SlideShare a Scribd company logo
1 of 3
Download to read offline
- VICTORIA PROJECT: SRI LANKA
EvSum392
VICTORIA PROJECT: SRI LANKA
The Project - The Evaluation - The Main Findings - Lessons
The Project
The Victoria project is part of the Accelerated Mahaweli Development Programme
(AMDP). It is a power and irrigation project, but the irrigation component consists only
of water storage in the reservoir behind the Victoria Dam. The project cost in excess of
Rs 9000m, including £113m (Rs 6557m) of British grant aid, and was inaugurated in
April 1985.
The Evaluation
The evaluation report was prepared by a team comprising an economist, engineer,
sociologist, and environmentalist, led by a member of the ODA Evaluation Department.
The work included a three week visit to Sri Lanka in May 1986.
The evaluation report re-assesses the project shortly after its completion. The report
contains some important lessons for planning similar projects or indeed any major
construction project in the future, and makes recommendations to assist in the future
operation of the project. The numerous detailed conclusions and recommendations are
readily accessible in the 30 page summary in Volume I.
Careful management and monitoring of the project by all concerned helped ensure that
the civil, electrical and mechanical works were completed successfully, on time and
within the original budget, in spite of some difficult problems which arose during
construction.
The main focus of the study was on the social, environmental and economic aspects
from which it was thought the main lessons were to be learned. These lessons are
summarised below.
The Main Findings
About 30,000 people were displaced by the project, over four times the number
predicted:
● Although implemented without outside assistance the resettlement programme
after a slow and very uncertain start was achieved within the necessary timetable.
● The lack of advance planning, the small number of staff and the initial
underestimation of the number of people affected, meant that the programme was
implemented under severe time pressure.
● This necessitated concentration on the immediate problems of property
file:///Y|/DFID_Original/Eval Report/ev_s392.htm (1 of 3) [22/07/2004 14:49:23]
- VICTORIA PROJECT: SRI LANKA
acquisition, compensation and resettlement, to the detriment of longer term
resettlement planning; this imposed unnecessary costs on the settlers.
The environment created by the dam is dynamic and complex:
● A number of aspects require management.
● In the absence of management plans drawn up prior to development these issues
were being addressed (in May 1986) on an ad-hoc basis, but there were
insufficient funds and a lack of focus and direction.
● Problems, such as control of water levels in the dam, prevention of malaria below
the dam, poor water quality in lakeside settlements might have been lessened and
the exploitation of benefits (fisheries, recreation, and a heightened awareness of
the need for watershed management) might have been increased had
environmental issues received greater attention during appraisal and project
monitoring.
● Assistance for remedial measures has been offered by the British Government and
is being considered with the Sri Lankan government.
The re-estimated rate-of-return is 8% about 4% less than that at appraisal, mainly
because power output is now expected to be less than forecast in 1978 and the prospects
for irrigation benefits are poor.
● But allocating the costs of Victoria between the power and irrigation components
shows that the project is a cost-effective means of power generation.
● The power output from Victoria depends on how the river systems are managed,
and on how other power plants and the irrigation schemes are operated. The
trade-offs are particularly complex.
● It is likely that continued improvements in planning and operational planning will
increase the returns to Victoria and other Maheweli projects taken together.
The Sri Lanka Electricity Board which now owns and operates the Victoria power
station is in a much healthier financial position than in 1978. This is as much due to
substantial increases in tariffs and improved management as to the expansion in sales
which the Victoria and other projects have made possible.
Lessons
● More comprehensive planning and more extensive data at the outset (had either
been available) might have improved the economic returns.
● It is very difficult to maximise benefits from power and irrigation projects in the
absence of comprehensive studies of the systems to which they contribute.
-- Preparation of such studies requires a mass of hydrological, financial, agricultural,
social and environmental data and computer models developed over a number of years.
-- The best way to achieve this is through development of the local institutions
concerned. Short term and partial studies by consultants are neither a cost-effective nor a
file:///Y|/DFID_Original/Eval Report/ev_s392.htm (2 of 3) [22/07/2004 14:49:23]
- VICTORIA PROJECT: SRI LANKA
professionally adequate substitute. In this instance there was not much alternative given
the severe time constraints.
● Long term planning and project preparation by both recipient institutions and aid
agencies might help avoid similar predicaments in the future, and thereby secure
higher rates of return.
● Projects such as Victoria require detailed attention to social and environmental
matters at the appraisal stage. A lack of knowledge and understanding about them
involves a degree of risk.
● Inadequate attention to social matters reduces the efficiency with which
resettlement programmes can be implemented and impose unnecessary cost on
evacuees and governments. This could cause financial crisis and lead to projects
being halted.
● Clear understanding of the environmental issues at appraisal facilitates better
arrangements for dealing with a range of problems (such as weed control and
malaria prevention) and provides a better basis for exploiting the environmental
benefits.
file:///Y|/DFID_Original/Eval Report/ev_s392.htm (3 of 3) [22/07/2004 14:49:23]

