lcc tower blocks + rfk (1)
2016 02-24 smart klub lcc tower blocks + rfk (1)2016 02-24 smart klub lcc tower blocks + rfk (1)
2016 02-24 smart klub lcc tower blocks + rfk (1)
 
Benchmarking Regulations on Energy Efficiency of Buildings
Benchmarking Regulations on Energy Efficiency of BuildingsBenchmarking Regulations on Energy Efficiency of Buildings
Benchmarking Regulations on Energy Efficiency of Buildings
 
ENERCRET summary
ENERCRET summaryENERCRET summary
ENERCRET summary
 

Similar to Conceptual design study Kriegers Flak 090618 redused

Smolders the 3 d unstructured scaldis model
Smolders the 3 d unstructured scaldis modelSmolders the 3 d unstructured scaldis model
Smolders the 3 d unstructured scaldis model
Waterbouwkundig Laboratorium
 
CV Skare Sigbjørn 2016_13062016
CV Skare Sigbjørn 2016_13062016CV Skare Sigbjørn 2016_13062016
CV Skare Sigbjørn 2016_13062016Skare Sigbjørn
 
Innovation landscape All Energy 2017
Innovation landscape All Energy 2017Innovation landscape All Energy 2017
Innovation landscape All Energy 2017
BVG Associates
 
Webinar: From compressor to reservoir – Flow assurance and control philosophy...
Webinar: From compressor to reservoir – Flow assurance and control philosophy...Webinar: From compressor to reservoir – Flow assurance and control philosophy...
Webinar: From compressor to reservoir – Flow assurance and control philosophy...
Global CCS Institute
 
Presentation EVM Europe 2013
Presentation EVM Europe 2013Presentation EVM Europe 2013
Presentation EVM Europe 2013
Joost Arnoudt
 
Modelling of offshore wind
Modelling of offshore windModelling of offshore wind
Modelling of offshore wind
IEA-ETSAP
 
Vedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance DredgingVedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam design & Techincal Consultancy Pvt Ltd.
 
2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind 2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind
MEC Intelligence
 
Offshore Wind Power Substations 2014
Offshore Wind Power Substations 2014Offshore Wind Power Substations 2014
Offshore Wind Power Substations 2014
Torben Haagh
 
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
Svenska Betongföreningen
 
Norway_Johan sverdrup, report 2015
Norway_Johan sverdrup, report 2015Norway_Johan sverdrup, report 2015
Norway_Johan sverdrup, report 2015
Business Finland
 
Asia Days 2013 - Korean opportunities maritime sector
Asia Days 2013 - Korean opportunities maritime sectorAsia Days 2013 - Korean opportunities maritime sector
Asia Days 2013 - Korean opportunities maritime sectorInnovation Norway
 
Typical challenges in tunnelling
Typical challenges in tunnellingTypical challenges in tunnelling
Typical challenges in tunnelling
Antti Nykänen
 
Visite du parc éolien Thorntonbank - Introduction to offshore wind
Visite du parc éolien Thorntonbank - Introduction to offshore windVisite du parc éolien Thorntonbank - Introduction to offshore wind
Visite du parc éolien Thorntonbank - Introduction to offshore wind
CCILVN
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgradeRobert Lee - CEng, MICE, PMP
 
Syzygy Renewables_Company_Info_August 2016
Syzygy Renewables_Company_Info_August 2016Syzygy Renewables_Company_Info_August 2016
Syzygy Renewables_Company_Info_August 2016Andrew Hancock
 
IOR drilling technologies
IOR drilling technologiesIOR drilling technologies
IOR drilling technologiesStatoil
 
DSD-INT 2016 Local effects of the reshape of the Niers - Walter
DSD-INT 2016 Local effects of the reshape of the Niers - WalterDSD-INT 2016 Local effects of the reshape of the Niers - Walter
DSD-INT 2016 Local effects of the reshape of the Niers - Walter
Deltares
 
Deep drilling - Risks and challenges with examples from the German Molasse Basin
Deep drilling - Risks and challenges with examples from the German Molasse BasinDeep drilling - Risks and challenges with examples from the German Molasse Basin
Deep drilling - Risks and challenges with examples from the German Molasse BasinGerd Tarand
 

Similar to Conceptual design study Kriegers Flak 090618 redused (20)

