SlideShare a Scribd company logo
1 of 51
Tech 3113
Manufacturing Tooling
Nageswara Rao Posinasetti
1. Introduction
December 2, 2015Nageswara Rao Posinasetti2
 Reduce the overall cost of manufacturing a product by
producing acceptable parts at lowest cost.
 Increase the production rate by designing tools that will
produce parts as quickly as possible.
 Maintain quality by designing tools which will consistently
produce parts with the required precision.
 Reduce the cost of special tooling by making every
design as cost effective and efficient as possible.
 Design tools that will be safe and easy to operate.
December 2, 2015Nageswara Rao Posinasetti3
Objectives of tool design
 Cutting tools, tool holders and cutting fluids
 Machine tools
 Jigs and fixtures
 Gages and measuring instruments
 Dies for sheet metal cutting and forming
 Dies for forging, cold finishing and extrusion
 Fixtures for welding, riveting and other
mechanical fastening
December 2, 2015Nageswara Rao Posinasetti4
Responsibilities of tool designer
 Statement and analysis of the problem
 Analysis of the requirements
 Development of initial ideas
 Development of design alternatives
 Finalization of design ideas
December 2, 2015Nageswara Rao Posinasetti5
The Tool Design Process
 Problem without tooling
 What the tool is supposed to do?
 Drill four holes
 Bottleneck in assembly
 Low productivity with out tooling
December 2, 2015Nageswara Rao Posinasetti6
Statement of the problem
 Must perform certain functions
 Must meet certain minimum precision
requirements
 Must keep the cost to a minimum
 Must be available when the production schedule
requires it
 Must be operated safely
 Must meet other requirements such as
adaptability to the machine tool, etc.
December 2, 2015Nageswara Rao Posinasetti7
Analysis of the requirements
Estimating cost of tooling
December 2, 2015Nageswara Rao Posinasetti8
 Cost of material
 Cost of manufacturing
 Cost of assembling
 Cost of standard parts
 Cost of tryout
December 2, 2015Nageswara Rao Posinasetti9
What is tool cost?
 Estimate the volume and mass - CAD
 Steel – 7.843 g/cm3
December 2, 2015Nageswara Rao Posinasetti10
Cost of material
 It includes
 Cost of machining
 Cost of heat treatment
December 2, 2015Nageswara Rao Posinasetti11
Cost of manufacturing
December 2, 2015Nageswara Rao Posinasetti12
Making a Cost Estimate
 This ability comes by experience
 Cost estimating procedures depends on
the source
 Purchase finished component
 Have a vendor produce the component
 In house manufacture
December 2, 2015Nageswara Rao Posinasetti13
The Cost of Machined Components
 Control factors that determine the cost of
machined components are:
 From what material is the component
produced?
 Cost of material
 Cost of scrap
 Ease with which the material can be removed
(machined)
December 2, 2015Nageswara Rao Posinasetti14
The Cost of Machined Components
 What type of machine is used to manufacture
the component?
 Lathe, horizontal mill, vertical mill, and so on.
 Cost of machine tool, tools and fixtures used
 What are the major dimensions of the
component?
 Size of the machine required
 That determines the machine overhead cost
December 2, 2015Nageswara Rao Posinasetti15
The Cost of Machined Components
 How many machined surfaces are there,
and how much material is to be removed?
 Gives a good estimate of time required for
machining
 How many components are made?
 Fixturing requirements
 Setting times and costs
December 2, 2015Nageswara Rao Posinasetti16
The Cost of Machined Components
 What tolerance and surface finishes are
required?
 Tighter tolerances are more expensive
 What is the labor rate for machinists?
December 2, 2015Nageswara Rao Posinasetti17
Thumb rules for estimation
 This is relatively easier part.
 Check with vendor.
December 2, 2015Nageswara Rao Posinasetti18
Cost of standard parts
 Drilling and fitting time and costs
 Depends on
 Number of parts
 Complexity
 Precision required
 Skill of the operator and judgment
 Prefers a rule of thumb rather than
sophisticated analysis
December 2, 2015Nageswara Rao Posinasetti19
Cost of Assembling and Tryout
 Using the listed alternatives, prepare a comparative
analysis for the following tooling problem: A total of 950
flange plates require four holes accurately drilled 90
degrees apart to mate with a connector valve. Which of the
listed alternatives is the most economically desirable?
A. Have a machinist who earns $20.00 per hour lay out and
drill each part at a rate of 2 minutes per part.
B. Use a template jig, capable of producing 50 parts per hour
and costing $50.00, in the production department, where
an operator earns $10.00 per hour.
C. Use a duplex jig, which costs $500.00 and can produce a
part every 26 seconds, in the production department,
where an operator earns $10.00 per hour.
December 2, 2015Nageswara Rao Posinasetti20
Tooling Economics
 Option a: Cost per piece = 20/30 = $0.67
 Option b: Production rate = 60/1.2 = 50 per hour
 Cost per piece = 50/950 + 10/50 = 0.05 + 0.20 = $0.25
 Option c: Production rate = 3600/26 = 138 per hour
 Cost per piece = 500/950 + 10/138 = 0.53 + 0.07 =
$0.60
 Cost per piece = 500/5000 + 10/138 = 0.10 + 0.07 =
$0.17 (If 5000 pieces are to be produced)
December 2, 2015Nageswara Rao Posinasetti21
Tooling Economics
 C = Initial cost of the fixture
 I = interest rate on investment, say 6%
 M = maintenance cost of fixture, say 10%
 T = tax requirement on fixture investment,
say 4%
 D = depreciation of fixture, say 50%
 Make depreciation 100% if the cost is to be
recovered in one year.
 S = setup cost per year = setup cost per
batch * setup cost
December 2, 2015Nageswara Rao Posinasetti22
Tooling Economics
 t = time saved because of the fixture,
hours
 a = Labor hourly cost
 A=Cost of saving due to fixture = a * t
 Y=Yearly cost of fixture = S +
C*(I+M+T+D)
 n = Annual production rate
 N = Pieces to be made per
year to justify fixture =
 It is necessary n > N December 2, 2015Nageswara Rao Posinasetti23
Tooling Economics
A
Y
 Economical cost of fixture,
 Number of years for fixture to pay itself
December 2, 2015Nageswara Rao Posinasetti24
Tooling Economics
DTMI
S-taN

