SlideShare a Scribd company logo
1 of 4
The Vertex Companies,Inc.(VERTEX)
www.vertexeng.com
pg. 1
How to Measure the Reasonableness of Completion Costs Post Termination-For-Cause
If an owner terminates its contractorfor cause,or if a generalcontractor or construction managerterminates
one of its subcontractors for cause,it owes the terminated party as well as its surety, if applicable, a duty to
incur only the reasonable and necessary costs to complete the work. 1
In other words, the non-default party
has a duty to mitigate the costs of completion.
How to Determine if Completion Costs are “reasonable.”
1. Finishing the Work
Per Article 14.2 of the AIA A201 General Conditions, which is incorporated in most AIA contracts, the
terminating party may “finish the Work by whatever reasonable method the Owner may deem expedient,
including making demand on the surety to perform the Work.” When this occurs,the Ownerwill not furnish
further payments to the Contractor until the work is finished. Once the work is complete, the Owner will
reconcile its completion costs with the remaining contract balance to determine any payments required to
the principal or potential damages to be recovered.
Similarly, the Standard Form of Agreement and General Conditions between Owner and Contractor
published by the Associated General Contractors of America (“AGC”) and the Standard Form of
Agreement between Contractor and Subcontractor (AGC Document No. 200 and 655 respectively) both
provide similar requirements. Section 11.3 of Document No. 200 indicates that following a termination for
cause:
All costs incurred by the Owner in performing the Work, including attorney’s fees, shall be
deducted from any moneys due or to become due the Contractor under this Agreement. The
Contractor shall be liable for the payment of any amount by which such expense may exceed the
unpaid balance of the Contract Price. If the unpaid balance of the Contract Price for Work
performed in accordance with this Agreement exceeds the expense of finishing the Work,
Contractor shall be paid for Work performed in accordance with the Contract Documents up to
the amount that the unpaid contract balance exceeds the expense of finishing the Work.
This paragraphfurther statesthat “[u]pon requestof the Contractor the Owner shallfurnish to the Contractor
a detailed accounting of the costs incurred by the Owner in finishing the Work.” AGC Document No. 655,
Section 10.1.2 presents nearly identical language.2
When an Owner terminates the Contractor and incurs costs to complete the Work (which often do exceed
the contractbalance),it is typically with an expectation that these costswill be recoveredfrom the defaulting
party.
1 Cushman, Richard F, et al., editors. Termination for Default from Owner’s Viewpoint. In Proving and Pricing
Construction Claims,Third Edition (pp. 214). New York, NY: Wolters Kluwer Law & Business,2001.
2 All costs incurred by the Contractor in performing the Subcontract Work, including reasonable overhead, profit
and attorneys'fees,costs and expenses, shall be deducted from any moneys due or to become due the Subcontractor.
The Subcontractorshall be liable for the payment of any amount by which such expense may exceed the unpaid
balance of the Subcontract Amount. At the Subcontractor's request,the Contractor shall provide a detailed
accounting of the costs to finish the Subcontract Work.
The Vertex Companies,Inc.(VERTEX)
www.vertexeng.com
pg. 2
2. When Are Costs Deemed Reasonable?
Reasonableness can be a subjective determination. In cases of construction contracts under federal
contracting guidelines, the Federal Acquisition Regulation (FAR) contemplates that “a cost is reasonable
if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the
conduct of competitive business.”3
The non-default party will often be looked upon favorably, and likely have its costs deemed reasonable if:
a. A Thoughtful Re-Solicitation is Performed
If the completion of work is being re-let, solicitation of multiple bidders can promote competitiveness
and allow for additional savings through cost negotiations. Original bidders on the project should be
considered for the completion as they likely already have familiarity with the plans and specifications.
Contractors familiar with completion work should also be considered. A proper bid analysis should be
conducted prior to award.
While reviewing multiple bids can provide a better understanding of the completion costs dictated by
the market, depending on the type or condition of the project, soliciting lump sum bids may not be
practical, and can result in high bid amounts due to bidder’s pricing contingencies and uncertainties
associated with a project default in their bids. Efforts such as site walkthroughs and access to sufficient
project documentation may help mitigate overestimates. Prudent consideration of the best means of
completing the work by the Owner and putting oneself in the best position to decide can support cost
reasonableness when electing to use a completion contractor.
b. Existing Subcontractors Are Utilized
Completion costs can typically be mitigated by entering into ratification agreements with the defaulted
principal’s subcontractorsand vendors to complete the subcontracted work, due to the monetary benefit
of using these subcontractors, time constraints and the ability to constrain overall completion costs.The
principal’s subcontractors may have already mobilized, are familiar with the project, and potentially
have material available or on order, therefore allowing them to complete the remaining work at a lower
price and in less time.4
When utilizing a completion contractor, assignment of existing subcontractors
can be a check against overstated costs, and can show reasonableness of costs as the principal would
have presumably incurred the balance of its own subcontractor’s costs if they had completed the work.
However,just because existing subcontractors are utilized may not mean that the costs are necessarily
reasonable.In one matter,the completion contractorwasutilizing assigned subcontractors,but wasalso
charging a significant markup on the subcontractor costs in addition to a separate Contractor’sFee.The
markup on subcontractor costs which the Owner paid the completion contractor on top of the
Contractor’s Fee was argued to be unreasonable.
3 FAR § 31.201–3
4 Clore, Duncan L, et al., editors. Takeover and Completion. In Bond Default Manual,Third Edition (pp. 223 – 241).
New York, NY: American Bar Association,2005
The Vertex Companies,Inc.(VERTEX)
