OLIVER MASSMANN - Partner, General Director
DUANE MORRIS VIETNAM LLC
INVESTING IN SOLAR ENERGY IN VIETNAM
How to do it right?
*
www.duanemorris.com
AGENDA
• POTENTIAL OF SOLAR ENERGY INDUSTRY
IN VIETNAM
• GOVERNMENT’S POLICY ON RENEWABLE
(SOLAR) ENERGY
• MARKET ACCESS FOR FOREIGN INVESTORS
• OPPORTUNITIES FOR INTERNATIONAL
DEVELOPERS
• RECOMMENDATIONS
*
www.duanemorris.com
Energy Sector Background
• Electricity consumption grew by an average of 14% annually
during 2004–2010, compared with 7% economic growth rate
per year during that period
• Electricity demand is expected to increase by up to 14.2 pct.
annually for the 2011-2015 period, 11.4 pct. for the 2016-
2020 period and 7 times to 800 billion Kwh in 2030
• Electricity consumption is projected to increase from 85,932
gigawatt hours (GWh) in 2010 to 251,763 GWh in 2020
• By end of 2014, The Vietnamese solar power market is still
relatively small with only around 4.5 MW installed capacity.
*
www.duanemorris.com
POTENTIAL OF SOLAR ENERGY INDUSTRY
IN VIETNAM
• Total number of sunshine hours up to 1400 – 3000
hours/year
• The average total radiation amounts to 230 – 250
kcal/cm2, and strengthens towards the south.
• Solar energy can be used for water boiling, power
production and other purposes, as e.g. drying, cooking
etc.
*
www.duanemorris.com
GOVERNMENT’S POLICY ON RENEWABLE
(SOLAR) ENERGY
• Viet Nam currently does not have a full-fledged legal
framework on renewable energy, especially solar energy
investment.
• Amended National Master Plan VII
• Decision No. 2068/QD-TTg specifically on development
plan for renewable energy (biomass, wind, and solar energy)
until 2030 and with a vision to 2050
• Draft Decision on supporting regime for solar power projects
to be adopted in the next 1-2 months
*
www.duanemorris.com
Clean energy policy reform – The dynamic process
*
• PROVINCIAL
• GOVTS
BLOCK
COAL/ BIG
HYDRO
• LOCAL
SOURCING/
• MANUFACTU
RING OF
EQUIPMENT
• LOCAL
POLLUTION
HEALTH/
SOCIAL
IMPACT AND
DISHARMON
Y
• SOE +
GoVN
• MARK
ET
• CONTR
OL
• ENERG
Y
INFLAT
ION
CONCE
RNS
• STA
TE/E
VN
• CAPI
TAL
• SCA
RCIT
Y
• ENER
GY
SUPP
LY
• SPEE
D OF
• GRO
WTH
Climate
Change
Commitments
International
Trade
Agreements
PRICE + SUPPLY CAPACITY = SPEED
SPEED + SUPPLY CAPACITY = PRICE
Key to the Dynagram
Arrows
• Direction Weakening/Growing Impact on
Policy Reform to Clean Energy
• Width Extent of Impact
Box /Circles
•Colour Green Dynamic Force For Change
Red Barriers to Change
Grey Circles No Force for Change
Donor Soft
Loans / Grants
• CAPEX-
FUELLE
D
CORRUP
TION
• POWER
CONSUMER
S DEMAND
GREEN
www.duanemorris.com
Amended Power Master Plan VII on the development
of electricity in Vietnam
• Revised National power development plan for 2011-2020 period with the vision to 2030
approved by the PM under his Decision No. 428/QD-TTg dated 18 March 2016
• Amended Master Plan VII focuses on energy security, energy efficiency, renewable
energy development and power market liberalization
• Objectives:
– To increase the aggregate output of imported and produced electricity to 235-245
billion kWh by 2020; 352 – 379 billion kWh by 2025 and 506 – 559 billion kWh by
2030
– To prioritize to develop renewable energy generation so that the proportion of
electricity generation of renewable energy will be increased from the present 3.5% of
the total electricity production to 7% in 2020 and 10% in 2030
– To promote the rural electrification program so that most of the rural households
will have access to the electricity by 2020
– To build flexible operation of electricity grid, high automation of the transmission to
distribution process, development of substations with no requirement for operating
personnel.
www.duanemorris.com
Amended Power Master Plan VII
• Strategies:
– Higher quality of electricity supply and more reasonable electricity price
– Diversification of domestic resources for power generation
– Developing new renewable power sources and updating technologies used in
existing plants
– Diversification of investment sources to overcome the lack of financial and technical
resources and also to improve economic efficiency
• Investment capital demand:
– Approximately USD 40 billion up to 2020: Two-thirds for power generation
development and one-third for power network development
– Approximately USD 108 billion for the period from 2021 to 2030: 74% for power
generation development and 26% for power network development
*
www.duanemorris.com
Amended Power Master Plan VII
• State to keep monopoly on transmission
• Prioritize development of renewable energy
• Renewable energy target rate at 7 pct. of total energy
output by 2020 and more than 10 pct. by 2030.
• Increase the solar power output to 850 MW by 2020,
4,000 MW in 2025 and 12,000 MW in 2030.
*
www.duanemorris.com
Vietnam’s electrical energy mix
• Vietnam policy emphasises the need to diversify the country’s
energy mix whilst maximising the use of local energy reserves
• Currently Vietnam is developing an energy mix sector with
the mainstay of coal fired power
*
www.duanemorris.com
Capacity additions each year to 2030
*
www.duanemorris.com
Cumulative capacity to 2030
*
www.duanemorris.com
DRAFT DECISION ON SUPPORTING REGIME
FOR SOLAR POWER PROJECTS
• EVN has to purchase electricity from on-grid solar energy projects at
VAT-excluded price of 11.2 US cents/kWh
• For on-grid rooftop solar projects,  the rate will be 18 UScents/ kWh
• The rate in VND will be indicated in the final Decision based on the
USD/VND exchange rate at that time and the MOIT will issue an
Official Letter every year to adjust the rate in VND according to the
fluctuation in the exchange rate.
• Rooftop solar projects of less than 50kW will not have to connect to
the grid. For those of more than 50kW, connection to the grid is
required and an electricity operating permit must be obtained.
• Term of solar energy PPAs: 20 years (renewable)
*
www.duanemorris.com
ENERGY RETAIL PRICES
• Circular 12/2014/TT-BCT:
– 7-10% increase with MOIT approval
– More than 10% requires PM approval
– EVN can decide independently for less than 7%
increases?
• Energy retail prices are expected to increase  Raise FiT
• It is unofficially known that the MOIT proposed to the
Government to approve for an FIT increase of up to
11.2 UScents/kwh to make the solar energy projects
become more financially feasible.*
www.duanemorris.com
Market access and Forms of investment
• No foreign ownership restriction
• Investment forms:
ü A wholly-owned foreign enterprise
ü A joint venture company between a foreign investor and domestic investor
ü Investment pursuant to the BOT legal framework (which includes establishment
of a project entity in the form of a wholly-owned foreign enterprise by way of a
BOT contract with the MOIT which is implemented through a wholly-owned
