THE CONTEXT OF INTERNATIONAL
PROJECTS IN TERMS OF
ORGANIZATIONAL STRATEGY AND
CULTURE
Chapter 2
HOW ARE INTERNATIONAL PROJECTS LINKED TO
ORGANIZATIONAL
STRATEGY?
An organization has a vision it pursues.
To achieve its vision, it has a kind of roadmap or plan: this
is also called its strategy.
To implement its strategy, the organization uses
(international) projects.
During the project and at the end of the project, the
organization checks whether the project has delivered the
desired results.
This is an ongoing cycle we also call strategic
management cycle.
2
Project 3
Project 2
Strategic Management Cycle
Business
Planning
Communi-
cating
and
high-level
aligning
Feedback
and
Learning
Translating
the Vision/
Mission
1
3 2
Project 1
4
Executing
Completing
Planning
Initiating
How (international) projects are part of the organization’s
strategy
3
THE CONNECTION BETWEEN (INTERNATIONAL)
PROJECTS AND
(INTERNATIONAL) PROGRAMS
A program can be defined as a bundle of projects.
Compared to a project, a program typically is bigger, requires
more resources,
and is crucial for the success of organizational strategy.
The projects within a program serve the same strategic
objective.
Projects in a program are interdependent. They share the same
objectives and
scarce resources.
They typically have a common infrastructure and share a certain
set of risks.
Programs have the following advantages:
gic alignment through interdependency of
objectives.
breaking them down
into smaller, easy-to control projects contributes to clearer
responsibilities,
minimizes risks, and boosts morale and motivation. It also
improves the quality
of the results.
Programs are essentially managed in the same way as projects.
4
PROJECT PORTFOLIO MANAGEMENT (PPM)
A project portfolio is a collection of projects managed under
one umbrella. These projects may be interrelated or not.
Purpose of PPM is to maximize the efficacy of projects in the
light of strategy execution.
There are two main management processes within project
portfolio management:
1. Selection and prioritization of projects.
2. Management of the projects within the portfolio by
monitoring target achievement.
A project portfolio is periodically adapted to the
organizational strategy.
The main activities of the PPM process are shown on the
following slide.
5
Required inputs:
1. Program/ project title
2. Project objective in light of
overall strategy
3. Risk level
4. Timeframe
5. Dependencies with other
programs/ projects
6. Estimated budget or ROI
7. Impact of not delivering the
program/project
1
3
2
4
Build or
Update
Project
Portfolio
Analyze
& Prioritize
Project
Portfolio
Monitor
& Adjust
Project
Portfolio
Consider
new
proposed
projects
The Project
Portfolio
Management
Process
1. Categorization of
program/project
3 . Organizational
capability and
capacity information
2. Program and project
information
1. Business requirements in
form of organization’s
strategy
3. Prioritization of programs/projects
according to criteria as:
•pressure from the market
•capability of the organization
•risks
•timescale for delivery
•impact of not doing the programs/projects
2. Determination of complexity
and challenge of portfolio
Required activities:
1. Monitoring objectives of single project
2. Monitoring combination of projects in
light of organizational success
3. Monitoring project selection in light of
change
Required tools & techniques:
Same as for project
management, cf. Chapter 7
Critical aspects to be monitored:
Required inputs:
6
PROJECT MANAGEMENT MATURITY
An organization gains experience about project management
over time.
Usually, the organization starts with single projects.
First, it develops an efficient way of project management.
Then, it reaches the stage in which projects perform well as an
entirety.
The final stage is a continuous selection of projects which
contribute to sustainable competitive edge of the organization.
The prerequisite for the last stage is well implemented and
smoothly working project portfolio management.
7
- Existence of processes to measure project effectiveness and
efficiency
- Continuous improvement of the efficiency of project portfolio
management
- Project management processes integrated in the corporate
processes
- Synchronization of projects with corporate strategy
- Solid analysis of project performance
- Standardization and institutionalization of project management
- Informal and unsystematic collection of project performance
data
- Project estimates and schedules based on industry standards
- Introduction of a structured project management methodology
- Inconsistent application (mainly for large visible project)
- Many ad-hoc processes in the organization
- Awareness development through senior management
regarding the
importance of structured project management
Level
5
Level
1
Level
4
Level
3
Level
2
In
c
re
a
s
e
o
f
p
ro
je
c
t
m
a
tu
ri
ty
Example of a 5 stage project management maturity model
8
PROJECT MANAGEMENT AND ORGANIZATIONAL
CULTURE
Organizational culture can be defined as the way an
organization is doing things.
A critical success factor of international projects is a supportive
project culture.
This has to be based on ethnorelativism: values as open
mindedness, respect, and trust.
Organizational culture goes like a common theme through
projects, programs, and project portfolios.
All members of the organization need to have a special set of
values, attitudes, and behaviours in order to help the
implementation of the organizational strategy.
Strategy and culture need to be in tune for maximal
organizational success.
9
4. Employee
welfare,
fairness and
trust
1. Degree of
internal
integration
5. Diversity
2. Autonomy
and
involvement
3. Adaptability:
speed,
innovation and
risk
ADEQUATE ELEMENTS OF ORGANIZATIONAL CULTURE
FOR
SUCCESSFUL INTERNATIONAL PROJECTS
10
Project
Management
Program
Management
Project
Portfolio
Management
Management
by Projects
Main Content of
Concept
Managing a single
project efficiently
within given
organizational
constraints and
context.
Clustering projects
pursuing the same
objectives into a
program to support
alignment with
overall
organization’s
strategy and to
increase flexibility.
Clustering projects
into portfolios to
ensure alignment
with organization’s
strategy. PPM
supports
coordinated