www.vertexeng.com
pg. 3
c. Detailed Cost Tracking Is Performed
If it is worth doing,it is worth documenting. Project records are key to identifying and substantiating
completion costs, must be furnished to the defaulted party upon request per standard contracting
clauses, and allowing for a swift resolution of disputes of the same.Change order, or ticket work, should
be coded separately from base contract work,to allow for segregation of these costs. Necessary rework
of the principal’s issues should be documented sufficiently, with photographs and descriptive narrative
in the daily field reports. Any self-induced deficiencies or inefficiencies should also be properly noted
and removed from the recoverable costs: proper documentation and fair assignment of costs provide
credibility to the recovery of completion costs. Typically, when a contractor is terminated, detailed
daily reports will be kept by the completing contractor to substantiate all work performed, as these logs
are the primary means of recordkeeping for activities occurring onsite and are especially important in
disputes.5
When the work is not properly documented, it may create issues substantiating the cost
reasonableness and necessity of the costs.
3. What Costs are not Reasonable for Recovery?
Costs may have been incurred in the completion of the work that are unreasonable or would otherwise be
unnecessary had the non-default party acted prudently. Even when acting prudently, some costs may not be
considered reasonable and therefore would not be recoverable.
Some examples of unreasonable costs are:
a. Betterments and changes to the scope of the original contract
Change orders issued after the termination, betterments to the project, and work performed that is not-
in-scope should not be considered recoverable in a termination.
b. Rework of completing party’s deficiencies
Costs incurred by the completing contractor correcting its own deficiencies are not reasonable costs to
be assigned to the default party. However,costs for remedial work for defects of the original contractor
would be reasonable if performed prudently.
c. Additional costs resulting from the non-default party not promptly completing the Work
Work, which remains dormant due the Owner inaction can be subject to escalation costs, repairs /
rework, standby costs, warranty issues, liquidated or actual damages, winter conditions and more. If
practical to progress the work meaningfully, these efforts must be considered, as costs resulting from
abandonment or significant delay to the completion effort by the Owner may not be reasonable.
In one example, after re-commencing work, raw steel installed by the terminated principal was left
exposed to oxidation. As priming of the steel was not promptly undertaken by the completing party,
additional costs for blasting and wire brushing became necessary to allow for the painting work to
proceed – these costs were not recoverable based on the work not being promptly resumed.
5 Clough, Richard H., et al. Construction Contracting:A Practical Guide to Company Management (Eight Ed.) (pp.
323 – 324). United States of America: John Wiley & Sons, 2015.
The Vertex Companies,Inc.(VERTEX)
www.vertexeng.com
pg. 4
In another example, UV-sensitive materials that were staged for installation prior to termination were
left exposed to sunlight and weather.While the duty to protect materials is often a contractualobligation
of the principal, based on the timing of the termination and barring of the contractor from returning to
the site, the material ended up remaining unprotected for longer than the manufacturer’sexposure limit,
and new material needed to be re-orderedand the existing material needed to be disposed of. Protecting
the material with tarpaulins would have been a reasonable action and compensable cost of the non-
default party. By not acting promptly, the cost incurred in replacing the materials was not reasonable.
d. Costs resulting from inexperience or unfamiliarity with type of construction
Completion work should be performed by a capable party who can perform the work efficiently and
per industry standards. If the work is performed by an inexperienced party, costs associated with
inefficiencies from the inexperienced contractor may not be considered reasonable.
In one case, a completion contractor was retained to construct an elevated parking deck with a pre-
engineered, factory-built, reusable concrete forming system.Atthe time of the termination, the elevated
deck work had not begun. When the completion contractor started this work, they proceeded in an
inefficient, circular sequence of deck placements that required concrete to cure and post-tension cables
to be stressedbefore cables could be laid on the subsequent deck area tobe poured. Had a more common
checkerboard sequence been utilized, which was possible with the forming equipment that was onsite,
concrete curing and cable stressing would not have been critical predecessors to the subsequent deck
placement, and the overall completion time of the project could have been reduced. The additional
delay damages,labor, and rental costs resulting from the inexperience of the completing party were not
reasonable as an experienced contractor, acting prudently, would have mitigated these costs by
performing the work in accordance with generally accepted practices.
e. Unnecessary costs of expediting
If completion of work is not constrained by a deadline, and costs are spent on overtime labor or winter
heating, these costs may not be practical and efficient, and would be disputed as unnecessary and
unreasonable.
Other costs incurred in completing the work following a termination may be deemed unreasonable. When
disputes over completion costs arise,the adverse parties may look to retain damages and allocation experts
to review the disputed costs. These experts will review the manner in which the work was completed, pore
over the financial data and construction documents, and prepare their own estimates to affirm or contest the
reasonableness of the costs.
Authored by: Jeffrey Katz, PE, The Vertex Companies, Inc.
VERTEX provides expert services and litigation support for attorneys, sureties, contractorsand Owners
who require cost estimating, damagesallocation and analysis of terminationsand completion costs. We
have prepared affirmative claims, counterclaims, and defenses on hundreds of matters across the United
States and internationally. For additional information, please visit us online or contact Ryan Phillips,PE
at mailto:mrphillips@vertexeng.com.