foreign enterprise; or a joint venture company by way of a BOT contract with
the MOIT which is implemented through a joint venture with a Vietnamese
entity (usually including EVN, but it is also possible with a private domestic
IPP)
ü Through the purchase of shares in either an EVN subsidiary being or having
been equitized or a private IPP holding power assets. investment in the form of
establishment of a new company can be undertaken in one or more of the
following ways.*
www.duanemorris.com
BOT – BEST INVESTMENT FORM
• Government’s Decree No. 15/2015/ND-CP on Public-
Private Partnership: making projects more bankable
• Easier to negotiate more favorable electricity rates.
• Easier to obtain more government guarantees, especially
in terms of EVN’s obligations to purchase all electricity
from the project.
• More fiscal and financial incentives.
• Precedent large-scaled BOT power projects in Vietnam:
Phu My, Vung Ang, Mong Duong 2
*
www.duanemorris.com
INVESTMENT INCENTIVES
• Land: exemption of land rental within 3 years from the operation date of the
project, etc.
• CIT 10%
– 15 years for new enterprises investing in power plant projects
– tax exemptions within 4 years and tax reduction by 50% in the next 9 years.
• Import duty exemption
– on goods imported to create fixed assets of the projects; components, materials and
semi-finished products which are not available at home for the project’s operation.
• Investment capital
– investors could apply for a loan of up to 70% of the total investment capital of their
project with a term of maximum 12 years.
– investors could also enjoy export credit incentives in the form of a loan of up to
85% of the export/ import contract value or L/C value also with a term of
maximum 12 years.
*
www.duanemorris.com
Project planning
• Investors has to obtain prior agreement of EVN on power purchase prior to
licensing procedure.
• Commitment of banks or credit institutions on financing the project must be
obtained prior to issuance of Investment Registration Certificate .
• In-principle approval of the local People’s Committee is required prior to
issuance of Investment Registration Certificate depending on the project size
• A solar power plant must obtain a power generation permit from the competent
State authorities in order to conduct power generation operations in Vietnam
• Term of the permit: maximum 20 years for large power plants with particularly
important meaning on economy, society, national defense and security as per
the list approved by the Prime Minister; and 10 years for other power plants
projects.
• The permit cannot be renewed but the investor may apply for a new one within
60 days prior to the expiry date of the current permit.
*
www.duanemorris.com
Project licensing
• Step 1: The investor obtains approval from the competent authority [e.g., Prime
Minister, MOIT] approving the solar power plant as part of the power
development master plan (if required).
• Step 2: The investor obtains in-principle approval from the competent People’s
Committee (or other competent authorities subject to the details of the project)
approving the solar power plant project, land demand / location, environment,
construction plan, other terms of the project.
• Step 3: Application for issuance of the Investment Registration Certificate and
the Enterprise Registration Certificate
• Step 4: Preparation of construction / operations of the solar power plant (for
example, acquiring land area, site clearance, preparation, land investigation,
conducting environmental assessment)
• Step 5: The project company to obtain necessary permits and relevant
agreements for its and the power plant’s operation.
• Step 6: Construction of solar power plant and operation
*
www.duanemorris.com
Opportunities for international developers
*
www.duanemorris.com
–
*
www.duanemorris.com
EVFTA – Bilateral negotiations
*
Launch of
negotiations
First
round in
Hanoi
15 rounds
alternately
in Vietnam
and
Brussels
Last
round in
Hanoi
Agreement
in
principle
• 06/
201
2
• 1
0
/
2
0
1
2
• H
a
r
d
w
o
r
k
• 7
/
2
0
1
5
• 8
/
2
0
1
5
• 0
2/
1
2/
2
0
1
5
• 0
2
/
0
2
/
2
0
1
6
Conclusion
of
negotiation
FTA text
released
www.duanemorris.com*
www.duanemorris.com*
www.duanemorris.com*
www.duanemorris.com
TPP and AEC intersection
*
Thailand
Malaysia
Brunei
CanadaAustralia
Cambodia
Indonesia Myanmar
Peru
Philippines
Japan
Laos
Mexico New Zealand
Singapore
The United States
Vietnam
Chile
www.duanemorris.com
ASEAN TPP: Market Access Liberalization as
Consequence of TPP
• Indonesia plans to loose restrictions on foreign investment in
nearly 50 sectors, including e-commerce, retail, healthcare,
movie and several other industries
• Indonesia prepares for the so-called “Negative Investment
List”, which provides a greater openness to foreign
investment and gets itself ready for the TPP
• China, Korea, the Philippines, Indonesia and Thailand are
also keen to join the TPP to overcome the disadvantages
*
www.duanemorris.com
Power/ Energy Sector
Level of commitment in Power / Energy sector
*
N/A Low High
www.duanemorris.com
Power/ Energy Sector
• WTO /
AFAS
• EVFTA • TPP
• N/A • Commitments are only
made in 3 sub-sectors
• Vietnam makes
commitments in all sub-
sectors with listed
restrictions (no other
restrictions are permitted).
•  
*
www.duanemorris.com
RECOMMENDATIONS FOR INVESTORS
• Difficult time but opportunities await.
• Public private partnerships (e.g. - BOT) should be the first option.
• Due care on negotiations of the PPA and grid connection agreement with EVN
• Electricity selling in off-grid areas can be a good choice
• Sound financing structure, good business model and great legal assistance are keys
to success.
• Accurate prediction of where the market is heading to, in the context of Vietnam’s
critical power shortage, should be considered.
• More pressure on the government to adequately address key issues on tariff
increase, demonopolization of the power market and government guarantee.
• Vietnam’s market is extremely in need of financing and EPC capability. There are
rooms for cost-effective and high quality EPC contractors and resourceful lenders.
• In many cases, you can “test the water” with a small power plant project.
*
www.duanemorris.com
DUANE MORRIS VIETNAM LLC
Thank you very much!
HANOI OFFICE HO CHI MINH CITY OFFICE
Pacific Place, Unit V1307/08, 13th Floor, Suite 1503/04, Saigon Tower
83B Ly Thuong Kiet, Hoan Kiem District 29 Le Duan Street, District 1
Hanoi, Vietnam Ho Chi Minh City, Vietnam
Tel.: +84 4 39462200 Tel.: +84 8 3824 0240
Fax: +84 4 3946 1311 Fax: +84 8 3824 0241
Contact email:
omassmann@duanemorris.com
*
www.duanemorris.com
References (1)
*
www.duanemorris.com
References (2)
*
www.duanemorris.com
References (3)
*
www.duanemorris.com
References (4)
*