resource allocation,
increases flexibility
of the whole
organization and
leads to sustainable
project success.
Managing the whole
organization as a
bundle of projects
based on a
supportive
organizational
culture. At the
extreme, the
organization
consists of one
complex project.
Scope
Limited to a set of
objectives linked to
one single project.
Business-unit or
organization-wide,
depending on
content of program.
An organization-
wide management
system.
A management
approach affecting
the whole
organization, also
inter-organizational.
Required Project
Maturity Level
Level 1 – 3:
Minimum level 1,
ideal level 3
Level 3 – 4 Level 4 – 5 Level 4 – 5
Overview of relevant project management methods – all aiming
at
strategy implementation
11
DEFINING THE INTERNATIONAL
PROJECT
Chapter 3
WHAT IS HAPPENING AT THE START OF AN
INTERNATIONAL PROJECT?
With reference to the project management life cycle, we are
in the initiating phase.
The project starts with an idea, a customer demand, a bid
issued by a government or other opportunities.
As each international project is unique, creativity is important
at this stage. Special techniques are helpful (see companion
website).
The project objective has to be in line with the organizational
strategy.
It is extremely important for the overall project success, that
the scene is set well at this stage of the project.
This is especially true for stakeholder involvement, and the
accuracy of the first rough schedule and budget.
2
Output
(deliverables)
Input
Initiating Phase: Input, Output, Controls and Mechanisms
Mechanisms:
Tools & techniques
(e.g. fishbone diagram) for
concept development
Controls:
Organization‘s project mgmt
standards/ procedures
Constraints: strategic, financial,
time, legal, cultural,
environmental, ethical
Initiating Phase
• Scope Statement
• Scope Acceptance
• Project Proposal
• Stakeholder Matrix
• Culture Gap Analysis
• Diversity-Complexity-
Assessment
• Organization’s Strategy
• Customer’s Requirements
• Market Demand
• Opportunities Provided
by Globalization
3
ATTENTION TO SCOPE MANAGEMENT
The project manager has to clarify from project start as clearly
as possible what the project should do, and what it should not
do.
Due to the heterogeneity of the stakeholders in an international
project, special care is due related to scope definition.
The danger of differences in associations, attached meanings
and general misunderstandings is high.
The SMART tool may be helpful:
able
4
DEFINING MILESTONES
A milestone is a major pre-defined event that represents
measurable accomplishment toward the project’s completion.
Milestones need to be passed in order to continue with the
project.
They divide the project into more manageable sub-parts.
Milestones are defined at the beginning of the project.
It is important to formulate them as clearly as possible.
It is also important to communicate them well within the project
team.
5
THE WORK BREAKDOWN STRUCTURE (WBS)
The milestones are typically the pillars of the so-called Work
Breakdown Structure.
It structures the entire project into little, manageable chunks.
The WBS creates a linked, hierarchical series of activities,
which
are independent units but at the same time part of the whole.
The Work Breakdown Structure typically looks like a tree
diagram
(see companion website). It can also take the form of a check
list.
The process is as follows:
State the project scope and make sure that all stakeholders
have
the same understanding.
6
MAPPING CULTURAL PROJECT CONTEXT
Among others, international projects are characterized by
diversity and complexity.
This is largely due to cultural heterogeneity.
Major stakeholders need to be understood as well as possible,
including their social identity.
All stakeholders’ behaviour is embedded in context.
An important part of context in international projects is local or
national culture, organizational culture, and professional culture
as
outlined in the next slide.
7
Individual (human nature,
personality)
Professional/
Functional Culture
Organizational
Culture (Corporate culture)
Sub-
cultureSub-
culture
National Culture
Sub-
culture
Sub-
culture
Sub-
culture
CULTURES WITH IMPACT ON
INTERNATIONAL PROJECTS
8
1. Power Distance
Hofstede‘s model to map differences in national
culture
9
Universalism Particularism
Individualism
Communi-
tarianism
Neutral Affective
Specific Diffuse
Achievement Aspiration
Internal locus
of control
External locus
of control
Sequential Synchronic
Future
orientation
Past
orientation
Trompenaars‘ model to map differences in national
culture
10
Managing risk and uncertainty (4)
Defining & planning the project (3, 5)
Organizing the project (6)
Leading and managing the team (8)
Communicating (9); Co-operating (10)
Equality Hierarchy
Defining the project (3)
Managing risk and uncertainty (4)
Planning the project (5)
Organizing the project (6)
Implementing & controlling the project (7)
Embracing
Risk
Avoiding
Risk
Managing risk (4)
Organizing the project (6)
Implementing & controlling (7)
Motivating and leading the team (8)
Communicating (9); Co-operating (10)
Learning (11)
Individual Group
Matching strategy with projects (2)
Defining the project (3)
Planning the project (5)
Implementing & controlling the project (7)
Learning (11)
Universal
Circumstan-
tial
The Cultural Gap Tool to systematically analyse the
national culture environment of international projects (1)
The figures in brackets (this slide and next) indicate the book
chapters in which the topics are mainly
discussed. 11
Defining scope (3)
Leading and managing the team (8)
Communicating (9); Co-operating (10)
Conflict Consensus
Managing stakeholders (3)
Planning the project (5)
Implementing & controlling (7)
Leading and managing the team (8)
Learning (11)
Task Relationship
Planning the project (5)
Organizing the project (6)
Implementing & controlling (7)
Motivating and leading the team (8)
Achievement
Standing /
Status
Defining the project (3)
Planning the project (5)
Implementing & controlling (7)
Sequential Synchronic
Planning the project (5)
Executing & controlling the project (7)
Learning (11)
Theoretical Pragmatic
The Cultural Gap Tool to systematically analyse the
national culture environment of international projects (2)
12
THE CONTEXT OF INTERNATIONAL PROJECTS IN TERMS OF ORGANI.docx

