2. In which of the following processes is training provided to the team?
A. Plan Resource Management
B. Acquire Resources
C. Develop Team
D. Manage Team
HINT: Which process involves training?
QUESTION:
3. The correct answer is C.
Training is conducted in the Develop Team process to improve individual competencies in
order to increase the probability that project team members can successfully complete
their project work. Training can take various forms. It may be formal or informal. It may be
delivered online, in a classroom, through mentoring, via on the job training, to name but a
few methods.
ANSWER: