SlideShare a Scribd company logo
1 of 8
Download to read offline
Our projects
Shell Prelude FLNG
A new landmark in the Offshore industry
Shell Prelude FLNG2
2009 – Master Agreement
It all started in 2009 when Shell and the Technip-Samsung Heavy
Industries Consortium signed a Master Agreement for the design,
construction and installation of multiple FLNG facilities over up
to 15 years.
Bolo bolo bolo bolo bolo bolo
Shell Prelude FLNG
milestones
2010 – FEED
Following this agreement, Technip carried out a generic FLNG FEED (Front-End Engineering and Design) study and, in 2010, it was
adapted to Prelude. In total, more than 600 people around the world spent over 1.6 million hours working on different design
options for the Prelude facility.
2011 – Notice to proceed
On May 30, 2011, the Technip-Samsung Consortium was given notice by Shell to proceed with the construction of Prelude FLNG,
the first floating liquefied natural gas facility in the world, to be located offshore Australia.
2012 – First steel cut
At the Samsung Heavy Industries ship yard in Geoje, South Korea, the steel cutting of the hull started in October 2012, followed
by the steel cutting of the topsides in January 2013. On November 30, 2013, the hull was completed in dry-dock and launched.
2012 – Subsea contract
In June 2012, Shell awarded Technip the subsea contract for the Prelude development, including the installation of all the necessary
flowlines, risers and umbilicals.
Client: Shell (operator: 67.5%)
Three joint venture partners: INPEX (17.5%), KOGAS (10%) and
CPC Taiwan (5%)
Contractors: Technip - Samsung Consortium
Location: approximately 475 kilometers North-North East of
Broome, Western Australia
Water depth: 200 - 250 meters
Australia
Prelude
FLNG
Shell Prelude FLNG 3
The largest floating facility
ever built
World-recognized partners to engineer and deliver this first-of-a-kind project
The Technip-Samsung Consortium (TSC) combines the strengths of each company to enable the
delivery of the Shell Prelude integrated FLNG facility:
Samsung Heavy Industries (SHI) performs all of
the construction on Prelude and has design
responsibility for the hull. SHI and Technip have a
solid track record together including FPSO’s. SHI
has the best equipped shipyard in the world with
large drydocks and floating docks and an 8,000t
floating crane. It has decades of experience in
construction of LNG carriers and offshore facilities.
Technip provides the TSC project management,
engineering, procurement, installation and
commissioning for Prelude. FLNG is a market where
Technip has quickly emerged as the leader due to
its industrial experience of natural gas liquefaction,
subsea field development and large floating oil
production platforms.
Prelude in figures
488 metres long (more than four FIFA football pitches)
74 metres wide
260,000 tons of steel, the equivalent of 36 Eiffel towers or 430,000 medium-sized cars
With its cargo tanks full, Prelude will weigh roughly six times as much as the largest aircraft carrier
The world’s largest non-disconnectable Turret Mooring System, taller than the Statue of Liberty with its base
Living quarters the size of the Arc de Triomphe
Shell Prelude FLNG is expected to yield an annual production of:
3.6 Mtpa of LNG
1.3 Mtpa of condensate
0.4 Mtpa of LPG
The facility’s storage tanks, located below the deck, can store up to 220,000 m3
of LNG, 90,000 m3
of LPG,
and 126,000 m3
of condensate. The total storage capacity is equivalent to around 175 Olympic swimming pools.
It is aimed at producing and exporting LNG off the coast of Australia and will help meet the growing natural gas demand
of Asia. Prelude’s LNG production will represent 10% of the annual consumption of natural gas of a country like France
and enough to easily satisfy Hong Kong’s annual natural gas needs.
Shell Prelude FLNG4
Commitment to safety in design:
goal zero
Cold spill risk analysis
The identification of potential cryogenic release scenarios, as well as the assessment of their frequencies and consequences
means the facility has been designed to avoid steel embrittlement and vaporization of spills. This analysis defines where Cold
Spill Protection is required on the facility, and the specifications of the protection.
Exhaust dispersion: CFD studies and wind tunnel tests
Both CFD (Computational Fluid Dynamics) simulations and wind tunnel
tests were performed to:
1 - Assess the impact of the exhaust plumes from the boiler exhausts on 	
helideck operations, in terms of local temperatures and turbulence levels.
2 - Quantify the overall availability of the helidecks, over a year,
	 from dispersion results and wind/heading analysis.
3 - Determine the best helideck locations
Safety is the primary focus in Shell’s FLNG design, with multiple formal safety
assessments at various stages of the design confirming that an FLNG facility
would be at least equally as safe and reliable as other modern offshore
production facilities currently in operation.
Explosion risk analysis