More Related Content

What's hot

What's hot (20)

INVESTING IN RENEWABLE ENERGY SECTOR Solar and Wind power projects – Getting ...
INVESTING IN RENEWABLE ENERGY SECTOR Solar and Wind power projects – Getting ...INVESTING IN RENEWABLE ENERGY SECTOR Solar and Wind power projects – Getting ...
INVESTING IN RENEWABLE ENERGY SECTOR Solar and Wind power projects – Getting ...
 
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – CHALLENGES IN SOLAR PROJECT...
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – CHALLENGES IN SOLAR PROJECT...LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – CHALLENGES IN SOLAR PROJECT...
LAWYER IN VIETNAM DR. OLIVER MASSMANN - VIETNAM – CHALLENGES IN SOLAR PROJECT...
 
Draft Decision on Supporting Regime for Solar Power Projects
Draft Decision on Supporting Regime for Solar Power Projects Draft Decision on Supporting Regime for Solar Power Projects
Draft Decision on Supporting Regime for Solar Power Projects
 
Dr. Oliver Massmann PhD Legal Framework of Coal,Gas,Power and Renewable Energ...
Dr. Oliver Massmann PhD Legal Framework of Coal,Gas,Power and Renewable Energ...Dr. Oliver Massmann PhD Legal Framework of Coal,Gas,Power and Renewable Energ...
Dr. Oliver Massmann PhD Legal Framework of Coal,Gas,Power and Renewable Energ...
 
VIETNAM –SOLAR POWER PROJECTS: HOW TO GET DEALS DONE
VIETNAM –SOLAR POWER PROJECTS: HOW TO GET DEALS DONEVIETNAM –SOLAR POWER PROJECTS: HOW TO GET DEALS DONE
VIETNAM –SOLAR POWER PROJECTS: HOW TO GET DEALS DONE
 
Oliver Massmann - Investing in Solar Energy in Vietnam - How to do it right?
Oliver Massmann - Investing in Solar Energy in Vietnam - How to do it right?Oliver Massmann - Investing in Solar Energy in Vietnam - How to do it right?
Oliver Massmann - Investing in Solar Energy in Vietnam - How to do it right?
 
VIETNAM – WIND AND SOLAR PROJECTS: HOW TO GET DEALS DONE
VIETNAM – WIND AND SOLAR PROJECTS:  HOW TO GET DEALS DONEVIETNAM – WIND AND SOLAR PROJECTS:  HOW TO GET DEALS DONE
VIETNAM – WIND AND SOLAR PROJECTS: HOW TO GET DEALS DONE
 
Lawyer in Vietnam Oliver Massmann Investing in Solar Energy in Vietnam How to...
Lawyer in Vietnam Oliver Massmann Investing in Solar Energy in Vietnam How to...Lawyer in Vietnam Oliver Massmann Investing in Solar Energy in Vietnam How to...
Lawyer in Vietnam Oliver Massmann Investing in Solar Energy in Vietnam How to...
 
Feed in-tariff regulations and getting wind power projects done (en)
Feed in-tariff regulations and getting wind power projects done (en)Feed in-tariff regulations and getting wind power projects done (en)
Feed in-tariff regulations and getting wind power projects done (en)
 
Lawyer in Vietnam Dr. Oliver Massmann - Vietnam - Wind Investment Guide
Lawyer in Vietnam Dr. Oliver Massmann - Vietnam -  Wind Investment GuideLawyer in Vietnam Dr. Oliver Massmann - Vietnam -  Wind Investment Guide
Lawyer in Vietnam Dr. Oliver Massmann - Vietnam - Wind Investment Guide
 
Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...
Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...
Dr Oliver Massmann - A new Era for Vietnam: Investing in Vietnam Solar Power ...
 
Investing in Myanmar under the new Investment Laws
Investing in Myanmar under the new Investment Laws  Investing in Myanmar under the new Investment Laws
Investing in Myanmar under the new Investment Laws
 
M&A in Vietnam: addressing key issues that arise under the enterprise law and...
M&A in Vietnam: addressing key issues that arise under the enterprise law and...M&A in Vietnam: addressing key issues that arise under the enterprise law and...
M&A in Vietnam: addressing key issues that arise under the enterprise law and...
 
VIETNAM – THE LATEST DRAFT DECREE ON PROVISION OF INTERNET SERVICES AND CROSS...
VIETNAM – THE LATEST DRAFT DECREE ON PROVISION OF INTERNET SERVICES AND CROSS...VIETNAM – THE LATEST DRAFT DECREE ON PROVISION OF INTERNET SERVICES AND CROSS...
VIETNAM – THE LATEST DRAFT DECREE ON PROVISION OF INTERNET SERVICES AND CROSS...
 
VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021
VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021
VIETNAM TO IMPLEMENT DIRECT POWER PURCHASE MECHANISM AFTER 2021
 
VIETNAM – THE GOVERNMENT ISSUES FAVORABLE POLICIES ON TAX AND FEES FOR BUSINE...
VIETNAM – THE GOVERNMENT ISSUES FAVORABLE POLICIES ON TAX AND FEES FOR BUSINE...VIETNAM – THE GOVERNMENT ISSUES FAVORABLE POLICIES ON TAX AND FEES FOR BUSINE...
VIETNAM – THE GOVERNMENT ISSUES FAVORABLE POLICIES ON TAX AND FEES FOR BUSINE...
 
Na Presentation Legal And Policy Framework Energy En
Na Presentation Legal And Policy Framework Energy EnNa Presentation Legal And Policy Framework Energy En
Na Presentation Legal And Policy Framework Energy En
 
Vietnam Solar Power Breaking News - New Draft Law on New Feed in Tariffs
Vietnam Solar Power Breaking News - New Draft Law on New Feed in TariffsVietnam Solar Power Breaking News - New Draft Law on New Feed in Tariffs
Vietnam Solar Power Breaking News - New Draft Law on New Feed in Tariffs
 
Lawyer in Vietnam Dr. Oliver Massmann ASEAN CPTPP and EUVNFTA - Amamzing leve...
Lawyer in Vietnam Dr. Oliver Massmann ASEAN CPTPP and EUVNFTA - Amamzing leve...Lawyer in Vietnam Dr. Oliver Massmann ASEAN CPTPP and EUVNFTA - Amamzing leve...
Lawyer in Vietnam Dr. Oliver Massmann ASEAN CPTPP and EUVNFTA - Amamzing leve...
 