More Related Content

What's hot

Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contractguestdb5e498
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract AdministratorsSarah Fox
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tenderneharajpl
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsAdi Iskandar Iliyas
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014SHKLaw
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...Praveen Premkumar
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-ContractsNikhil Kumar
 
Construction contract
Construction contractConstruction contract
Construction contractAqsa Shafique
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Bhalindra Bath - projects & M&A law
 
Construction management 2
Construction management 2Construction management 2
Construction management 2smumbahelp
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Francis Ho
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotKhaled M. Al Kolfat MS.Eng,MoP,P3O,PMOC,PMP,M.ASCE
 

What's hot (20)

Construction contract
Construction contract Construction contract
Construction contract
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Conditions Of Contract
Conditions Of ContractConditions Of Contract
Conditions Of Contract
 
Guide for Construction Contract Administrators
Guide for Construction Contract AdministratorsGuide for Construction Contract Administrators
Guide for Construction Contract Administrators
 
Contract management sys
Contract management sysContract management sys
Contract management sys
 
Cpm ch 2tender
Cpm ch 2tenderCpm ch 2tender
Cpm ch 2tender
 
Construction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting StandardsConstruction contract_Existing and Proposed Accounting Standards
Construction contract_Existing and Proposed Accounting Standards
 
Effective contract administration may 2014
Effective contract administration may 2014Effective contract administration may 2014
Effective contract administration may 2014
 
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
3.0 Common Types of Construction Contracts & Standard Conditions of Contract ...
 
civil engineering-Contracts
civil engineering-Contractscivil engineering-Contracts
civil engineering-Contracts
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...Design & Build contracts - key points for a main contractor with technology a...
Design & Build contracts - key points for a main contractor with technology a...
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
Construction management 2
Construction management 2Construction management 2
Construction management 2
 
IAS 11 Construction Contracts
IAS 11 Construction ContractsIAS 11 Construction Contracts
IAS 11 Construction Contracts
 
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
Variations and their Consequences - Olswang Construction Law Masterclass - 5 ...
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 
Estimation
EstimationEstimation
Estimation
 
Ias11
Ias11Ias11
Ias11
 
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEotمحاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
محاضرة تمهيدية في إعداد و تحليل المطالبات الزمنيةEot
 

Similar to Reasonableness of Construction Completion Costs

Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Cicerone
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfChelDems
 
Final types of contracts- different types of contracts
Final types of contracts- different types of contractsFinal types of contracts- different types of contracts
Final types of contracts- different types of contractsMohammedAlfayad2
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingRai University
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxsulevrunda
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts MANNU KUMAR
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)James Baker
 
Beyond Contract Series Article One
Beyond Contract Series   Article OneBeyond Contract Series   Article One
Beyond Contract Series Article OneMy own
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
types of contracts
 types of contracts types of contracts
types of contractsKEVINMISTRY8
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction ContractSarah Fox
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costingCollen Mahambo
 
Your Construction Subcontract. The 23 Points That Matter Most
Your Construction Subcontract. The 23 Points That Matter MostYour Construction Subcontract. The 23 Points That Matter Most
Your Construction Subcontract. The 23 Points That Matter MostAlex Barthet
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03ypinada
 

Similar to Reasonableness of Construction Completion Costs (20)

Construction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of ResidencesConstruction Contract Issues for Owners of Residences
Construction Contract Issues for Owners of Residences
 
CE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdfCE-CONTRACTS-REPORT.pdf
CE-CONTRACTS-REPORT.pdf
 
Final types of contracts- different types of contracts
Final types of contracts- different types of contractsFinal types of contracts- different types of contracts
Final types of contracts- different types of contracts
 
Bba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costingBba ii cost and management accounting u 3.3 contract costing
Bba ii cost and management accounting u 3.3 contract costing
 
Chapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptxChapter-2 Construction Contract. Subject code:3160614ptx
Chapter-2 Construction Contract. Subject code:3160614ptx
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Types of contracts
Types of contracts   Types of contracts
Types of contracts
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Construction contract
Construction contractConstruction contract
Construction contract
 
