3. Reduce the overall cost of manufacturing a product by
producing acceptable parts at lowest cost.
Increase the production rate by designing tools that will
produce parts as quickly as possible.
Maintain quality by designing tools which will consistently
produce parts with the required precision.
Reduce the cost of special tooling by making every
design as cost effective and efficient as possible.
Design tools that will be safe and easy to operate.
December 2, 2015Nageswara Rao Posinasetti3
Objectives of tool design
4. Cutting tools, tool holders and cutting fluids
Machine tools
Jigs and fixtures
Gages and measuring instruments
Dies for sheet metal cutting and forming
Dies for forging, cold finishing and extrusion
Fixtures for welding, riveting and other
mechanical fastening
December 2, 2015Nageswara Rao Posinasetti4
Responsibilities of tool designer
5. Statement and analysis of the problem
Analysis of the requirements
Development of initial ideas
Development of design alternatives
Finalization of design ideas
December 2, 2015Nageswara Rao Posinasetti5
The Tool Design Process
6. Problem without tooling
What the tool is supposed to do?
Drill four holes
Bottleneck in assembly
Low productivity with out tooling
December 2, 2015Nageswara Rao Posinasetti6
Statement of the problem
7. Must perform certain functions
Must meet certain minimum precision
requirements
Must keep the cost to a minimum
Must be available when the production schedule
requires it
Must be operated safely
Must meet other requirements such as
adaptability to the machine tool, etc.
December 2, 2015Nageswara Rao Posinasetti7
Analysis of the requirements
9. Cost of material
Cost of manufacturing
Cost of assembling
Cost of standard parts
Cost of tryout
December 2, 2015Nageswara Rao Posinasetti9
What is tool cost?
10. Estimate the volume and mass - CAD
Steel – 7.843 g/cm3
December 2, 2015Nageswara Rao Posinasetti10
Cost of material
11. It includes
Cost of machining
Cost of heat treatment
December 2, 2015Nageswara Rao Posinasetti11
Cost of manufacturing
12. December 2, 2015Nageswara Rao Posinasetti12
Making a Cost Estimate
This ability comes by experience
Cost estimating procedures depends on
the source
Purchase finished component
Have a vendor produce the component
In house manufacture
13. December 2, 2015Nageswara Rao Posinasetti13
The Cost of Machined Components
Control factors that determine the cost of
machined components are:
From what material is the component
produced?
Cost of material
Cost of scrap
Ease with which the material can be removed
(machined)
14. December 2, 2015Nageswara Rao Posinasetti14
The Cost of Machined Components
What type of machine is used to manufacture
the component?
Lathe, horizontal mill, vertical mill, and so on.
Cost of machine tool, tools and fixtures used
What are the major dimensions of the
component?
Size of the machine required
That determines the machine overhead cost
15. December 2, 2015Nageswara Rao Posinasetti15
The Cost of Machined Components
How many machined surfaces are there,
and how much material is to be removed?
Gives a good estimate of time required for
machining
How many components are made?
Fixturing requirements
Setting times and costs
16. December 2, 2015Nageswara Rao Posinasetti16
The Cost of Machined Components
What tolerance and surface finishes are
required?
Tighter tolerances are more expensive
What is the labor rate for machinists?
18. This is relatively easier part.
Check with vendor.
December 2, 2015Nageswara Rao Posinasetti18
Cost of standard parts
19. Drilling and fitting time and costs
Depends on
Number of parts
Complexity
Precision required
Skill of the operator and judgment
Prefers a rule of thumb rather than
sophisticated analysis
December 2, 2015Nageswara Rao Posinasetti19
Cost of Assembling and Tryout
20. Using the listed alternatives, prepare a comparative
analysis for the following tooling problem: A total of 950
flange plates require four holes accurately drilled 90
degrees apart to mate with a connector valve. Which of the
listed alternatives is the most economically desirable?
A. Have a machinist who earns $20.00 per hour lay out and
drill each part at a rate of 2 minutes per part.
B. Use a template jig, capable of producing 50 parts per hour
and costing $50.00, in the production department, where
an operator earns $10.00 per hour.
C. Use a duplex jig, which costs $500.00 and can produce a
part every 26 seconds, in the production department,
where an operator earns $10.00 per hour.