Technip dedicated a large amount of time to Explosion Risk Analysis, not only to assess the likelihood and severity of a
potential vapour cloud explosion, but also to derive design loads, such as potential overpressure magnitude, impulse and
durations, or blast wind drag forces.
Shell Prelude FLNG 5
The HSE studies conducted in close collaboration with Shell mean that Prelude will be an
extremely safe and reliable facility despite the new challenges. The layout of Prelude FLNG
reflects the following principles that were adopted at an early stage.
Layout
Higher risk process and storage areas are located furthest from living
quarters (LQ).
Blast-rated bulkheads, utility modules and safety gaps separate the
LQ from the process modules.
The LQ on the LNG carrier is aligned with the FLNG living quarters
during offloading.
20m safety gaps, open process and turret area layouts minimize the
consequences of a potential incident and the likelihood of
escalation.
Flammable material storage areas separated from ignition sources.
Lifting equipment is deployed to facilitate maintenance access.
Handling routes avoid lifting over live process areas.
Dual helidecks increase helicopter operations availability.
Escape routes, temporary refuges and means of evacuation in
sufficient number and redundancy.
Air dispersion study
The health of the operating personnel is a primary concern to Shell
and the TSC consortium. In order to assess the impact of gaseous
emissions on air quality at deck level and at Living Quarters air inlets
and compare to occupational and residential air quality criteria set
by regulations, multiple Air Dispersion Studies were conducted.
Acoustic study for topsides
In order to improve working conditions,
and enhance resting periods for the crew,
acoustic studies were performed to:
1 - Better estimate noise levels in the topsides and in 	
	 front of the local equipment rooms and living quarters.
2 - Determine noise mitigation measures to meet 		
	 company and statutory regulations.
Shell Prelude FLNG6
Passion for Quality: zero defect
Quality on Prelude FLNG
A key operational priority on Prelude is to be focused on project execution.
Shell, our client has established a “Zero Defect Policy” for Quality & Safety,
for which our Quartz program is a good support.
Hull launching – November 30, 2013
Client oriented, with regular Customer Satisfaction Surveys.
People oriented, with strong support to our partner Samsung Heavy
Industries (SHI) during construction.
Problem solving and continuous improvement oriented, with support
to SHI and our vendors through the 10 Quality Golden Rules policy.
Best practices & lessons learnt oriented, to support future projects.
Risks management oriented.
We are:
Shell Prelude FLNG 7
The partnership between Technip and SHI is very rewarding and we learn a lot from each other. Our common goal, as one team,
is to ensure the best Quality level within all the project disciplines and phases.
Each of us, is a key player in terms of Quality on the
Prelude project. We always stay focused to drive our goal
of Zero Default.”
“
Arnaud Bourgault - TSC Quality Manager - Prelude FLNG Project
FLNG is a game changer
for the LNG industry
The novel concept of Floating Liquefied Natural
Gas (FLNG) has been extensively studied in the
last decade. It consists of a combination of
several technologies that aim at liquefying natural
gas at sea. FLNG solutions have the potential to
place gas liquefaction facilities directly over
offshore gas fields, and unlock new energy
resources offshore. They will enable access to
stranded gas reserves that up until now were too
costly and difficult to exploit.
HEADQUARTERS
Technip
89 avenue de la Grande Armée
75773 Paris Cedex 16
France
Phone: +33 (0)1 47 78 24 00
CONTACTS
Offshore Business & Technologies
Jean-Marc LETOURNEL
Phone: +33 (0)1 47 78 35 42
Fax: +33 (0)1 47 78 37 87
Email: jmletournel@technip.com
LNG
Phil HAGYARD
Phone: +33 (0)1 47 78 27 17
Email: phagyard@technip.com
This document is the property of Technip and is not intended to be a binding contractual document.
Any information contained herein shall not result in any binding obligation on the part of Technip, or
any of its affiliates, and is provided for information purposes only.
Technip - Group Communications - February 2016 - Photo credits: Shell, Technip and Samsung Heavy Industries
www.technip.com
The challenge is to develop an offshore version of an onshore LNG plant,
in a facility that is one-quarter the size. FLNGs offer a novel
environmentally-friendly approach for monetization of offshore gas fields
and avoid the potential environmental impact of building and operating a
plant onshore, including long-distance pipelines to shore and extensive
onshore infrastructure.
Through the Shell Prelude FLNG project, Technip and Samsung, are
contributing to today’s most ambitious energy infrastructure project.
The Technip-Samsung Consortium is proud of the contribution to this
making of history and to support a visionary client pushing back together
the limits of technology.

