Re-membering the Bard: Revisiting The Compleat Wrks of Wllm Shkspr (Abridged)...
Adam Skinner, P2 Consulting & Steve Leary, TCS - How does a Portfolio Management Office differ from the Programme Management Office?
1. What’s in a P?
Portfolio Management Specific Interest Group
Februaryb20181
How does the Portfolio Management Office
differ from the Programme Management Office?
2. Introductions
Adam Skinner
Director – PMO & Portfolio Practice:
P2 Consulting
adam.skinner@p2consulting.com
Steve Leary
Managing Consultant:
Tata Consulting Services Ltd.
Stephen.Leary@tcs.com
1. What do an ‘office’ do in the context of the Programme and the Portfolio?
2. Where are they similar and where do they differ?
3. Does the delivery methodology make a difference?
Portfolio
Management
SIG
3. Innovation coordination & continuous improvement
PMO activities ….
Value & benefits mgt
KPIs, metrics & dashboards
Management of governance
Strategic alignment
Quality assurance
Plans and schedule mgt.
Dependency mgt.
Delivery mgt
Scope and change control
Financial monitoring & control
Resource monitoring & control
Stakeholder engagement & monitoring
Communications mgt
Progress & outlook
Prioritisation
Optimisation
Processes & templates
An ‘Office’ drives
efficient and effective
decision-making
through
4. Portfolio management
Portfolio management is the selection, prioritisation
and control of an organisation's projects and
programmes in line with its strategic objectives and
capacity to deliver. The goal is to balance change
initiatives and business-as-usual while optimising
return on investment.
This is a continuous process to achieve the evolving
strategy of the organisation.
Programme management
Programme management is the action of
coordinating, organizing, directing and
implementing the temporary, flexible
organization that consists of a dossier of
projects and transformational activities to
achieve outcomes and realise benefits of
strategic importance to the business.
Definitions
4 2018
Source: APM BoKSource: MSP
Coordinate & Control
Projects
Strategic Objectives
Similar
• Co-ordination & control
• Projects alignment
• Strategic objectives & focus
5. Portfolio management
Portfolio management is the selection, prioritisation
and control of an organisation's projects and
programmes in line with its strategic objectives and
capacity to deliver. The goal is to balance change
initiatives and business-as-usual while optimising
return on investment.
This is a continuous process to achieve the evolving
strategy of the organisation.
Definitions
Programme management
Programme management is the action of
coordinating, organizing, directing and
implementing the temporary, flexible
organization that consists of a dossier of
projects and transformational activities to
achieve outcomes and realise benefits of
strategic importance to the business.
5 2018
Source: APM BoKSource: MSP
Similar
• Co-ordination & control
• Project alignment
• Strategic objectives & focus
Different?
• Selection and prioritisation
• Balance and optimisation
• Permanent vs temporary
6. What supports good decision making?
Programme MO Portfolio MO
Analytics and reportingProgramme delivery focus Focused on achieving the strategic goals
Planning & Dependency MgtProgramme delivery focus External dependencies, strategic plan
GovernanceTranche end progress reviews & decisions Embedded into BAU organisation governance
Stakeholder mgt & CommsS/h groups impacted by programme Executive levels across the organisation
Risk & Issue ManagementProgramme & project risks & issues External organisational & systemic risks
Change ControlFormal change process Decides which initiatives to stop & start
Standards, Tools & TemplatesOrganisational or programme standards Ensures consistent standards across programmes
Finance & Resource ManagementProgramme focus Overall investment budget & allocations
Business Case & Benefits MgtKey programme responsibility Optimised overall value
Delivery AssuranceAssures to organisation standards Delegated to programmes & projects
Strategic Planning Continual, regular investment reviews
Prioritisation & Optimisation Portfolio focus to achieve goals & max value
ScopeIdentified programme All programmes & projects (& BAU)
7. Prioritisation & optimisation
The portfolio mgt office continually prioritises the initiatives – stopping &
starting projects & reallocating resource to meet the goals & optimise value
The programme mgt office manages the costs & risks to deliver the
desired programme outcomes and vision.
