SlideShare a Scribd company logo
1 of 36
A PRESENTATION ON
National Thermal Power Corporation Ltd.
Submitted by:
Amit Sharma
Naresh Sharma
Submitted to:
Sandeep Sharda
INTRODUCTION
• Incorporated on November 7,1975.
• Shri D.V. Kapur took over on March 19,1976 as the
first chairman & managing director of NTPC
• On December 8,1976 the government of India cleared
ntpc's first pithead super thermal power project at
singrauli in uttar pradesh
• The authorised share capital of the company was
RS.125 crore
• The first Major contract of Rs.57.5 million was
awarded for site leaving work at Singrauli in June
1977
• Construction of the first transmission network
Singrauli-Korba-Kanpur of 400 KV system started in
1978
• In March 1979 Government of India approved the
implementation of Farakka (West Bengal) Project
• The authorised share capital of the company rose
from Rs.125 crore to Rs 300 crore
• In 1980 Former Soviet Union offered to assist in seeting
up of power stations. Vidhayachal (M.P.) was identified
as the first project for such assistance
• The authorized share capital was raised from Rs.300
crore to Rs.800 crore in June 1980.
• In the very first year of its commercial operation ,
NTPC earned a profit of Rs.4.51 crore in the financial
year 1982-83
• First unit (88 MW) of first gas based combined cycle power
plant at Anta, Rajasthan commissioned in 1989.
• Total installed capacity crossed 10000 MW in 1990.
• Dr. Arup Roy Choudhury is the Chairman & Managing
Director, NTPC Limited since September 01, 2010.
• NTPC became a Maharatna company in May 2010.
• NTPC was ranked 431st in the ‘2015, Forbes Global 2000’
ranking of the World’s biggest companies.
Electricity Power Demand In India
• The 17th electric power survey of India report claims
• Over 2010–11, India's
• Industrial Demand 35%,
• Domestic Household 28%,
• Agriculture 21%,
• Commercial 9%,
• public lighting and other miscellaneous applications accounted
for the rest.
• The electrical energy demand expected to be at least for
• 2016–17 1,392 Tera Watt Hours,
with peak electric demand of 218 GW.
• 2021–22 1,915 Tera Watt Hours,
with peak electric demand of 298 GW.
The total installed capacity as on 31 March 2015 is
2,71,722.17 MW with sector wise & type wise break
up as given below.
Sector Coal Gas Diesel Total Nuclear Hydro RES@
Grand
Total
(MW)
Central 48130.00 7519.73 0 55649.73
5780.0
0
11091.4
3
0
72521.1
6
State 58100.50 6974.42 602.61 65677.53 0
27482.0
0
3803.67
96963.2
0
Private 58405.38 8568.00 597.14 67570.52 0 2694.00
31973.2
9
102237.
81
All
India
164635.88
23062.1
5
1199.75
188897.7
8
5780.0
0
41267.4
3
35776.9
6
271722.
17
• The break up of RES (Renewable Energy Source) is
• small hydro 4055.36 MW
• wind power 23444.00 MW
• Bio mass power 1410.20 MW
& gasification
• Bagasse cogeneration 3008.35 MW
• Waste to power 115.08 MW
• Solar power 3743.97 MW
Total Installed Capacity Of The Company
• The total installed capacity of the company is
45,548 MW (including JVs) with
»18 coal based and
»7 gas based stations.
»7 Joint Venture stations are coal based and
»8 renewable energy projects.
NTPC Power Generation
• Coal Based Power Stations 34,425 MW
production
• Coal Based Joint Ventures: 4,229 MW
• Gas Based Power Stations 4,017.23 MW
production
• Gas Based Joint Ventures: 1,967.08 MW
• Hydro Based Power Projects 800 MW
• Renewable Energy Projects 110 MW
Contribution To National Power
Production
• NTPC has been operating its plants at high
efficiency levels.
Although the company has 17.73% of the total
national capacity,
• It contributes 25.91% of total power generation
due to its focus on high efficiency.
Public sector undertaking
• In October 2004, NTPC launched its Initial Public Offering (IPO)
consisting of 5.25% as fresh issue and 5.25% as offer for sale by the
Government of India.
• NTPC thus became a listed company in November 2004 with the
Government holding 89.5% of the equity share capital.
• In February 2010, the Shareholding of Government of India was
reduced from 89.5% to 84.5% through a further public offer.
• Government of India has further divested 9.5% shares
through OFS route in February 2013.
• With this, GOI's holding in NTPC has reduced from
84.5% to 75%. The rest is held by Institutional
Investors, banks and Public.
NTPC Power stations
Joint Venture
1. NTPC-SAIL POWER COMPANY (PVT) LTD (NSPCL)
2. NTPC TAMILNADU ENERGY COMPANY LIMITED
3. ARAVALI POWER COMPANY PRIVATE LTD.
4. MEJA URJA NIGAM PRIVATE LIMITED
5. RATNAGIRI GAS & POWER PVT. LIMITED
6. NABINAGAR POWER GENERATING CO. PVT. LTD.
7. NTPC -ALSTOM POWER SERVICES PVT. LTD.
(NASL)
8. UTILITY POWER TECH LTD.
9. NATIONAL HIGH POWER TEST LABORATORY PVT.
LTD. (NHPTL)
10. NATIONAL POWER EXCHANGE LTD.(NPEX)
11. NTPC – SCCL GLOBAL VENTURES PRIVATE LTD.
12. INTERNATIONAL COAL VENTURES PVT. LIMITED
(ICVL)
13. NTPC-BHEL POWER PROJECTS PVT.LTD
14. BF NTPC ENERGY SYSTEM LIMITED.
15. NTPC-TELK
16. ENERGY EFFICIENCY SERVICES LTD. (EESL)
17. CIL-NTPC URJA PRIVATE LIMITED (CNUPL)
18. ANUSHAKTI VIDHYUT NIGAM LIMITED (ASHVINI)
19. PAN-ASIAN RENEWABLES PRIVATE LIMITED
20. TRINCOMALEE POWER COMPANY LIMITED
21. BANGLADESH-INDIA FRIENDSHIP POWER
COMPANY PRIVATE LIMITED (BIFPCL)
Working of power plant
• To understand working of NTPC we studied Anta Gas Based
Combined Cycle Power Project.
• Anta Gas Based Combined Cycle Power Project is not only
the first Gas Power Plant of NTPC but is also the beginning
of an era of state of art Combined Cycle Power Plants in the
country.
NTPC Gas Power Plant Anta
• Established in : 1989
• Type of station : Gas based combined cycle
• Location : Anta in Baran district of Rajasthan
• Total land : 390.75 acres.
• Fuel : Natural Gas, Naphtha
• Fuel source : By GAIL through HBJ
Pipe line
• Water source : KOTA RIGHT MAIN CANAL
• Reservoir : 10 Million m3 , for One Month
• Gas Turbine Output : 3 X 88.71 MW
• Steam Turbine Output : 153.20 MW