Smolders the 3 d unstructured scaldis model
Smolders the 3 d unstructured scaldis modelSmolders the 3 d unstructured scaldis model
Smolders the 3 d unstructured scaldis model
 
CV Skare Sigbjørn 2016_13062016
CV Skare Sigbjørn 2016_13062016CV Skare Sigbjørn 2016_13062016
CV Skare Sigbjørn 2016_13062016
 
Innovation landscape All Energy 2017
Innovation landscape All Energy 2017Innovation landscape All Energy 2017
Innovation landscape All Energy 2017
 
Webinar: From compressor to reservoir – Flow assurance and control philosophy...
Webinar: From compressor to reservoir – Flow assurance and control philosophy...Webinar: From compressor to reservoir – Flow assurance and control philosophy...
Webinar: From compressor to reservoir – Flow assurance and control philosophy...
 
Presentation EVM Europe 2013
Presentation EVM Europe 2013Presentation EVM Europe 2013
Presentation EVM Europe 2013
 
Modelling of offshore wind
Modelling of offshore windModelling of offshore wind
Modelling of offshore wind
 
Vedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance DredgingVedam Designs: Solutions for Shallow Water maintenance Dredging
Vedam Designs: Solutions for Shallow Water maintenance Dredging
 
2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind 2015 Foundations for larger and deeper Offshore Wind
2015 Foundations for larger and deeper Offshore Wind
 
Offshore Wind Power Substations 2014
Offshore Wind Power Substations 2014Offshore Wind Power Substations 2014
Offshore Wind Power Substations 2014
 
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
D2 (A5) Øyvind Bjontegaard - Concrete R&D activities involvement; Norwegian P...
 
Norway_Johan sverdrup, report 2015
Norway_Johan sverdrup, report 2015Norway_Johan sverdrup, report 2015
Norway_Johan sverdrup, report 2015
 
Asia Days 2013 - Korean opportunities maritime sector
Asia Days 2013 - Korean opportunities maritime sectorAsia Days 2013 - Korean opportunities maritime sector
Asia Days 2013 - Korean opportunities maritime sector
 
Olivia Errey - FEED Secondments - Annual ECR Meeting London 23rd June 2015
Olivia Errey - FEED Secondments - Annual ECR Meeting London 23rd June 2015Olivia Errey - FEED Secondments - Annual ECR Meeting London 23rd June 2015
Olivia Errey - FEED Secondments - Annual ECR Meeting London 23rd June 2015
 
Typical challenges in tunnelling
Typical challenges in tunnellingTypical challenges in tunnelling
Typical challenges in tunnelling
 
Visite du parc éolien Thorntonbank - Introduction to offshore wind
Visite du parc éolien Thorntonbank - Introduction to offshore windVisite du parc éolien Thorntonbank - Introduction to offshore wind
Visite du parc éolien Thorntonbank - Introduction to offshore wind
 
rup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgraderup-20151016-part-1-item07-victoria-station-upgrade
rup-20151016-part-1-item07-victoria-station-upgrade
 
Syzygy Renewables_Company_Info_August 2016
Syzygy Renewables_Company_Info_August 2016Syzygy Renewables_Company_Info_August 2016
Syzygy Renewables_Company_Info_August 2016
 
IOR drilling technologies
IOR drilling technologiesIOR drilling technologies
IOR drilling technologies
 
DSD-INT 2016 Local effects of the reshape of the Niers - Walter
DSD-INT 2016 Local effects of the reshape of the Niers - WalterDSD-INT 2016 Local effects of the reshape of the Niers - Walter
DSD-INT 2016 Local effects of the reshape of the Niers - Walter
 
Deep drilling - Risks and challenges with examples from the German Molasse Basin
Deep drilling - Risks and challenges with examples from the German Molasse BasinDeep drilling - Risks and challenges with examples from the German Molasse Basin
Deep drilling - Risks and challenges with examples from the German Molasse Basin
 