December 2, 2015Nageswara Rao Posinasetti20
Tooling Economics
21. Option a: Cost per piece = 20/30 = $0.67
Option b: Production rate = 60/1.2 = 50 per hour
Cost per piece = 50/950 + 10/50 = 0.05 + 0.20 = $0.25
Option c: Production rate = 3600/26 = 138 per hour
Cost per piece = 500/950 + 10/138 = 0.53 + 0.07 =
$0.60
Cost per piece = 500/5000 + 10/138 = 0.10 + 0.07 =
$0.17 (If 5000 pieces are to be produced)
December 2, 2015Nageswara Rao Posinasetti21
Tooling Economics
22. C = Initial cost of the fixture
I = interest rate on investment, say 6%
M = maintenance cost of fixture, say 10%
T = tax requirement on fixture investment,
say 4%
D = depreciation of fixture, say 50%
Make depreciation 100% if the cost is to be
recovered in one year.
S = setup cost per year = setup cost per
batch * setup cost
December 2, 2015Nageswara Rao Posinasetti22
Tooling Economics
23. t = time saved because of the fixture,
hours
a = Labor hourly cost
A=Cost of saving due to fixture = a * t
Y=Yearly cost of fixture = S +
C*(I+M+T+D)
n = Annual production rate
N = Pieces to be made per
year to justify fixture =
It is necessary n > N December 2, 2015Nageswara Rao Posinasetti23
Tooling Economics
A
Y
24. Economical cost of fixture,
Number of years for fixture to pay itself
December 2, 2015Nageswara Rao Posinasetti24
Tooling Economics
DTMI
S-taN
C
T)M(IC-S-taN
C
Years
25. The Initial cost of a fixture is $ 500. Given that the
interest rate on investment as 6%, maintenance
cost of fixture is 10%, tax requirement on fixture
investment is 4% and the depreciation of fixture is
to be taken as 50% per year. Setup cost of the
fixture is about $10 per single setup. If the time
saved because of the use of fixture is about 0.03
hours with a labor hourly cost of $10, calculate the
number of parts to be produced per year to offset
the cost of the fixture. If the cost of the fixture is to
be recovered in the first year, what should be the
production volume required? If the economical
batch size of manufacture for the parts is 1000,
how many batches should be produced per year to
offset the cost of the fixture?
December 2, 2015Nageswara Rao Posinasetti25
26. December 2, 2015Nageswara Rao Posinasetti26
Q5
C = Initial cost of the fixture $ 500.00
I = interest rate on investment 6%
M = maintenance cost of fixture 10%
T = tax requirement on fixture investment 4%
D = depreciation of fixture 50%
S = setup cost $ 10.00
Y=Yearly cost of fixture = S + C*(I+M+T+D) $ 675.00
t = time saved because of the fixture, hours 0.03
a = Labour hourly cost $ 10.00
A=Cost of saving due to fixture = a * t $ 0.30
Number of pieces to be made per year 2,250
Make depreciation 100% if the cost is to be recovered in one year. 100%
Yearly cost of the fixture if the cost is to be recovered in one year. $ 800.00
Number of pieces to be produced if the cost is to be recovered in
one year. 2,667
Economical batch size of manufacture 1000
Number of batches 3
Setup cost per year = setup cost per batch * Number of batches $ 30.00
Y=Yearly cost of fixture = S + C*(I+M+T+D) $ 3,175.00
Number of pieces to be made per year 10,583
27. Design alternatives
Create Analyze in terms of these criteria
Alternatives Function Quality Cost Date Auxiliary
A
B
.
.
December 2, 2015Nageswara Rao Posinasetti27
28. Temporary tooling
Permanent tooling
December 2, 2015Nageswara Rao Posinasetti28
Economics of Design
29. Break-even charts are perhaps most
widely used to determine profits based on
anticipated sales.
They have other uses, however, such as
for selecting equipment or for measuring
the advisability of increased automation.
December 2, 2015Nageswara Rao Posinasetti29
Break-Even Charts
30. To determine which of two machines is
most economical, the fixed cost and
variable cost of each machine are plotted
The total cost is composed of the sum of
the fixed and variable costs.
December 2, 2015Nageswara Rao Posinasetti30
Break-Even Charts
31. Fixed cost, which relates to the initial
investment on the equipment and tools
required for the process.
Variable cost on the other hand varies with
the actual number of objects made.
The total cost is the sum of both fixed and
variable cost.
