SlideShare a Scribd company logo
1 of 9
Download to read offline
Transient Recovery Voltage Analysis
Part-2 Final
By
Karthikeyan.S
Modelling:
โ€ข The most common problem found in EMTP case on TRV is to model the stray capacitance for
all equipment in the substation especially for the very large inductive machines like
transformer , reactor,..etc. The reason behind it is even a small value of capacitance can
contribute to the Rate of Rise of Recovery Voltage.
โ€ข For Line modelling , either go for constant paramter or frequency dependent model it would
be better. Comparing to IEEE guidelines model , FD model would give more accurate result.
โ€ข TRV is fairly a local study which means 30-40 miles radius around the circuit breaker would
be modelled especially for line TRV. Whenever these trasient studies are performed , by
default a travelling wave will be forwarding in the circuit. The network should be modelled
in such a way that the travelling wave would go far enough and donโ€™t have time to come
back and in practice if it have time to come back it means then the remote network also
need to be modelled. This is especially valide for Line TRV.
โ€ข When it comes to Transformer (Transformer Limited Fault) or Reactor TRV, it is not as critical
to model far off away the way of the capacitor of the breaker but for line charge it is
definitely important.
Sample Network:
The Below marked line need to be performed TRV studies. Here the total line length is 10KM(Short
Line). It is being modelled as 2 KM one line and in series with an other 8 KM Line. The reason behind
this type of modelling is which is very easy to place a single phase to ground in between them and
then it can isolated with the help of a TRV breaker. For the sake of modelling , both 2KM and 8KM
Line are FD model. When we perform TRV analysis, we typically focus on worst case scenario. They
are
1. Single Phase to Ground Fault( This will give us the worst RRRV . When the breaker trips,
current would be cut and the voltage will rise very quickly due to the first travelling wave at
the point where the fault is applied)
2. Three Phase Fault( This will give us the worst maximum TRV)
For TRV studies , a specific breaker is recommended for TRV in EMTP Tools
Network Details:
1. all transmission lines are modelled up to the next discontinuity.
2. Here , the transformers are not modelled with discontinuity why because it's a large inductive
device and transients will not go through it and there is no need to model discontinuity but
before it a simple network equivalent or a network equivalent source can be placed. This
source might can have parameters like source impedance which may be defined either with
short circuit impedance or with a short circuit current and power.
3. Substation is modelled here as node and all capacitances of the substation are lumped as a
single capacitor.
4. The stray capacitance of the Transformer are modelled as below image
For better precision, consider the straight capacitance between winding to winding and from
the primary to the secondary and winding to ground on the other side. This would be even a
best practice.
Fault Specification (3 phase/ single phase to ground/Transformer limited fault):
Terminal Fault (3 phase):
A three-phase fault ungrounded is being applied here which is the worst-case scenario would happen
for the sake of the demonstration which would open the TRV breaker. Now the TRV Breaker
parameters are entered. Here the circuit breaker opens at zero crossing for each phase individually.
Each phase will cut the current individually because the zero crossing will not occur at the same time.
The current margin needs to be specified which is called the chopping current (ranges from 0 to
maximum 50). Ex: For a VCB it is 50A
At the TRV Data tab of TRV Breaker properties dialog box, data required for the TRV Envelope need
to be entered. They are
1. Standard
2. Frequency
3. Breaker Class
4. Rated Voltage
5. Rated Short circuit current
6. Type of fault
7. Short circuit current to clear
The short circuit current to clear is the main parameter to define the TRV Envelope. This data can be
obtained from the steady state simulation.
Now the time domain simulation is started
The TRV is un successful.
Reason: Prospective TRV is not remain inside the inherent TRV
Analysis:
As 3 phase ungrounded fault is the most unlikely happening worst case scenario, modelling the
breaker with fault would increase the current rating of the breaker which in turn not a cost-
effective solution too.
Now the circuit is given a 3 phase to ground fault which is a normally happening scenario mostly
modelled for designing circuit breaker.
Similar methodology is followed for the Single Phase to Ground fault. Here also the TRV is
successful.
Transformer limited Fault (IEEE C37.06.01)
Network:
Type of Fault: 3ph-ground fault
TRV Data:
if the CB cuts at the maximum rated short circuit current then the curve here which will be used is
what is called the t100 which is the TRV for the maximum current.
if the CB cuts at 60% of this maximum current, then the curve here which will be used is what is
called the t60 and similarly we have the t30 and the t10.
This is a typical type of curve we get for a transformer fault. It is called as a Resonant TRV. It is
almost a pure sinusoidal where the frequency depends on the transformer inductance and the stray
capacitance between the breaker and the transformer.
In medium voltage application it's possible to use a RC Snubber circuit in order to lower this
frequency and the magnitude. The selected RC Snubber will have the resistance which will be equal
to the surge impedance of the cable/line system so typically between 40 and 70 ohm and then we will
put a capacitance of a 0.4 or a few micro farads in order to lower the frequency.
Credits to: EMTP Learner World.