C
T)M(IC-S-taN
C

Years
 The Initial cost of a fixture is $ 500. Given that the
interest rate on investment as 6%, maintenance
cost of fixture is 10%, tax requirement on fixture
investment is 4% and the depreciation of fixture is
to be taken as 50% per year. Setup cost of the
fixture is about $10 per single setup. If the time
saved because of the use of fixture is about 0.03
hours with a labor hourly cost of $10, calculate the
number of parts to be produced per year to offset
the cost of the fixture. If the cost of the fixture is to
be recovered in the first year, what should be the
production volume required? If the economical
batch size of manufacture for the parts is 1000,
how many batches should be produced per year to
offset the cost of the fixture?
December 2, 2015Nageswara Rao Posinasetti25
December 2, 2015Nageswara Rao Posinasetti26
Q5
C = Initial cost of the fixture $ 500.00
I = interest rate on investment 6%
M = maintenance cost of fixture 10%
T = tax requirement on fixture investment 4%
D = depreciation of fixture 50%
S = setup cost $ 10.00
Y=Yearly cost of fixture = S + C*(I+M+T+D) $ 675.00
t = time saved because of the fixture, hours 0.03
a = Labour hourly cost $ 10.00
A=Cost of saving due to fixture = a * t $ 0.30
Number of pieces to be made per year 2,250
Make depreciation 100% if the cost is to be recovered in one year. 100%
Yearly cost of the fixture if the cost is to be recovered in one year. $ 800.00
Number of pieces to be produced if the cost is to be recovered in
one year. 2,667
Economical batch size of manufacture 1000
Number of batches 3
Setup cost per year = setup cost per batch * Number of batches $ 30.00
Y=Yearly cost of fixture = S + C*(I+M+T+D) $ 3,175.00
Number of pieces to be made per year 10,583
Design alternatives
Create Analyze in terms of these criteria
Alternatives Function Quality Cost Date Auxiliary
A
B
.
.
December 2, 2015Nageswara Rao Posinasetti27
 Temporary tooling
 Permanent tooling
December 2, 2015Nageswara Rao Posinasetti28
Economics of Design
 Break-even charts are perhaps most
widely used to determine profits based on
anticipated sales.
 They have other uses, however, such as
for selecting equipment or for measuring
the advisability of increased automation.
December 2, 2015Nageswara Rao Posinasetti29
Break-Even Charts
 To determine which of two machines is
most economical, the fixed cost and
variable cost of each machine are plotted
 The total cost is composed of the sum of
the fixed and variable costs.
December 2, 2015Nageswara Rao Posinasetti30
Break-Even Charts
 Fixed cost, which relates to the initial
investment on the equipment and tools
required for the process.
 Variable cost on the other hand varies with
the actual number of objects made.
 The total cost is the sum of both fixed and
variable cost.
December 2, 2015Nageswara Rao Posinasetti31
Break Even Analysis
 TC = total cost
 FC = fixed cost
 VC = variable cost per piece
 N = production quantity
December 2, 2015Nageswara Rao Posinasetti32
NVC+FC=TC 
December 2, 2015Nageswara Rao Posinasetti33
NCV+CF=NCV+CF 2211 
CV-CV
CF-CF
=N
21
12
N = Break even quantity
Permanent mould
casting, ($)
Die casting
($)
Tooling 3600 7000
Setup cost 6.8 17.0
Labor cost 0.50 0.33
Material cost 0.50 0.25
December 2, 2015Nageswara Rao Posinasetti34
An aluminum canopy can be obtained by either permanent
mould casting or die casting process. The costs in dollars in
either case are
Find out the break-even quantity of production
from 1000 to 15 000 pieces.
December 2, 2015Nageswara Rao Posinasetti35
Permanent mould casting
($)
Die casting
($)
Tooling 3600 7000
Setup cost 6.8 17.0
Fixed cost 3606.80 7017.00
December 2, 2015Nageswara Rao Posinasetti36
Permanent mould casting
($)
Die casting
($)
Tooling 3600 7000
Setup cost 6.8 17.0
Fixed cost 3606.80 7017.00
Labor cost 0.50 0.33
Material cost 0.50 0.25
Variable cost 1.00 0.58
December 2, 2015Nageswara Rao Posinasetti37
Prod
quantity
Permanent mould
casting, ($)
Die casting
($)
1000 4606.80 7580.00
5000 8606.80 9917.00
10,000 13,606.80 12,800.00
15,000 18606.80 15717.00
Break even quantity =
= 8119.52
58.000.1
80.36067017