More Related Content

Similar to THE CONTEXT OF INTERNATIONAL PROJECTS IN TERMS OF ORGANI.docx

Project management frame work part 1
Project management frame work part 1Project management frame work part 1
Project management frame work part 1Mohamed , PMP
 
Report doc-soriano-project-and-planning-manangement.pptx- references
Report doc-soriano-project-and-planning-manangement.pptx- referencesReport doc-soriano-project-and-planning-manangement.pptx- references
Report doc-soriano-project-and-planning-manangement.pptx- referencesoryzasativa0720
 
PMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKPMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKskiltful
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slidesdotesch
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - FundamentalsJulen Mohanty
 
Program and Portfolio Management Basics Brief
Program and Portfolio Management Basics BriefProgram and Portfolio Management Basics Brief
Program and Portfolio Management Basics BriefSpyros Ktenas
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager PrimerTom Cremins
 
PMP preparation course
PMP preparation coursePMP preparation course
PMP preparation coursemohamed fawzy
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]OyetadeTobi
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Amr Miqdadi
 
Project Management
Project ManagementProject Management
Project Managementirfan ali
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Renee Jones
 
Archibald Interfaces Keynote Dynamics2010
Archibald Interfaces Keynote Dynamics2010Archibald Interfaces Keynote Dynamics2010
Archibald Interfaces Keynote Dynamics2010Russell Archibald
 
Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementYamanta Raj Niroula, PMP
 

Similar to THE CONTEXT OF INTERNATIONAL PROJECTS IN TERMS OF ORGANI.docx (20)

Portfolio management
Portfolio managementPortfolio management
Portfolio management
 
Project management frame work part 1
Project management frame work part 1Project management frame work part 1
Project management frame work part 1
 
Report doc-soriano-project-and-planning-manangement.pptx- references
Report doc-soriano-project-and-planning-manangement.pptx- referencesReport doc-soriano-project-and-planning-manangement.pptx- references
Report doc-soriano-project-and-planning-manangement.pptx- references
 
PMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOKPMP Certification Chapter one Summary of PMBOK
PMP Certification Chapter one Summary of PMBOK
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
Chapter 3 Lecture Slides
Chapter 3 Lecture SlidesChapter 3 Lecture Slides
Chapter 3 Lecture Slides
 
Program management - Fundamentals
Program management   - FundamentalsProgram management   - Fundamentals
Program management - Fundamentals
 