More Related Content

What's hot

EC6503 TLWG - Waveform Distortion
EC6503 TLWG - Waveform DistortionEC6503 TLWG - Waveform Distortion
EC6503 TLWG - Waveform Distortionchitrarengasamy
ย 
General theory of transmission lines
General theory of transmission linesGeneral theory of transmission lines
General theory of transmission linesGopinathD17
ย 
Inrush current reduction in three phase power transformer by using prefluxing...
Inrush current reduction in three phase power transformer by using prefluxing...Inrush current reduction in three phase power transformer by using prefluxing...
Inrush current reduction in three phase power transformer by using prefluxing...IAEME Publication
ย 
Lineprotection basics june2008
Lineprotection basics june2008Lineprotection basics june2008
Lineprotection basics june2008lankeshdb
ย 
519 transmission line theory
519 transmission line theory519 transmission line theory
519 transmission line theorychanjee
ย 
Class06 transmission line_basics
Class06 transmission line_basicsClass06 transmission line_basics
Class06 transmission line_basicss.p.c.e.t.
ย 
Document org
Document orgDocument org
Document orgUday Reddy
ย 
K046016266
K046016266K046016266
K046016266IJERA Editor
ย 
BASIC CONCEPTS OF TRANSMISSION LINES & WAVEGUIDES ForC 18 DECE unit 1, SBTET
BASIC CONCEPTS OF TRANSMISSION LINES  &  WAVEGUIDES ForC 18 DECE unit 1, SBTETBASIC CONCEPTS OF TRANSMISSION LINES  &  WAVEGUIDES ForC 18 DECE unit 1, SBTET
BASIC CONCEPTS OF TRANSMISSION LINES & WAVEGUIDES ForC 18 DECE unit 1, SBTETjanakiravi
ย 
transmission line theory prp
transmission line theory prptransmission line theory prp
transmission line theory prpDr. Pravin Prajapati
ย 
Design & Implementation of Zero Voltage Switching Buck Converter
Design & Implementation of Zero Voltage Switching Buck ConverterDesign & Implementation of Zero Voltage Switching Buck Converter
Design & Implementation of Zero Voltage Switching Buck ConverterIJERA Editor
ย 
Symmetrical components in transient regime
Symmetrical components in transient regimeSymmetrical components in transient regime
Symmetrical components in transient regimegaonioni
ย 
Research Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and ScienceResearch Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and Scienceinventy
ย 
Unit-2 Three Phase controlled converter
Unit-2 Three Phase controlled converter Unit-2 Three Phase controlled converter
Unit-2 Three Phase controlled converter johny renoald
ย 
Mw lecture 3
Mw lecture 3Mw lecture 3
Mw lecture 3Sadaf Ayesha
ย 
ECNG 3015- System Earthing
ECNG 3015- System EarthingECNG 3015- System Earthing
ECNG 3015- System EarthingChandrabhan Sharma
ย 
Ec 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides bEc 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides barularumugam09
ย 
pulse width modulated inverter techniques
pulse width modulated inverter techniquespulse width modulated inverter techniques
pulse width modulated inverter techniquesSAURABH KUMAR
ย 

