SlideShare a Scribd company logo
1 of 2
Download to read offline
Analyse Solve Construct
Recycle Manufacture Blend
“A temporary alignment plus a
staged paving sequence allowed
for 95% of surfacing to completed
in one sequence, minimizing joins.
Tandem paving eliminated any
longitudinal joins.”
The Tatuanui junction has heavy traffic loadings with B
Train trucks travelling day and night en-route between
Auckland and Rotorua/Taupo. The existing intersection
was a staggered “T” which often caused significant
queuing, poor driving decisions and resulted in a high
accident rate. The eastbound and westbound traffic often
delayed northbound and southbound traffic causing
frustration and erratic movements. The construction of a
new roundabout has improved both traffic flow and safety
to this section of the state highway network.
Client New Zealand Transport Agency
Consultant AECOM
Principal Contractor J Swap Contractors Limited
State Highway 26/27 Tatuanui
Roundabout and Passing Lane
– constructing an intersection that will withstand
high volume, heavy and oversized traffic loads
www.asphaltproducts.co.nz
www.blacktop.co.nz
The project team developed a sequencing
plan; the resulting staging of works critical
in maintaining the flow of traffic on the
state highway, and reducing the project’s
impact on the railway line.
An innovative methodology was developed to address the
high stress and loadings on the pavement and proportion
of heavy commercial vehicles through the intersection.
A ‘Hi-Lab” pavement base was constructed comprising
a cement stabilized basecpurse designed for the project.
To further strengthen the pavement a durable multi-layer
AC14 NAS (with a HPSV) surface course was constructed.
This was developed as an alternative to using Stone Mastic
Asphalt (SMA) which had demonstrated limited surface life
on other similarly trafficked roundabouts.
The AC 14 design was devised with a 14mm stone, Grade
3/5 chip and PAP. It is a denser graded mix, impervious
compared to SMA, and has greater strength and service life
in situations such as this. The denser mix design has the
advantage of being less prone to oxidation of bitumen, and
exhibiting stronger resistance to shear stresses under heavy
traffic. This is expected to translate to a design life of 20 –
25 years as opposed to 8 – 10 years with SMA.
Asphaltic paving was completed in two lifts, to achieve
structural strength and improved surface ride quality –
one 40mm layer of AC 14 NAS followed by a second
35mm AC20 NAS was used beside the railway lines to
accommodate loadings and vibrations from rail operations.
The paving sequence developed ensured there were minimal
surface joints. This was very important due to the heavy and
light turning nature of traffic loading on the roundabout.
Traffic volumes 10,000 vehicles per day
Asphalt cartage time to site 75 minutes
Asphalt lay rate 30 tonnes per hour
Mix Design
40mm layer of AC14 NAS
35mm layer of AC 14 NAS
There were multiple constraints with the project sequencing.
Advanced planning was required for asphalt manufacture
and transportation; a 75 minute cartage time to the site
had to be factored in. Blacktop Construction drew up a
detailed batching and cartage schedule to establish a set
and predictable delivery of product to the site. This allowed
consistent operation of paving and compaction plant on site,
improving ride and joint quality throughout.
The resultant finished ride was exceptional, and with the
project constructed within an accelerated timeframe, this
earned the project an overall PACE scores of 84/100.
Railw
ay
Lines
A
D
E
F
CB
A
BLACKTOPGROUPBLACKTOPGROUP
“A ‘customer first’ approach
was adopted to ensure traffic
on this critical route flowed and
experienced minimal delays.”
A Day 1 AC 14NAS/40mm
B Day 1a
AC 20NAS
variable thickness
C Day 2a
AC 20NAS
variable thickness
D
Day2 AC 14NAS/40mm
Day 3 AC 14NAS/35mm
E
Day 1 AC 14NAS/40mm
Day 3 AC 14NAS/35mm
F
Day 4 AC 14NAS/40mm
Day 4a AC 14NAS/50mm
NOTE
1	 Day 1 = Paved 1st layer (40mm AC 14NAS)
1a	 Day 1 = Paved AC 20NAS (Variable Depth)
2a	 Day 2 = Paved AC 20NAS (Variable Depth)
2	 Day 2 = Paved 1st layer (40mm AC 14NAS)
3	 Day 3 = Paved final layer (35mm AC 14NAS)
4	 Day 4 = Paved 1st layer (40mm AC 14NAS)
4a	 Day 4 = Final layer at last stage