Pmbok
PmbokPmbok
Pmbok
 
Program and Portfolio Management Basics Brief
Program and Portfolio Management Basics BriefProgram and Portfolio Management Basics Brief
Program and Portfolio Management Basics Brief
 
Project Manager Primer
Project Manager PrimerProject Manager Primer
Project Manager Primer
 
PMP preparation course
PMP preparation coursePMP preparation course
PMP preparation course
 
Project management [module 1]
Project management [module 1]Project management [module 1]
Project management [module 1]
 
Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2Undestand PMBok 5th, Section 1&2
Undestand PMBok 5th, Section 1&2
 
PMBOK7-101-200.pdf
PMBOK7-101-200.pdfPMBOK7-101-200.pdf
PMBOK7-101-200.pdf
 
Project Management
Project ManagementProject Management
Project Management
 
Pmp Complete Notes
Pmp Complete NotesPmp Complete Notes
Pmp Complete Notes
 
Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.Project Management Msc. 7Pjmn009W Project Management Project.
Project Management Msc. 7Pjmn009W Project Management Project.
 
0. project management framework (fundamentals)
0. project management framework (fundamentals)0. project management framework (fundamentals)
0. project management framework (fundamentals)
 
Archibald Interfaces Keynote Dynamics2010
Archibald Interfaces Keynote Dynamics2010Archibald Interfaces Keynote Dynamics2010
Archibald Interfaces Keynote Dynamics2010
 
Challenging Aspects of Modern Project Management
Challenging Aspects of Modern Project ManagementChallenging Aspects of Modern Project Management
Challenging Aspects of Modern Project Management
 

More from rtodd643

The company you MUST use is Capital OneImpacts of .docx
The company you MUST use is Capital OneImpacts of .docxThe company you MUST use is Capital OneImpacts of .docx
The company you MUST use is Capital OneImpacts of .docxrtodd643
 
The Comparison and Contrast Block Comparison Essay TemplateThe B.docx
The Comparison and Contrast Block Comparison Essay TemplateThe B.docxThe Comparison and Contrast Block Comparison Essay TemplateThe B.docx
The Comparison and Contrast Block Comparison Essay TemplateThe B.docxrtodd643
 
The company uses the periodic inventory system. A physical .docx
The company uses the periodic inventory system.  A physical .docxThe company uses the periodic inventory system.  A physical .docx
The company uses the periodic inventory system. A physical .docxrtodd643
 
The company that I decided to follow is Entercom Atlanta which a c.docx
The company that I decided to follow is Entercom Atlanta which a c.docxThe company that I decided to follow is Entercom Atlanta which a c.docx
The company that I decided to follow is Entercom Atlanta which a c.docxrtodd643
 
The company of choice is Take-Two InteractiveWrite a 1,050.docx
The company of choice is Take-Two InteractiveWrite a 1,050.docxThe company of choice is Take-Two InteractiveWrite a 1,050.docx
The company of choice is Take-Two InteractiveWrite a 1,050.docxrtodd643
 
The Company to use is AppleCreate  Microsoft® PowerPoint® .docx
The Company to use is AppleCreate  Microsoft® PowerPoint® .docxThe Company to use is AppleCreate  Microsoft® PowerPoint® .docx
The Company to use is AppleCreate  Microsoft® PowerPoint® .docxrtodd643
 
The company I work for is WILDLAWNSubmit a detailed plan fo.docx
The company I work for is WILDLAWNSubmit a detailed plan fo.docxThe company I work for is WILDLAWNSubmit a detailed plan fo.docx
The company I work for is WILDLAWNSubmit a detailed plan fo.docxrtodd643
 
The Company I choose is AlibabaThe topic I will cover is C.docx
The Company I choose is AlibabaThe topic I will cover is C.docxThe Company I choose is AlibabaThe topic I will cover is C.docx
The Company I choose is AlibabaThe topic I will cover is C.docxrtodd643
 
THE COMPANY ETHICAL ISSUES Student’s  Name John Blair.docx
THE COMPANY ETHICAL ISSUES Student’s  Name John Blair.docxTHE COMPANY ETHICAL ISSUES Student’s  Name John Blair.docx
THE COMPANY ETHICAL ISSUES Student’s  Name John Blair.docxrtodd643
 
The company being used is COCA COLA 10 pages not including cover.docx
The company being used is COCA COLA 10 pages not including cover.docxThe company being used is COCA COLA 10 pages not including cover.docx
The company being used is COCA COLA 10 pages not including cover.docxrtodd643
 
The community college’s career development center (CDC) was impres.docx
The community college’s career development center (CDC) was impres.docxThe community college’s career development center (CDC) was impres.docx
The community college’s career development center (CDC) was impres.docxrtodd643
 