What's hot (20)

EC6503 TLWG - Waveform Distortion
EC6503 TLWG - Waveform DistortionEC6503 TLWG - Waveform Distortion
EC6503 TLWG - Waveform Distortion
ย 
General theory of transmission lines
General theory of transmission linesGeneral theory of transmission lines
General theory of transmission lines
ย 
Inrush current reduction in three phase power transformer by using prefluxing...
Inrush current reduction in three phase power transformer by using prefluxing...Inrush current reduction in three phase power transformer by using prefluxing...
Inrush current reduction in three phase power transformer by using prefluxing...
ย 
Lineprotection basics june2008
Lineprotection basics june2008Lineprotection basics june2008
Lineprotection basics june2008
ย 
519 transmission line theory
519 transmission line theory519 transmission line theory
519 transmission line theory
ย 
Class06 transmission line_basics
Class06 transmission line_basicsClass06 transmission line_basics
Class06 transmission line_basics
ย 
Document org
Document orgDocument org
Document org
ย 
K046016266
K046016266K046016266
K046016266
ย 
BASIC CONCEPTS OF TRANSMISSION LINES & WAVEGUIDES ForC 18 DECE unit 1, SBTET
BASIC CONCEPTS OF TRANSMISSION LINES  &  WAVEGUIDES ForC 18 DECE unit 1, SBTETBASIC CONCEPTS OF TRANSMISSION LINES  &  WAVEGUIDES ForC 18 DECE unit 1, SBTET
BASIC CONCEPTS OF TRANSMISSION LINES & WAVEGUIDES ForC 18 DECE unit 1, SBTET
ย 
transmission line theory prp
transmission line theory prptransmission line theory prp
transmission line theory prp
ย 
Design & Implementation of Zero Voltage Switching Buck Converter
Design & Implementation of Zero Voltage Switching Buck ConverterDesign & Implementation of Zero Voltage Switching Buck Converter
Design & Implementation of Zero Voltage Switching Buck Converter
ย 
Project mac
Project macProject mac
Project mac
ย 
Symmetrical components in transient regime
Symmetrical components in transient regimeSymmetrical components in transient regime
Symmetrical components in transient regime
ย 
Research Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and ScienceResearch Inventy : International Journal of Engineering and Science
Research Inventy : International Journal of Engineering and Science
ย 
Unit-2 Three Phase controlled converter
Unit-2 Three Phase controlled converter Unit-2 Three Phase controlled converter
Unit-2 Three Phase controlled converter
ย 
ECNG 6503 #2
ECNG 6503  #2ECNG 6503  #2
ECNG 6503 #2
ย 
Mw lecture 3
Mw lecture 3Mw lecture 3
Mw lecture 3
ย 
ECNG 3015- System Earthing
ECNG 3015- System EarthingECNG 3015- System Earthing
ECNG 3015- System Earthing
ย 
Ec 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides bEc 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides b
ย 
pulse width modulated inverter techniques
pulse width modulated inverter techniquespulse width modulated inverter techniques
pulse width modulated inverter techniques
ย 