More Related Content

What's hot

3rd lng bunkering 2015 web
3rd lng bunkering 2015 web3rd lng bunkering 2015 web
3rd lng bunkering 2015 webRuoh Yi Tham
 
New base 547 special 24 february 2015
New base 547 special 24 february  2015New base 547 special 24 february  2015
New base 547 special 24 february 2015Khaled Al Awadi
 
Demonstrating a basis for safe operations with no regulatory driver - Paper f...
Demonstrating a basis for safe operations with no regulatory driver - Paper f...Demonstrating a basis for safe operations with no regulatory driver - Paper f...
Demonstrating a basis for safe operations with no regulatory driver - Paper f...Richard Pocock
 
New base special 10 november 2014
New base special  10 november  2014New base special  10 november  2014
New base special 10 november 2014Khaled Al Awadi
 
PE976 Offshore Platform Decommissioning
PE976 Offshore Platform DecommissioningPE976 Offshore Platform Decommissioning
PE976 Offshore Platform DecommissioningpetroEDGE
 
Developments in Heavy-Oil EOR for the Era of Low Oil Pricing
Developments in Heavy-Oil EOR for the Era of Low Oil PricingDevelopments in Heavy-Oil EOR for the Era of Low Oil Pricing
Developments in Heavy-Oil EOR for the Era of Low Oil PricingSociety of Petroleum Engineers
 
Qatargas debottlenecking project
Qatargas debottlenecking projectQatargas debottlenecking project
Qatargas debottlenecking projectJohn Kingsley
 
Hpht direct new: Improving safety in HPHT
Hpht direct new: Improving safety in HPHTHpht direct new: Improving safety in HPHT
Hpht direct new: Improving safety in HPHTHPHT Wells Summit
 
Major Challenges in HPHT Operations
Major Challenges in HPHT OperationsMajor Challenges in HPHT Operations
Major Challenges in HPHT OperationsHPHT Wells Summit
 
CV_Doug_Mast
CV_Doug_MastCV_Doug_Mast
CV_Doug_MastDoug Mast
 
Natural Gas Liquids Units Selection, Sizing and Troubleshooting
Natural Gas Liquids Units Selection, Sizing and Troubleshooting Natural Gas Liquids Units Selection, Sizing and Troubleshooting
Natural Gas Liquids Units Selection, Sizing and Troubleshooting Karl Kolmetz
 
Webinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experienceWebinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experienceGlobal CCS Institute
 

What's hot (19)

3rd lng bunkering 2015 web
3rd lng bunkering 2015 web3rd lng bunkering 2015 web
3rd lng bunkering 2015 web
 
ATB PE Portfolio2016
ATB PE Portfolio2016ATB PE Portfolio2016
ATB PE Portfolio2016
 
New base 547 special 24 february 2015
New base 547 special 24 february  2015New base 547 special 24 february  2015
New base 547 special 24 february 2015
 
CV
CVCV
CV
 
Demonstrating a basis for safe operations with no regulatory driver - Paper f...
Demonstrating a basis for safe operations with no regulatory driver - Paper f...Demonstrating a basis for safe operations with no regulatory driver - Paper f...
Demonstrating a basis for safe operations with no regulatory driver - Paper f...
 