The Community as a StakeholderI The Business-Community R.docx
The Community as a StakeholderI The Business-Community R.docxThe Community as a StakeholderI The Business-Community R.docx
The Community as a StakeholderI The Business-Community R.docxrtodd643
 
The comments Good start ! Id loke to know more on the point you.docx
The comments Good start ! Id loke to know more on the point you.docxThe comments Good start ! Id loke to know more on the point you.docx
The comments Good start ! Id loke to know more on the point you.docxrtodd643
 
The color of an artwork can effect my feelings or moods by the war.docx
The color of an artwork can effect my feelings or moods by the war.docxThe color of an artwork can effect my feelings or moods by the war.docx
The color of an artwork can effect my feelings or moods by the war.docxrtodd643
 
THE COMETW.E.B. DuBoisHe stood a moment on the steps of .docx
THE COMETW.E.B. DuBoisHe stood a moment on the steps of .docxTHE COMETW.E.B. DuBoisHe stood a moment on the steps of .docx
THE COMETW.E.B. DuBoisHe stood a moment on the steps of .docxrtodd643
 
The Columbian Exchange.1. Select3items or elements.docx
The Columbian Exchange.1. Select3items or elements.docxThe Columbian Exchange.1. Select3items or elements.docx
The Columbian Exchange.1. Select3items or elements.docxrtodd643
 
The Collision of Cultures, England’s Colonies, Colonial Ways of .docx
The Collision of Cultures, England’s Colonies, Colonial Ways of .docxThe Collision of Cultures, England’s Colonies, Colonial Ways of .docx
The Collision of Cultures, England’s Colonies, Colonial Ways of .docxrtodd643
 
The color of a defendant and victims skin plays a crucial and unacc.docx
The color of a defendant and victims skin plays a crucial and unacc.docxThe color of a defendant and victims skin plays a crucial and unacc.docx
The color of a defendant and victims skin plays a crucial and unacc.docxrtodd643
 
The Colonial Context of Filipino American Immigrants’ Psycholo.docx
The Colonial Context of Filipino American Immigrants’ Psycholo.docxThe Colonial Context of Filipino American Immigrants’ Psycholo.docx
The Colonial Context of Filipino American Immigrants’ Psycholo.docxrtodd643
 
The collection of evidence is an activity that occurs with an endgam.docx
The collection of evidence is an activity that occurs with an endgam.docxThe collection of evidence is an activity that occurs with an endgam.docx
The collection of evidence is an activity that occurs with an endgam.docxrtodd643
 

More from rtodd643 (20)

The company you MUST use is Capital OneImpacts of .docx
The company you MUST use is Capital OneImpacts of .docxThe company you MUST use is Capital OneImpacts of .docx
The company you MUST use is Capital OneImpacts of .docx
 
The Comparison and Contrast Block Comparison Essay TemplateThe B.docx
The Comparison and Contrast Block Comparison Essay TemplateThe B.docxThe Comparison and Contrast Block Comparison Essay TemplateThe B.docx
The Comparison and Contrast Block Comparison Essay TemplateThe B.docx
 
The company uses the periodic inventory system. A physical .docx
The company uses the periodic inventory system.  A physical .docxThe company uses the periodic inventory system.  A physical .docx
The company uses the periodic inventory system. A physical .docx
 
The company that I decided to follow is Entercom Atlanta which a c.docx
The company that I decided to follow is Entercom Atlanta which a c.docxThe company that I decided to follow is Entercom Atlanta which a c.docx
The company that I decided to follow is Entercom Atlanta which a c.docx
 
The company of choice is Take-Two InteractiveWrite a 1,050.docx
The company of choice is Take-Two InteractiveWrite a 1,050.docxThe company of choice is Take-Two InteractiveWrite a 1,050.docx
The company of choice is Take-Two InteractiveWrite a 1,050.docx
 
The Company to use is AppleCreate  Microsoft® PowerPoint® .docx
The Company to use is AppleCreate  Microsoft® PowerPoint® .docxThe Company to use is AppleCreate  Microsoft® PowerPoint® .docx
The Company to use is AppleCreate  Microsoft® PowerPoint® .docx
 
The company I work for is WILDLAWNSubmit a detailed plan fo.docx
The company I work for is WILDLAWNSubmit a detailed plan fo.docxThe company I work for is WILDLAWNSubmit a detailed plan fo.docx
The company I work for is WILDLAWNSubmit a detailed plan fo.docx
 
The Company I choose is AlibabaThe topic I will cover is C.docx
The Company I choose is AlibabaThe topic I will cover is C.docxThe Company I choose is AlibabaThe topic I will cover is C.docx
The Company I choose is AlibabaThe topic I will cover is C.docx
 