Lawyer in Myanmar Dr. Oliver Massmann Investing and Financing Power Projects ...
Lawyer in Myanmar Dr. Oliver Massmann Investing and Financing Power Projects ...Lawyer in Myanmar Dr. Oliver Massmann Investing and Financing Power Projects ...
Lawyer in Myanmar Dr. Oliver Massmann Investing and Financing Power Projects ...
 

Viewers also liked

Công ty chúng tôi tự hào là một dịch vụ chất lượng tiềm năng !
Công ty chúng tôi tự hào là một dịch vụ chất lượng tiềm năng !Công ty chúng tôi tự hào là một dịch vụ chất lượng tiềm năng !
Công ty chúng tôi tự hào là một dịch vụ chất lượng tiềm năng !
Mỹ Hoàng
 

Viewers also liked (19)

Recommendation of Excellence Services of Mr. Oliver Massmann - Sopec
Recommendation of Excellence Services of Mr. Oliver Massmann - SopecRecommendation of Excellence Services of Mr. Oliver Massmann - Sopec
Recommendation of Excellence Services of Mr. Oliver Massmann - Sopec
 
Lawyer in Vietnam Oliver Massmann EU Vietnam Free Trade Agreement Effect on S...
Lawyer in Vietnam Oliver Massmann EU Vietnam Free Trade Agreement Effect on S...Lawyer in Vietnam Oliver Massmann EU Vietnam Free Trade Agreement Effect on S...
Lawyer in Vietnam Oliver Massmann EU Vietnam Free Trade Agreement Effect on S...
 
Vietnam_ The most Important Clause in Any Commercial Contract in Vietnam - Ge...
Vietnam_ The most Important Clause in Any Commercial Contract in Vietnam - Ge...Vietnam_ The most Important Clause in Any Commercial Contract in Vietnam - Ge...
Vietnam_ The most Important Clause in Any Commercial Contract in Vietnam - Ge...
 
LUẬT SƯ OLIVER MASSMANN PHÁT BIỂU TRƯỚC CÁC ĐẠI BIỂU QUỐC HỘI VIỆT NAM VỀ HIỆ...
LUẬT SƯ OLIVER MASSMANN PHÁT BIỂU TRƯỚC CÁC ĐẠI BIỂU QUỐC HỘI VIỆT NAM VỀ HIỆ...LUẬT SƯ OLIVER MASSMANN PHÁT BIỂU TRƯỚC CÁC ĐẠI BIỂU QUỐC HỘI VIỆT NAM VỀ HIỆ...
LUẬT SƯ OLIVER MASSMANN PHÁT BIỂU TRƯỚC CÁC ĐẠI BIỂU QUỐC HỘI VIỆT NAM VỀ HIỆ...
 
VIETNAM CASINO BUSINESS BREAKING NEWS - THE LAW IS ISSUED – VIETNAMESE CAN G...
VIETNAM CASINO BUSINESS BREAKING NEWS  - THE LAW IS ISSUED – VIETNAMESE CAN G...VIETNAM CASINO BUSINESS BREAKING NEWS  - THE LAW IS ISSUED – VIETNAMESE CAN G...
VIETNAM CASINO BUSINESS BREAKING NEWS - THE LAW IS ISSUED – VIETNAMESE CAN G...
 
VIETNAM’S BUSINESS ENVIRONMENT - Investment opportunities and challenges for...
VIETNAM’S BUSINESS ENVIRONMENT - Investment opportunities and challenges for...VIETNAM’S BUSINESS ENVIRONMENT - Investment opportunities and challenges for...
VIETNAM’S BUSINESS ENVIRONMENT - Investment opportunities and challenges for...
 
Stephanie Carretero: DigComp: Marco Europeo de Competencias Digitales para la...
Stephanie Carretero: DigComp: Marco Europeo de Competencias Digitales para la...Stephanie Carretero: DigComp: Marco Europeo de Competencias Digitales para la...
Stephanie Carretero: DigComp: Marco Europeo de Competencias Digitales para la...
 
Lawyer in Vietnam Oliver Massmann Flat World Opportunities for Vietnamese Ent...
Lawyer in Vietnam Oliver Massmann Flat World Opportunities for Vietnamese Ent...Lawyer in Vietnam Oliver Massmann Flat World Opportunities for Vietnamese Ent...
Lawyer in Vietnam Oliver Massmann Flat World Opportunities for Vietnamese Ent...
 
Công ty chúng tôi tự hào là một dịch vụ chất lượng tiềm năng !
Công ty chúng tôi tự hào là một dịch vụ chất lượng tiềm năng !Công ty chúng tôi tự hào là một dịch vụ chất lượng tiềm năng !
Công ty chúng tôi tự hào là một dịch vụ chất lượng tiềm năng !
 
Minh Le | DOE Solar Program
Minh Le | DOE Solar ProgramMinh Le | DOE Solar Program
Minh Le | DOE Solar Program
 
HOW CAN EUROPEAN BUSINESSES BENEFIT FROM THE EU- VIETNAM FREE TRADE AGREEMENT?
HOW CAN EUROPEAN BUSINESSES BENEFIT FROM THE EU- VIETNAM FREE TRADE AGREEMENT? HOW CAN EUROPEAN BUSINESSES BENEFIT FROM THE EU- VIETNAM FREE TRADE AGREEMENT?
HOW CAN EUROPEAN BUSINESSES BENEFIT FROM THE EU- VIETNAM FREE TRADE AGREEMENT?
 
Rechtsanwalt in Vietnam Oliver Massmann – AKTUELLE HANDELSABKOMMEN –TPP, EVFT...
Rechtsanwalt in Vietnam Oliver Massmann – AKTUELLE HANDELSABKOMMEN –TPP, EVFT...Rechtsanwalt in Vietnam Oliver Massmann – AKTUELLE HANDELSABKOMMEN –TPP, EVFT...
Rechtsanwalt in Vietnam Oliver Massmann – AKTUELLE HANDELSABKOMMEN –TPP, EVFT...
 