Cost
Risk
Achievability
Achieve the strategic goals
Optimise value
Maximise Benefits
Cost
Risk
Achievability
Achieve the programme outcomes
Deliver Benefits
8. What’s the difference in mindset?
Thinking in Lines Thinking in Wheels
Risks are quantifiable
Solutions derived from key principles & experience
Clear Boundaries (cost/time)
Limited impact of stakeholder perception
Low complexity & interdependencies
Risks are subject to wide confidence ranges
Solutions derived from context & trial and error
Fuzzy Boundaries
Stakeholder perception has major impact on
success
High complexity & interdependencies
Reductionist, rational approach is more effective when Holistic, empirical approach is more effective when
There is a nominal solution There is an optimal solution
Value is process & methodology driven Value is people & creativity driven
There is a fairly high degree of predictability There is a low level of predictability
10. The Agile Management Office?
1
Continuous
Flow of value
2
Frequent
Customer
interaction
3
Iterative &
adaptive
4
Creativity &
innovation
5
Shared
Responsibility
For results
6
Situational
Specific
strategies
Business Agile Mindset - Source: Gartner, 2018
Portfolio
Programme
Delivery Vehicle
PrioritisationofValue
Source: Agile Business Consortium, 2018
11. 2019 Conference
201812
• Five case-study presentations, speakers arranged and confirmed
• private and public sector organisations
• Structured break-out sessions to exchange delegates’ views & capture key learnings
• The launch of the APM's official - “Guide to Portfolio Management”
• sneak peaks at its content and case-studies
• Walk-through of the outputs of our Portfolio Director Dinner
• focused on ‘The Agile Portfolio’
• Opportunities to network with colleagues and speakers
• drinks reception after the event at the Marquis Cornwallis
Thursday 23 May 2019
Holiday Inn, Bloomsbury, London, near Russell Square tube
Portfolio Management in a Digital Age - Delivering the portfolio in a world of rapid
value delivery and constant change
14. Agile Business Consortium
Six core behaviours
Focus on creation of value
Review the portfolio continuously
Involve the right people to shape & manage the portfolio
Clearly & continuously demonstrate that the portfolio is
delivering optimum value
Encourage innovation & creativity
Encourage collaboration and empowerment
Copyright APM Portfolio Management SIG 201815
15. Portfolio management
Manage risks
Vision Corporate
goals &
strategy
Deliver
benefit
s
Achieve
goals
Portfolio governance
Create
strategic
plan
Construct &
prioritise
portfolio
Review
portfolio
Assess
performance
of portfolio
Develop, monitor & control the portfolio
(Manage & deliver the programmes & projects)
Reporting on the portfolio
Management of
different
delivery
methods
From vision to achieving the goals
Editor's Notes
Programmes are likely to have a lifespan of several years.
We will focus on some of the principles today (highlighted in red).
Focus of pfm is to deliver the corporate goals and achieve the strategy.
Managing the investment in programmes & projects &, sometimes, BAU.
Stopping projects and programmes where the resources can be used more effectively elsewhere.
Redirecting resources.
Deciding whether to start new initiatives.
Measuring actual benefits to inform those decisions.
Extra complexity of dealing with corporate-wide business units to understand full impact of portfolio – eg planning, strategy, risk, finance, products, services
Contrasting with programmes, portfolio management continues until the goals are achieved, it’s an ongoing process.
Q: How many have portfolio management in their organisation?
Q: Roughly what % of in-flight projects or programmes are stopped?
Programmes are likely to have a lifespan of several years.
We will focus on some of the principles today (highlighted in red).
Programmes, by nature, are complex in so many ways.
How a programme is organised, Inter-dependencies, the best strategies to deliver a successful outcome. stakeholder relations, inter-related project and programme risks all require careful consideration.
Many organisations will focus on a few ‘critical elements’ of a programme, which may be an area within their comfort zone. For example, a number of clients responsible for delivering major infrastructure programmes tend to focus on scheduling and resourcing and hope that everything else will just fall into place.
To be successful, however, programmes require exponential levels of effort (people, processes and systems) in all programme and project management disciplines in order to maintain their course.
Programmes are complex because of the number of interactions between projects and between levels of organisation.
A complex programme therefore needs to be guided, nurtured and managed so that it has every opportunity to succeed. This is best achieved by proper planning at the programme’s initiation.
Programmes must focus early on developing effective programme strategies, such as stakeholder management, design & delivery, commercial, performance monitoring and operational integration – and lock these strategies down. Many programmes fail due to a lack of cohesive strategies leading to at best misinterpretation of the intended approach or worse, the adoption of competing strategies by project teams within the programme; the outcome of which is often chaotic.
