NETWORK ANALYSIS
(CPM & PERT)
NAME: NARRA MOUNIKA
PIN: 21BQ5A0514
NETWORKANALYSIS
 Network Analysis refers to a number of techniques for
the planning and control of complex projects.
 The two most frequently used forms Of network
planning are:
1. Programme Evaluation and ReviewT
echnique
2. Critical Path Method (CPM)
WHAT ISANETWORK?
A network is a graphical diagram
consisting of certain configuration of “Arrows”
() and “Nodes” () for showing the logical
sequence of various tasks to be performed to
achieve the project objective.
TERMS USED INANETWORK
1. Activity: An effort that is required to
complete a part of the project. It is
represented by “”.
2. Node: It represents the beginning or
completion of an activity. It is
represented by “”
RULES OF NETWORK CONSTRUCTION
1. Each defined activity is represented by one
and only one arrow in the network.
2. Before an activity can be undertaken, all
activities preceding it must be completed.
3. The arrows depicting various activities are
indicative of logical procedure only. The
length and bearing of the arrows are of no
significance.
4. The arrow direction indicates the general
progression in time. Head events and Tail events.
5. When a number of activities terminate at one
event, it indicates that no activity emanating from
that event may start unless all activities terminating
there have been completed.
6. Events are identified by numbers.
7. The activities are identified by the numbers of their
starting and ending events or by alphabets.
8. Anetwork should have only one initial and terminal
node.
Merge Event
Burst Event
A
B
C
A
B
C
10. Parallel activities between two events, without
intervening events, are prohibited. When two or
more parallel activities in a project have the same
head and tail events, dummy activities are needed in
constructing the network.
Dummy activities do not consume time or
resources. An efficient network contains a
minimum number of dummy activities required to
portray the correct precedence relationships.
11. Looping is not permitted in a network.
NETWORK SYMBOLS
SYMBOL MEANING
Activity
Event
Activity A must be completed before
Activity B completed
Activities A & B can occur
concurrently, but both must be
completed before activity C can begin
Activities A & B must be completed
before activities C & D can begin, but
C can begin independently of D & vice
versa
SAMPLE NETWORK
DUMMY ACTIVITY
CRITICAL PATH METHOD
CPM aims at the determination of the
time to complete a project and the
important activities on which a
manager shall focus attention.
PROCEDURE
Consider all the paths in a project, beginning with
the start event and stopping at the end event.
 For each path, calculate the time of execution.
The path with the largest time is called the critical
path and the activities along this path are called
critical activities or bottleneck activities.
THANKING YOU

More Related Content

Similar to EEM MID2.PPT.pptx

Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMMubashir Ali
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 pptahsanrabbani
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
 
Network analysis
Network analysisNetwork analysis
Network analysisKamel Attar
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxTecnicoItca
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxNaimishKishor
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLSiddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02kongara
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking TechniquesAaliButt1
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxYagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxjeffevans62972
 

Similar to EEM MID2.PPT.pptx (20)

Lect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPMLect-6&7: Network Diagrams, PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
Spm
SpmSpm
Spm
 
CPM and PERT
CPM and  PERTCPM and  PERT
CPM and PERT
 
Network analysis
Network analysisNetwork analysis
Network analysis
 
Qabd 13
Qabd 13Qabd 13
Qabd 13
 
PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Network Anaysis_ critical path methods
Network Anaysis_ critical path methodsNetwork Anaysis_ critical path methods
Network Anaysis_ critical path methods
 
project network
project networkproject network
project network
 
Network construction
Network construction  Network construction
Network construction
 
Project Networking Techniques
Project Networking TechniquesProject Networking Techniques
Project Networking Techniques
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
IGNOU PERT CPM
IGNOU PERT CPMIGNOU PERT CPM
IGNOU PERT CPM
 
Ovi project
Ovi  projectOvi  project
Ovi project
 
Scheduling
SchedulingScheduling
Scheduling
 
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docxYagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
Yagmur Bostanci47 Hackensack Street, East Rutherford, NJ929-22.docx
 

More from mounikanarra3

functionsinc-130108032745-phpapp01.pdf
functionsinc-130108032745-phpapp01.pdffunctionsinc-130108032745-phpapp01.pdf
functionsinc-130108032745-phpapp01.pdfmounikanarra3
 
travelingsalesmanproblem-170122053648.pdf
travelingsalesmanproblem-170122053648.pdftravelingsalesmanproblem-170122053648.pdf
travelingsalesmanproblem-170122053648.pdfmounikanarra3
 
Space complexity-DAA.pptx
Space complexity-DAA.pptxSpace complexity-DAA.pptx
Space complexity-DAA.pptxmounikanarra3
 
(PAD_5)Dynamic_Programming.ppt
(PAD_5)Dynamic_Programming.ppt(PAD_5)Dynamic_Programming.ppt
(PAD_5)Dynamic_Programming.pptmounikanarra3
 
sequencediagram-150302224029-conversion-gate01 (1).pdf
sequencediagram-150302224029-conversion-gate01 (1).pdfsequencediagram-150302224029-conversion-gate01 (1).pdf
sequencediagram-150302224029-conversion-gate01 (1).pdfmounikanarra3
 
exp227-jan-170127160848 (3) (1).pdf
exp227-jan-170127160848 (3) (1).pdfexp227-jan-170127160848 (3) (1).pdf
exp227-jan-170127160848 (3) (1).pdfmounikanarra3
 
stephenhawkingppt-160402093003.pdf
stephenhawkingppt-160402093003.pdfstephenhawkingppt-160402093003.pdf
stephenhawkingppt-160402093003.pdfmounikanarra3
 