Don't leave money on the table - Get the most our of your licensed property
Don't leave money on the table - Get the most our of your licensed propertyDon't leave money on the table - Get the most our of your licensed property
Don't leave money on the table - Get the most our of your licensed property
 
Solar Power Project (45 MW): Bulgarian Electricity Market Study
Solar Power Project (45 MW): Bulgarian Electricity Market  Study  Solar Power Project (45 MW): Bulgarian Electricity Market  Study
Solar Power Project (45 MW): Bulgarian Electricity Market Study
 
Tài liệu đào tạo quy trình bán hàng
Tài liệu đào tạo quy trình bán hàngTài liệu đào tạo quy trình bán hàng
Tài liệu đào tạo quy trình bán hàng
 
Solar power project
Solar power projectSolar power project
Solar power project
 
Quản lý chung cư - PMC
Quản lý chung cư - PMCQuản lý chung cư - PMC
Quản lý chung cư - PMC
 
Lawyer in Vietnam Oliver Massmann TPP and EUVN FTA Rules of Origin Analysis
Lawyer in Vietnam Oliver Massmann TPP and EUVN FTA Rules of Origin AnalysisLawyer in Vietnam Oliver Massmann TPP and EUVN FTA Rules of Origin Analysis
Lawyer in Vietnam Oliver Massmann TPP and EUVN FTA Rules of Origin Analysis
 
The Potential for Energy Efficiency in Multifamily Housing (Pies for Pi Day)
The Potential for Energy Efficiency in Multifamily Housing (Pies for Pi Day)The Potential for Energy Efficiency in Multifamily Housing (Pies for Pi Day)
The Potential for Energy Efficiency in Multifamily Housing (Pies for Pi Day)
 

Similar to Lawyer in Vietnam Oliver Massmann - Investing in Solar Energy - How To Do It Right

Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort
Priyank Jain
 
On-the-Ground Challenges and Opportunities in Solar Implementation
On-the-Ground Challenges and Opportunities in Solar ImplementationOn-the-Ground Challenges and Opportunities in Solar Implementation
On-the-Ground Challenges and Opportunities in Solar Implementation
Frederick Heinle
 

Similar to Lawyer in Vietnam Oliver Massmann - Investing in Solar Energy - How To Do It Right (20)

VIETNAM’S SOLAR MARKET – MARKET STATUS, POTENTIAL AND KEY TO SUCCESSFUL PROJECTS
VIETNAM’S SOLAR MARKET – MARKET STATUS, POTENTIAL AND KEY TO SUCCESSFUL PROJECTSVIETNAM’S SOLAR MARKET – MARKET STATUS, POTENTIAL AND KEY TO SUCCESSFUL PROJECTS
VIETNAM’S SOLAR MARKET – MARKET STATUS, POTENTIAL AND KEY TO SUCCESSFUL PROJECTS
 
VIETNAM - ONSHORE AND OFFSHORE WIND ENERGY PROJECTS - GETTING DEALS DONE
VIETNAM - ONSHORE AND OFFSHORE WIND ENERGY PROJECTS - GETTING DEALS DONEVIETNAM - ONSHORE AND OFFSHORE WIND ENERGY PROJECTS - GETTING DEALS DONE
VIETNAM - ONSHORE AND OFFSHORE WIND ENERGY PROJECTS - GETTING DEALS DONE
 
Dr. Oliver Massmann - Future Energy of Vietnam - Opportunities and Challenges
Dr. Oliver Massmann - Future Energy of Vietnam - Opportunities and Challenges Dr. Oliver Massmann - Future Energy of Vietnam - Opportunities and Challenges
Dr. Oliver Massmann - Future Energy of Vietnam - Opportunities and Challenges
 
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...OMassmann - Investment into the grid and transmission system in Vietnam (2024...
OMassmann - Investment into the grid and transmission system in Vietnam (2024...
 
Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...
Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...
Vietnam Power and Energy Future with Power Development Plan 8 - Getting deals...
 
Lawyer in Vietnam Dr. Oliver Massmann VIETNAM - ONSHORE AND OFFSHORE WIND EN...
Lawyer in Vietnam Dr. Oliver Massmann  VIETNAM - ONSHORE AND OFFSHORE WIND EN...Lawyer in Vietnam Dr. Oliver Massmann  VIETNAM - ONSHORE AND OFFSHORE WIND EN...
Lawyer in Vietnam Dr. Oliver Massmann VIETNAM - ONSHORE AND OFFSHORE WIND EN...
 
Omass - Vietnam Energy Future - PDP 8
Omass - Vietnam Energy Future - PDP 8 Omass - Vietnam Energy Future - PDP 8
Omass - Vietnam Energy Future - PDP 8
 
VIETNAM - ONSHORE AND OFFSHORE WIND ENERGY PROJECTS -GETTING DEALS DONE!
VIETNAM - ONSHORE AND OFFSHORE WIND ENERGY PROJECTS -GETTING DEALS DONE!VIETNAM - ONSHORE AND OFFSHORE WIND ENERGY PROJECTS -GETTING DEALS DONE!
VIETNAM - ONSHORE AND OFFSHORE WIND ENERGY PROJECTS -GETTING DEALS DONE!
 
Lawyer in Vietnam Dr. Oliver Massmann - POWER and ENERGY IN VIETNAM — How to ...
Lawyer in Vietnam Dr. Oliver Massmann - POWER and ENERGY IN VIETNAM — How to ...Lawyer in Vietnam Dr. Oliver Massmann - POWER and ENERGY IN VIETNAM — How to ...
Lawyer in Vietnam Dr. Oliver Massmann - POWER and ENERGY IN VIETNAM — How to ...
 
Omass - Decarbonization - PDP 8
Omass - Decarbonization - PDP 8 Omass - Decarbonization - PDP 8
Omass - Decarbonization - PDP 8
 
Lawyer in Vietnam Dr. Oliver Massmann LEGAL FRAMEWORK AND INVESTMENT POLICIES...
Lawyer in Vietnam Dr. Oliver Massmann LEGAL FRAMEWORK AND INVESTMENT POLICIES...Lawyer in Vietnam Dr. Oliver Massmann LEGAL FRAMEWORK AND INVESTMENT POLICIES...
Lawyer in Vietnam Dr. Oliver Massmann LEGAL FRAMEWORK AND INVESTMENT POLICIES...
 
Hydro Priyank jain
Hydro Priyank jain Hydro Priyank jain
Hydro Priyank jain
 
TÜV Rheinland "Solar Investment Risk Mitigation Workshop"
TÜV Rheinland "Solar Investment Risk Mitigation Workshop"TÜV Rheinland "Solar Investment Risk Mitigation Workshop"
TÜV Rheinland "Solar Investment Risk Mitigation Workshop"
 
Omassmann legal obstacles for renewable energy development in vietnam
Omassmann legal obstacles for renewable energy development in vietnamOmassmann legal obstacles for renewable energy development in vietnam
Omassmann legal obstacles for renewable energy development in vietnam
 
Options analysis for private sector investment into Vietnam’s transmission ne...
Options analysis for private sector investment into Vietnam’s transmission ne...Options analysis for private sector investment into Vietnam’s transmission ne...
Options analysis for private sector investment into Vietnam’s transmission ne...
 