• Net plant Output : 419.33MW
Applications of Gas Turbine
Conventional applications are
• Simple cycle operation.
• Combined cycle operation.
Electric utility companies use gas turbine predominantly
in simple cycle and combined cycle applications.
Combined cycle operation is much efficient than open
cycle operation.
COMBINED CYCLE
Combined cycle power plant integrates two power
conversion cycles
• Brayton cycle (gas-turbine) and
• Rankine cycle (steam-turbine)
• with the principal objective of increasing overall plant
efficiency.
G
Gas Turbine
Air
Fuel
100%
input
Exhaust gas
G
15%
Steam
16%Steam
Turbine
WHRB
33%
Condenser
36%
Combined Cycle Process
Reservoir
Inlet Temp. 1005 °C
flue gas temp. 505 °C
Combined Cycle Process
• Gas turbine exhaust is at temperature of 500-550 c
• Rankine cycle heat is required to generate of 500-550 c
• Gas turbine exhaust heat can be recovered using a waste
heat recovery boiler to run a steam turbine on Rankine
cycle
• If efficiency of gas turbine cycle is 33% and
• the efficiency of Rankine cycle is 16%
• then over all efficiency comes to 49%.
Waste Heat Recovery Boiler
• Anta Combined cycle power plant also known as
Waste Heat Recovery Boilers (WHRB) plant.
• which are of non-fired, dual pressure and forced
circulation type.
• The boiler has two different water/steam cycle known
as high-pressure system and low-pressure system.
220 kV Switchyard
A Switchyard is the
place at which switching
operation of power
distribution is
performed.
NTPC-Anta Gas Power
Station has a 220 kV
Switchyard which is used
for switching operation
and power evacuation for
six 220 kV transmission
lines.
There are total six 220 kv transmission lines for
evacuation of power generated at Anta.
 Two lines for Bhilwara,
 One lines for Dousa,
 One lines for SawaiMadhopur,
 One line for Kota and
 One line for RAPP.
POWER EVACUATION FROM NTPC-ANTA
Vision And Mission Of NTPC
• Vision
• To be the world’s largest and best power producer,
powering India’s growth.
• Mission
• Develop and provide reliable power, related
products and services at competitive prices,
integrating multiple energy sources with innovative
and eco-friendly technologies and contribute to
society.
Core Values – BE COMMITTED
• B Business Ethics
• E Environmentally & Economically Sustainable
• C Customer Focus
• O Organisational & Professional Pride
• M Mutual Respect & Trust
• M Motivating Self & others
• I Innovation & Speed
• T Total Quality for Excellence
• T Transparent & Respected Organisation
• E Enterprising
• D Devoted
Strategy
• to contribute to sustainable development by discharging
corporate social responsibilities.
• To lead the sector in the areas of resettlement &
rehabilitation, environment protection including effective
ash utilization, peripheral development and energy
conservation practices.
• To lead development efforts in the Indian power sector
through efforts at policy advocacy, assisting customers in
reforms, disseminating best practices in the operation and
management of power plants etc.
Policies
• Contribute towards clean and sustainable environment with respect to
land, water and air.
• Conserve resources by reduction, reuse and recycling
• Initiate and support measures to optimize the use of renewable
energy, increase energy efficiency and reduce Green House Gases
emissions.
• Be transparent, ethical and fair to all stakeholders
• Be supportive in developing and enhancing people’s standard of living
in and around the plants.
• Generate awareness, share knowledge and support training
programmes on sustainable development among the employees,
neighbouring communities and public at large.
FINANCIAL RESULTS
2013-14 2013-14 2012-13 2012-13
Revenue Rs. Crore US $ Mn* Rs. Crore US $ Mn*
Net Revenue from
Operations
72,018.93 11,882.35 65,737.04 10,845.91
Other Income 2,688.89 443.64 3,118.77 514.56
Total Revenue 74,707.82 12,325.99 68,855.81 11,360.47
Expenses
Total Expenses 60,803.17 10,031.87 53,961.29 8,903.04
Profit before Tax and
exceptional items
13,904.65 2,294.12 14,894.52 2,457.43
Exceptional items - - 1,684.11 277.86
Profit before tax 13,904.65 2,294.12 16,578.63 2,735.29
Tax Expense 2,929.91 483.40 3,959.24 653.23
Profit for the year 10,974.74 1,810.71 12,619.39 2,082.06
2013-14 2013-14 2012-13 2012-13
Appropriations:
Rs. Crore US $ Mn* Rs. Crore US $ Mn*
Transfer to bond redemption
reserve
576.08 95.05 492.79 81.31
Transfer to general reserve 5,000.00 824.95 6,500.00 1,072.43
Transfer to capital reserve 4.98 0.82 0.97 0.16
Interim dividend 3,298.19 544.17 3,092.07 510.16
Proposed dividend 1,442.96 238.07 1,649.09 272.08
Tax on dividend 804.74 132.77 781.87 129.00
*1US $= Rs. 60.61 as on March 31, 2014
Recognitions & Awards
• Company Rankings:-
• NTPC has been bestowed the honour of being most respected
company in Power Sector for the year 2011 by Business world.
• Company is ranked 424th largest company in the world, 16th
among the global electric utilities.
• 2nd among the Asian electric utilities as per Forbes Global 2000
ranking for 2014.
• Company was ranked No. 1 Independent Power Producer and
Energy Trader Globally in the Platts Top 250 Global Energy
Company Rankings, 2013. Company has been able to maintain
this ranking consistently since 2011.
• Environment Awards:-
Earth care Award 2012 to NTPC for Climate Change Initiatives.
and many more awards are presented to NTPC.
Future plan of NTPC
NTPC has formulated a long term Corporate Plan to
become a 1,28,000 MW company upto 2032.
Towards this goal, NTPC has adopted a multi prong
strategy to ensure robust growth of the company.
References
• http://www.ntpc.co.in/en
• https://en.wikipedia.org/wiki/Electricity_sector_in_India#Demand
• https://en.wikipedia.org/wiki/World_energy_consumption
• https://en.wikipedia.org/wiki/List_of_power_stations_in_India
• http://www.moneycontrol.com/annual-report/ntpc/directors-
report/NTP#NTP
THANK YOU !
ANY QUERY?