New base special 10 november 2014
New base special  10 november  2014New base special  10 november  2014
New base special 10 november 2014
 
20190403 cv sigve hamilton aspelund
20190403 cv sigve hamilton aspelund20190403 cv sigve hamilton aspelund
20190403 cv sigve hamilton aspelund
 
PE976 Offshore Platform Decommissioning
PE976 Offshore Platform DecommissioningPE976 Offshore Platform Decommissioning
PE976 Offshore Platform Decommissioning
 
Jonathan Hemming CV
Jonathan Hemming CVJonathan Hemming CV
Jonathan Hemming CV
 
OceanicSpring 2008
OceanicSpring 2008OceanicSpring 2008
OceanicSpring 2008
 
Developments in Heavy-Oil EOR for the Era of Low Oil Pricing
Developments in Heavy-Oil EOR for the Era of Low Oil PricingDevelopments in Heavy-Oil EOR for the Era of Low Oil Pricing
Developments in Heavy-Oil EOR for the Era of Low Oil Pricing
 
Qatargas debottlenecking project
Qatargas debottlenecking projectQatargas debottlenecking project
Qatargas debottlenecking project
 
Hpht direct new: Improving safety in HPHT
Hpht direct new: Improving safety in HPHTHpht direct new: Improving safety in HPHT
Hpht direct new: Improving safety in HPHT
 
CV JMCNAB
CV JMCNABCV JMCNAB
CV JMCNAB
 
Major Challenges in HPHT Operations
Major Challenges in HPHT OperationsMajor Challenges in HPHT Operations
Major Challenges in HPHT Operations
 
CV_Doug_Mast
CV_Doug_MastCV_Doug_Mast
CV_Doug_Mast
 
Natural Gas Liquids Units Selection, Sizing and Troubleshooting
Natural Gas Liquids Units Selection, Sizing and Troubleshooting Natural Gas Liquids Units Selection, Sizing and Troubleshooting
Natural Gas Liquids Units Selection, Sizing and Troubleshooting
 
Austin Okwordu CV PDF
Austin Okwordu CV PDFAustin Okwordu CV PDF
Austin Okwordu CV PDF
 
Webinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experienceWebinar: CCS major project development lessons from the ZeroGen experience
Webinar: CCS major project development lessons from the ZeroGen experience
 

Similar to shell_0

Cofely Fabricom Brochure OilGas 2015
Cofely Fabricom Brochure OilGas 2015Cofely Fabricom Brochure OilGas 2015
Cofely Fabricom Brochure OilGas 2015Jailton Rodrigues
 
Introduction to Floating Storage & Regasification Unit (FSRU)
Introduction to Floating Storage & Regasification Unit (FSRU)Introduction to Floating Storage & Regasification Unit (FSRU)
Introduction to Floating Storage & Regasification Unit (FSRU)petroEDGE
 
7th study meeting Tokyo - Holger Bietz
7th study meeting Tokyo - Holger Bietz7th study meeting Tokyo - Holger Bietz
7th study meeting Tokyo - Holger BietzGlobal CCS Institute
 
Linked In Pres R Toet Rev1
Linked In Pres R Toet Rev1Linked In Pres R Toet Rev1
Linked In Pres R Toet Rev1RToet
 
Webinar: How to manage technical risk in CO2 capture technology development
Webinar: How to manage technical risk in CO2 capture technology developmentWebinar: How to manage technical risk in CO2 capture technology development
Webinar: How to manage technical risk in CO2 capture technology developmentGlobal CCS Institute
 
Improving Efficiency Tight Gas
Improving Efficiency Tight GasImproving Efficiency Tight Gas
Improving Efficiency Tight GasNeil Harvey
 
FloatingLNGRevolutionEvolution
FloatingLNGRevolutionEvolutionFloatingLNGRevolutionEvolution
FloatingLNGRevolutionEvolutionAndy Varoshiotis
 
Rope Access Presentation from Abfad Limited, World Leaders in Rope Access Tec...
Rope Access Presentation from Abfad Limited, World Leaders in Rope Access Tec...Rope Access Presentation from Abfad Limited, World Leaders in Rope Access Tec...
Rope Access Presentation from Abfad Limited, World Leaders in Rope Access Tec...The Images Group
 
Basic technology & solutions of LNG
Basic technology & solutions of LNGBasic technology & solutions of LNG
Basic technology & solutions of LNGAbu Bakar Siddiqui
 
Linked In Pres R Toet Rev2
Linked In Pres R Toet Rev2Linked In Pres R Toet Rev2
Linked In Pres R Toet Rev2RToet
 