THE COMPANY ETHICAL ISSUES Student’s  Name John Blair.docx
THE COMPANY ETHICAL ISSUES Student’s  Name John Blair.docxTHE COMPANY ETHICAL ISSUES Student’s  Name John Blair.docx
THE COMPANY ETHICAL ISSUES Student’s  Name John Blair.docx
 
The company being used is COCA COLA 10 pages not including cover.docx
The company being used is COCA COLA 10 pages not including cover.docxThe company being used is COCA COLA 10 pages not including cover.docx
The company being used is COCA COLA 10 pages not including cover.docx
 
The community college’s career development center (CDC) was impres.docx
The community college’s career development center (CDC) was impres.docxThe community college’s career development center (CDC) was impres.docx
The community college’s career development center (CDC) was impres.docx
 
The Community as a StakeholderI The Business-Community R.docx
The Community as a StakeholderI The Business-Community R.docxThe Community as a StakeholderI The Business-Community R.docx
The Community as a StakeholderI The Business-Community R.docx
 
The comments Good start ! Id loke to know more on the point you.docx
The comments Good start ! Id loke to know more on the point you.docxThe comments Good start ! Id loke to know more on the point you.docx
The comments Good start ! Id loke to know more on the point you.docx
 
The color of an artwork can effect my feelings or moods by the war.docx
The color of an artwork can effect my feelings or moods by the war.docxThe color of an artwork can effect my feelings or moods by the war.docx
The color of an artwork can effect my feelings or moods by the war.docx
 
THE COMETW.E.B. DuBoisHe stood a moment on the steps of .docx
THE COMETW.E.B. DuBoisHe stood a moment on the steps of .docxTHE COMETW.E.B. DuBoisHe stood a moment on the steps of .docx
THE COMETW.E.B. DuBoisHe stood a moment on the steps of .docx
 
The Columbian Exchange.1. Select3items or elements.docx
The Columbian Exchange.1. Select3items or elements.docxThe Columbian Exchange.1. Select3items or elements.docx
The Columbian Exchange.1. Select3items or elements.docx
 
The Collision of Cultures, England’s Colonies, Colonial Ways of .docx
The Collision of Cultures, England’s Colonies, Colonial Ways of .docxThe Collision of Cultures, England’s Colonies, Colonial Ways of .docx
The Collision of Cultures, England’s Colonies, Colonial Ways of .docx
 
The color of a defendant and victims skin plays a crucial and unacc.docx
The color of a defendant and victims skin plays a crucial and unacc.docxThe color of a defendant and victims skin plays a crucial and unacc.docx
The color of a defendant and victims skin plays a crucial and unacc.docx
 
The Colonial Context of Filipino American Immigrants’ Psycholo.docx
The Colonial Context of Filipino American Immigrants’ Psycholo.docxThe Colonial Context of Filipino American Immigrants’ Psycholo.docx
The Colonial Context of Filipino American Immigrants’ Psycholo.docx
 
The collection of evidence is an activity that occurs with an endgam.docx
The collection of evidence is an activity that occurs with an endgam.docxThe collection of evidence is an activity that occurs with an endgam.docx
The collection of evidence is an activity that occurs with an endgam.docx
 

Recently uploaded

“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 

Recently uploaded (20)