 Draw and dimension with due consideration for
someone using the drawing to make the item in
the tool room.
 Do not crowd views or dimensions.
 Analyze each cut to be sure it can be done with
standard tools.
 Use only as many views as necessary to show
all required detail.
December 2, 2015Nageswara Rao Posinasetti38
Tool Drawings
 Surface roughness must be specified.
 Tolerances and fits peculiar to tools need special
consideration.
 It is not economical as a rule to tolerance both details
of a pair of mating parts as is required on production
part detailing.
 In cases where a hole and a plug are on different
details to be made and mated, the fit tolerance should
be put on the male piece and the hole should carry a
nominal size.
December 2, 2015Nageswara Rao Posinasetti39
Tool Drawings
 The stock list of any tool drawings should
indicate all sizes required to obtain the
right amount for each detail.
 As far as possible, stock sizes known to be
on hand should be used, but in all cases,
available sizes should be specified. A proper,
finished detail is dependent upon starting with
the right material.
December 2, 2015Nageswara Rao Posinasetti40
Tool Drawings
 Use notes to convey ideas that cannot be
communicated by conventional drawing.
Heat treatments and finishes are usually
identified as specification references
rather than being spelled out on each
drawing.
December 2, 2015Nageswara Rao Posinasetti41
Tool Drawings
 Secondary operations such as surface
grinding, machining of edges, polishing,
heat treating, or similar specifications
should be kept to a minimum.
 Only employ these operations when they are
important to the overall function of the tool;
otherwise these operations will only add cost,
not quality to the tool.
December 2, 2015Nageswara Rao Posinasetti42
Tool Drawings
 Apply tolerances realistically. Overly tight
tolerances can add a great deal of
additional cost with little or no added value
to the tool.
 The function of the detail should determine
the specific tolerance, not a standard title
block tolerance value.
December 2, 2015Nageswara Rao Posinasetti43
Tool Drawings
 Layout the part in an identifying color (red
is suggested).
 Layout any cutting tools. Possible
interference or other confining items
should be indicated in another identifying
color (blue suggested). Use of the cutting
tool should not damage the machine or the
fixture.
December 2, 2015Nageswara Rao Posinasetti44
Tooling Layout
 Indicate all locating requirements for the
part. There are three locating planes: use
three points in one, two points in the
second, and only one point in the third
plane.
 This is called the 3-2-1 locate system. Do not
locate on the parting line of castings or
forgings. All locators must be accessible for
simple cleaning of chips and dirt.
December 2, 2015Nageswara Rao Posinasetti45
Tooling Layout
 Indicate all clamping requirements for the
part.
 Be careful to avoid marking or deforming
finished or delicate surfaces.
 Consider the clamping movements of the
operator so injury to the hands or unsafe
situations are eliminated.
 Be sure it is possible to load and unload
the part.
December 2, 2015Nageswara Rao Posinasetti46
Tooling Layout
 Layout the details with due considerations
to stock sizes, so as to minimize
machining requirements.
 Use full scale in the layout if possible.
 Indicate the use of standard fixture parts
(shelf items) whenever possible.
December 2, 2015Nageswara Rao Posinasetti47
Tooling Layout
 Identify each different item or detail of any
design by the use of balloons with leaders
and arrows pointing to the detail in the
view that best shows the outline of the
item. These should not go to a line that is
common to other details.
December 2, 2015Nageswara Rao Posinasetti48
Tooling Layout
 Safety should be designed into the tooling.
 Cutting should never be performed against a
clamp, because of vibration and tool chatter.
Instead, parts should be nested against pins in
order to take the cutter load.
 Rigidity and fool proofing should always be built
into the tooling.
December 2, 2015Nageswara Rao Posinasetti49
Safety as Related to Tool Design
 Make drill jigs large enough to hold without
the danger of spinning.
 Small drill jigs should always be clamped
in a vise or against a bar or backstop.
 Install plexiglass guards around all milling
and fIycutting operations where chips
endanger workers or work areas.
December 2, 2015Nageswara Rao Posinasetti50
Safety as Related to Tool Design
Questions?
December 2, 2015Nageswara Rao Posinasetti51

More Related Content

What's hot

Dies Design - Cutting Operations Part 2
Dies Design - Cutting Operations Part 2Dies Design - Cutting Operations Part 2
Dies Design - Cutting Operations Part 2Federick Pocoyo
 
Theory of metal cutting MG University(S8 Production Notes)
Theory of metal cutting MG University(S8 Production Notes)Theory of metal cutting MG University(S8 Production Notes)
Theory of metal cutting MG University(S8 Production Notes)Denny John
 
Tool wear, tool life & machinability
Tool wear, tool life & machinabilityTool wear, tool life & machinability
Tool wear, tool life & machinabilityDENNY OTTARACKAL
 
Tooling Design
Tooling DesignTooling Design
Tooling Designmrg timoq
 
Shaping, planing and slotting operations
Shaping, planing and slotting operationsShaping, planing and slotting operations
Shaping, planing and slotting operationssabry said
 
Economics of metal cutting operations
Economics of metal cutting operationsEconomics of metal cutting operations
Economics of metal cutting operationsDarshan Panchal
 
press tool, jigs & fixtures, gear and thread manufacturing,manufacturing pro...
 press tool, jigs & fixtures, gear and thread manufacturing,manufacturing pro... press tool, jigs & fixtures, gear and thread manufacturing,manufacturing pro...
press tool, jigs & fixtures, gear and thread manufacturing,manufacturing pro...Prof.Mayur Modi
 
Design of Machine Elements- Unit 2 Procedures
Design of Machine Elements- Unit 2 ProceduresDesign of Machine Elements- Unit 2 Procedures
Design of Machine Elements- Unit 2 Proceduress Kumaravel
 
Sheet Metal Forming
Sheet Metal FormingSheet Metal Forming
Sheet Metal Formingvins049
 
Tool engineering by McGRAW HILL
Tool engineering by McGRAW HILLTool engineering by McGRAW HILL
Tool engineering by McGRAW HILLParthiv Panchal
 

What's hot (20)

Machine tools
Machine toolsMachine tools
Machine tools
 
Dies Design - Cutting Operations Part 2
Dies Design - Cutting Operations Part 2Dies Design - Cutting Operations Part 2
Dies Design - Cutting Operations Part 2
 
METAL CUTTING
METAL CUTTINGMETAL CUTTING
METAL CUTTING
 
Tool wear (04 10-10)
Tool wear (04 10-10)Tool wear (04 10-10)
Tool wear (04 10-10)
 