More Related Content

What's hot

King Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 PresentationKing Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 Presentationguest2d44ee
 
Cc channel lining aberdeen western peripheral route - transport scotland (1)
Cc channel lining   aberdeen western peripheral route - transport scotland (1)Cc channel lining   aberdeen western peripheral route - transport scotland (1)
Cc channel lining aberdeen western peripheral route - transport scotland (1)Oscar044
 
Cargo Talk JUNE -2015 Low res 22
Cargo Talk JUNE -2015 Low res 22Cargo Talk JUNE -2015 Low res 22
Cargo Talk JUNE -2015 Low res 22Abeer Ray
 
alsafi_ahmad_visualcv_resume
alsafi_ahmad_visualcv_resumealsafi_ahmad_visualcv_resume
alsafi_ahmad_visualcv_resumealsafi ahmed
 
Présentation1 Linked In english ind B
Présentation1 Linked In english ind BPrésentation1 Linked In english ind B
Présentation1 Linked In english ind BJean-Claude Rodet
 
Highway engineering - history
Highway engineering - history Highway engineering - history
Highway engineering - history Shyam P S
 
8th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 20158th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 2015City Brandon
 
MSc project supervision list
MSc project supervision listMSc project supervision list
MSc project supervision listLucy Philip
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationCrosstown TO
 
Rm 3 Assembly transportation committee project list
Rm 3 Assembly transportation committee project list Rm 3 Assembly transportation committee project list
Rm 3 Assembly transportation committee project list Adina Levin
 
4 mining road designconstrucion&m cm 2011 thompson sa
4 mining road designconstrucion&m cm 2011 thompson sa4 mining road designconstrucion&m cm 2011 thompson sa
4 mining road designconstrucion&m cm 2011 thompson saSierra Francisco Justo
 

What's hot (20)

King Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 PresentationKing Abdullah Road 4 12 07 Presentation
King Abdullah Road 4 12 07 Presentation
 
Cc channel lining aberdeen western peripheral route - transport scotland (1)
Cc channel lining   aberdeen western peripheral route - transport scotland (1)Cc channel lining   aberdeen western peripheral route - transport scotland (1)
Cc channel lining aberdeen western peripheral route - transport scotland (1)
 
Woden Bus Interchange Progress report - ACTED
Woden Bus Interchange Progress report - ACTEDWoden Bus Interchange Progress report - ACTED
Woden Bus Interchange Progress report - ACTED
 
ScottA new resume 2017
ScottA new resume 2017ScottA new resume 2017
ScottA new resume 2017
 
Do 022 s2011
Do 022 s2011Do 022 s2011
Do 022 s2011
 
Cargo Talk JUNE -2015 Low res 22
Cargo Talk JUNE -2015 Low res 22Cargo Talk JUNE -2015 Low res 22
Cargo Talk JUNE -2015 Low res 22
 
3. Railway Strategies - July 2012
3. Railway Strategies - July 20123. Railway Strategies - July 2012
3. Railway Strategies - July 2012
 
alsafi_ahmad_visualcv_resume
alsafi_ahmad_visualcv_resumealsafi_ahmad_visualcv_resume
alsafi_ahmad_visualcv_resume
 
Présentation1 Linked In english ind B
Présentation1 Linked In english ind BPrésentation1 Linked In english ind B
Présentation1 Linked In english ind B
 
Highway engineering - history
Highway engineering - history Highway engineering - history
Highway engineering - history
 
2000_Charleston_cement
2000_Charleston_cement2000_Charleston_cement
2000_Charleston_cement
 
8th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 20158th Street Bridge Community Information Session November 19th, 2015
8th Street Bridge Community Information Session November 19th, 2015
 
Spotlight 1Astander
Spotlight 1AstanderSpotlight 1Astander
Spotlight 1Astander
 
Aruwakkalu Limestone Quarry
Aruwakkalu Limestone QuarryAruwakkalu Limestone Quarry
Aruwakkalu Limestone Quarry
 
LRTP Freight Projects, October 22, 2014
LRTP Freight Projects, October 22, 2014LRTP Freight Projects, October 22, 2014
LRTP Freight Projects, October 22, 2014
 
MSc project supervision list
MSc project supervision listMSc project supervision list
MSc project supervision list
 