More Related Content

Similar to ev392s.pdf

Hydro Priyank jain
Hydro Priyank jain Hydro Priyank jain
Hydro Priyank jain PRIYANK JAIN
 
CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...
CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...
CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...OECD Environment
 
Nationally Appropriate Mitigation Actions (NAMA) in the Energy Generation and...
Nationally Appropriate Mitigation Actions (NAMA) in the Energy Generation and...Nationally Appropriate Mitigation Actions (NAMA) in the Energy Generation and...
Nationally Appropriate Mitigation Actions (NAMA) in the Energy Generation and...Janathakshan Gte Ltd
 
Bunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model townBunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model townSmart Villages
 
Roadmap workshop II, Cecilia Tam, Chetna Hareesh Kumar, OECD
Roadmap workshop II, Cecilia Tam, Chetna Hareesh Kumar, OECDRoadmap workshop II, Cecilia Tam, Chetna Hareesh Kumar, OECD
Roadmap workshop II, Cecilia Tam, Chetna Hareesh Kumar, OECDOECD Environment
 
National Adaptation Plan Zambia Country Experience
National Adaptation Plan Zambia Country ExperienceNational Adaptation Plan Zambia Country Experience
National Adaptation Plan Zambia Country ExperienceUNDP Climate
 
NAP Zambia Country Experience
NAP Zambia Country ExperienceNAP Zambia Country Experience
NAP Zambia Country ExperienceExternalEvents
 
P3 presentation - CCA.PPTX
P3 presentation - CCA.PPTXP3 presentation - CCA.PPTX
P3 presentation - CCA.PPTXMatt Meaker
 
Philippine Energy Plan: Towards a Sustainable and Clean Energy Future - Felix...
Philippine Energy Plan: Towards a Sustainable and Clean Energy Future - Felix...Philippine Energy Plan: Towards a Sustainable and Clean Energy Future - Felix...
Philippine Energy Plan: Towards a Sustainable and Clean Energy Future - Felix...OECD Environment
 
Climate finance - K. Enting (kfw) CCXG GF March 2014
Climate finance - K. Enting (kfw) CCXG GF March 2014Climate finance - K. Enting (kfw) CCXG GF March 2014
Climate finance - K. Enting (kfw) CCXG GF March 2014OECD Environment
 
Workshop WCP_WACDEP CAM_carolina carías_1 sep
Workshop WCP_WACDEP CAM_carolina carías_1 sepWorkshop WCP_WACDEP CAM_carolina carías_1 sep
Workshop WCP_WACDEP CAM_carolina carías_1 sepGlobal Water Partnership
 
The Inception Report
The Inception ReportThe Inception Report
The Inception Reportjryalo
 
Looking to a Future Climate-Smart Development in Bangladesh
Looking to a Future Climate-Smart Development in BangladeshLooking to a Future Climate-Smart Development in Bangladesh
Looking to a Future Climate-Smart Development in BangladeshPolicy Adda
 
Session 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilienceSession 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilienceNAP Events
 
Key issues and barriers in developing countries
Key issues and barriers in developing countriesKey issues and barriers in developing countries
Key issues and barriers in developing countriesGlobal CCS Institute
 
Enhancing Climate Resilience in African's Infrastructure
Enhancing Climate Resilience in African's Infrastructure Enhancing Climate Resilience in African's Infrastructure
Enhancing Climate Resilience in African's Infrastructure NAP Events
 