Press machines ppt
Press machines pptPress machines ppt
Press machines ppt
 
Theory of metal cutting MG University(S8 Production Notes)
Theory of metal cutting MG University(S8 Production Notes)Theory of metal cutting MG University(S8 Production Notes)
Theory of metal cutting MG University(S8 Production Notes)
 
Drill bushes
Drill bushesDrill bushes
Drill bushes
 
Tool wear, tool life & machinability
Tool wear, tool life & machinabilityTool wear, tool life & machinability
Tool wear, tool life & machinability
 
Tooling Design
Tooling DesignTooling Design
Tooling Design
 
Shaping, planing and slotting operations
Shaping, planing and slotting operationsShaping, planing and slotting operations
Shaping, planing and slotting operations
 
Economics of metal cutting operations
Economics of metal cutting operationsEconomics of metal cutting operations
Economics of metal cutting operations
 
Cutting tool geometry
Cutting tool geometryCutting tool geometry
Cutting tool geometry
 
Jig and fixtures
Jig and fixturesJig and fixtures
Jig and fixtures
 
Abrasive jet machining
Abrasive jet machiningAbrasive jet machining
Abrasive jet machining
 
Merchant's circle
Merchant's circleMerchant's circle
Merchant's circle
 
Metrology of threads
Metrology of threadsMetrology of threads
Metrology of threads
 
press tool, jigs & fixtures, gear and thread manufacturing,manufacturing pro...
 press tool, jigs & fixtures, gear and thread manufacturing,manufacturing pro... press tool, jigs & fixtures, gear and thread manufacturing,manufacturing pro...
press tool, jigs & fixtures, gear and thread manufacturing,manufacturing pro...
 
Design of Machine Elements- Unit 2 Procedures
Design of Machine Elements- Unit 2 ProceduresDesign of Machine Elements- Unit 2 Procedures
Design of Machine Elements- Unit 2 Procedures
 
Sheet Metal Forming
Sheet Metal FormingSheet Metal Forming
Sheet Metal Forming
 
Tool engineering by McGRAW HILL
Tool engineering by McGRAW HILLTool engineering by McGRAW HILL
Tool engineering by McGRAW HILL
 

Viewers also liked

Viewers also liked (9)

Mfg tooling 02 materials
Mfg tooling  02 materialsMfg tooling  02 materials
Mfg tooling 02 materials
 
2015 trends in education-pn rao
2015 trends in education-pn rao2015 trends in education-pn rao
2015 trends in education-pn rao
 
Mfg tooling 03 cutting tools
Mfg tooling  03 cutting toolsMfg tooling  03 cutting tools
Mfg tooling 03 cutting tools
 
Basic Economic Tools in Business Economics
Basic Economic Tools in Business EconomicsBasic Economic Tools in Business Economics
Basic Economic Tools in Business Economics
 
Lean manufacturing system (lms) 19-march-sgd
Lean manufacturing system (lms) 19-march-sgdLean manufacturing system (lms) 19-march-sgd
Lean manufacturing system (lms) 19-march-sgd
 
Mfg tooling 04 cutting tool design
Mfg tooling  04 cutting tool designMfg tooling  04 cutting tool design
Mfg tooling 04 cutting tool design
 
PPT on break even analysis
PPT on break even analysisPPT on break even analysis
PPT on break even analysis
 
Break even analysis
Break even analysisBreak even analysis
Break even analysis
 
Break Even Analysis
Break Even AnalysisBreak Even Analysis
Break Even Analysis
 

Similar to Manufacturing Tooling Design and Economics

Project feasibilty report on Pricision Auto pistons aniket kulkarni
Project feasibilty report on Pricision Auto pistons aniket kulkarniProject feasibilty report on Pricision Auto pistons aniket kulkarni
Project feasibilty report on Pricision Auto pistons aniket kulkarniANIKET KULKARNI
 
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIRJET Journal
 
Stability, Security & Innovation in Networking
Stability, Security & Innovation in NetworkingStability, Security & Innovation in Networking
Stability, Security & Innovation in NetworkingHunter Gorman
 
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed ManufacturingIRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed ManufacturingIRJET Journal
 
Manufacturing of Toggle Jack
Manufacturing of Toggle JackManufacturing of Toggle Jack
Manufacturing of Toggle JackIRJET Journal
 
Design and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing MachineDesign and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing MachineIRJET Journal
 
costestimating-110323025231-phpapp02.pptx
costestimating-110323025231-phpapp02.pptxcostestimating-110323025231-phpapp02.pptx
costestimating-110323025231-phpapp02.pptxRedhaElhuni
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTIRJET Journal
 
IRJET- Design and Analysis of Progressive Die for Industrial Component Ta...
IRJET-  	  Design and Analysis of Progressive Die for Industrial Component Ta...IRJET-  	  Design and Analysis of Progressive Die for Industrial Component Ta...
IRJET- Design and Analysis of Progressive Die for Industrial Component Ta...IRJET Journal
 
Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02hlksd
 
8ACC122 Midterm Exam – Problems (7 points each)Student .docx
8ACC122   Midterm Exam – Problems    (7 points each)Student .docx8ACC122   Midterm Exam – Problems    (7 points each)Student .docx
8ACC122 Midterm Exam – Problems (7 points each)Student .docxevonnehoggarth79783
 
Concept of Value Engineering with Case Study
Concept of Value Engineering with Case StudyConcept of Value Engineering with Case Study
Concept of Value Engineering with Case StudyAditya Deshpande
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET Journal
 