PD193 FPSO & FLNG DESIGN & tECHNOLOGY -LEVEL 2
PD193 FPSO & FLNG DESIGN & tECHNOLOGY -LEVEL 2PD193 FPSO & FLNG DESIGN & tECHNOLOGY -LEVEL 2
PD193 FPSO & FLNG DESIGN & tECHNOLOGY -LEVEL 2Zaharah Kasim
 
Pipeline Integrity Maintenance Forum 2010
Pipeline Integrity Maintenance Forum 2010Pipeline Integrity Maintenance Forum 2010
Pipeline Integrity Maintenance Forum 2010Elisa_Ramella
 

Similar to shell_0 (20)

Cofely Fabricom Brochure OilGas 2015
Cofely Fabricom Brochure OilGas 2015Cofely Fabricom Brochure OilGas 2015
Cofely Fabricom Brochure OilGas 2015
 
Introduction to Floating Storage & Regasification Unit (FSRU)
Introduction to Floating Storage & Regasification Unit (FSRU)Introduction to Floating Storage & Regasification Unit (FSRU)
Introduction to Floating Storage & Regasification Unit (FSRU)
 
LNG Cap - Jan 2016
LNG Cap - Jan 2016LNG Cap - Jan 2016
LNG Cap - Jan 2016
 
PlatformOptimization
PlatformOptimizationPlatformOptimization
PlatformOptimization
 
7th study meeting Tokyo - Holger Bietz
7th study meeting Tokyo - Holger Bietz7th study meeting Tokyo - Holger Bietz
7th study meeting Tokyo - Holger Bietz
 
Linked In Pres R Toet Rev1
Linked In Pres R Toet Rev1Linked In Pres R Toet Rev1
Linked In Pres R Toet Rev1
 
Webinar: How to manage technical risk in CO2 capture technology development
Webinar: How to manage technical risk in CO2 capture technology developmentWebinar: How to manage technical risk in CO2 capture technology development
Webinar: How to manage technical risk in CO2 capture technology development
 
RINA_Paper
RINA_PaperRINA_Paper
RINA_Paper
 
Clough Enercore Brochure
Clough Enercore BrochureClough Enercore Brochure
Clough Enercore Brochure
 
Improving Efficiency Tight Gas
Improving Efficiency Tight GasImproving Efficiency Tight Gas
Improving Efficiency Tight Gas
 
FloatingLNGRevolutionEvolution
FloatingLNGRevolutionEvolutionFloatingLNGRevolutionEvolution
FloatingLNGRevolutionEvolution
 
TSC Group Holdings
TSC Group HoldingsTSC Group Holdings
TSC Group Holdings
 
PQ_SEC _2014
PQ_SEC _2014PQ_SEC _2014
PQ_SEC _2014
 
Rope Access Presentation from Abfad Limited, World Leaders in Rope Access Tec...
Rope Access Presentation from Abfad Limited, World Leaders in Rope Access Tec...Rope Access Presentation from Abfad Limited, World Leaders in Rope Access Tec...
Rope Access Presentation from Abfad Limited, World Leaders in Rope Access Tec...
 
Wallin mikael
Wallin mikaelWallin mikael
Wallin mikael
 
Basic technology & solutions of LNG
Basic technology & solutions of LNGBasic technology & solutions of LNG
Basic technology & solutions of LNG
 
Linked In Pres R Toet Rev2
Linked In Pres R Toet Rev2Linked In Pres R Toet Rev2
Linked In Pres R Toet Rev2
 
PD193 FPSO & FLNG DESIGN & tECHNOLOGY -LEVEL 2
PD193 FPSO & FLNG DESIGN & tECHNOLOGY -LEVEL 2PD193 FPSO & FLNG DESIGN & tECHNOLOGY -LEVEL 2
PD193 FPSO & FLNG DESIGN & tECHNOLOGY -LEVEL 2
 
brochuredeepoffshore_1_0
brochuredeepoffshore_1_0brochuredeepoffshore_1_0
brochuredeepoffshore_1_0
 