Investing in wind energy in Vietnam — legal certainty and bankability — makin...
Investing in wind energy in Vietnam — legal certainty and bankability — makin...Investing in wind energy in Vietnam — legal certainty and bankability — makin...
Investing in wind energy in Vietnam — legal certainty and bankability — makin...
 
2017 Outlook for Vietnam Renewable Energy
2017 Outlook for Vietnam Renewable Energy2017 Outlook for Vietnam Renewable Energy
2017 Outlook for Vietnam Renewable Energy
 
Vietnam _Green Growth
Vietnam _Green GrowthVietnam _Green Growth
Vietnam _Green Growth
 
Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort Indian Hydro Power - A new regulatory effort
Indian Hydro Power - A new regulatory effort
 
On-the-Ground Challenges and Opportunities in Solar Implementation
On-the-Ground Challenges and Opportunities in Solar ImplementationOn-the-Ground Challenges and Opportunities in Solar Implementation
On-the-Ground Challenges and Opportunities in Solar Implementation
 

More from Dr. Oliver Massmann

More from Dr. Oliver Massmann (20)

Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
 
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
Vietnam - Global Water Intelligence interviewing Dr. Oliver Massmann on persp...
 
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
Legal Alert - Vietnam - First draft Decree on mechanisms and policies to enco...
 
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
Anwalt in Vietnam Dr. Oliver Massmann - Vietnam's Plan für die Implementierun...
 
Vietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key HighlightsVietnam's Plan for Implementation of PDP8 – Key Highlights
Vietnam's Plan for Implementation of PDP8 – Key Highlights
 
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
VIETNAM - THE NEW LAW ON CREDIT INSTITUTIONS - WHAT YOU MUST KNOW:
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
ANWALT IN VIETNAM DR. OLIVER MASSMANN RECHTLICHER HINWEIS ZUM RUNDSCHREIBEN M...
 
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
VIETNAM - LEGAL ALERT ON CIRCULAR PROVIDING REGULATIONS ON METHOD TO FORMULAT...
 
Vietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key HighlightsVietnam's National Energy Development Strategy – Key Highlights
Vietnam's National Energy Development Strategy – Key Highlights
 
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
Anwalt in Vietnam Dr. Oliver Massmann Corporate Sustainability Due Diligence ...
 
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
ANWALT IN VIETNAM DR OLIVER MASSMANN MÖGLICHE RATIFIZIERUNG DES ÜBEREINKOMMEN...
 
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
Corporate Sustainability Due Diligence Directive (CSDDD or the EU Supply Chai...
 
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
Anwalt in Vietnam Dr. Oliver Massmann- Franchising – Eine Strategie als Schlü...
 
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
POTENTIAL RATIFICATION OF CONVENTION 87 OF THE INTERNATIONAL LABOUR ORGANIZAT...
 
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
KEY TASKS SET OUT BY THE PRIME MINISTER FOR THE YEAR 2024 AND THE EMERGING MA...
 
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
Lawyer in Vietnam Dr. Oliver Massmann - Doing Business and Getting Deals Done...
 
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
Anwalt in Vietnam Dr. Oliver Massmann im Interview mit Asia Business Law Jour...
 
Lawyer in Vietnam Dr Oliver Massmann - Vietnam and the World
Lawyer in Vietnam Dr Oliver Massmann - Vietnam and the WorldLawyer in Vietnam Dr Oliver Massmann - Vietnam and the World
Lawyer in Vietnam Dr Oliver Massmann - Vietnam and the World
 

Recently uploaded

一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
e9733fc35af6
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
MollyBrown86
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
Airst S
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
bd2c5966a56d
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
Airst S
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
Airst S
 
Contract law. Indemnity
Contract law.                     IndemnityContract law.                     Indemnity
Contract law. Indemnity
mahikaanand16
 
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
A AA
 

Recently uploaded (20)

How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
How do cyber crime lawyers in Mumbai collaborate with law enforcement agencie...
 
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptxKEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
KEY NOTE- IBC(INSOLVENCY & BANKRUPTCY CODE) DESIGN- PPT.pptx
 
ARTICLE 370 PDF about the indian constitution.
ARTICLE 370 PDF about the  indian constitution.ARTICLE 370 PDF about the  indian constitution.
ARTICLE 370 PDF about the indian constitution.
 
589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf589308994-interpretation-of-statutes-notes-law-college.pdf
589308994-interpretation-of-statutes-notes-law-college.pdf
 
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURYA SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
A SHORT HISTORY OF LIBERTY'S PROGREE THROUGH HE EIGHTEENTH CENTURY
 
MOCK GENERAL MEETINGS (SS-2)- PPT- Part 2.pptx
MOCK GENERAL MEETINGS (SS-2)- PPT- Part 2.pptxMOCK GENERAL MEETINGS (SS-2)- PPT- Part 2.pptx
MOCK GENERAL MEETINGS (SS-2)- PPT- Part 2.pptx
 
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
一比一原版(纽大毕业证书)美国纽约大学毕业证如何办理
 
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxxAudience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
Audience profile - SF.pptxxxxxxxxxxxxxxxxxxxxxxxxxxx
 
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
一比一原版(JCU毕业证书)詹姆斯库克大学毕业证如何办理
 
PPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptxPPT- Voluntary Liquidation (Under section 59).pptx
PPT- Voluntary Liquidation (Under section 59).pptx
 
Human Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptxHuman Rights_FilippoLuciani diritti umani.pptx
Human Rights_FilippoLuciani diritti umani.pptx
 
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
一比一原版(QUT毕业证书)昆士兰科技大学毕业证如何办理
 
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
Independent Call Girls Pune | 8005736733 Independent Escorts & Dating Escorts...
 
Police Misconduct Lawyers - Law Office of Jerry L. Steering
Police Misconduct Lawyers - Law Office of Jerry L. SteeringPolice Misconduct Lawyers - Law Office of Jerry L. Steering
Police Misconduct Lawyers - Law Office of Jerry L. Steering
 
一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理一比一原版曼彻斯特城市大学毕业证如何办理
一比一原版曼彻斯特城市大学毕业证如何办理
 
一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理一比一原版埃克塞特大学毕业证如何办理
一比一原版埃克塞特大学毕业证如何办理
 
Contract law. Indemnity
Contract law.                     IndemnityContract law.                     Indemnity
Contract law. Indemnity
 
Clarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo forClarifying Land Donation Issues Memo for
Clarifying Land Donation Issues Memo for
 
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
一比一原版(USYD毕业证书)澳洲悉尼大学毕业证如何办理
 
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptxIBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
IBC (Insolvency and Bankruptcy Code 2016)-IOD - PPT.pptx
 