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)Ipwea inspire-issue-12- nov-2019- managing contractors (1)
Ipwea inspire-issue-12- nov-2019- managing contractors (1)
 
Beyond Contract Series Article One
Beyond Contract Series   Article OneBeyond Contract Series   Article One
Beyond Contract Series Article One
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
Ias 11
Ias 11Ias 11
Ias 11
 
types of contracts
 types of contracts types of contracts
types of contracts
 
MODULE 5.pptx
MODULE 5.pptxMODULE 5.pptx
MODULE 5.pptx
 
10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract10 Essentials For An Effective Construction Contract
10 Essentials For An Effective Construction Contract
 
Job,batch and contract costing
Job,batch and contract costingJob,batch and contract costing
Job,batch and contract costing
 
Your Construction Subcontract. The 23 Points That Matter Most
Your Construction Subcontract. The 23 Points That Matter MostYour Construction Subcontract. The 23 Points That Matter Most
Your Construction Subcontract. The 23 Points That Matter Most
 
Pai 3-03
Pai 3-03Pai 3-03
Pai 3-03
 

More from The Vertex Companies, LLC

The State of the Construction Industry - 2020
The State of the Construction Industry - 2020The State of the Construction Industry - 2020
The State of the Construction Industry - 2020The Vertex Companies, LLC
 
Vertex annual state of the construction industry presentation 2018
Vertex annual state of the construction industry presentation   2018Vertex annual state of the construction industry presentation   2018
Vertex annual state of the construction industry presentation 2018The Vertex Companies, LLC
 
VERTEX Annual State of the Construction Industry 2018
VERTEX Annual State of the Construction Industry 2018VERTEX Annual State of the Construction Industry 2018
VERTEX Annual State of the Construction Industry 2018The Vertex Companies, LLC
 
Vertex 2017 mexico habitat trip power point-8.28.2017
Vertex   2017 mexico habitat trip power point-8.28.2017Vertex   2017 mexico habitat trip power point-8.28.2017
Vertex 2017 mexico habitat trip power point-8.28.2017The Vertex Companies, LLC
 
Construction of Manufactured Homes - Understanding the Hazards & Risks
Construction of Manufactured Homes - Understanding the Hazards & RisksConstruction of Manufactured Homes - Understanding the Hazards & Risks
Construction of Manufactured Homes - Understanding the Hazards & RisksThe Vertex Companies, LLC
 
PLRB - Hail Damage to Thermoset and Thermoplastic Roofing Membranes
PLRB - Hail Damage to Thermoset and Thermoplastic Roofing MembranesPLRB - Hail Damage to Thermoset and Thermoplastic Roofing Membranes
PLRB - Hail Damage to Thermoset and Thermoplastic Roofing MembranesThe Vertex Companies, LLC
 
PAST, PRESENT, AND FUTURE ANALYSIS OF THE ARCHITECTURAL & ENGINEERING DESIGN ...
PAST, PRESENT, AND FUTURE ANALYSIS OF THE ARCHITECTURAL & ENGINEERING DESIGN ...PAST, PRESENT, AND FUTURE ANALYSIS OF THE ARCHITECTURAL & ENGINEERING DESIGN ...
PAST, PRESENT, AND FUTURE ANALYSIS OF THE ARCHITECTURAL & ENGINEERING DESIGN ...The Vertex Companies, LLC
 
Environmental Business Journal - VERTEX Growth
Environmental Business Journal - VERTEX GrowthEnvironmental Business Journal - VERTEX Growth
Environmental Business Journal - VERTEX GrowthThe Vertex Companies, LLC
 
State of the Construction & Surety Industry Report (2008)
State of the Construction & Surety Industry Report (2008)State of the Construction & Surety Industry Report (2008)
State of the Construction & Surety Industry Report (2008)The Vertex Companies, LLC
 
State of the Construction & Surety Industry (2006 2007)
State of the Construction & Surety Industry (2006 2007)State of the Construction & Surety Industry (2006 2007)
State of the Construction & Surety Industry (2006 2007)The Vertex Companies, LLC
 
State of the Construction and Surety Industry Report (2009)
State of the Construction and Surety Industry Report (2009)State of the Construction and Surety Industry Report (2009)
State of the Construction and Surety Industry Report (2009)The Vertex Companies, LLC
 
State of the Construction Industry Report (2010)
State of the Construction Industry Report (2010)State of the Construction Industry Report (2010)
State of the Construction Industry Report (2010)The Vertex Companies, LLC
 
State of the Construction Industry Report (2015)
State of the Construction Industry Report (2015)State of the Construction Industry Report (2015)
State of the Construction Industry Report (2015)The Vertex Companies, LLC
 
State of the Construction and Surety Industry Report (2016)
State of the Construction and Surety Industry Report (2016)State of the Construction and Surety Industry Report (2016)
State of the Construction and Surety Industry Report (2016)The Vertex Companies, LLC
 