Pipeline Integrity Maintenance Forum 2010
Pipeline Integrity Maintenance Forum 2010Pipeline Integrity Maintenance Forum 2010
Pipeline Integrity Maintenance Forum 2010
 

shell_0

  • 1. Our projects Shell Prelude FLNG A new landmark in the Offshore industry
  • 2. Shell Prelude FLNG2 2009 – Master Agreement It all started in 2009 when Shell and the Technip-Samsung Heavy Industries Consortium signed a Master Agreement for the design, construction and installation of multiple FLNG facilities over up to 15 years. Bolo bolo bolo bolo bolo bolo Shell Prelude FLNG milestones 2010 – FEED Following this agreement, Technip carried out a generic FLNG FEED (Front-End Engineering and Design) study and, in 2010, it was adapted to Prelude. In total, more than 600 people around the world spent over 1.6 million hours working on different design options for the Prelude facility. 2011 – Notice to proceed On May 30, 2011, the Technip-Samsung Consortium was given notice by Shell to proceed with the construction of Prelude FLNG, the first floating liquefied natural gas facility in the world, to be located offshore Australia. 2012 – First steel cut At the Samsung Heavy Industries ship yard in Geoje, South Korea, the steel cutting of the hull started in October 2012, followed by the steel cutting of the topsides in January 2013. On November 30, 2013, the hull was completed in dry-dock and launched. 2012 – Subsea contract In June 2012, Shell awarded Technip the subsea contract for the Prelude development, including the installation of all the necessary flowlines, risers and umbilicals. Client: Shell (operator: 67.5%) Three joint venture partners: INPEX (17.5%), KOGAS (10%) and CPC Taiwan (5%) Contractors: Technip - Samsung Consortium Location: approximately 475 kilometers North-North East of Broome, Western Australia Water depth: 200 - 250 meters Australia Prelude FLNG
  • 3. Shell Prelude FLNG 3 The largest floating facility ever built World-recognized partners to engineer and deliver this first-of-a-kind project The Technip-Samsung Consortium (TSC) combines the strengths of each company to enable the delivery of the Shell Prelude integrated FLNG facility: Samsung Heavy Industries (SHI) performs all of the construction on Prelude and has design responsibility for the hull. SHI and Technip have a solid track record together including FPSO’s. SHI has the best equipped shipyard in the world with large drydocks and floating docks and an 8,000t floating crane. It has decades of experience in construction of LNG carriers and offshore facilities. Technip provides the TSC project management, engineering, procurement, installation and commissioning for Prelude. FLNG is a market where Technip has quickly emerged as the leader due to its industrial experience of natural gas liquefaction, subsea field development and large floating oil production platforms. Prelude in figures 488 metres long (more than four FIFA football pitches) 74 metres wide 260,000 tons of steel, the equivalent of 36 Eiffel towers or 430,000 medium-sized cars With its cargo tanks full, Prelude will weigh roughly six times as much as the largest aircraft carrier The world’s largest non-disconnectable Turret Mooring System, taller than the Statue of Liberty with its base Living quarters the size of the Arc de Triomphe Shell Prelude FLNG is expected to yield an annual production of: 3.6 Mtpa of LNG 1.3 Mtpa of condensate 0.4 Mtpa of LPG The facility’s storage tanks, located below the deck, can store up to 220,000 m3 of LNG, 90,000 m3 of LPG, and 126,000 m3 of condensate. The total storage capacity is equivalent to around 175 Olympic swimming pools. It is aimed at producing and exporting LNG off the coast of Australia and will help meet the growing natural gas demand of Asia. Prelude’s LNG production will represent 10% of the annual consumption of natural gas of a country like France and enough to easily satisfy Hong Kong’s annual natural gas needs.
  • 4. Shell Prelude FLNG4 Commitment to safety in design: goal zero Cold spill risk analysis The identification of potential cryogenic release scenarios, as well as the assessment of their frequencies and consequences means the facility has been designed to avoid steel embrittlement and vaporization of spills. This analysis defines where Cold Spill Protection is required on the facility, and the specifications of the protection. Exhaust dispersion: CFD studies and wind tunnel tests Both CFD (Computational Fluid Dynamics) simulations and wind tunnel tests were performed to: 1 - Assess the impact of the exhaust plumes from the boiler exhausts on helideck operations, in terms of local temperatures and turbulence levels. 2 - Quantify the overall availability of the helidecks, over a year, from dispersion results and wind/heading analysis. 3 - Determine the best helideck locations Safety is the primary focus in Shell’s FLNG design, with multiple formal safety assessments at various stages of the design confirming that an FLNG facility would be at least equally as safe and reliable as other modern offshore production facilities currently in operation. Explosion risk analysis Technip dedicated a large amount of time to Explosion Risk Analysis, not only to assess the likelihood and severity of a potential vapour cloud explosion, but also to derive design loads, such as potential overpressure magnitude, impulse and durations, or blast wind drag forces.