Lawyer in Vietnam Oliver Massmann - Investing in Solar Energy - How To Do It Right

  • 1. www.duanemorris.com ©2010 Duane Morris LLP. All Rights Reserved. Duane Morris is a registered service mark of Duane Morris LLP. Duane Morris – Firm and Affiliate Offices | New York | London | Singapore | Los Angeles | Chicago | Houston | Hanoi | Philadelphia | San Diego | San Francisco | Baltimore | Boston | Washington, D.C. Las Vegas | Atlanta | Miami | Pittsburgh | Newark | Boca Raton | Wilmington | Cherry Hill | Princeton | Lake Tahoe | Ho Chi Minh City | Duane Morris LLP – A Delaware limited liability partnership OLIVER MASSMANN - Partner, General Director DUANE MORRIS VIETNAM LLC INVESTING IN SOLAR ENERGY IN VIETNAM How to do it right? *
  • 2. www.duanemorris.com AGENDA • POTENTIAL OF SOLAR ENERGY INDUSTRY IN VIETNAM • GOVERNMENT’S POLICY ON RENEWABLE (SOLAR) ENERGY • MARKET ACCESS FOR FOREIGN INVESTORS • OPPORTUNITIES FOR INTERNATIONAL DEVELOPERS • RECOMMENDATIONS *
  • 3. www.duanemorris.com Energy Sector Background • Electricity consumption grew by an average of 14% annually during 2004–2010, compared with 7% economic growth rate per year during that period • Electricity demand is expected to increase by up to 14.2 pct. annually for the 2011-2015 period, 11.4 pct. for the 2016- 2020 period and 7 times to 800 billion Kwh in 2030 • Electricity consumption is projected to increase from 85,932 gigawatt hours (GWh) in 2010 to 251,763 GWh in 2020 • By end of 2014, The Vietnamese solar power market is still relatively small with only around 4.5 MW installed capacity. *
  • 4. www.duanemorris.com POTENTIAL OF SOLAR ENERGY INDUSTRY IN VIETNAM • Total number of sunshine hours up to 1400 – 3000 hours/year • The average total radiation amounts to 230 – 250 kcal/cm2, and strengthens towards the south. • Solar energy can be used for water boiling, power production and other purposes, as e.g. drying, cooking etc. *
  • 5. www.duanemorris.com GOVERNMENT’S POLICY ON RENEWABLE (SOLAR) ENERGY • Viet Nam currently does not have a full-fledged legal framework on renewable energy, especially solar energy investment. • Amended National Master Plan VII • Decision No. 2068/QD-TTg specifically on development plan for renewable energy (biomass, wind, and solar energy) until 2030 and with a vision to 2050 • Draft Decision on supporting regime for solar power projects to be adopted in the next 1-2 months *
  • 6. www.duanemorris.com Clean energy policy reform – The dynamic process * • PROVINCIAL • GOVTS BLOCK COAL/ BIG HYDRO • LOCAL SOURCING/ • MANUFACTU RING OF EQUIPMENT • LOCAL POLLUTION HEALTH/ SOCIAL IMPACT AND DISHARMON Y • SOE + GoVN • MARK ET • CONTR OL • ENERG Y INFLAT ION CONCE RNS • STA TE/E VN • CAPI TAL • SCA RCIT Y • ENER GY SUPP LY • SPEE D OF • GRO WTH Climate Change Commitments International Trade Agreements PRICE + SUPPLY CAPACITY = SPEED SPEED + SUPPLY CAPACITY = PRICE Key to the Dynagram Arrows • Direction Weakening/Growing Impact on Policy Reform to Clean Energy • Width Extent of Impact Box /Circles •Colour Green Dynamic Force For Change Red Barriers to Change Grey Circles No Force for Change Donor Soft Loans / Grants • CAPEX- FUELLE D CORRUP TION • POWER CONSUMER S DEMAND GREEN
  • 7. www.duanemorris.com Amended Power Master Plan VII on the development of electricity in Vietnam • Revised National power development plan for 2011-2020 period with the vision to 2030 approved by the PM under his Decision No. 428/QD-TTg dated 18 March 2016 • Amended Master Plan VII focuses on energy security, energy efficiency, renewable energy development and power market liberalization • Objectives: – To increase the aggregate output of imported and produced electricity to 235-245 billion kWh by 2020; 352 – 379 billion kWh by 2025 and 506 – 559 billion kWh by 2030 – To prioritize to develop renewable energy generation so that the proportion of electricity generation of renewable energy will be increased from the present 3.5% of the total electricity production to 7% in 2020 and 10% in 2030 – To promote the rural electrification program so that most of the rural households will have access to the electricity by 2020 – To build flexible operation of electricity grid, high automation of the transmission to distribution process, development of substations with no requirement for operating personnel.
  • 8. www.duanemorris.com Amended Power Master Plan VII • Strategies: – Higher quality of electricity supply and more reasonable electricity price – Diversification of domestic resources for power generation – Developing new renewable power sources and updating technologies used in existing plants – Diversification of investment sources to overcome the lack of financial and technical resources and also to improve economic efficiency • Investment capital demand: – Approximately USD 40 billion up to 2020: Two-thirds for power generation development and one-third for power network development – Approximately USD 108 billion for the period from 2021 to 2030: 74% for power generation development and 26% for power network development *
  • 9. www.duanemorris.com Amended Power Master Plan VII • State to keep monopoly on transmission • Prioritize development of renewable energy • Renewable energy target rate at 7 pct. of total energy output by 2020 and more than 10 pct. by 2030. • Increase the solar power output to 850 MW by 2020, 4,000 MW in 2025 and 12,000 MW in 2030. *
  • 10. www.duanemorris.com Vietnam’s electrical energy mix • Vietnam policy emphasises the need to diversify the country’s energy mix whilst maximising the use of local energy reserves • Currently Vietnam is developing an energy mix sector with the mainstay of coal fired power *
  • 13. www.duanemorris.com DRAFT DECISION ON SUPPORTING REGIME FOR SOLAR POWER PROJECTS • EVN has to purchase electricity from on-grid solar energy projects at VAT-excluded price of 11.2 US cents/kWh • For on-grid rooftop solar projects,  the rate will be 18 UScents/ kWh • The rate in VND will be indicated in the final Decision based on the USD/VND exchange rate at that time and the MOIT will issue an Official Letter every year to adjust the rate in VND according to the fluctuation in the exchange rate. • Rooftop solar projects of less than 50kW will not have to connect to the grid. For those of more than 50kW, connection to the grid is required and an electricity operating permit must be obtained. • Term of solar energy PPAs: 20 years (renewable) *
  • 14. www.duanemorris.com ENERGY RETAIL PRICES • Circular 12/2014/TT-BCT: – 7-10% increase with MOIT approval – More than 10% requires PM approval – EVN can decide independently for less than 7% increases? • Energy retail prices are expected to increase  Raise FiT • It is unofficially known that the MOIT proposed to the Government to approve for an FIT increase of up to 11.2 UScents/kwh to make the solar energy projects become more financially feasible.*