Design and Manufacturing of Lathe Tool Post Grinding Attachment
Design and Manufacturing of Lathe Tool Post Grinding AttachmentDesign and Manufacturing of Lathe Tool Post Grinding Attachment
Design and Manufacturing of Lathe Tool Post Grinding AttachmentIRJET Journal
 
Cost estimating & Costing
Cost estimating & CostingCost estimating & Costing
Cost estimating & CostingGanesh Murugan
 
Piston ring kuldeep agrawal
Piston ring  kuldeep agrawalPiston ring  kuldeep agrawal
Piston ring kuldeep agrawalANIKET KULKARNI
 
ACT 333__Cost accounting report on fountain
ACT 333__Cost accounting report on fountainACT 333__Cost accounting report on fountain
ACT 333__Cost accounting report on fountainKhorsed Prince
 

Similar to Manufacturing Tooling Design and Economics (20)

ME-6th-sem.pdf
ME-6th-sem.pdfME-6th-sem.pdf
ME-6th-sem.pdf
 
Project feasibilty report on Pricision Auto pistons aniket kulkarni
Project feasibilty report on Pricision Auto pistons aniket kulkarniProject feasibilty report on Pricision Auto pistons aniket kulkarni
Project feasibilty report on Pricision Auto pistons aniket kulkarni
 
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVANIMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
IMPLEMENTATION OF LEAN TOOLS AND EGONOMIC ASPECTS IN THE DESIGN OF A CARAVAN
 
Stability, Security & Innovation in Networking
Stability, Security & Innovation in NetworkingStability, Security & Innovation in Networking
Stability, Security & Innovation in Networking
 
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed ManufacturingIRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
IRJET- Value Analysis Aimed at Cost Reduction in Wooden Bed Manufacturing
 
Manufacturing of Toggle Jack
Manufacturing of Toggle JackManufacturing of Toggle Jack
Manufacturing of Toggle Jack
 
Design and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing MachineDesign and Development of Dynamo Testing Machine
Design and Development of Dynamo Testing Machine
 
Project preparation
Project preparationProject preparation
Project preparation
 
costestimating-110323025231-phpapp02.pptx
costestimating-110323025231-phpapp02.pptxcostestimating-110323025231-phpapp02.pptx
costestimating-110323025231-phpapp02.pptx
 
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECTOPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
OPTIMIZATION OF PRODUCTION COST IN CONSTRUCTION PROJECT
 
IRJET- Design and Analysis of Progressive Die for Industrial Component Ta...
IRJET-  	  Design and Analysis of Progressive Die for Industrial Component Ta...IRJET-  	  Design and Analysis of Progressive Die for Industrial Component Ta...
IRJET- Design and Analysis of Progressive Die for Industrial Component Ta...
 
Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02Costestimating 110323025231-phpapp02
Costestimating 110323025231-phpapp02
 
8ACC122 Midterm Exam – Problems (7 points each)Student .docx
8ACC122   Midterm Exam – Problems    (7 points each)Student .docx8ACC122   Midterm Exam – Problems    (7 points each)Student .docx
8ACC122 Midterm Exam – Problems (7 points each)Student .docx
 
Concept of Value Engineering with Case Study
Concept of Value Engineering with Case StudyConcept of Value Engineering with Case Study
Concept of Value Engineering with Case Study
 
Act 333
Act 333Act 333
Act 333
 
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
IRJET- Design of Manufacture of Fixtures for CNC Machine to Improve Productiv...
 
Design and Manufacturing of Lathe Tool Post Grinding Attachment
Design and Manufacturing of Lathe Tool Post Grinding AttachmentDesign and Manufacturing of Lathe Tool Post Grinding Attachment
Design and Manufacturing of Lathe Tool Post Grinding Attachment
 
Cost estimating & Costing
Cost estimating & CostingCost estimating & Costing
Cost estimating & Costing
 
Piston ring kuldeep agrawal
Piston ring  kuldeep agrawalPiston ring  kuldeep agrawal
Piston ring kuldeep agrawal
 
ACT 333__Cost accounting report on fountain
ACT 333__Cost accounting report on fountainACT 333__Cost accounting report on fountain
ACT 333__Cost accounting report on fountain
 

More from Nageswara Rao Posinasetti (6)

Adv mfg 04 no figs
Adv mfg 04 no figsAdv mfg 04 no figs
Adv mfg 04 no figs
 
Adv mfg 03 nofig
Adv mfg 03 nofigAdv mfg 03 nofig
Adv mfg 03 nofig
 
Adv mfg 02
Adv mfg 02Adv mfg 02
Adv mfg 02
 
Adv mfg 01-introduction to cnc
Adv mfg 01-introduction to cncAdv mfg 01-introduction to cnc
Adv mfg 01-introduction to cnc
 
Adv mfg 01
Adv mfg 01Adv mfg 01
Adv mfg 01
 
2015 emerging trends in education-pn rao-gwalior
2015 emerging trends in education-pn rao-gwalior2015 emerging trends in education-pn rao-gwalior
2015 emerging trends in education-pn rao-gwalior
 

Recently uploaded

Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Pooja Nehwal
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrsaastr
 
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptxMohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptxmohammadalnahdi22
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AITatiana Gurgel
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyPooja Nehwal
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...henrik385807
 
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceDelhi Call girls
 
Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Vipesco
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkataanamikaraghav4
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...Sheetaleventcompany
 
Presentation on Engagement in Book Clubs
Presentation on Engagement in Book ClubsPresentation on Engagement in Book Clubs
Presentation on Engagement in Book Clubssamaasim06
 
Mathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMoumonDas2
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Chameera Dedduwage
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...NETWAYS
 
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxNikitaBankoti2
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024eCommerce Institute
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024eCommerce Institute
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Kayode Fayemi
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Delhi Call girls
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfhenrik385807
 

Recently uploaded (20)

Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
Navi Mumbai Call Girls Service Pooja 9892124323 Real Russian Girls Looking Mo...
 