More Related Content

What's hot

Final reprt at ntpc vindhyanagar , singrauli
Final  reprt at ntpc vindhyanagar , singrauliFinal  reprt at ntpc vindhyanagar , singrauli
Final reprt at ntpc vindhyanagar , singrauliDevanshu Yadav
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar Dilip kumar
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCADITYA ARYAN
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarRishikesh .
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...haxxo24
 
NTPC BADARPUR SUMMER TRAINING REPORT
NTPC BADARPUR SUMMER TRAINING REPORTNTPC BADARPUR SUMMER TRAINING REPORT
NTPC BADARPUR SUMMER TRAINING REPORTAnubhav Ghosh
 
Internship report of NTPC kawas ,summer internship report of ntpc
Internship report of  NTPC kawas ,summer internship report of ntpcInternship report of  NTPC kawas ,summer internship report of ntpc
Internship report of NTPC kawas ,summer internship report of ntpcLalitGoyal27
 
Ntpc kahalgaon training report
Ntpc kahalgaon training reportNtpc kahalgaon training report
Ntpc kahalgaon training reportravi kant
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training reportsanjeevps12345
 
FINAL REPORT OF ONGC
FINAL REPORT OF ONGCFINAL REPORT OF ONGC
FINAL REPORT OF ONGCBIDHAN DAS
 
VOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVIKASH BAGHEL
 
Ntpc information
Ntpc informationNtpc information
Ntpc informationNTPC
 
Ashish Modi ONGC
Ashish Modi ONGCAshish Modi ONGC
Ashish Modi ONGCAshish Modi
 

What's hot (20)

Final reprt at ntpc vindhyanagar , singrauli
Final  reprt at ntpc vindhyanagar , singrauliFinal  reprt at ntpc vindhyanagar , singrauli
Final reprt at ntpc vindhyanagar , singrauli
 
training report NTPC Muzaffarpur Bihar
training report  NTPC Muzaffarpur Bihar training report  NTPC Muzaffarpur Bihar
training report NTPC Muzaffarpur Bihar
 
INTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPCINTERNSHIP REPORT NTPC
INTERNSHIP REPORT NTPC
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC Shaktinagar
 
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
Ntpc (national thermal power corporation) sipat mechanical vocational trainin...
 