Similar to Transient Recovery Voltage Part-2

Factors to be considered while selecting CT
Factors to be considered while selecting CTFactors to be considered while selecting CT
Factors to be considered while selecting CTParth Patel
ย 
Transient Recovery Voltage (TRV) Studies.pdf
Transient Recovery Voltage (TRV) Studies.pdfTransient Recovery Voltage (TRV) Studies.pdf
Transient Recovery Voltage (TRV) Studies.pdfssuserfe5963
ย 
C0212014018
C0212014018C0212014018
C0212014018theijes
ย 
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...Premier Publishers
ย 
Electrical Protection Schemes in detail
Electrical Protection Schemes in detailElectrical Protection Schemes in detail
Electrical Protection Schemes in detailSlides Hub
ย 
A Design Technique To Reduce Nbti Effects From 5t Sram Cells
A Design Technique To Reduce Nbti Effects From 5t Sram CellsA Design Technique To Reduce Nbti Effects From 5t Sram Cells
A Design Technique To Reduce Nbti Effects From 5t Sram CellsIJERA Editor
ย 
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.pptAshaLatha456489
ย 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculationsRonald Santos
ย 
4b. INSTRUMENT TRANSFORMER SELECTION GUIDES.ppt
4b. INSTRUMENT TRANSFORMER SELECTION GUIDES.ppt4b. INSTRUMENT TRANSFORMER SELECTION GUIDES.ppt
4b. INSTRUMENT TRANSFORMER SELECTION GUIDES.pptssuserb444c3
ย 
Electrical measurement & measuring instruments [emmi (nee-302) -unit-2]
Electrical measurement & measuring instruments [emmi  (nee-302) -unit-2]Electrical measurement & measuring instruments [emmi  (nee-302) -unit-2]
Electrical measurement & measuring instruments [emmi (nee-302) -unit-2]Md Irshad Ahmad
ย 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrushmichaeljmack
ย 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrushsaad karboua
ย 
36-DGSG-Mod 6-Lec 33 Harmonic Indices.pdf
36-DGSG-Mod 6-Lec 33 Harmonic Indices.pdf36-DGSG-Mod 6-Lec 33 Harmonic Indices.pdf
36-DGSG-Mod 6-Lec 33 Harmonic Indices.pdfvikip35
ย 
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...Manmeet Singh
ย 
Vignettes in Grounding
Vignettes in GroundingVignettes in Grounding
Vignettes in Groundingmichaeljmack
ย 
Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme Samuel Okhuegbe
ย 

Similar to Transient Recovery Voltage Part-2 (20)

Factors to be considered while selecting CT
Factors to be considered while selecting CTFactors to be considered while selecting CT
Factors to be considered while selecting CT
ย 
CT and VT.pptx
CT and VT.pptxCT and VT.pptx
CT and VT.pptx
ย 
General electric
General electricGeneral electric
General electric
ย 
Transient Recovery Voltage (TRV) Studies.pdf
Transient Recovery Voltage (TRV) Studies.pdfTransient Recovery Voltage (TRV) Studies.pdf
Transient Recovery Voltage (TRV) Studies.pdf
ย 
C0212014018
C0212014018C0212014018
C0212014018
ย 
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
Dynamic Performance of Distance Relayson Series Compensated Transmission Line...
ย 
Introduction to CTs and PTs
Introduction to CTs and PTsIntroduction to CTs and PTs
Introduction to CTs and PTs
ย 
Electrical Protection Schemes in detail
Electrical Protection Schemes in detailElectrical Protection Schemes in detail
Electrical Protection Schemes in detail
ย 
A Design Technique To Reduce Nbti Effects From 5t Sram Cells
A Design Technique To Reduce Nbti Effects From 5t Sram CellsA Design Technique To Reduce Nbti Effects From 5t Sram Cells
A Design Technique To Reduce Nbti Effects From 5t Sram Cells
ย 
Introduction to CTs and PTs
Introduction to CTs and PTsIntroduction to CTs and PTs
Introduction to CTs and PTs
ย 
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt283481961-POWER-SYSTEM-FAULTS-ppt.ppt
283481961-POWER-SYSTEM-FAULTS-ppt.ppt
ย 
Short circuit current calculations
Short circuit current calculationsShort circuit current calculations
Short circuit current calculations
ย 
4b. INSTRUMENT TRANSFORMER SELECTION GUIDES.ppt
4b. INSTRUMENT TRANSFORMER SELECTION GUIDES.ppt4b. INSTRUMENT TRANSFORMER SELECTION GUIDES.ppt
4b. INSTRUMENT TRANSFORMER SELECTION GUIDES.ppt
ย 
Electrical measurement & measuring instruments [emmi (nee-302) -unit-2]
Electrical measurement & measuring instruments [emmi  (nee-302) -unit-2]Electrical measurement & measuring instruments [emmi  (nee-302) -unit-2]
Electrical measurement & measuring instruments [emmi (nee-302) -unit-2]
ย 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
ย 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
ย 
36-DGSG-Mod 6-Lec 33 Harmonic Indices.pdf
36-DGSG-Mod 6-Lec 33 Harmonic Indices.pdf36-DGSG-Mod 6-Lec 33 Harmonic Indices.pdf
36-DGSG-Mod 6-Lec 33 Harmonic Indices.pdf
ย 
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...
Presentation_ON-CHIP CURRENT SENSING TECHNIQUE FOR CMOS MONOLITHIC SWITCH-MOD...
ย 
Vignettes in Grounding
Vignettes in GroundingVignettes in Grounding
Vignettes in Grounding
ย 
Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme Summary Presentation on PMU Based Transmission Line Protection Scheme
Summary Presentation on PMU Based Transmission Line Protection Scheme
ย 