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStrSaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
SaaStr Workshop Wednesday w: Jason Lemkin, SaaStr
 
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptxMohammad_Alnahdi_Oral_Presentation_Assignment.pptx
Mohammad_Alnahdi_Oral_Presentation_Assignment.pptx
 
Microsoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AIMicrosoft Copilot AI for Everyone - created by AI
Microsoft Copilot AI for Everyone - created by AI
 
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night EnjoyCall Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
Call Girl Number in Khar Mumbai📲 9892124323 💞 Full Night Enjoy
 
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
CTAC 2024 Valencia - Sven Zoelle - Most Crucial Invest to Digitalisation_slid...
 
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort ServiceBDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
BDSM⚡Call Girls in Sector 93 Noida Escorts >༒8448380779 Escort Service
 
Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510Thirunelveli call girls Tamil escorts 7877702510
Thirunelveli call girls Tamil escorts 7877702510
 
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls KolkataRussian Call Girls in Kolkata Vaishnavi 🤌  8250192130 🚀 Vip Call Girls Kolkata
Russian Call Girls in Kolkata Vaishnavi 🤌 8250192130 🚀 Vip Call Girls Kolkata
 
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
No Advance 8868886958 Chandigarh Call Girls , Indian Call Girls For Full Nigh...
 
Presentation on Engagement in Book Clubs
Presentation on Engagement in Book ClubsPresentation on Engagement in Book Clubs
Presentation on Engagement in Book Clubs
 
Mathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptxMathematics of Finance Presentation.pptx
Mathematics of Finance Presentation.pptx
 
Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)Introduction to Prompt Engineering (Focusing on ChatGPT)
Introduction to Prompt Engineering (Focusing on ChatGPT)
 
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
OSCamp Kubernetes 2024 | A Tester's Guide to CI_CD as an Automated Quality Co...
 
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docxANCHORING SCRIPT FOR A CULTURAL EVENT.docx
ANCHORING SCRIPT FOR A CULTURAL EVENT.docx
 
George Lever - eCommerce Day Chile 2024
George Lever -  eCommerce Day Chile 2024George Lever -  eCommerce Day Chile 2024
George Lever - eCommerce Day Chile 2024
 
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
Andrés Ramírez Gossler, Facundo Schinnea - eCommerce Day Chile 2024
 
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
Governance and Nation-Building in Nigeria: Some Reflections on Options for Po...
 
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
Night 7k Call Girls Noida Sector 128 Call Me: 8448380779
 
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdfCTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
CTAC 2024 Valencia - Henrik Hanke - Reduce to the max - slideshare.pdf
 