Ntpc
NtpcNtpc
Ntpc
 
NTPC BADARPUR SUMMER TRAINING REPORT
NTPC BADARPUR SUMMER TRAINING REPORTNTPC BADARPUR SUMMER TRAINING REPORT
NTPC BADARPUR SUMMER TRAINING REPORT
 
ntpc annual presentation
ntpc annual presentationntpc annual presentation
ntpc annual presentation
 
Internship report of NTPC kawas ,summer internship report of ntpc
Internship report of  NTPC kawas ,summer internship report of ntpcInternship report of  NTPC kawas ,summer internship report of ntpc
Internship report of NTPC kawas ,summer internship report of ntpc
 
Report ON NTPC DADRI .BY ....EMAM
Report ON NTPC DADRI  .BY ....EMAMReport ON NTPC DADRI  .BY ....EMAM
Report ON NTPC DADRI .BY ....EMAM
 
Ntpc kahalgaon training report
Ntpc kahalgaon training reportNtpc kahalgaon training report
Ntpc kahalgaon training report
 
NTPC summer training report
NTPC summer training reportNTPC summer training report
NTPC summer training report
 
FINAL REPORT OF ONGC
FINAL REPORT OF ONGCFINAL REPORT OF ONGC
FINAL REPORT OF ONGC
 
NTPC PROJECT..
NTPC PROJECT..NTPC PROJECT..
NTPC PROJECT..
 
VOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBAVOCATIONAL TRAINING REPORT ON NTPC KORBA
VOCATIONAL TRAINING REPORT ON NTPC KORBA
 
Ntpc.ppt
Ntpc.pptNtpc.ppt
Ntpc.ppt
 
ntpc khalgaon
ntpc khalgaonntpc khalgaon
ntpc khalgaon
 
Ntpc information
Ntpc informationNtpc information
Ntpc information
 
Ashish Modi ONGC
Ashish Modi ONGCAshish Modi ONGC
Ashish Modi ONGC
 
Ntpc dadri
Ntpc dadriNtpc dadri
Ntpc dadri
 

Viewers also liked

Assesment feed back report_ajayan karunakaran
Assesment feed back report_ajayan karunakaranAssesment feed back report_ajayan karunakaran
Assesment feed back report_ajayan karunakaranAjay Karun
 
Departmental trainors job responsibilities
Departmental trainors job responsibilitiesDepartmental trainors job responsibilities
Departmental trainors job responsibilitiesMahalaxmi
 
Adani Power, Tirora- Project Report
Adani Power, Tirora- Project ReportAdani Power, Tirora- Project Report
Adani Power, Tirora- Project ReportNemish Kanwar
 
Ntpc final presentation
Ntpc final presentationNtpc final presentation
Ntpc final presentationAmit Kanabar
 
Presentation on cotton contamination survey
Presentation on cotton contamination surveyPresentation on cotton contamination survey
Presentation on cotton contamination surveyitc-elearning
 
Indian Power Sector - Industry Analysis
Indian Power Sector - Industry AnalysisIndian Power Sector - Industry Analysis
Indian Power Sector - Industry AnalysisArjun Yadav
 
NTPC Ltd. Strategy Analysis
NTPC Ltd. Strategy AnalysisNTPC Ltd. Strategy Analysis
NTPC Ltd. Strategy AnalysisPrasoon Kumar
 
House of Tata: Acquiring a Global Footprint
House of Tata: Acquiring a Global FootprintHouse of Tata: Acquiring a Global Footprint
House of Tata: Acquiring a Global FootprintAbhigyan Singh
 
Panipat thermal power station training ppt
Panipat thermal power station training pptPanipat thermal power station training ppt
Panipat thermal power station training pptMohit Verma
 
Indian power sector report
Indian power sector reportIndian power sector report
Indian power sector reportChandra M. Verma
 
Iim bangalore (passive india)
Iim bangalore (passive india)Iim bangalore (passive india)
Iim bangalore (passive india)Mudra Redkar
 
Bcg Matrix + Porters Five Force Model - Anuj Gandhi
Bcg Matrix + Porters Five Force Model - Anuj GandhiBcg Matrix + Porters Five Force Model - Anuj Gandhi
Bcg Matrix + Porters Five Force Model - Anuj GandhiAnuj Gandhi
 