  • 15. www.duanemorris.com Market access and Forms of investment • No foreign ownership restriction • Investment forms: ü A wholly-owned foreign enterprise ü A joint venture company between a foreign investor and domestic investor ü Investment pursuant to the BOT legal framework (which includes establishment of a project entity in the form of a wholly-owned foreign enterprise by way of a BOT contract with the MOIT which is implemented through a wholly-owned foreign enterprise; or a joint venture company by way of a BOT contract with the MOIT which is implemented through a joint venture with a Vietnamese entity (usually including EVN, but it is also possible with a private domestic IPP) ü Through the purchase of shares in either an EVN subsidiary being or having been equitized or a private IPP holding power assets. investment in the form of establishment of a new company can be undertaken in one or more of the following ways.*
  • 16. www.duanemorris.com BOT – BEST INVESTMENT FORM • Government’s Decree No. 15/2015/ND-CP on Public- Private Partnership: making projects more bankable • Easier to negotiate more favorable electricity rates. • Easier to obtain more government guarantees, especially in terms of EVN’s obligations to purchase all electricity from the project. • More fiscal and financial incentives. • Precedent large-scaled BOT power projects in Vietnam: Phu My, Vung Ang, Mong Duong 2 *
  • 17. www.duanemorris.com INVESTMENT INCENTIVES • Land: exemption of land rental within 3 years from the operation date of the project, etc. • CIT 10% – 15 years for new enterprises investing in power plant projects – tax exemptions within 4 years and tax reduction by 50% in the next 9 years. • Import duty exemption – on goods imported to create fixed assets of the projects; components, materials and semi-finished products which are not available at home for the project’s operation. • Investment capital – investors could apply for a loan of up to 70% of the total investment capital of their project with a term of maximum 12 years. – investors could also enjoy export credit incentives in the form of a loan of up to 85% of the export/ import contract value or L/C value also with a term of maximum 12 years. *
  • 18. www.duanemorris.com Project planning • Investors has to obtain prior agreement of EVN on power purchase prior to licensing procedure. • Commitment of banks or credit institutions on financing the project must be obtained prior to issuance of Investment Registration Certificate . • In-principle approval of the local People’s Committee is required prior to issuance of Investment Registration Certificate depending on the project size • A solar power plant must obtain a power generation permit from the competent State authorities in order to conduct power generation operations in Vietnam • Term of the permit: maximum 20 years for large power plants with particularly important meaning on economy, society, national defense and security as per the list approved by the Prime Minister; and 10 years for other power plants projects. • The permit cannot be renewed but the investor may apply for a new one within 60 days prior to the expiry date of the current permit. *
  • 19. www.duanemorris.com Project licensing • Step 1: The investor obtains approval from the competent authority [e.g., Prime Minister, MOIT] approving the solar power plant as part of the power development master plan (if required). • Step 2: The investor obtains in-principle approval from the competent People’s Committee (or other competent authorities subject to the details of the project) approving the solar power plant project, land demand / location, environment, construction plan, other terms of the project. • Step 3: Application for issuance of the Investment Registration Certificate and the Enterprise Registration Certificate • Step 4: Preparation of construction / operations of the solar power plant (for example, acquiring land area, site clearance, preparation, land investigation, conducting environmental assessment) • Step 5: The project company to obtain necessary permits and relevant agreements for its and the power plant’s operation. • Step 6: Construction of solar power plant and operation *
  • 22. www.duanemorris.com EVFTA – Bilateral negotiations * Launch of negotiations First round in Hanoi 15 rounds alternately in Vietnam and Brussels Last round in Hanoi Agreement in principle • 06/ 201 2 • 1 0 / 2 0 1 2 • H a r d w o r k • 7 / 2 0 1 5 • 8 / 2 0 1 5 • 0 2/ 1 2/ 2 0 1 5 • 0 2 / 0 2 / 2 0 1 6 Conclusion of negotiation FTA text released
  • 26. www.duanemorris.com TPP and AEC intersection * Thailand Malaysia Brunei CanadaAustralia Cambodia Indonesia Myanmar Peru Philippines Japan Laos Mexico New Zealand Singapore The United States Vietnam Chile
  • 27. www.duanemorris.com ASEAN TPP: Market Access Liberalization as Consequence of TPP • Indonesia plans to loose restrictions on foreign investment in nearly 50 sectors, including e-commerce, retail, healthcare, movie and several other industries • Indonesia prepares for the so-called “Negative Investment List”, which provides a greater openness to foreign investment and gets itself ready for the TPP • China, Korea, the Philippines, Indonesia and Thailand are also keen to join the TPP to overcome the disadvantages *
  • 28. www.duanemorris.com Power/ Energy Sector Level of commitment in Power / Energy sector * N/A Low High
  • 29. www.duanemorris.com Power/ Energy Sector • WTO / AFAS • EVFTA • TPP • N/A • Commitments are only made in 3 sub-sectors • Vietnam makes commitments in all sub- sectors with listed restrictions (no other restrictions are permitted). •   *
  • 30. www.duanemorris.com RECOMMENDATIONS FOR INVESTORS • Difficult time but opportunities await. • Public private partnerships (e.g. - BOT) should be the first option. • Due care on negotiations of the PPA and grid connection agreement with EVN • Electricity selling in off-grid areas can be a good choice • Sound financing structure, good business model and great legal assistance are keys to success. • Accurate prediction of where the market is heading to, in the context of Vietnam’s critical power shortage, should be considered. • More pressure on the government to adequately address key issues on tariff increase, demonopolization of the power market and government guarantee. • Vietnam’s market is extremely in need of financing and EPC capability. There are rooms for cost-effective and high quality EPC contractors and resourceful lenders. • In many cases, you can “test the water” with a small power plant project. *
  • 31. www.duanemorris.com DUANE MORRIS VIETNAM LLC Thank you very much! HANOI OFFICE HO CHI MINH CITY OFFICE Pacific Place, Unit V1307/08, 13th Floor, Suite 1503/04, Saigon Tower 83B Ly Thuong Kiet, Hoan Kiem District 29 Le Duan Street, District 1 Hanoi, Vietnam Ho Chi Minh City, Vietnam Tel.: +84 4 39462200 Tel.: +84 8 3824 0240 Fax: +84 4 3946 1311 Fax: +84 8 3824 0241 Contact email: omassmann@duanemorris.com *