Conceptual design study Kriegers Flak 090618 redused

  • 1. © Vattenfall AB Conceptual Design Study Kriegers Flak Windforce 09, 18th june, 2009 Thomas Stalin, Vattenfall Wind Power AB
  • 2. © Vattenfall AB 2 Vattenfall Wind Power • Activity in DK, FI, SE, UK, DE, PL • Appr. 160 employee + x consultants • VF Target in Europe, 49 TWh wind power by 2030 • One offshore project will be built per year in Europe • Thanet, UK • Electricity to 10 million households • 1/3 Nordic 1/3 UK 1/3 Central Europe
  • 3. © Vattenfall AB 3 Targets for Sweden • Vattenfall share 8 TWh of 16 TWh to 2016 – 4 TWh onshore – 4 TWh offshore • New political target 25 TWh to 2020 – Vattenfalls share even larger!!!! • Focus in Sweden first be onshore in the forest • Offshore has high technical risk and high investment cost • Price for green certificates equal for onshore and offshore • Vattenfall will first build offshore in the countries where we can meet profitability, GB and DE • When turbines have matured and total price for green electricity has increased we will build offshore in Sweden – Political process • Kriegers flak is planned to be built in phases starting 2013
  • 4. © Vattenfall AB 44 SE 103 wtg 160 MW - 440 GWh FI 10 wtg 4 MW - 8 GWh DE 386 wtg 307 MW - 800 GWh UK 30 wtg 90 MW - 270 GWh Total: Appr. 560 wtg 600 MW 1.6 TWh Nordic: Appr. 500 wtg 470 MW 1.3 TWh 1.6 TWh Annual Production PL 15 wtg 30 MW - 60 GWh DE 13 wtg 14 MW - 29 GWh
  • 5. © Vattenfall AB 5 Conceptual Design Study, Kriegers Flak • Study during 2008 • Budget 700 000 Euro • Four foundation concepts + ref. monopile • Presentation 28th February 2008 • Proposals from Intrested parties • Selected five experts • Started work April/May • Three meetings • Draft report in January 2009 • Final Seminary March 2009 • EOW session KF + Final report
  • 6. © Vattenfall AB 6 Aim of Project • Costefficient Foundations for 15 to 45 meter water deepths – Calculations and drawings – Installation method and specification of equipment – Including estimate of fabrication and installation cost • Reduce the cost = Reduce the risk – Use the time to investigate the conditions – Find areas that needs further investigations • Conceptual design for the tender process – Good base for estimate of volumes of material and labour – Detailed drawings and worked through concepts • Establish contacts to Contractors well in advance of tender – Good knowledge of the project • Transfer of knowledge to Vattenfall – Ability to make conceptual design and estimate cost • Support the generall knowledge – Develop concepts for deeper waters
  • 7. © Vattenfall AB 7 Prehistory • Year 2003 to 2005 Project development focused on permits and not on implementations and long term ownership – Millions on environmental investigation – Before permit => 100% risk to loose money invested in technical problem solving – Long technical lead times when permit ready => Work in parallel • Project development without knowing final cost • No projects built on deep waters • STEM Call for Offshore Pilot Studies • Application in March April 2004 • In May 2005 project sold to Vattenfall – Long term ownership • Funds approved by STEM 2005
  • 8. © Vattenfall AB 8 Background • Started Design Basis 2007 • Detailed geotechnical investigation 2007 – Geobore S, CPTs, Vibro core – Analyse first half 2008 • How to utilize time to reduce risk – While project starts 2013 • How to get lower prices for foundations – Better information for tendering phase – Several pre-engineered concepts – Contractors see possibilities and understand risk • Optimal time schedule for tendering process – Adopt time to allow the best solution a chance to win • Volunteer before tendering in order to get the things done in advance that should be done but normally first is done after the contract is signed
  • 9. © Vattenfall AB 9 Consultants • Ramböll and MTHojgaard – Jacket – Ref. Monopile • ISC and Skanska – Concrete Tripod • COWI and Aahrsleff – Cone Gravity foundation • Ballast Nedam and MTPiling – Drilled Concrete Monopile • Pihl – Automatic stone bed preparation robot
  • 10. © Vattenfall AB 10 Rambøll tasks Two generic turbines of 3.6 MW and 5.0 MW • Natural Frequency Range • 3.6 MW 0.27 – 0.30 Hz • 5.0 MW 0.23 – 0.26 Hz • Life Time of Foundations 25 Years Monopiles • 3.6 MW and 5.0 MW Turbine • 20-35 m Water Depth Jacket • 5.0 MW Turbine • 35 m Water Depth Two Concepts to be developed
  • 11. © Vattenfall AB 11 Monopile Concept for Kriegers Flak Total Steel Weights • 3.6 MW 400-750 tons • 5.0 MW 525-1050 tons Pile Penetrations • 3.6 MW 26-29 m • 5.0 MW 25-29 m Pile Diameters • 3.6 MW 4750-6000 mm • 5.0 MW 5750-6750 mm Ice cone at sea level Grouted connection by mud line Depending on soil profile
  • 12. © Vattenfall AB 12 Jacket Concept for Kriegers Flak - Results Weights – Jacket – 261 tons • Piles – 248 tons • Transition Piece – 700 tons • Secondary Steel – 24 tons Geometry • Foot Print 12 x 12 m • Interface 10.5 m • Pile Penetration 42 m
  • 13. © Vattenfall AB GRAVITY BASED FOUNDATION, COWI - AARSLEFF
  • 14. © Vattenfall AB 27/03/2015 Gravity Based Foundation - Conceptual design 14 Concepts alternatives "Traditional" cone, Thornton type Floating caisson, KIS (Keep It Simple) Semi floating cone, Pontoon supported
  • 15. © Vattenfall AB 27/03/2015 Gravity Based Foundation - Conceptual design 15 Cone foundation properties Volume of concrete  Base case solid ice cone: 1320 m³ (3300 t)  Hollow ice cone: 1170 m³ (2925 t)  0.2m reduced bottom slab height 1080 m³ (2700 t) (hollow ice cone) Cost & time implications marginal due to increased reinforcement Volume of sand ballast  1830 m³ (3550 t) Gravel Bed  1m thickness (575 m³) Dredging  2 m deep (~ 3,000 m³) -32.0 FOUNDATION LEVEL +2.0 -2.0 +3.5 MSL
  • 16. © Vattenfall AB 16 Concept level Cost Estimate 1 Cone Foundation of 40 in total EUR excl. VAT Casting Yard (1 of 40) 175,000 Primary Structures: 1.125,000 Secondary Structures: 85,000 Ballast 40,000 Dredging and deposit: 135,000 Stone works: 470,000 Transport & Installation 350,000 SUM 2,380,000 ~ 480,000 EUR/MW Assuming normal weather year, Hs < 0.75 m 140 days Feb. - Nov. Floating concept: ~ 4,000,000 EUR Semi floating concept: ~ 3,000,000 EUR
  • 17. © Vattenfall AB 17 Construction/installation KIS - TOWING Transport  Towed to installation site by tugs Installation  Lowered by ballasting , tug aided positioning  Stability to be assured during lowering
  • 18. © Vattenfall AB 18 Construction/installation SEMI FLOATING - Transport Construction  Completed on land, and immersed in shallow waters (dry dock, skidding ramp, syncrolift) Transport  The GBF picked up by pontoon and transported to site Installation  Controlled lowering by hydraulic winches and released when in place
  • 19. © Vattenfall AB 19 Concrete Tripod, ISC and Skanska
  • 22. © Vattenfall AB 22 DRILLED CONCRETE MONOPILE
  • 23. © Vattenfall AB 23 FABRICATION Fabrication method conform project Saudi Arabia Bahrain Causeway (1984): • Prefab reinforcement cages; • Casting ring elements; • Storage and curing ring elements; • Monopile assembly: • Aligning ements; • Grouting element joints; • Installation post tensioning; • Grouting post tensioning ducts. • Finishing works: • Installation cutting toe; • Installation injection lines for drillmix; • Installation pile plugs.
  • 24. © Vattenfall AB 24 Drilling inside and under monopile: Inside monopile • Start drilling process • Soft upper layers • Diameter 5300 mm DESIGN DRILLING EQUIPMENT Under monopile • Deeper soil layers • Extended cutter head (6700/7100 mm)
  • 32. © Vattenfall AB 32 COST Total cost per MW as function of amount and turbine type:
  • 41. © Vattenfall AB 41 Result • Based on Geotechnical investigations and measurements on Wind and Waves we have developed a Design Basis that was used in the project – First test of design basis • Individual experts developed the concepts with comments from the others experts, team-work under competition, sharing of experience. Helge Gravesen was the project manager • Worked out five foundation concepts and one seabed preparation robot • Managed to find some solutions in the range below 500 Euro/kW • For the coming Tender process we have a good material in form of the five worked out Conceptual designs • Vattenfall gained knowledge on volumes, prices and time schedules • The contractors knows about KF – the conditions, the potential alternatives and the competition. • Proved to be possible to create exchange between competitive parties • Two complete new concepts have been developed • All participants have enjoyed the process