Value chain analysis
Value chain analysisValue chain analysis
Value chain analysisKamal Singh
 
10 steps in giving effective Feedback
10 steps in giving effective Feedback10 steps in giving effective Feedback
10 steps in giving effective FeedbackTrainers Advice
 

Viewers also liked (20)

Assesment feed back report_ajayan karunakaran
Assesment feed back report_ajayan karunakaranAssesment feed back report_ajayan karunakaran
Assesment feed back report_ajayan karunakaran
 
Ntpc
NtpcNtpc
Ntpc
 
Departmental trainors job responsibilities
Departmental trainors job responsibilitiesDepartmental trainors job responsibilities
Departmental trainors job responsibilities
 
Adani Power, Tirora- Project Report
Adani Power, Tirora- Project ReportAdani Power, Tirora- Project Report
Adani Power, Tirora- Project Report
 
Ntpc final presentation
Ntpc final presentationNtpc final presentation
Ntpc final presentation
 
NTPC Report
NTPC ReportNTPC Report
NTPC Report
 
Presentation on cotton contamination survey
Presentation on cotton contamination surveyPresentation on cotton contamination survey
Presentation on cotton contamination survey
 
Tatapower.ppt
Tatapower.pptTatapower.ppt
Tatapower.ppt
 
Indian Power Sector - Industry Analysis
Indian Power Sector - Industry AnalysisIndian Power Sector - Industry Analysis
Indian Power Sector - Industry Analysis
 
NTPC Ltd. Strategy Analysis
NTPC Ltd. Strategy AnalysisNTPC Ltd. Strategy Analysis
NTPC Ltd. Strategy Analysis
 
House of Tata: Acquiring a Global Footprint
House of Tata: Acquiring a Global FootprintHouse of Tata: Acquiring a Global Footprint
House of Tata: Acquiring a Global Footprint
 
Panipat thermal power station training ppt
Panipat thermal power station training pptPanipat thermal power station training ppt
Panipat thermal power station training ppt
 
Indian power sector report
Indian power sector reportIndian power sector report
Indian power sector report
 
Iim bangalore (passive india)
Iim bangalore (passive india)Iim bangalore (passive india)
Iim bangalore (passive india)
 
Indian oil corporation
Indian oil corporationIndian oil corporation
Indian oil corporation
 
Adani group
Adani groupAdani group
Adani group
 
Bcg Matrix + Porters Five Force Model - Anuj Gandhi
Bcg Matrix + Porters Five Force Model - Anuj GandhiBcg Matrix + Porters Five Force Model - Anuj Gandhi
Bcg Matrix + Porters Five Force Model - Anuj Gandhi
 
importance of feed back
importance of feed backimportance of feed back
importance of feed back
 
Value chain analysis
Value chain analysisValue chain analysis
Value chain analysis
 
10 steps in giving effective Feedback
10 steps in giving effective Feedback10 steps in giving effective Feedback
10 steps in giving effective Feedback
 

Similar to Ntpc Ltd.

Power energy generation report
Power energy generation reportPower energy generation report
Power energy generation reportprianca07
 
Ntpc tranning report
Ntpc tranning report Ntpc tranning report
Ntpc tranning report Study Hub
 
Abhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd Unchahar
Abhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd UnchaharAbhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd Unchahar
Abhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd UnchaharABHINAV KUMAR
 
CONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTCONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTSubarna Poddar
 
Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil Singh
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in IndiaDaya Kherwar
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT94600banti
 
Environmental Management Practices in a Super Thermal Power Plant.
Environmental Management Practices in a Super Thermal Power Plant.Environmental Management Practices in a Super Thermal Power Plant.
Environmental Management Practices in a Super Thermal Power Plant.Debasis Ray
 

Similar to Ntpc Ltd. (20)

Energy sector
Energy sectorEnergy sector
Energy sector
 
ntpc unchahar
ntpc unchaharntpc unchahar
ntpc unchahar
 
ARNAB12.pdf
ARNAB12.pdfARNAB12.pdf
ARNAB12.pdf
 
Ntpc report harsh
Ntpc report  harshNtpc report  harsh
Ntpc report harsh
 
Power energy generation report
Power energy generation reportPower energy generation report
Power energy generation report
 
Ntpc report
Ntpc reportNtpc report
Ntpc report
 
Ntpc tranning report
Ntpc tranning report Ntpc tranning report
Ntpc tranning report
 
177683808 case-study
177683808 case-study177683808 case-study
177683808 case-study
 
Thermal power
Thermal powerThermal power
Thermal power
 
Energy
EnergyEnergy
Energy
 
Abhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd Unchahar
Abhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd UnchaharAbhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd Unchahar
Abhinav Kumar Mechanical Engineering Vocational Training NTPC Ltd Unchahar
 
Report ntpc
Report ntpcReport ntpc
Report ntpc
 
Geeta power industry
Geeta power industryGeeta power industry
Geeta power industry
 
CONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANTCONTROL AND INSTRUMENTATION OF POWER PLANT
CONTROL AND INSTRUMENTATION OF POWER PLANT
 
Report ntpc auraiya
Report ntpc auraiyaReport ntpc auraiya
Report ntpc auraiya
 
Nikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTINikhil kumar project report ON NTPC KANTI
Nikhil kumar project report ON NTPC KANTI
 
Power sector in India
Power sector in IndiaPower sector in India
Power sector in India
 
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANTBanti industrial training-report-on-ntpc-dadri GAS POWER PLANT
Banti industrial training-report-on-ntpc-dadri GAS POWER PLANT
 
presentation vsv.ppt
presentation vsv.pptpresentation vsv.ppt
presentation vsv.ppt
 
Environmental Management Practices in a Super Thermal Power Plant.
Environmental Management Practices in a Super Thermal Power Plant.Environmental Management Practices in a Super Thermal Power Plant.
Environmental Management Practices in a Super Thermal Power Plant.
 

More from naresh sharma

More from naresh sharma (7)

Marketing mgmt
Marketing mgmtMarketing mgmt
Marketing mgmt
 
Written communication in business management
Written communication in business managementWritten communication in business management
Written communication in business management
 
Bill gates
Bill gatesBill gates
Bill gates
 
Split of hp
Split of hpSplit of hp
Split of hp
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Frederick w. taylor
Frederick w. taylorFrederick w. taylor
Frederick w. taylor
 
Dbms
DbmsDbms
Dbms
 

Recently uploaded

data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...tanu pandey
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Arindam Chakraborty, Ph.D., P.E. (CA, TX)
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086anil_gaur
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Standamitlee9823
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 

Recently uploaded (20)

data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 

Ntpc Ltd.

