CAMP Exam
Sample Q & A
In which of the following processes will training plans be developed and executed?
A. Plan Resource Management and Acquire Resources
B. Plan Resource Management and Develop Team
C. Develop Team
D. Acquire Resources and Manage Team
HINT: Which process involves training?
QUESTION:
All our questions are updated to the latest A Guide to the Project Management Body of Knowledge
(PMBOK® Guide) standard.
Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.
ANSWER:
The correct answer is C.
As a part of developing a project team, observation and conversation, and project
performance appraisals are techniques used to discover additional training
requirements and to develop individual training plans to optimize the team's
performance. Training is conducted in the Develop Team process to improve
individual competencies in order to increase the probability that project team
members can successfully complete their project work. While Acquire Resources is
to obtain necessary human resources for the project, it does not deal with planning
and executing additional training.

Free CAPM Exam Sample Q & A

  • 1.
  • 2.
    In which ofthe following processes will training plans be developed and executed? A. Plan Resource Management and Acquire Resources B. Plan Resource Management and Develop Team C. Develop Team D. Acquire Resources and Manage Team HINT: Which process involves training? QUESTION:
  • 3.
    All our questionsare updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard. Stop by at free.pm-exam-simulator.com/ and try the PM Exam Simulator free for 7 days.
  • 4.
    ANSWER: The correct answeris C. As a part of developing a project team, observation and conversation, and project performance appraisals are techniques used to discover additional training requirements and to develop individual training plans to optimize the team's performance. Training is conducted in the Develop Team process to improve individual competencies in order to increase the probability that project team members can successfully complete their project work. While Acquire Resources is to obtain necessary human resources for the project, it does not deal with planning and executing additional training.