Grenada Experiences with Prioritization for Pipeline Development
Grenada Experiences with Prioritization for Pipeline DevelopmentGrenada Experiences with Prioritization for Pipeline Development
Grenada Experiences with Prioritization for Pipeline DevelopmentNAP Global Network
 

Similar to ev392s.pdf (20)

Hydro Priyank jain
Hydro Priyank jain Hydro Priyank jain
Hydro Priyank jain
 
Edwin Nateminya - Green Growth Diagnostics for Africa
Edwin Nateminya - Green Growth Diagnostics for AfricaEdwin Nateminya - Green Growth Diagnostics for Africa
Edwin Nateminya - Green Growth Diagnostics for Africa
 
CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...
CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...
CCXG March 2019 Veronica Gundu Jakarasi Challenges and Opportunities for Impl...
 
Nationally Appropriate Mitigation Actions (NAMA) in the Energy Generation and...
Nationally Appropriate Mitigation Actions (NAMA) in the Energy Generation and...Nationally Appropriate Mitigation Actions (NAMA) in the Energy Generation and...
Nationally Appropriate Mitigation Actions (NAMA) in the Energy Generation and...
 
Bunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model townBunaken Island | Nov-15 | Bitung low carbon model town
Bunaken Island | Nov-15 | Bitung low carbon model town
 
Roadmap workshop II, Cecilia Tam, Chetna Hareesh Kumar, OECD
Roadmap workshop II, Cecilia Tam, Chetna Hareesh Kumar, OECDRoadmap workshop II, Cecilia Tam, Chetna Hareesh Kumar, OECD
Roadmap workshop II, Cecilia Tam, Chetna Hareesh Kumar, OECD
 
National Adaptation Plan Zambia Country Experience
National Adaptation Plan Zambia Country ExperienceNational Adaptation Plan Zambia Country Experience
National Adaptation Plan Zambia Country Experience
 
NAP Zambia Country Experience
NAP Zambia Country ExperienceNAP Zambia Country Experience
NAP Zambia Country Experience
 
P3 presentation - CCA.PPTX
P3 presentation - CCA.PPTXP3 presentation - CCA.PPTX
P3 presentation - CCA.PPTX
 
Philippine Energy Plan: Towards a Sustainable and Clean Energy Future - Felix...
Philippine Energy Plan: Towards a Sustainable and Clean Energy Future - Felix...Philippine Energy Plan: Towards a Sustainable and Clean Energy Future - Felix...
Philippine Energy Plan: Towards a Sustainable and Clean Energy Future - Felix...
 
World Bank IAG1_Aug1997
World Bank IAG1_Aug1997World Bank IAG1_Aug1997
World Bank IAG1_Aug1997
 
Status of Climate Change Policy Development, Implementation, NAPA and NAMA in...
Status of Climate Change Policy Development, Implementation, NAPA and NAMA in...Status of Climate Change Policy Development, Implementation, NAPA and NAMA in...
Status of Climate Change Policy Development, Implementation, NAPA and NAMA in...
 
Climate finance - K. Enting (kfw) CCXG GF March 2014
Climate finance - K. Enting (kfw) CCXG GF March 2014Climate finance - K. Enting (kfw) CCXG GF March 2014
Climate finance - K. Enting (kfw) CCXG GF March 2014
 
Workshop WCP_WACDEP CAM_carolina carías_1 sep
Workshop WCP_WACDEP CAM_carolina carías_1 sepWorkshop WCP_WACDEP CAM_carolina carías_1 sep
Workshop WCP_WACDEP CAM_carolina carías_1 sep
 
The Inception Report
The Inception ReportThe Inception Report
The Inception Report
 
Looking to a Future Climate-Smart Development in Bangladesh
Looking to a Future Climate-Smart Development in BangladeshLooking to a Future Climate-Smart Development in Bangladesh
Looking to a Future Climate-Smart Development in Bangladesh
 
Session 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilienceSession 5.1: Programatic approach in building resilience
Session 5.1: Programatic approach in building resilience
 
Key issues and barriers in developing countries
Key issues and barriers in developing countriesKey issues and barriers in developing countries
Key issues and barriers in developing countries
 