  • 1. A PRESENTATION ON National Thermal Power Corporation Ltd. Submitted by: Amit Sharma Naresh Sharma Submitted to: Sandeep Sharda
  • 2. INTRODUCTION • Incorporated on November 7,1975. • Shri D.V. Kapur took over on March 19,1976 as the first chairman & managing director of NTPC • On December 8,1976 the government of India cleared ntpc's first pithead super thermal power project at singrauli in uttar pradesh • The authorised share capital of the company was RS.125 crore
  • 3. • The first Major contract of Rs.57.5 million was awarded for site leaving work at Singrauli in June 1977 • Construction of the first transmission network Singrauli-Korba-Kanpur of 400 KV system started in 1978 • In March 1979 Government of India approved the implementation of Farakka (West Bengal) Project • The authorised share capital of the company rose from Rs.125 crore to Rs 300 crore
  • 4. • In 1980 Former Soviet Union offered to assist in seeting up of power stations. Vidhayachal (M.P.) was identified as the first project for such assistance • The authorized share capital was raised from Rs.300 crore to Rs.800 crore in June 1980. • In the very first year of its commercial operation , NTPC earned a profit of Rs.4.51 crore in the financial year 1982-83
  • 5. • First unit (88 MW) of first gas based combined cycle power plant at Anta, Rajasthan commissioned in 1989. • Total installed capacity crossed 10000 MW in 1990. • Dr. Arup Roy Choudhury is the Chairman & Managing Director, NTPC Limited since September 01, 2010. • NTPC became a Maharatna company in May 2010. • NTPC was ranked 431st in the ‘2015, Forbes Global 2000’ ranking of the World’s biggest companies.
  • 6. Electricity Power Demand In India • The 17th electric power survey of India report claims • Over 2010–11, India's • Industrial Demand 35%, • Domestic Household 28%, • Agriculture 21%, • Commercial 9%, • public lighting and other miscellaneous applications accounted for the rest. • The electrical energy demand expected to be at least for • 2016–17 1,392 Tera Watt Hours, with peak electric demand of 218 GW. • 2021–22 1,915 Tera Watt Hours, with peak electric demand of 298 GW.
  • 7.
  • 8. The total installed capacity as on 31 March 2015 is 2,71,722.17 MW with sector wise & type wise break up as given below. Sector Coal Gas Diesel Total Nuclear Hydro RES@ Grand Total (MW) Central 48130.00 7519.73 0 55649.73 5780.0 0 11091.4 3 0 72521.1 6 State 58100.50 6974.42 602.61 65677.53 0 27482.0 0 3803.67 96963.2 0 Private 58405.38 8568.00 597.14 67570.52 0 2694.00 31973.2 9 102237. 81 All India 164635.88 23062.1 5 1199.75 188897.7 8 5780.0 0 41267.4 3 35776.9 6 271722. 17
  • 9. • The break up of RES (Renewable Energy Source) is • small hydro 4055.36 MW • wind power 23444.00 MW • Bio mass power 1410.20 MW & gasification • Bagasse cogeneration 3008.35 MW • Waste to power 115.08 MW • Solar power 3743.97 MW
  • 10. Total Installed Capacity Of The Company • The total installed capacity of the company is 45,548 MW (including JVs) with »18 coal based and »7 gas based stations. »7 Joint Venture stations are coal based and »8 renewable energy projects.
  • 11. NTPC Power Generation • Coal Based Power Stations 34,425 MW production • Coal Based Joint Ventures: 4,229 MW • Gas Based Power Stations 4,017.23 MW production • Gas Based Joint Ventures: 1,967.08 MW • Hydro Based Power Projects 800 MW • Renewable Energy Projects 110 MW
  • 12. Contribution To National Power Production • NTPC has been operating its plants at high efficiency levels. Although the company has 17.73% of the total national capacity, • It contributes 25.91% of total power generation due to its focus on high efficiency.
  • 13. Public sector undertaking • In October 2004, NTPC launched its Initial Public Offering (IPO) consisting of 5.25% as fresh issue and 5.25% as offer for sale by the Government of India. • NTPC thus became a listed company in November 2004 with the Government holding 89.5% of the equity share capital. • In February 2010, the Shareholding of Government of India was reduced from 89.5% to 84.5% through a further public offer.
  • 14. • Government of India has further divested 9.5% shares through OFS route in February 2013. • With this, GOI's holding in NTPC has reduced from 84.5% to 75%. The rest is held by Institutional Investors, banks and Public.
  • 16. Joint Venture 1. NTPC-SAIL POWER COMPANY (PVT) LTD (NSPCL) 2. NTPC TAMILNADU ENERGY COMPANY LIMITED 3. ARAVALI POWER COMPANY PRIVATE LTD. 4. MEJA URJA NIGAM PRIVATE LIMITED 5. RATNAGIRI GAS & POWER PVT. LIMITED 6. NABINAGAR POWER GENERATING CO. PVT. LTD. 7. NTPC -ALSTOM POWER SERVICES PVT. LTD. (NASL) 8. UTILITY POWER TECH LTD. 9. NATIONAL HIGH POWER TEST LABORATORY PVT. LTD. (NHPTL) 10. NATIONAL POWER EXCHANGE LTD.(NPEX)
  • 17. 11. NTPC – SCCL GLOBAL VENTURES PRIVATE LTD. 12. INTERNATIONAL COAL VENTURES PVT. LIMITED (ICVL) 13. NTPC-BHEL POWER PROJECTS PVT.LTD 14. BF NTPC ENERGY SYSTEM LIMITED. 15. NTPC-TELK 16. ENERGY EFFICIENCY SERVICES LTD. (EESL) 17. CIL-NTPC URJA PRIVATE LIMITED (CNUPL) 18. ANUSHAKTI VIDHYUT NIGAM LIMITED (ASHVINI) 19. PAN-ASIAN RENEWABLES PRIVATE LIMITED 20. TRINCOMALEE POWER COMPANY LIMITED 21. BANGLADESH-INDIA FRIENDSHIP POWER COMPANY PRIVATE LIMITED (BIFPCL)
  • 18. Working of power plant • To understand working of NTPC we studied Anta Gas Based Combined Cycle Power Project. • Anta Gas Based Combined Cycle Power Project is not only the first Gas Power Plant of NTPC but is also the beginning of an era of state of art Combined Cycle Power Plants in the country.
  • 19. NTPC Gas Power Plant Anta • Established in : 1989 • Type of station : Gas based combined cycle • Location : Anta in Baran district of Rajasthan • Total land : 390.75 acres. • Fuel : Natural Gas, Naphtha • Fuel source : By GAIL through HBJ Pipe line • Water source : KOTA RIGHT MAIN CANAL • Reservoir : 10 Million m3 , for One Month • Gas Turbine Output : 3 X 88.71 MW • Steam Turbine Output : 153.20 MW • Net plant Output : 419.33MW