Recently uploaded

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
ย 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
ย 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VDineshKumar4165
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
ย 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
ย 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...SUHANI PANDEY
ย 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
ย 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Christo Ananth
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
ย 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
ย 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
ย 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesPrabhanshu Chaturvedi
ย 
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...Call Girls in Nagpur High Profile
ย 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
ย 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
ย 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .DerechoLaboralIndivi
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
ย 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
ย 
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...9953056974 Low Rate Call Girls In Saket, Delhi NCR
ย 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spaintimesproduction05
ย 

Recently uploaded (20)

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
ย 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
ย 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
ย 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
ย 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
ย 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
ย 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
ย 
Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...Call for Papers - International Journal of Intelligent Systems and Applicatio...
Call for Papers - International Journal of Intelligent Systems and Applicatio...
ย 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
ย 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
ย 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
ย 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
ย 
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth โŸŸ 6297143586 โŸŸ Call Me For Genuine Se...
ย 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
ย 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
ย 
NFPA 5000 2024 standard .
NFPA 5000 2024 standard                                  .NFPA 5000 2024 standard                                  .
NFPA 5000 2024 standard .
ย 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
ย 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
ย 
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar  โ‰ผ๐Ÿ” Delhi door step de...
Call Now โ‰ฝ 9953056974 โ‰ผ๐Ÿ” Call Girls In New Ashok Nagar โ‰ผ๐Ÿ” Delhi door step de...
ย 
Vivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design SpainVivazz, Mieres Social Housing Design Spain
Vivazz, Mieres Social Housing Design Spain
ย 