More from mounikanarra3 (15)

unit-2.pdf
unit-2.pdfunit-2.pdf
unit-2.pdf
 
Unit - 4.pptx
Unit - 4.pptxUnit - 4.pptx
Unit - 4.pptx
 
UNIT-1 (4).pdf
UNIT-1 (4).pdfUNIT-1 (4).pdf
UNIT-1 (4).pdf
 
functionsinc-130108032745-phpapp01.pdf
functionsinc-130108032745-phpapp01.pdffunctionsinc-130108032745-phpapp01.pdf
functionsinc-130108032745-phpapp01.pdf
 
travelingsalesmanproblem-170122053648.pdf
travelingsalesmanproblem-170122053648.pdftravelingsalesmanproblem-170122053648.pdf
travelingsalesmanproblem-170122053648.pdf
 
Space complexity-DAA.pptx
Space complexity-DAA.pptxSpace complexity-DAA.pptx
Space complexity-DAA.pptx
 
MID2 UML (1).pptx
MID2 UML (1).pptxMID2 UML (1).pptx
MID2 UML (1).pptx
 
(PAD_5)Dynamic_Programming.ppt
(PAD_5)Dynamic_Programming.ppt(PAD_5)Dynamic_Programming.ppt
(PAD_5)Dynamic_Programming.ppt
 
sequencediagram-150302224029-conversion-gate01 (1).pdf
sequencediagram-150302224029-conversion-gate01 (1).pdfsequencediagram-150302224029-conversion-gate01 (1).pdf
sequencediagram-150302224029-conversion-gate01 (1).pdf
 
UML.PPT.pptx
UML.PPT.pptxUML.PPT.pptx
UML.PPT.pptx
 
exp227-jan-170127160848 (3) (1).pdf
exp227-jan-170127160848 (3) (1).pdfexp227-jan-170127160848 (3) (1).pdf
exp227-jan-170127160848 (3) (1).pdf
 
stephenhawkingppt-160402093003.pdf
stephenhawkingppt-160402093003.pdfstephenhawkingppt-160402093003.pdf
stephenhawkingppt-160402093003.pdf
 
CP-STRING (1).ppt
CP-STRING (1).pptCP-STRING (1).ppt
CP-STRING (1).ppt
 
Array.pdf
Array.pdfArray.pdf
Array.pdf
 
routing.pptx
routing.pptxrouting.pptx
routing.pptx
 

Recently uploaded

Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction managementMariconPadriquez1
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptJasonTagapanGulla
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsSachinPawar510423
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 

Recently uploaded (20)

Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
computer application and construction management
computer application and construction managementcomputer application and construction management
computer application and construction management
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Solving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.pptSolving The Right Triangles PowerPoint 2.ppt
Solving The Right Triangles PowerPoint 2.ppt
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Vishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documentsVishratwadi & Ghorpadi Bridge Tender documents
Vishratwadi & Ghorpadi Bridge Tender documents
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 

EEM MID2.PPT.pptx

  • 1. NETWORK ANALYSIS (CPM & PERT) NAME: NARRA MOUNIKA PIN: 21BQ5A0514
  • 2. NETWORKANALYSIS  Network Analysis refers to a number of techniques for the planning and control of complex projects.  The two most frequently used forms Of network planning are: 1. Programme Evaluation and ReviewT echnique 2. Critical Path Method (CPM)
  • 3. WHAT ISANETWORK? A network is a graphical diagram consisting of certain configuration of “Arrows” () and “Nodes” () for showing the logical sequence of various tasks to be performed to achieve the project objective.
  • 4. TERMS USED INANETWORK 1. Activity: An effort that is required to complete a part of the project. It is represented by “”. 2. Node: It represents the beginning or completion of an activity. It is represented by “”
  • 5. RULES OF NETWORK CONSTRUCTION 1. Each defined activity is represented by one and only one arrow in the network. 2. Before an activity can be undertaken, all activities preceding it must be completed. 3. The arrows depicting various activities are indicative of logical procedure only. The length and bearing of the arrows are of no significance.
  • 6. 4. The arrow direction indicates the general progression in time. Head events and Tail events. 5. When a number of activities terminate at one event, it indicates that no activity emanating from that event may start unless all activities terminating there have been completed. 6. Events are identified by numbers. 7. The activities are identified by the numbers of their starting and ending events or by alphabets.
  • 7. 8. Anetwork should have only one initial and terminal node. Merge Event Burst Event A B C A B C
  • 8. 10. Parallel activities between two events, without intervening events, are prohibited. When two or more parallel activities in a project have the same head and tail events, dummy activities are needed in constructing the network. Dummy activities do not consume time or resources. An efficient network contains a minimum number of dummy activities required to portray the correct precedence relationships. 11. Looping is not permitted in a network.
  • 9. NETWORK SYMBOLS SYMBOL MEANING Activity Event Activity A must be completed before Activity B completed Activities A & B can occur concurrently, but both must be completed before activity C can begin Activities A & B must be completed before activities C & D can begin, but C can begin independently of D & vice versa
  • 12. CRITICAL PATH METHOD CPM aims at the determination of the time to complete a project and the important activities on which a manager shall focus attention.
  • 13. PROCEDURE Consider all the paths in a project, beginning with the start event and stopping at the end event.  For each path, calculate the time of execution. The path with the largest time is called the critical path and the activities along this path are called critical activities or bottleneck activities.