  • 5. Shell Prelude FLNG 5 The HSE studies conducted in close collaboration with Shell mean that Prelude will be an extremely safe and reliable facility despite the new challenges. The layout of Prelude FLNG reflects the following principles that were adopted at an early stage. Layout Higher risk process and storage areas are located furthest from living quarters (LQ). Blast-rated bulkheads, utility modules and safety gaps separate the LQ from the process modules. The LQ on the LNG carrier is aligned with the FLNG living quarters during offloading. 20m safety gaps, open process and turret area layouts minimize the consequences of a potential incident and the likelihood of escalation. Flammable material storage areas separated from ignition sources. Lifting equipment is deployed to facilitate maintenance access. Handling routes avoid lifting over live process areas. Dual helidecks increase helicopter operations availability. Escape routes, temporary refuges and means of evacuation in sufficient number and redundancy. Air dispersion study The health of the operating personnel is a primary concern to Shell and the TSC consortium. In order to assess the impact of gaseous emissions on air quality at deck level and at Living Quarters air inlets and compare to occupational and residential air quality criteria set by regulations, multiple Air Dispersion Studies were conducted. Acoustic study for topsides In order to improve working conditions, and enhance resting periods for the crew, acoustic studies were performed to: 1 - Better estimate noise levels in the topsides and in front of the local equipment rooms and living quarters. 2 - Determine noise mitigation measures to meet company and statutory regulations.
  • 6. Shell Prelude FLNG6 Passion for Quality: zero defect Quality on Prelude FLNG A key operational priority on Prelude is to be focused on project execution. Shell, our client has established a “Zero Defect Policy” for Quality & Safety, for which our Quartz program is a good support. Hull launching – November 30, 2013 Client oriented, with regular Customer Satisfaction Surveys. People oriented, with strong support to our partner Samsung Heavy Industries (SHI) during construction. Problem solving and continuous improvement oriented, with support to SHI and our vendors through the 10 Quality Golden Rules policy. Best practices & lessons learnt oriented, to support future projects. Risks management oriented. We are:
  • 7. Shell Prelude FLNG 7 The partnership between Technip and SHI is very rewarding and we learn a lot from each other. Our common goal, as one team, is to ensure the best Quality level within all the project disciplines and phases. Each of us, is a key player in terms of Quality on the Prelude project. We always stay focused to drive our goal of Zero Default.” “ Arnaud Bourgault - TSC Quality Manager - Prelude FLNG Project
  • 8. FLNG is a game changer for the LNG industry The novel concept of Floating Liquefied Natural Gas (FLNG) has been extensively studied in the last decade. It consists of a combination of several technologies that aim at liquefying natural gas at sea. FLNG solutions have the potential to place gas liquefaction facilities directly over offshore gas fields, and unlock new energy resources offshore. They will enable access to stranded gas reserves that up until now were too costly and difficult to exploit. HEADQUARTERS Technip 89 avenue de la Grande Armée 75773 Paris Cedex 16 France Phone: +33 (0)1 47 78 24 00 CONTACTS Offshore Business & Technologies Jean-Marc LETOURNEL Phone: +33 (0)1 47 78 35 42 Fax: +33 (0)1 47 78 37 87 Email: jmletournel@technip.com LNG Phil HAGYARD Phone: +33 (0)1 47 78 27 17 Email: phagyard@technip.com This document is the property of Technip and is not intended to be a binding contractual document. Any information contained herein shall not result in any binding obligation on the part of Technip, or any of its affiliates, and is provided for information purposes only. Technip - Group Communications - February 2016 - Photo credits: Shell, Technip and Samsung Heavy Industries www.technip.com The challenge is to develop an offshore version of an onshore LNG plant, in a facility that is one-quarter the size. FLNGs offer a novel environmentally-friendly approach for monetization of offshore gas fields and avoid the potential environmental impact of building and operating a plant onshore, including long-distance pipelines to shore and extensive onshore infrastructure. Through the Shell Prelude FLNG project, Technip and Samsung, are contributing to today’s most ambitious energy infrastructure project. The Technip-Samsung Consortium is proud of the contribution to this making of history and to support a visionary client pushing back together the limits of technology.