“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 

THE CONTEXT OF INTERNATIONAL PROJECTS IN TERMS OF ORGANI.docx

  • 1. THE CONTEXT OF INTERNATIONAL PROJECTS IN TERMS OF ORGANIZATIONAL STRATEGY AND CULTURE Chapter 2 HOW ARE INTERNATIONAL PROJECTS LINKED TO ORGANIZATIONAL STRATEGY? An organization has a vision it pursues. To achieve its vision, it has a kind of roadmap or plan: this is also called its strategy. To implement its strategy, the organization uses (international) projects. During the project and at the end of the project, the organization checks whether the project has delivered the desired results. This is an ongoing cycle we also call strategic management cycle. 2
  • 2. Project 3 Project 2 Strategic Management Cycle Business Planning Communi- cating and high-level aligning Feedback and Learning Translating the Vision/ Mission 1 3 2 Project 1
  • 3. 4 Executing Completing Planning Initiating How (international) projects are part of the organization’s strategy 3 THE CONNECTION BETWEEN (INTERNATIONAL) PROJECTS AND (INTERNATIONAL) PROGRAMS A program can be defined as a bundle of projects. Compared to a project, a program typically is bigger, requires more resources, and is crucial for the success of organizational strategy. The projects within a program serve the same strategic objective. Projects in a program are interdependent. They share the same objectives and scarce resources.
  • 4. They typically have a common infrastructure and share a certain set of risks. Programs have the following advantages: gic alignment through interdependency of objectives. breaking them down into smaller, easy-to control projects contributes to clearer responsibilities, minimizes risks, and boosts morale and motivation. It also improves the quality of the results. Programs are essentially managed in the same way as projects. 4 PROJECT PORTFOLIO MANAGEMENT (PPM) A project portfolio is a collection of projects managed under one umbrella. These projects may be interrelated or not. Purpose of PPM is to maximize the efficacy of projects in the light of strategy execution. There are two main management processes within project portfolio management: 1. Selection and prioritization of projects. 2. Management of the projects within the portfolio by monitoring target achievement.
  • 5. A project portfolio is periodically adapted to the organizational strategy. The main activities of the PPM process are shown on the following slide. 5 Required inputs: 1. Program/ project title 2. Project objective in light of overall strategy 3. Risk level 4. Timeframe 5. Dependencies with other programs/ projects 6. Estimated budget or ROI 7. Impact of not delivering the program/project 1 3
  • 6. 2 4 Build or Update Project Portfolio Analyze & Prioritize Project Portfolio Monitor & Adjust Project Portfolio Consider new proposed projects
  • 7. The Project Portfolio Management Process 1. Categorization of program/project 3 . Organizational capability and capacity information 2. Program and project information 1. Business requirements in form of organization’s strategy 3. Prioritization of programs/projects according to criteria as: •pressure from the market •capability of the organization
  • 8. •risks •timescale for delivery •impact of not doing the programs/projects 2. Determination of complexity and challenge of portfolio Required activities: 1. Monitoring objectives of single project 2. Monitoring combination of projects in light of organizational success 3. Monitoring project selection in light of change Required tools & techniques: Same as for project management, cf. Chapter 7 Critical aspects to be monitored: Required inputs: 6
  • 9. PROJECT MANAGEMENT MATURITY An organization gains experience about project management over time. Usually, the organization starts with single projects. First, it develops an efficient way of project management. Then, it reaches the stage in which projects perform well as an entirety. The final stage is a continuous selection of projects which contribute to sustainable competitive edge of the organization. The prerequisite for the last stage is well implemented and smoothly working project portfolio management. 7 - Existence of processes to measure project effectiveness and efficiency - Continuous improvement of the efficiency of project portfolio management - Project management processes integrated in the corporate processes - Synchronization of projects with corporate strategy - Solid analysis of project performance
  • 10. - Standardization and institutionalization of project management - Informal and unsystematic collection of project performance data - Project estimates and schedules based on industry standards - Introduction of a structured project management methodology - Inconsistent application (mainly for large visible project) - Many ad-hoc processes in the organization - Awareness development through senior management regarding the importance of structured project management Level 5 Level 1 Level 4 Level 3 Level 2
  • 11. In c re a s e o f p ro je c t m a tu ri ty Example of a 5 stage project management maturity model 8 PROJECT MANAGEMENT AND ORGANIZATIONAL CULTURE Organizational culture can be defined as the way an organization is doing things.
  • 12. A critical success factor of international projects is a supportive project culture. This has to be based on ethnorelativism: values as open mindedness, respect, and trust. Organizational culture goes like a common theme through projects, programs, and project portfolios. All members of the organization need to have a special set of values, attitudes, and behaviours in order to help the implementation of the organizational strategy. Strategy and culture need to be in tune for maximal organizational success. 9 4. Employee welfare, fairness and trust 1. Degree of internal integration 5. Diversity
  • 13. 2. Autonomy and involvement 3. Adaptability: speed, innovation and risk ADEQUATE ELEMENTS OF ORGANIZATIONAL CULTURE FOR SUCCESSFUL INTERNATIONAL PROJECTS 10 Project Management Program Management Project Portfolio Management
  • 14. Management by Projects Main Content of Concept Managing a single project efficiently within given organizational constraints and context. Clustering projects pursuing the same objectives into a program to support alignment with overall organization’s strategy and to