State of the Construction and Surety Industry Report (2017)
State of the Construction and Surety Industry Report (2017)State of the Construction and Surety Industry Report (2017)
State of the Construction and Surety Industry Report (2017)The Vertex Companies, LLC
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 

More from The Vertex Companies, LLC (20)

The State of the Construction Industry - 2020
The State of the Construction Industry - 2020The State of the Construction Industry - 2020
The State of the Construction Industry - 2020
 
State of the Industry Report Q4 of 2018
State of the Industry Report Q4 of 2018State of the Industry Report Q4 of 2018
State of the Industry Report Q4 of 2018
 
Vertex annual state of the construction industry presentation 2018
Vertex annual state of the construction industry presentation   2018Vertex annual state of the construction industry presentation   2018
Vertex annual state of the construction industry presentation 2018
 
VERTEX Annual State of the Construction Industry 2018
VERTEX Annual State of the Construction Industry 2018VERTEX Annual State of the Construction Industry 2018
VERTEX Annual State of the Construction Industry 2018
 
State of the Industry Report 2017
State of the Industry Report 2017State of the Industry Report 2017
State of the Industry Report 2017
 
Vertex 2017 mexico habitat trip power point-8.28.2017
Vertex   2017 mexico habitat trip power point-8.28.2017Vertex   2017 mexico habitat trip power point-8.28.2017
Vertex 2017 mexico habitat trip power point-8.28.2017
 
Construction of Manufactured Homes - Understanding the Hazards & Risks
Construction of Manufactured Homes - Understanding the Hazards & RisksConstruction of Manufactured Homes - Understanding the Hazards & Risks
Construction of Manufactured Homes - Understanding the Hazards & Risks
 
PLRB - Hail Damage to Thermoset and Thermoplastic Roofing Membranes
PLRB - Hail Damage to Thermoset and Thermoplastic Roofing MembranesPLRB - Hail Damage to Thermoset and Thermoplastic Roofing Membranes
PLRB - Hail Damage to Thermoset and Thermoplastic Roofing Membranes
 
PAST, PRESENT, AND FUTURE ANALYSIS OF THE ARCHITECTURAL & ENGINEERING DESIGN ...
PAST, PRESENT, AND FUTURE ANALYSIS OF THE ARCHITECTURAL & ENGINEERING DESIGN ...PAST, PRESENT, AND FUTURE ANALYSIS OF THE ARCHITECTURAL & ENGINEERING DESIGN ...
PAST, PRESENT, AND FUTURE ANALYSIS OF THE ARCHITECTURAL & ENGINEERING DESIGN ...
 
Environmental Business Journal - VERTEX Growth
Environmental Business Journal - VERTEX GrowthEnvironmental Business Journal - VERTEX Growth
Environmental Business Journal - VERTEX Growth
 
State of the Construction & Surety Industry Report (2008)
State of the Construction & Surety Industry Report (2008)State of the Construction & Surety Industry Report (2008)
State of the Construction & Surety Industry Report (2008)
 
State of the Construction & Surety Industry (2006 2007)
State of the Construction & Surety Industry (2006 2007)State of the Construction & Surety Industry (2006 2007)
State of the Construction & Surety Industry (2006 2007)
 
Lifecycles of Large AEC Companies
Lifecycles of Large AEC CompaniesLifecycles of Large AEC Companies
Lifecycles of Large AEC Companies
 
State of the Construction and Surety Industry Report (2009)
State of the Construction and Surety Industry Report (2009)State of the Construction and Surety Industry Report (2009)
State of the Construction and Surety Industry Report (2009)
 
State of the Construction Industry Report (2010)
State of the Construction Industry Report (2010)State of the Construction Industry Report (2010)
State of the Construction Industry Report (2010)
 
State of the US Economy (2016)
State of the US Economy (2016)State of the US Economy (2016)
State of the US Economy (2016)
 
State of the Construction Industry Report (2015)
State of the Construction Industry Report (2015)State of the Construction Industry Report (2015)
State of the Construction Industry Report (2015)
 
State of the Construction and Surety Industry Report (2016)
State of the Construction and Surety Industry Report (2016)State of the Construction and Surety Industry Report (2016)
State of the Construction and Surety Industry Report (2016)
 
State of the Construction and Surety Industry Report (2017)
State of the Construction and Surety Industry Report (2017)State of the Construction and Surety Industry Report (2017)
State of the Construction and Surety Industry Report (2017)
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 

Recently uploaded

Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...ApartmentWala1
 
Nyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdfNyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdfabbu831446
 
Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024VickyAulakh1
 
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
Kalpataru Exquisite Wakad Pune  E-Brochure.pdfKalpataru Exquisite Wakad Pune  E-Brochure.pdf
Kalpataru Exquisite Wakad Pune E-Brochure.pdfManishSaxena95
 
Top tourism places in Dubai - Inch & Brick Realty
Top tourism places in Dubai - Inch & Brick RealtyTop tourism places in Dubai - Inch & Brick Realty
Top tourism places in Dubai - Inch & Brick Realtypunitranainchbrick02
 
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdfManishSaxena95
 
Rohan Harita Tathawade Pune Brochure.pdf
Rohan Harita Tathawade Pune Brochure.pdfRohan Harita Tathawade Pune Brochure.pdf
Rohan Harita Tathawade Pune Brochure.pdfabbu831446
 
Yedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing TurkeyYedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing TurkeyListing Turkey
 
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...asmaqueen5
 
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhiasmaqueen5
 
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)delhi24hrs1
 
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...asmaqueen5
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)delhi24hrs1
 
Prestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdfPrestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdfkishor21012022
 
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...ApartmentWala1
 
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...ApartmentWala1
 
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...ApartmentWala1
 
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & RequirementsExplore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirementsmarketingkingdomofku
 
Kohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living SpacesKohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living Spacesaidasheikh47
 
Best Interior Design Services in Haldwani
Best Interior Design Services in HaldwaniBest Interior Design Services in Haldwani
Best Interior Design Services in HaldwaniGeomatrix
 

Recently uploaded (20)

Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
Low Density Living New Project in BPTP THE AMAARIO Sector 37D Gurgaon Haryana...
 
Nyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdfNyati Elite NIBM Road Pune E Brochure.pdf
Nyati Elite NIBM Road Pune E Brochure.pdf
 
Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024Parksville 96 Surrey Floor Plans May 2024
Parksville 96 Surrey Floor Plans May 2024
 
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
Kalpataru Exquisite Wakad Pune  E-Brochure.pdfKalpataru Exquisite Wakad Pune  E-Brochure.pdf
Kalpataru Exquisite Wakad Pune E-Brochure.pdf
 
Top tourism places in Dubai - Inch & Brick Realty
Top tourism places in Dubai - Inch & Brick RealtyTop tourism places in Dubai - Inch & Brick Realty
Top tourism places in Dubai - Inch & Brick Realty
 
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdfKohinoor Teiko Hinjewadi Phase 2 Pune  E-Brochure.pdf
Kohinoor Teiko Hinjewadi Phase 2 Pune E-Brochure.pdf
 
Rohan Harita Tathawade Pune Brochure.pdf
Rohan Harita Tathawade Pune Brochure.pdfRohan Harita Tathawade Pune Brochure.pdf
Rohan Harita Tathawade Pune Brochure.pdf
 
Yedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing TurkeyYedi Mavi TOBB Zeytinburnu - Listing Turkey
Yedi Mavi TOBB Zeytinburnu - Listing Turkey
 
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
Call girls in Shakti Nagar Delhi~8447779280°/=@/ Short 1500 Night 6000}ESCORT...
 
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
~Call Girls In Roop Nagar {8447779280}(Low Price) Escort Service In Delhi
 
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
Cheap Rate ✨➥9582086666▻✨Call Girls In Gurgaon Sector 1 (Gurgaon)
 
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
Low rate ↬Call girls in Sabzi Mandi Delhi | 8447779280}Escort Service In All ...
 
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
Low Rate ✨➥9711108085▻✨Call Girls In East Of Kailash (E.K) (Delhi)
 
Prestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdfPrestige Sancoale Goa Residneces Brochure.pdf
Prestige Sancoale Goa Residneces Brochure.pdf
 
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
BPTP THE AMAARIO For The Royals Of Tomorrow in Sector 37D Gurgaon Dwarka Expr...
 
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...Bptp The Amaario Launch  Luxury Project  Sector 37D Gurgaon Dwarka Expressway...
Bptp The Amaario Launch Luxury Project Sector 37D Gurgaon Dwarka Expressway...
 
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
BPTP THE AMAARIO Luxury Project Invest Like Royalty in Sector 37D Gurgaon Dwa...
 
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & RequirementsExplore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
 
Kohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living SpacesKohinoor Courtyard One Wakad Pune | Elegant Living Spaces
Kohinoor Courtyard One Wakad Pune | Elegant Living Spaces
 
Best Interior Design Services in Haldwani
Best Interior Design Services in HaldwaniBest Interior Design Services in Haldwani
Best Interior Design Services in Haldwani
 