Manufacturing Tooling Design and Economics

  • 2. 1. Introduction December 2, 2015Nageswara Rao Posinasetti2
  • 3.  Reduce the overall cost of manufacturing a product by producing acceptable parts at lowest cost.  Increase the production rate by designing tools that will produce parts as quickly as possible.  Maintain quality by designing tools which will consistently produce parts with the required precision.  Reduce the cost of special tooling by making every design as cost effective and efficient as possible.  Design tools that will be safe and easy to operate. December 2, 2015Nageswara Rao Posinasetti3 Objectives of tool design
  • 4.  Cutting tools, tool holders and cutting fluids  Machine tools  Jigs and fixtures  Gages and measuring instruments  Dies for sheet metal cutting and forming  Dies for forging, cold finishing and extrusion  Fixtures for welding, riveting and other mechanical fastening December 2, 2015Nageswara Rao Posinasetti4 Responsibilities of tool designer
  • 5.  Statement and analysis of the problem  Analysis of the requirements  Development of initial ideas  Development of design alternatives  Finalization of design ideas December 2, 2015Nageswara Rao Posinasetti5 The Tool Design Process
  • 6.  Problem without tooling  What the tool is supposed to do?  Drill four holes  Bottleneck in assembly  Low productivity with out tooling December 2, 2015Nageswara Rao Posinasetti6 Statement of the problem
  • 7.  Must perform certain functions  Must meet certain minimum precision requirements  Must keep the cost to a minimum  Must be available when the production schedule requires it  Must be operated safely  Must meet other requirements such as adaptability to the machine tool, etc. December 2, 2015Nageswara Rao Posinasetti7 Analysis of the requirements
  • 8. Estimating cost of tooling December 2, 2015Nageswara Rao Posinasetti8
  • 9.  Cost of material  Cost of manufacturing  Cost of assembling  Cost of standard parts  Cost of tryout December 2, 2015Nageswara Rao Posinasetti9 What is tool cost?
  • 10.  Estimate the volume and mass - CAD  Steel – 7.843 g/cm3 December 2, 2015Nageswara Rao Posinasetti10 Cost of material
  • 11.  It includes  Cost of machining  Cost of heat treatment December 2, 2015Nageswara Rao Posinasetti11 Cost of manufacturing
  • 12. December 2, 2015Nageswara Rao Posinasetti12 Making a Cost Estimate  This ability comes by experience  Cost estimating procedures depends on the source  Purchase finished component  Have a vendor produce the component  In house manufacture
  • 13. December 2, 2015Nageswara Rao Posinasetti13 The Cost of Machined Components  Control factors that determine the cost of machined components are:  From what material is the component produced?  Cost of material  Cost of scrap  Ease with which the material can be removed (machined)
  • 14. December 2, 2015Nageswara Rao Posinasetti14 The Cost of Machined Components  What type of machine is used to manufacture the component?  Lathe, horizontal mill, vertical mill, and so on.  Cost of machine tool, tools and fixtures used  What are the major dimensions of the component?  Size of the machine required  That determines the machine overhead cost
  • 15. December 2, 2015Nageswara Rao Posinasetti15 The Cost of Machined Components  How many machined surfaces are there, and how much material is to be removed?  Gives a good estimate of time required for machining  How many components are made?  Fixturing requirements  Setting times and costs
  • 16. December 2, 2015Nageswara Rao Posinasetti16 The Cost of Machined Components  What tolerance and surface finishes are required?  Tighter tolerances are more expensive  What is the labor rate for machinists?
  • 17. December 2, 2015Nageswara Rao Posinasetti17 Thumb rules for estimation
  • 18.  This is relatively easier part.  Check with vendor. December 2, 2015Nageswara Rao Posinasetti18 Cost of standard parts
  • 19.  Drilling and fitting time and costs  Depends on  Number of parts  Complexity  Precision required  Skill of the operator and judgment  Prefers a rule of thumb rather than sophisticated analysis December 2, 2015Nageswara Rao Posinasetti19 Cost of Assembling and Tryout
  • 20.  Using the listed alternatives, prepare a comparative analysis for the following tooling problem: A total of 950 flange plates require four holes accurately drilled 90 degrees apart to mate with a connector valve. Which of the listed alternatives is the most economically desirable? A. Have a machinist who earns $20.00 per hour lay out and drill each part at a rate of 2 minutes per part. B. Use a template jig, capable of producing 50 parts per hour and costing $50.00, in the production department, where an operator earns $10.00 per hour. C. Use a duplex jig, which costs $500.00 and can produce a part every 26 seconds, in the production department, where an operator earns $10.00 per hour. December 2, 2015Nageswara Rao Posinasetti20 Tooling Economics
  • 21.  Option a: Cost per piece = 20/30 = $0.67  Option b: Production rate = 60/1.2 = 50 per hour  Cost per piece = 50/950 + 10/50 = 0.05 + 0.20 = $0.25  Option c: Production rate = 3600/26 = 138 per hour  Cost per piece = 500/950 + 10/138 = 0.53 + 0.07 = $0.60  Cost per piece = 500/5000 + 10/138 = 0.10 + 0.07 = $0.17 (If 5000 pieces are to be produced) December 2, 2015Nageswara Rao Posinasetti21 Tooling Economics
  • 22.  C = Initial cost of the fixture  I = interest rate on investment, say 6%  M = maintenance cost of fixture, say 10%  T = tax requirement on fixture investment, say 4%  D = depreciation of fixture, say 50%  Make depreciation 100% if the cost is to be recovered in one year.  S = setup cost per year = setup cost per batch * setup cost December 2, 2015Nageswara Rao Posinasetti22 Tooling Economics
  • 23.  t = time saved because of the fixture, hours  a = Labor hourly cost  A=Cost of saving due to fixture = a * t  Y=Yearly cost of fixture = S + C*(I+M+T+D)  n = Annual production rate  N = Pieces to be made per year to justify fixture =  It is necessary n > N December 2, 2015Nageswara Rao Posinasetti23 Tooling Economics A Y
  • 24.  Economical cost of fixture,  Number of years for fixture to pay itself December 2, 2015Nageswara Rao Posinasetti24 Tooling Economics DTMI S-taN  C T)M(IC-S-taN C  Years
  • 25.  The Initial cost of a fixture is $ 500. Given that the interest rate on investment as 6%, maintenance cost of fixture is 10%, tax requirement on fixture investment is 4% and the depreciation of fixture is to be taken as 50% per year. Setup cost of the fixture is about $10 per single setup. If the time saved because of the use of fixture is about 0.03 hours with a labor hourly cost of $10, calculate the number of parts to be produced per year to offset the cost of the fixture. If the cost of the fixture is to be recovered in the first year, what should be the production volume required? If the economical batch size of manufacture for the parts is 1000, how many batches should be produced per year to offset the cost of the fixture? December 2, 2015Nageswara Rao Posinasetti25