Transient Recovery Voltage Part-2

  • 1. Transient Recovery Voltage Analysis Part-2 Final By Karthikeyan.S
  • 2. Modelling: โ€ข The most common problem found in EMTP case on TRV is to model the stray capacitance for all equipment in the substation especially for the very large inductive machines like transformer , reactor,..etc. The reason behind it is even a small value of capacitance can contribute to the Rate of Rise of Recovery Voltage. โ€ข For Line modelling , either go for constant paramter or frequency dependent model it would be better. Comparing to IEEE guidelines model , FD model would give more accurate result. โ€ข TRV is fairly a local study which means 30-40 miles radius around the circuit breaker would be modelled especially for line TRV. Whenever these trasient studies are performed , by default a travelling wave will be forwarding in the circuit. The network should be modelled in such a way that the travelling wave would go far enough and donโ€™t have time to come back and in practice if it have time to come back it means then the remote network also need to be modelled. This is especially valide for Line TRV. โ€ข When it comes to Transformer (Transformer Limited Fault) or Reactor TRV, it is not as critical to model far off away the way of the capacitor of the breaker but for line charge it is definitely important. Sample Network: The Below marked line need to be performed TRV studies. Here the total line length is 10KM(Short Line). It is being modelled as 2 KM one line and in series with an other 8 KM Line. The reason behind this type of modelling is which is very easy to place a single phase to ground in between them and then it can isolated with the help of a TRV breaker. For the sake of modelling , both 2KM and 8KM Line are FD model. When we perform TRV analysis, we typically focus on worst case scenario. They are 1. Single Phase to Ground Fault( This will give us the worst RRRV . When the breaker trips, current would be cut and the voltage will rise very quickly due to the first travelling wave at the point where the fault is applied) 2. Three Phase Fault( This will give us the worst maximum TRV)
  • 3. For TRV studies , a specific breaker is recommended for TRV in EMTP Tools Network Details: 1. all transmission lines are modelled up to the next discontinuity. 2. Here , the transformers are not modelled with discontinuity why because it's a large inductive device and transients will not go through it and there is no need to model discontinuity but before it a simple network equivalent or a network equivalent source can be placed. This source might can have parameters like source impedance which may be defined either with short circuit impedance or with a short circuit current and power. 3. Substation is modelled here as node and all capacitances of the substation are lumped as a single capacitor.
  • 4. 4. The stray capacitance of the Transformer are modelled as below image For better precision, consider the straight capacitance between winding to winding and from the primary to the secondary and winding to ground on the other side. This would be even a best practice. Fault Specification (3 phase/ single phase to ground/Transformer limited fault): Terminal Fault (3 phase):
  • 5. A three-phase fault ungrounded is being applied here which is the worst-case scenario would happen for the sake of the demonstration which would open the TRV breaker. Now the TRV Breaker parameters are entered. Here the circuit breaker opens at zero crossing for each phase individually. Each phase will cut the current individually because the zero crossing will not occur at the same time. The current margin needs to be specified which is called the chopping current (ranges from 0 to maximum 50). Ex: For a VCB it is 50A At the TRV Data tab of TRV Breaker properties dialog box, data required for the TRV Envelope need to be entered. They are 1. Standard 2. Frequency 3. Breaker Class 4. Rated Voltage 5. Rated Short circuit current 6. Type of fault 7. Short circuit current to clear The short circuit current to clear is the main parameter to define the TRV Envelope. This data can be obtained from the steady state simulation.
  • 6. Now the time domain simulation is started The TRV is un successful. Reason: Prospective TRV is not remain inside the inherent TRV
  • 7. Analysis: As 3 phase ungrounded fault is the most unlikely happening worst case scenario, modelling the breaker with fault would increase the current rating of the breaker which in turn not a cost- effective solution too. Now the circuit is given a 3 phase to ground fault which is a normally happening scenario mostly modelled for designing circuit breaker. Similar methodology is followed for the Single Phase to Ground fault. Here also the TRV is successful.
  • 8. Transformer limited Fault (IEEE C37.06.01) Network: Type of Fault: 3ph-ground fault
  • 9. TRV Data: if the CB cuts at the maximum rated short circuit current then the curve here which will be used is what is called the t100 which is the TRV for the maximum current. if the CB cuts at 60% of this maximum current, then the curve here which will be used is what is called the t60 and similarly we have the t30 and the t10. This is a typical type of curve we get for a transformer fault. It is called as a Resonant TRV. It is almost a pure sinusoidal where the frequency depends on the transformer inductance and the stray capacitance between the breaker and the transformer. In medium voltage application it's possible to use a RC Snubber circuit in order to lower this frequency and the magnitude. The selected RC Snubber will have the resistance which will be equal to the surge impedance of the cable/line system so typically between 40 and 70 ohm and then we will put a capacitance of a 0.4 or a few micro farads in order to lower the frequency. Credits to: EMTP Learner World.