  • 20. Applications of Gas Turbine Conventional applications are • Simple cycle operation. • Combined cycle operation. Electric utility companies use gas turbine predominantly in simple cycle and combined cycle applications. Combined cycle operation is much efficient than open cycle operation.
  • 21. COMBINED CYCLE Combined cycle power plant integrates two power conversion cycles • Brayton cycle (gas-turbine) and • Rankine cycle (steam-turbine) • with the principal objective of increasing overall plant efficiency.
  • 22. G Gas Turbine Air Fuel 100% input Exhaust gas G 15% Steam 16%Steam Turbine WHRB 33% Condenser 36% Combined Cycle Process Reservoir Inlet Temp. 1005 °C flue gas temp. 505 °C
  • 23. Combined Cycle Process • Gas turbine exhaust is at temperature of 500-550 c • Rankine cycle heat is required to generate of 500-550 c • Gas turbine exhaust heat can be recovered using a waste heat recovery boiler to run a steam turbine on Rankine cycle • If efficiency of gas turbine cycle is 33% and • the efficiency of Rankine cycle is 16% • then over all efficiency comes to 49%.
  • 24. Waste Heat Recovery Boiler • Anta Combined cycle power plant also known as Waste Heat Recovery Boilers (WHRB) plant. • which are of non-fired, dual pressure and forced circulation type. • The boiler has two different water/steam cycle known as high-pressure system and low-pressure system.
  • 25. 220 kV Switchyard A Switchyard is the place at which switching operation of power distribution is performed. NTPC-Anta Gas Power Station has a 220 kV Switchyard which is used for switching operation and power evacuation for six 220 kV transmission lines.
  • 26. There are total six 220 kv transmission lines for evacuation of power generated at Anta.  Two lines for Bhilwara,  One lines for Dousa,  One lines for SawaiMadhopur,  One line for Kota and  One line for RAPP. POWER EVACUATION FROM NTPC-ANTA
  • 27. Vision And Mission Of NTPC • Vision • To be the world’s largest and best power producer, powering India’s growth. • Mission • Develop and provide reliable power, related products and services at competitive prices, integrating multiple energy sources with innovative and eco-friendly technologies and contribute to society.
  • 28. Core Values – BE COMMITTED • B Business Ethics • E Environmentally & Economically Sustainable • C Customer Focus • O Organisational & Professional Pride • M Mutual Respect & Trust • M Motivating Self & others • I Innovation & Speed • T Total Quality for Excellence • T Transparent & Respected Organisation • E Enterprising • D Devoted
  • 29. Strategy • to contribute to sustainable development by discharging corporate social responsibilities. • To lead the sector in the areas of resettlement & rehabilitation, environment protection including effective ash utilization, peripheral development and energy conservation practices. • To lead development efforts in the Indian power sector through efforts at policy advocacy, assisting customers in reforms, disseminating best practices in the operation and management of power plants etc.
  • 30. Policies • Contribute towards clean and sustainable environment with respect to land, water and air. • Conserve resources by reduction, reuse and recycling • Initiate and support measures to optimize the use of renewable energy, increase energy efficiency and reduce Green House Gases emissions. • Be transparent, ethical and fair to all stakeholders • Be supportive in developing and enhancing people’s standard of living in and around the plants. • Generate awareness, share knowledge and support training programmes on sustainable development among the employees, neighbouring communities and public at large.
  • 31. FINANCIAL RESULTS 2013-14 2013-14 2012-13 2012-13 Revenue Rs. Crore US $ Mn* Rs. Crore US $ Mn* Net Revenue from Operations 72,018.93 11,882.35 65,737.04 10,845.91 Other Income 2,688.89 443.64 3,118.77 514.56 Total Revenue 74,707.82 12,325.99 68,855.81 11,360.47 Expenses Total Expenses 60,803.17 10,031.87 53,961.29 8,903.04 Profit before Tax and exceptional items 13,904.65 2,294.12 14,894.52 2,457.43 Exceptional items - - 1,684.11 277.86 Profit before tax 13,904.65 2,294.12 16,578.63 2,735.29 Tax Expense 2,929.91 483.40 3,959.24 653.23 Profit for the year 10,974.74 1,810.71 12,619.39 2,082.06
  • 32. 2013-14 2013-14 2012-13 2012-13 Appropriations: Rs. Crore US $ Mn* Rs. Crore US $ Mn* Transfer to bond redemption reserve 576.08 95.05 492.79 81.31 Transfer to general reserve 5,000.00 824.95 6,500.00 1,072.43 Transfer to capital reserve 4.98 0.82 0.97 0.16 Interim dividend 3,298.19 544.17 3,092.07 510.16 Proposed dividend 1,442.96 238.07 1,649.09 272.08 Tax on dividend 804.74 132.77 781.87 129.00 *1US $= Rs. 60.61 as on March 31, 2014
  • 33. Recognitions & Awards • Company Rankings:- • NTPC has been bestowed the honour of being most respected company in Power Sector for the year 2011 by Business world. • Company is ranked 424th largest company in the world, 16th among the global electric utilities. • 2nd among the Asian electric utilities as per Forbes Global 2000 ranking for 2014. • Company was ranked No. 1 Independent Power Producer and Energy Trader Globally in the Platts Top 250 Global Energy Company Rankings, 2013. Company has been able to maintain this ranking consistently since 2011. • Environment Awards:- Earth care Award 2012 to NTPC for Climate Change Initiatives. and many more awards are presented to NTPC.
  • 34. Future plan of NTPC NTPC has formulated a long term Corporate Plan to become a 1,28,000 MW company upto 2032. Towards this goal, NTPC has adopted a multi prong strategy to ensure robust growth of the company.
  • 35. References • http://www.ntpc.co.in/en • https://en.wikipedia.org/wiki/Electricity_sector_in_India#Demand • https://en.wikipedia.org/wiki/World_energy_consumption • https://en.wikipedia.org/wiki/List_of_power_stations_in_India • http://www.moneycontrol.com/annual-report/ntpc/directors- report/NTP#NTP
  • 36. THANK YOU ! ANY QUERY?