14.30 tarek shuaib, pace
14.30 tarek shuaib, pace14.30 tarek shuaib, pace
14.30 tarek shuaib, pace
 
Kennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting PresentationKennedy Station Design Update Meeting Presentation
Kennedy Station Design Update Meeting Presentation
 
Rm 3 Assembly transportation committee project list
Rm 3 Assembly transportation committee project list Rm 3 Assembly transportation committee project list
Rm 3 Assembly transportation committee project list
 
4 mining road designconstrucion&m cm 2011 thompson sa
4 mining road designconstrucion&m cm 2011 thompson sa4 mining road designconstrucion&m cm 2011 thompson sa
4 mining road designconstrucion&m cm 2011 thompson sa
 

Similar to BT_TatuanuiCaseStudy_F

Milestone Smart Choices
Milestone Smart ChoicesMilestone Smart Choices
Milestone Smart Choicescoreycarr
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Runway resurfacing and repairing using modern materials and
Runway resurfacing and repairing using modern materials andRunway resurfacing and repairing using modern materials and
Runway resurfacing and repairing using modern materials andAglaia Connect
 
Viapont® - Lightened asphalt concrete
Viapont® - Lightened asphalt concreteViapont® - Lightened asphalt concrete
Viapont® - Lightened asphalt concreteEurovia_Group
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportBeing Deepak
 
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdf
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdfASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdf
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdfHaddushGebremedhin
 
Pipeline - MIT.ppt for pipeline engineering
Pipeline - MIT.ppt for pipeline engineeringPipeline - MIT.ppt for pipeline engineering
Pipeline - MIT.ppt for pipeline engineeringTauqueerAhmad17
 
12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LR12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LRAndrew de Villiers
 
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_20142014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014Wendy Ling
 
New ppt on road construction
New ppt on road construction New ppt on road construction
New ppt on road construction Kuldeep317348
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking pptPatel Tapan
 
Armoured Ford - Low Water Stream Crossing
Armoured Ford - Low Water Stream CrossingArmoured Ford - Low Water Stream Crossing
Armoured Ford - Low Water Stream CrossingEric Lestock Kay
 
Rsta road surface treatments handbook v23
Rsta road surface treatments handbook v23Rsta road surface treatments handbook v23
Rsta road surface treatments handbook v23Ken Bigjonhson
 

Similar to BT_TatuanuiCaseStudy_F (20)

2022 Long-life asphalt pavement at Caltrans
2022 Long-life asphalt pavement at Caltrans2022 Long-life asphalt pavement at Caltrans
2022 Long-life asphalt pavement at Caltrans
 
Milestone Smart Choices
Milestone Smart ChoicesMilestone Smart Choices
Milestone Smart Choices
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Highway network system
Highway network system Highway network system
Highway network system
 
Runway resurfacing and repairing using modern materials and
Runway resurfacing and repairing using modern materials andRunway resurfacing and repairing using modern materials and
Runway resurfacing and repairing using modern materials and
 
Roadstab 2017
Roadstab 2017Roadstab 2017
Roadstab 2017
 
PPT FINAL.pptx
PPT FINAL.pptxPPT FINAL.pptx
PPT FINAL.pptx
 
Presentation
PresentationPresentation
Presentation
 
Viapont® - Lightened asphalt concrete
Viapont® - Lightened asphalt concreteViapont® - Lightened asphalt concrete
Viapont® - Lightened asphalt concrete
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar report
 
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdf
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdfASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdf
ASQ_QC_CIVILENG_GP6_DMIAC_ROAD_CRACK.pdf
 
Pipeline - MIT.ppt for pipeline engineering
Pipeline - MIT.ppt for pipeline engineeringPipeline - MIT.ppt for pipeline engineering
Pipeline - MIT.ppt for pipeline engineering
 
12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LR12632_CSAsphalt_Enfield_Terminal_LR
12632_CSAsphalt_Enfield_Terminal_LR
 
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_20142014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014
 
Bituminous Road
 Bituminous Road Bituminous Road
Bituminous Road
 
New ppt on road construction
New ppt on road construction New ppt on road construction
New ppt on road construction
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Level crossings tech note august 2017
Level crossings tech note august 2017Level crossings tech note august 2017
Level crossings tech note august 2017
 
Armoured Ford - Low Water Stream Crossing
Armoured Ford - Low Water Stream CrossingArmoured Ford - Low Water Stream Crossing
Armoured Ford - Low Water Stream Crossing
 