A crucial component in supporting the finalisation and communication of programme strategies is a comprehensive suite of Programme Management Plans. These should be clearly and succinctly drafted so that they engage the wider programme. The style should be journalistic and professionally presented which makes the embedding of the strategies within the programme a far easier task.
Many project disciplines are very applicable to a programme and risk management is very much one of them. The principles are the same, but just applied at the most appropriate level so that risks are mitigated properly.
In terms of critical skills, I would suggest two that are important.
In a complex environment, keep solutions simple. Over complicating just adds to the complexity.
Softer skills are very important. Having a focus on outcomes is not as black and white as being output focussed (which is what a project manager must be). Flexibility, agility, not being afraid of change are necessary attributes required by programme leaders.
Programmes, by nature, are complex in so many ways.
How a programme is organised, Inter-dependencies, the best strategies to deliver a successful outcome. stakeholder relations, inter-related project and programme risks all require careful consideration.
Many organisations will focus on a few ‘critical elements’ of a programme, which may be an area within their comfort zone. For example, a number of clients responsible for delivering major infrastructure programmes tend to focus on scheduling and resourcing and hope that everything else will just fall into place.
To be successful, however, programmes require exponential levels of effort (people, processes and systems) in all programme and project management disciplines in order to maintain their course.
Programmes are complex because of the number of interactions between projects and between levels of organisation.
A complex programme therefore needs to be guided, nurtured and managed so that it has every opportunity to succeed. This is best achieved by proper planning at the programme’s initiation.
Programmes must focus early on developing effective programme strategies, such as stakeholder management, design & delivery, commercial, performance monitoring and operational integration – and lock these strategies down. Many programmes fail due to a lack of cohesive strategies leading to at best misinterpretation of the intended approach or worse, the adoption of competing strategies by project teams within the programme; the outcome of which is often chaotic.
A crucial component in supporting the finalisation and communication of programme strategies is a comprehensive suite of Programme Management Plans. These should be clearly and succinctly drafted so that they engage the wider programme. The style should be journalistic and professionally presented which makes the embedding of the strategies within the programme a far easier task.
Many project disciplines are very applicable to a programme and risk management is very much one of them. The principles are the same, but just applied at the most appropriate level so that risks are mitigated properly.
In terms of critical skills, I would suggest two that are important.
In a complex environment, keep solutions simple. Over complicating just adds to the complexity.
Softer skills are very important. Having a focus on outcomes is not as black and white as being output focussed (which is what a project manager must be). Flexibility, agility, not being afraid of change are necessary attributes required by programme leaders.
The end-to-end view of portfolio management, from vision to achieving the benefits and strategic goals.
Key is to understand the corporate goals and strategy – is it clear and unambiguous? - if not then clarification needs to be sought from the Exec or Board.
Does the organisation have a clear investment prioritisation model across:
BAU (operations);
Existing change programmes, projects and initiatives, i.e. those already in progress;
New change initiatives required to meet the corporate goals and strategy;
New initiatives with strong business cases and ROI?
Organisations may choose to define broad levels of investment, for example 60% of their overall investment for BAU, 40% for change. This gives a means of measuring and tracking investment levels and can be adjusted by the Board if necessary. A more rigorous approach would be to rank all initiatives (or groups of initiatives) including BAU by contribution to goals and levels of benefit.
Prioritisation guidelines should therefore be developed by and/or agreed with the Board. Typically this would be determined by several factors, including:
Prioritisation of the corporate goals – some will be more important than others
Benefits anticipated, and these will need to be in comparable formats
Timing - investment in short term gains may take priority over longer term, or vice versa.
Regulatory, compliance or upgrades to non-supported versions of software may be initially perceived as ‘must do’, but need to have business cases, even if brief. It may be a better use of resources to remain non-compliant and pay the fines, or hire specialist techies to support older versions of software rather than upgrade, at least in the short term.
Risk, performance and capability will also be an input to this process, however this is the ‘second stage’. Prioritisation to meet the strategic goals should be separate to decisions about risk, capability and achievability.
Critical to the success is complete alignment of the Execs behind the approach and the prioritisation criteria, they all need to be fully committed and have ‘cabinet responsibility’. Ref key success factors later in the presentation.
The vision and goals need to be communicated and cascaded clearly and unambiguously.