Reasonableness of Construction Completion Costs

  • 1. The Vertex Companies,Inc.(VERTEX) www.vertexeng.com pg. 1 How to Measure the Reasonableness of Completion Costs Post Termination-For-Cause If an owner terminates its contractorfor cause,or if a generalcontractor or construction managerterminates one of its subcontractors for cause,it owes the terminated party as well as its surety, if applicable, a duty to incur only the reasonable and necessary costs to complete the work. 1 In other words, the non-default party has a duty to mitigate the costs of completion. How to Determine if Completion Costs are “reasonable.” 1. Finishing the Work Per Article 14.2 of the AIA A201 General Conditions, which is incorporated in most AIA contracts, the terminating party may “finish the Work by whatever reasonable method the Owner may deem expedient, including making demand on the surety to perform the Work.” When this occurs,the Ownerwill not furnish further payments to the Contractor until the work is finished. Once the work is complete, the Owner will reconcile its completion costs with the remaining contract balance to determine any payments required to the principal or potential damages to be recovered. Similarly, the Standard Form of Agreement and General Conditions between Owner and Contractor published by the Associated General Contractors of America (“AGC”) and the Standard Form of Agreement between Contractor and Subcontractor (AGC Document No. 200 and 655 respectively) both provide similar requirements. Section 11.3 of Document No. 200 indicates that following a termination for cause: All costs incurred by the Owner in performing the Work, including attorney’s fees, shall be deducted from any moneys due or to become due the Contractor under this Agreement. The Contractor shall be liable for the payment of any amount by which such expense may exceed the unpaid balance of the Contract Price. If the unpaid balance of the Contract Price for Work performed in accordance with this Agreement exceeds the expense of finishing the Work, Contractor shall be paid for Work performed in accordance with the Contract Documents up to the amount that the unpaid contract balance exceeds the expense of finishing the Work. This paragraphfurther statesthat “[u]pon requestof the Contractor the Owner shallfurnish to the Contractor a detailed accounting of the costs incurred by the Owner in finishing the Work.” AGC Document No. 655, Section 10.1.2 presents nearly identical language.2 When an Owner terminates the Contractor and incurs costs to complete the Work (which often do exceed the contractbalance),it is typically with an expectation that these costswill be recoveredfrom the defaulting party. 1 Cushman, Richard F, et al., editors. Termination for Default from Owner’s Viewpoint. In Proving and Pricing Construction Claims,Third Edition (pp. 214). New York, NY: Wolters Kluwer Law & Business,2001. 2 All costs incurred by the Contractor in performing the Subcontract Work, including reasonable overhead, profit and attorneys'fees,costs and expenses, shall be deducted from any moneys due or to become due the Subcontractor. The Subcontractorshall be liable for the payment of any amount by which such expense may exceed the unpaid balance of the Subcontract Amount. At the Subcontractor's request,the Contractor shall provide a detailed accounting of the costs to finish the Subcontract Work.
  • 2. The Vertex Companies,Inc.(VERTEX) www.vertexeng.com pg. 2 2. When Are Costs Deemed Reasonable? Reasonableness can be a subjective determination. In cases of construction contracts under federal contracting guidelines, the Federal Acquisition Regulation (FAR) contemplates that “a cost is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the conduct of competitive business.”3 The non-default party will often be looked upon favorably, and likely have its costs deemed reasonable if: a. A Thoughtful Re-Solicitation is Performed If the completion of work is being re-let, solicitation of multiple bidders can promote competitiveness and allow for additional savings through cost negotiations. Original bidders on the project should be considered for the completion as they likely already have familiarity with the plans and specifications. Contractors familiar with completion work should also be considered. A proper bid analysis should be conducted prior to award. While reviewing multiple bids can provide a better understanding of the completion costs dictated by the market, depending on the type or condition of the project, soliciting lump sum bids may not be practical, and can result in high bid amounts due to bidder’s pricing contingencies and uncertainties associated with a project default in their bids. Efforts such as site walkthroughs and access to sufficient project documentation may help mitigate overestimates. Prudent consideration of the best means of completing the work by the Owner and putting oneself in the best position to decide can support cost reasonableness when electing to use a completion contractor. b. Existing Subcontractors Are Utilized Completion costs can typically be mitigated by entering into ratification agreements with the defaulted principal’s subcontractorsand vendors to complete the subcontracted work, due to the monetary benefit of using these subcontractors, time constraints and the ability to constrain overall completion costs.The principal’s subcontractors may have already mobilized, are familiar with the project, and potentially have material available or on order, therefore allowing them to complete the remaining work at a lower price and in less time.4 When utilizing a completion contractor, assignment of existing subcontractors can be a check against overstated costs, and can show reasonableness of costs as the principal would have presumably incurred the balance of its own subcontractor’s costs if they had completed the work. However,just because existing subcontractors are utilized may not mean that the costs are necessarily reasonable.In one matter,the completion contractorwasutilizing assigned subcontractors,but wasalso charging a significant markup on the subcontractor costs in addition to a separate Contractor’sFee.The markup on subcontractor costs which the Owner paid the completion contractor on top of the Contractor’s Fee was argued to be unreasonable. 3 FAR § 31.201–3 4 Clore, Duncan L, et al., editors. Takeover and Completion. In Bond Default Manual,Third Edition (pp. 223 – 241). New York, NY: American Bar Association,2005