  • 26. December 2, 2015Nageswara Rao Posinasetti26 Q5 C = Initial cost of the fixture $ 500.00 I = interest rate on investment 6% M = maintenance cost of fixture 10% T = tax requirement on fixture investment 4% D = depreciation of fixture 50% S = setup cost $ 10.00 Y=Yearly cost of fixture = S + C*(I+M+T+D) $ 675.00 t = time saved because of the fixture, hours 0.03 a = Labour hourly cost $ 10.00 A=Cost of saving due to fixture = a * t $ 0.30 Number of pieces to be made per year 2,250 Make depreciation 100% if the cost is to be recovered in one year. 100% Yearly cost of the fixture if the cost is to be recovered in one year. $ 800.00 Number of pieces to be produced if the cost is to be recovered in one year. 2,667 Economical batch size of manufacture 1000 Number of batches 3 Setup cost per year = setup cost per batch * Number of batches $ 30.00 Y=Yearly cost of fixture = S + C*(I+M+T+D) $ 3,175.00 Number of pieces to be made per year 10,583
  • 27. Design alternatives Create Analyze in terms of these criteria Alternatives Function Quality Cost Date Auxiliary A B . . December 2, 2015Nageswara Rao Posinasetti27
  • 28.  Temporary tooling  Permanent tooling December 2, 2015Nageswara Rao Posinasetti28 Economics of Design
  • 29.  Break-even charts are perhaps most widely used to determine profits based on anticipated sales.  They have other uses, however, such as for selecting equipment or for measuring the advisability of increased automation. December 2, 2015Nageswara Rao Posinasetti29 Break-Even Charts
  • 30.  To determine which of two machines is most economical, the fixed cost and variable cost of each machine are plotted  The total cost is composed of the sum of the fixed and variable costs. December 2, 2015Nageswara Rao Posinasetti30 Break-Even Charts
  • 31.  Fixed cost, which relates to the initial investment on the equipment and tools required for the process.  Variable cost on the other hand varies with the actual number of objects made.  The total cost is the sum of both fixed and variable cost. December 2, 2015Nageswara Rao Posinasetti31 Break Even Analysis
  • 32.  TC = total cost  FC = fixed cost  VC = variable cost per piece  N = production quantity December 2, 2015Nageswara Rao Posinasetti32 NVC+FC=TC 
  • 33. December 2, 2015Nageswara Rao Posinasetti33 NCV+CF=NCV+CF 2211  CV-CV CF-CF =N 21 12 N = Break even quantity
  • 34. Permanent mould casting, ($) Die casting ($) Tooling 3600 7000 Setup cost 6.8 17.0 Labor cost 0.50 0.33 Material cost 0.50 0.25 December 2, 2015Nageswara Rao Posinasetti34 An aluminum canopy can be obtained by either permanent mould casting or die casting process. The costs in dollars in either case are Find out the break-even quantity of production from 1000 to 15 000 pieces.
  • 35. December 2, 2015Nageswara Rao Posinasetti35 Permanent mould casting ($) Die casting ($) Tooling 3600 7000 Setup cost 6.8 17.0 Fixed cost 3606.80 7017.00
  • 36. December 2, 2015Nageswara Rao Posinasetti36 Permanent mould casting ($) Die casting ($) Tooling 3600 7000 Setup cost 6.8 17.0 Fixed cost 3606.80 7017.00 Labor cost 0.50 0.33 Material cost 0.50 0.25 Variable cost 1.00 0.58
  • 37. December 2, 2015Nageswara Rao Posinasetti37 Prod quantity Permanent mould casting, ($) Die casting ($) 1000 4606.80 7580.00 5000 8606.80 9917.00 10,000 13,606.80 12,800.00 15,000 18606.80 15717.00 Break even quantity = = 8119.52 58.000.1 80.36067017  
  • 38.  Draw and dimension with due consideration for someone using the drawing to make the item in the tool room.  Do not crowd views or dimensions.  Analyze each cut to be sure it can be done with standard tools.  Use only as many views as necessary to show all required detail. December 2, 2015Nageswara Rao Posinasetti38 Tool Drawings
  • 39.  Surface roughness must be specified.  Tolerances and fits peculiar to tools need special consideration.  It is not economical as a rule to tolerance both details of a pair of mating parts as is required on production part detailing.  In cases where a hole and a plug are on different details to be made and mated, the fit tolerance should be put on the male piece and the hole should carry a nominal size. December 2, 2015Nageswara Rao Posinasetti39 Tool Drawings
  • 40.  The stock list of any tool drawings should indicate all sizes required to obtain the right amount for each detail.  As far as possible, stock sizes known to be on hand should be used, but in all cases, available sizes should be specified. A proper, finished detail is dependent upon starting with the right material. December 2, 2015Nageswara Rao Posinasetti40 Tool Drawings
  • 41.  Use notes to convey ideas that cannot be communicated by conventional drawing. Heat treatments and finishes are usually identified as specification references rather than being spelled out on each drawing. December 2, 2015Nageswara Rao Posinasetti41 Tool Drawings
  • 42.  Secondary operations such as surface grinding, machining of edges, polishing, heat treating, or similar specifications should be kept to a minimum.  Only employ these operations when they are important to the overall function of the tool; otherwise these operations will only add cost, not quality to the tool. December 2, 2015Nageswara Rao Posinasetti42 Tool Drawings
  • 43.  Apply tolerances realistically. Overly tight tolerances can add a great deal of additional cost with little or no added value to the tool.  The function of the detail should determine the specific tolerance, not a standard title block tolerance value. December 2, 2015Nageswara Rao Posinasetti43 Tool Drawings
  • 44.  Layout the part in an identifying color (red is suggested).  Layout any cutting tools. Possible interference or other confining items should be indicated in another identifying color (blue suggested). Use of the cutting tool should not damage the machine or the fixture. December 2, 2015Nageswara Rao Posinasetti44 Tooling Layout
  • 45.  Indicate all locating requirements for the part. There are three locating planes: use three points in one, two points in the second, and only one point in the third plane.  This is called the 3-2-1 locate system. Do not locate on the parting line of castings or forgings. All locators must be accessible for simple cleaning of chips and dirt. December 2, 2015Nageswara Rao Posinasetti45 Tooling Layout
  • 46.  Indicate all clamping requirements for the part.  Be careful to avoid marking or deforming finished or delicate surfaces.  Consider the clamping movements of the operator so injury to the hands or unsafe situations are eliminated.  Be sure it is possible to load and unload the part. December 2, 2015Nageswara Rao Posinasetti46 Tooling Layout
  • 47.  Layout the details with due considerations to stock sizes, so as to minimize machining requirements.  Use full scale in the layout if possible.  Indicate the use of standard fixture parts (shelf items) whenever possible. December 2, 2015Nageswara Rao Posinasetti47 Tooling Layout
  • 48.  Identify each different item or detail of any design by the use of balloons with leaders and arrows pointing to the detail in the view that best shows the outline of the item. These should not go to a line that is common to other details. December 2, 2015Nageswara Rao Posinasetti48 Tooling Layout
  • 49.  Safety should be designed into the tooling.  Cutting should never be performed against a clamp, because of vibration and tool chatter. Instead, parts should be nested against pins in order to take the cutter load.  Rigidity and fool proofing should always be built into the tooling. December 2, 2015Nageswara Rao Posinasetti49 Safety as Related to Tool Design
  • 50.  Make drill jigs large enough to hold without the danger of spinning.  Small drill jigs should always be clamped in a vise or against a bar or backstop.  Install plexiglass guards around all milling and fIycutting operations where chips endanger workers or work areas. December 2, 2015Nageswara Rao Posinasetti50 Safety as Related to Tool Design