Rsta road surface treatments handbook v23
Rsta road surface treatments handbook v23Rsta road surface treatments handbook v23
Rsta road surface treatments handbook v23
 

BT_TatuanuiCaseStudy_F

  • 1. Analyse Solve Construct Recycle Manufacture Blend “A temporary alignment plus a staged paving sequence allowed for 95% of surfacing to completed in one sequence, minimizing joins. Tandem paving eliminated any longitudinal joins.” The Tatuanui junction has heavy traffic loadings with B Train trucks travelling day and night en-route between Auckland and Rotorua/Taupo. The existing intersection was a staggered “T” which often caused significant queuing, poor driving decisions and resulted in a high accident rate. The eastbound and westbound traffic often delayed northbound and southbound traffic causing frustration and erratic movements. The construction of a new roundabout has improved both traffic flow and safety to this section of the state highway network. Client New Zealand Transport Agency Consultant AECOM Principal Contractor J Swap Contractors Limited State Highway 26/27 Tatuanui Roundabout and Passing Lane – constructing an intersection that will withstand high volume, heavy and oversized traffic loads www.asphaltproducts.co.nz www.blacktop.co.nz
  • 2. The project team developed a sequencing plan; the resulting staging of works critical in maintaining the flow of traffic on the state highway, and reducing the project’s impact on the railway line. An innovative methodology was developed to address the high stress and loadings on the pavement and proportion of heavy commercial vehicles through the intersection. A ‘Hi-Lab” pavement base was constructed comprising a cement stabilized basecpurse designed for the project. To further strengthen the pavement a durable multi-layer AC14 NAS (with a HPSV) surface course was constructed. This was developed as an alternative to using Stone Mastic Asphalt (SMA) which had demonstrated limited surface life on other similarly trafficked roundabouts. The AC 14 design was devised with a 14mm stone, Grade 3/5 chip and PAP. It is a denser graded mix, impervious compared to SMA, and has greater strength and service life in situations such as this. The denser mix design has the advantage of being less prone to oxidation of bitumen, and exhibiting stronger resistance to shear stresses under heavy traffic. This is expected to translate to a design life of 20 – 25 years as opposed to 8 – 10 years with SMA. Asphaltic paving was completed in two lifts, to achieve structural strength and improved surface ride quality – one 40mm layer of AC 14 NAS followed by a second 35mm AC20 NAS was used beside the railway lines to accommodate loadings and vibrations from rail operations. The paving sequence developed ensured there were minimal surface joints. This was very important due to the heavy and light turning nature of traffic loading on the roundabout. Traffic volumes 10,000 vehicles per day Asphalt cartage time to site 75 minutes Asphalt lay rate 30 tonnes per hour Mix Design 40mm layer of AC14 NAS 35mm layer of AC 14 NAS There were multiple constraints with the project sequencing. Advanced planning was required for asphalt manufacture and transportation; a 75 minute cartage time to the site had to be factored in. Blacktop Construction drew up a detailed batching and cartage schedule to establish a set and predictable delivery of product to the site. This allowed consistent operation of paving and compaction plant on site, improving ride and joint quality throughout. The resultant finished ride was exceptional, and with the project constructed within an accelerated timeframe, this earned the project an overall PACE scores of 84/100. Railw ay Lines A D E F CB A BLACKTOPGROUPBLACKTOPGROUP “A ‘customer first’ approach was adopted to ensure traffic on this critical route flowed and experienced minimal delays.” A Day 1 AC 14NAS/40mm B Day 1a AC 20NAS variable thickness C Day 2a AC 20NAS variable thickness D Day2 AC 14NAS/40mm Day 3 AC 14NAS/35mm E Day 1 AC 14NAS/40mm Day 3 AC 14NAS/35mm F Day 4 AC 14NAS/40mm Day 4a AC 14NAS/50mm NOTE 1 Day 1 = Paved 1st layer (40mm AC 14NAS) 1a Day 1 = Paved AC 20NAS (Variable Depth) 2a Day 2 = Paved AC 20NAS (Variable Depth) 2 Day 2 = Paved 1st layer (40mm AC 14NAS) 3 Day 3 = Paved final layer (35mm AC 14NAS) 4 Day 4 = Paved 1st layer (40mm AC 14NAS) 4a Day 4 = Final layer at last stage