  • 3. The Vertex Companies,Inc.(VERTEX) www.vertexeng.com pg. 3 c. Detailed Cost Tracking Is Performed If it is worth doing,it is worth documenting. Project records are key to identifying and substantiating completion costs, must be furnished to the defaulted party upon request per standard contracting clauses, and allowing for a swift resolution of disputes of the same.Change order, or ticket work, should be coded separately from base contract work,to allow for segregation of these costs. Necessary rework of the principal’s issues should be documented sufficiently, with photographs and descriptive narrative in the daily field reports. Any self-induced deficiencies or inefficiencies should also be properly noted and removed from the recoverable costs: proper documentation and fair assignment of costs provide credibility to the recovery of completion costs. Typically, when a contractor is terminated, detailed daily reports will be kept by the completing contractor to substantiate all work performed, as these logs are the primary means of recordkeeping for activities occurring onsite and are especially important in disputes.5 When the work is not properly documented, it may create issues substantiating the cost reasonableness and necessity of the costs. 3. What Costs are not Reasonable for Recovery? Costs may have been incurred in the completion of the work that are unreasonable or would otherwise be unnecessary had the non-default party acted prudently. Even when acting prudently, some costs may not be considered reasonable and therefore would not be recoverable. Some examples of unreasonable costs are: a. Betterments and changes to the scope of the original contract Change orders issued after the termination, betterments to the project, and work performed that is not- in-scope should not be considered recoverable in a termination. b. Rework of completing party’s deficiencies Costs incurred by the completing contractor correcting its own deficiencies are not reasonable costs to be assigned to the default party. However,costs for remedial work for defects of the original contractor would be reasonable if performed prudently. c. Additional costs resulting from the non-default party not promptly completing the Work Work, which remains dormant due the Owner inaction can be subject to escalation costs, repairs / rework, standby costs, warranty issues, liquidated or actual damages, winter conditions and more. If practical to progress the work meaningfully, these efforts must be considered, as costs resulting from abandonment or significant delay to the completion effort by the Owner may not be reasonable. In one example, after re-commencing work, raw steel installed by the terminated principal was left exposed to oxidation. As priming of the steel was not promptly undertaken by the completing party, additional costs for blasting and wire brushing became necessary to allow for the painting work to proceed – these costs were not recoverable based on the work not being promptly resumed. 5 Clough, Richard H., et al. Construction Contracting:A Practical Guide to Company Management (Eight Ed.) (pp. 323 – 324). United States of America: John Wiley & Sons, 2015.
  • 4. The Vertex Companies,Inc.(VERTEX) www.vertexeng.com pg. 4 In another example, UV-sensitive materials that were staged for installation prior to termination were left exposed to sunlight and weather.While the duty to protect materials is often a contractualobligation of the principal, based on the timing of the termination and barring of the contractor from returning to the site, the material ended up remaining unprotected for longer than the manufacturer’sexposure limit, and new material needed to be re-orderedand the existing material needed to be disposed of. Protecting the material with tarpaulins would have been a reasonable action and compensable cost of the non- default party. By not acting promptly, the cost incurred in replacing the materials was not reasonable. d. Costs resulting from inexperience or unfamiliarity with type of construction Completion work should be performed by a capable party who can perform the work efficiently and per industry standards. If the work is performed by an inexperienced party, costs associated with inefficiencies from the inexperienced contractor may not be considered reasonable. In one case, a completion contractor was retained to construct an elevated parking deck with a pre- engineered, factory-built, reusable concrete forming system.Atthe time of the termination, the elevated deck work had not begun. When the completion contractor started this work, they proceeded in an inefficient, circular sequence of deck placements that required concrete to cure and post-tension cables to be stressedbefore cables could be laid on the subsequent deck area tobe poured. Had a more common checkerboard sequence been utilized, which was possible with the forming equipment that was onsite, concrete curing and cable stressing would not have been critical predecessors to the subsequent deck placement, and the overall completion time of the project could have been reduced. The additional delay damages,labor, and rental costs resulting from the inexperience of the completing party were not reasonable as an experienced contractor, acting prudently, would have mitigated these costs by performing the work in accordance with generally accepted practices. e. Unnecessary costs of expediting If completion of work is not constrained by a deadline, and costs are spent on overtime labor or winter heating, these costs may not be practical and efficient, and would be disputed as unnecessary and unreasonable. Other costs incurred in completing the work following a termination may be deemed unreasonable. When disputes over completion costs arise,the adverse parties may look to retain damages and allocation experts to review the disputed costs. These experts will review the manner in which the work was completed, pore over the financial data and construction documents, and prepare their own estimates to affirm or contest the reasonableness of the costs. Authored by: Jeffrey Katz, PE, The Vertex Companies, Inc. VERTEX provides expert services and litigation support for attorneys, sureties, contractorsand Owners who require cost estimating, damagesallocation and analysis of terminationsand completion costs. We have prepared affirmative claims, counterclaims, and defenses on hundreds of matters across the United States and internationally. For additional information, please visit us online or contact Ryan Phillips,PE at mailto:mrphillips@vertexeng.com.