December 2, 2015Nageswara Rao Posinasetti31
Break Even Analysis
32. TC = total cost
FC = fixed cost
VC = variable cost per piece
N = production quantity
December 2, 2015Nageswara Rao Posinasetti32
NVC+FC=TC
33. December 2, 2015Nageswara Rao Posinasetti33
NCV+CF=NCV+CF 2211
CV-CV
CF-CF
=N
21
12
N = Break even quantity
34. Permanent mould
casting, ($)
Die casting
($)
Tooling 3600 7000
Setup cost 6.8 17.0
Labor cost 0.50 0.33
Material cost 0.50 0.25
December 2, 2015Nageswara Rao Posinasetti34
An aluminum canopy can be obtained by either permanent
mould casting or die casting process. The costs in dollars in
either case are
Find out the break-even quantity of production
from 1000 to 15 000 pieces.
38. Draw and dimension with due consideration for
someone using the drawing to make the item in
the tool room.
Do not crowd views or dimensions.
Analyze each cut to be sure it can be done with
standard tools.
Use only as many views as necessary to show
all required detail.
December 2, 2015Nageswara Rao Posinasetti38
Tool Drawings
39. Surface roughness must be specified.
Tolerances and fits peculiar to tools need special
consideration.
It is not economical as a rule to tolerance both details
of a pair of mating parts as is required on production
part detailing.
In cases where a hole and a plug are on different
details to be made and mated, the fit tolerance should
be put on the male piece and the hole should carry a
nominal size.
December 2, 2015Nageswara Rao Posinasetti39
Tool Drawings
40. The stock list of any tool drawings should
indicate all sizes required to obtain the
right amount for each detail.
As far as possible, stock sizes known to be
on hand should be used, but in all cases,
available sizes should be specified. A proper,
finished detail is dependent upon starting with
the right material.
December 2, 2015Nageswara Rao Posinasetti40
Tool Drawings
41. Use notes to convey ideas that cannot be
communicated by conventional drawing.
Heat treatments and finishes are usually
identified as specification references
rather than being spelled out on each
drawing.
December 2, 2015Nageswara Rao Posinasetti41
Tool Drawings
42. Secondary operations such as surface
grinding, machining of edges, polishing,
heat treating, or similar specifications
should be kept to a minimum.
Only employ these operations when they are
important to the overall function of the tool;
otherwise these operations will only add cost,
not quality to the tool.
December 2, 2015Nageswara Rao Posinasetti42
Tool Drawings
43. Apply tolerances realistically. Overly tight
tolerances can add a great deal of
additional cost with little or no added value
to the tool.
The function of the detail should determine
the specific tolerance, not a standard title
block tolerance value.
December 2, 2015Nageswara Rao Posinasetti43
Tool Drawings
44. Layout the part in an identifying color (red
is suggested).
Layout any cutting tools. Possible
interference or other confining items
should be indicated in another identifying
color (blue suggested). Use of the cutting
tool should not damage the machine or the
fixture.
December 2, 2015Nageswara Rao Posinasetti44
Tooling Layout
45. Indicate all locating requirements for the
part. There are three locating planes: use
three points in one, two points in the
second, and only one point in the third
plane.
This is called the 3-2-1 locate system. Do not
locate on the parting line of castings or
forgings. All locators must be accessible for
simple cleaning of chips and dirt.
December 2, 2015Nageswara Rao Posinasetti45
Tooling Layout
46. Indicate all clamping requirements for the
part.
Be careful to avoid marking or deforming
finished or delicate surfaces.
Consider the clamping movements of the
operator so injury to the hands or unsafe
situations are eliminated.
Be sure it is possible to load and unload
the part.
December 2, 2015Nageswara Rao Posinasetti46
Tooling Layout
47. Layout the details with due considerations
to stock sizes, so as to minimize
machining requirements.
Use full scale in the layout if possible.
Indicate the use of standard fixture parts
(shelf items) whenever possible.
December 2, 2015Nageswara Rao Posinasetti47
Tooling Layout
48. Identify each different item or detail of any
design by the use of balloons with leaders
and arrows pointing to the detail in the
view that best shows the outline of the
item. These should not go to a line that is
common to other details.
December 2, 2015Nageswara Rao Posinasetti48
Tooling Layout
49. Safety should be designed into the tooling.
Cutting should never be performed against a
clamp, because of vibration and tool chatter.
Instead, parts should be nested against pins in
order to take the cutter load.
Rigidity and fool proofing should always be built
into the tooling.
December 2, 2015Nageswara Rao Posinasetti49
Safety as Related to Tool Design
50. Make drill jigs large enough to hold without
the danger of spinning.
Small drill jigs should always be clamped
in a vise or against a bar or backstop.
Install plexiglass guards around all milling
and fIycutting operations where chips
endanger workers or work areas.
December 2, 2015Nageswara Rao Posinasetti50
Safety as Related to Tool Design