  • 15. increase flexibility. Clustering projects into portfolios to ensure alignment with organization’s strategy. PPM supports coordinated resource allocation, increases flexibility of the whole organization and leads to sustainable project success. Managing the whole organization as a bundle of projects based on a
  • 16. supportive organizational culture. At the extreme, the organization consists of one complex project. Scope Limited to a set of objectives linked to one single project. Business-unit or organization-wide, depending on content of program. An organization- wide management system.
  • 17. A management approach affecting the whole organization, also inter-organizational. Required Project Maturity Level Level 1 – 3: Minimum level 1, ideal level 3 Level 3 – 4 Level 4 – 5 Level 4 – 5 Overview of relevant project management methods – all aiming at strategy implementation 11 DEFINING THE INTERNATIONAL PROJECT
  • 18. Chapter 3 WHAT IS HAPPENING AT THE START OF AN INTERNATIONAL PROJECT? With reference to the project management life cycle, we are in the initiating phase. The project starts with an idea, a customer demand, a bid issued by a government or other opportunities. As each international project is unique, creativity is important at this stage. Special techniques are helpful (see companion website). The project objective has to be in line with the organizational strategy. It is extremely important for the overall project success, that the scene is set well at this stage of the project. This is especially true for stakeholder involvement, and the accuracy of the first rough schedule and budget. 2 Output (deliverables) Input Initiating Phase: Input, Output, Controls and Mechanisms
  • 19. Mechanisms: Tools & techniques (e.g. fishbone diagram) for concept development Controls: Organization‘s project mgmt standards/ procedures Constraints: strategic, financial, time, legal, cultural, environmental, ethical Initiating Phase • Scope Statement • Scope Acceptance • Project Proposal • Stakeholder Matrix • Culture Gap Analysis • Diversity-Complexity- Assessment • Organization’s Strategy
  • 20. • Customer’s Requirements • Market Demand • Opportunities Provided by Globalization 3 ATTENTION TO SCOPE MANAGEMENT The project manager has to clarify from project start as clearly as possible what the project should do, and what it should not do. Due to the heterogeneity of the stakeholders in an international project, special care is due related to scope definition. The danger of differences in associations, attached meanings and general misunderstandings is high. The SMART tool may be helpful: able
  • 21. 4 DEFINING MILESTONES A milestone is a major pre-defined event that represents measurable accomplishment toward the project’s completion. Milestones need to be passed in order to continue with the project. They divide the project into more manageable sub-parts. Milestones are defined at the beginning of the project. It is important to formulate them as clearly as possible. It is also important to communicate them well within the project team. 5 THE WORK BREAKDOWN STRUCTURE (WBS) The milestones are typically the pillars of the so-called Work Breakdown Structure. It structures the entire project into little, manageable chunks. The WBS creates a linked, hierarchical series of activities, which are independent units but at the same time part of the whole.
  • 22. The Work Breakdown Structure typically looks like a tree diagram (see companion website). It can also take the form of a check list. The process is as follows: State the project scope and make sure that all stakeholders have the same understanding. 6 MAPPING CULTURAL PROJECT CONTEXT Among others, international projects are characterized by diversity and complexity. This is largely due to cultural heterogeneity. Major stakeholders need to be understood as well as possible, including their social identity. All stakeholders’ behaviour is embedded in context. An important part of context in international projects is local or national culture, organizational culture, and professional culture
  • 23. as outlined in the next slide. 7 Individual (human nature, personality) Professional/ Functional Culture Organizational Culture (Corporate culture) Sub- cultureSub- culture National Culture Sub- culture Sub- culture Sub-
  • 24. culture CULTURES WITH IMPACT ON INTERNATIONAL PROJECTS 8 1. Power Distance Hofstede‘s model to map differences in national culture 9 Universalism Particularism Individualism Communi- tarianism Neutral Affective Specific Diffuse Achievement Aspiration Internal locus of control
  • 25. External locus of control Sequential Synchronic Future orientation Past orientation Trompenaars‘ model to map differences in national culture 10 Managing risk and uncertainty (4) Defining & planning the project (3, 5) Organizing the project (6) Leading and managing the team (8) Communicating (9); Co-operating (10) Equality Hierarchy Defining the project (3) Managing risk and uncertainty (4)
  • 26. Planning the project (5) Organizing the project (6) Implementing & controlling the project (7) Embracing Risk Avoiding Risk Managing risk (4) Organizing the project (6) Implementing & controlling (7) Motivating and leading the team (8) Communicating (9); Co-operating (10) Learning (11) Individual Group Matching strategy with projects (2) Defining the project (3) Planning the project (5) Implementing & controlling the project (7)
  • 27. Learning (11) Universal Circumstan- tial The Cultural Gap Tool to systematically analyse the national culture environment of international projects (1) The figures in brackets (this slide and next) indicate the book chapters in which the topics are mainly discussed. 11 Defining scope (3) Leading and managing the team (8) Communicating (9); Co-operating (10) Conflict Consensus Managing stakeholders (3) Planning the project (5) Implementing & controlling (7) Leading and managing the team (8) Learning (11)
  • 28. Task Relationship Planning the project (5) Organizing the project (6) Implementing & controlling (7) Motivating and leading the team (8) Achievement Standing / Status Defining the project (3) Planning the project (5) Implementing & controlling (7) Sequential Synchronic Planning the project (5) Executing & controlling the project (7) Learning (11) Theoretical Pragmatic The Cultural Gap Tool to systematically analyse the national culture environment of international projects (2) 12