Enhancing Climate Resilience in African's Infrastructure
Enhancing Climate Resilience in African's Infrastructure Enhancing Climate Resilience in African's Infrastructure
Enhancing Climate Resilience in African's Infrastructure
 
Grenada Experiences with Prioritization for Pipeline Development
Grenada Experiences with Prioritization for Pipeline DevelopmentGrenada Experiences with Prioritization for Pipeline Development
Grenada Experiences with Prioritization for Pipeline Development
 

Recently uploaded

UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 

Recently uploaded (20)

UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 

ev392s.pdf

  • 1. - VICTORIA PROJECT: SRI LANKA EvSum392 VICTORIA PROJECT: SRI LANKA The Project - The Evaluation - The Main Findings - Lessons The Project The Victoria project is part of the Accelerated Mahaweli Development Programme (AMDP). It is a power and irrigation project, but the irrigation component consists only of water storage in the reservoir behind the Victoria Dam. The project cost in excess of Rs 9000m, including £113m (Rs 6557m) of British grant aid, and was inaugurated in April 1985. The Evaluation The evaluation report was prepared by a team comprising an economist, engineer, sociologist, and environmentalist, led by a member of the ODA Evaluation Department. The work included a three week visit to Sri Lanka in May 1986. The evaluation report re-assesses the project shortly after its completion. The report contains some important lessons for planning similar projects or indeed any major construction project in the future, and makes recommendations to assist in the future operation of the project. The numerous detailed conclusions and recommendations are readily accessible in the 30 page summary in Volume I. Careful management and monitoring of the project by all concerned helped ensure that the civil, electrical and mechanical works were completed successfully, on time and within the original budget, in spite of some difficult problems which arose during construction. The main focus of the study was on the social, environmental and economic aspects from which it was thought the main lessons were to be learned. These lessons are summarised below. The Main Findings About 30,000 people were displaced by the project, over four times the number predicted: ● Although implemented without outside assistance the resettlement programme after a slow and very uncertain start was achieved within the necessary timetable. ● The lack of advance planning, the small number of staff and the initial underestimation of the number of people affected, meant that the programme was implemented under severe time pressure. ● This necessitated concentration on the immediate problems of property file:///Y|/DFID_Original/Eval Report/ev_s392.htm (1 of 3) [22/07/2004 14:49:23]
  • 2. - VICTORIA PROJECT: SRI LANKA acquisition, compensation and resettlement, to the detriment of longer term resettlement planning; this imposed unnecessary costs on the settlers. The environment created by the dam is dynamic and complex: ● A number of aspects require management. ● In the absence of management plans drawn up prior to development these issues were being addressed (in May 1986) on an ad-hoc basis, but there were insufficient funds and a lack of focus and direction. ● Problems, such as control of water levels in the dam, prevention of malaria below the dam, poor water quality in lakeside settlements might have been lessened and the exploitation of benefits (fisheries, recreation, and a heightened awareness of the need for watershed management) might have been increased had environmental issues received greater attention during appraisal and project monitoring. ● Assistance for remedial measures has been offered by the British Government and is being considered with the Sri Lankan government. The re-estimated rate-of-return is 8% about 4% less than that at appraisal, mainly because power output is now expected to be less than forecast in 1978 and the prospects for irrigation benefits are poor. ● But allocating the costs of Victoria between the power and irrigation components shows that the project is a cost-effective means of power generation. ● The power output from Victoria depends on how the river systems are managed, and on how other power plants and the irrigation schemes are operated. The trade-offs are particularly complex. ● It is likely that continued improvements in planning and operational planning will increase the returns to Victoria and other Maheweli projects taken together. The Sri Lanka Electricity Board which now owns and operates the Victoria power station is in a much healthier financial position than in 1978. This is as much due to substantial increases in tariffs and improved management as to the expansion in sales which the Victoria and other projects have made possible. Lessons ● More comprehensive planning and more extensive data at the outset (had either been available) might have improved the economic returns. ● It is very difficult to maximise benefits from power and irrigation projects in the absence of comprehensive studies of the systems to which they contribute. -- Preparation of such studies requires a mass of hydrological, financial, agricultural, social and environmental data and computer models developed over a number of years. -- The best way to achieve this is through development of the local institutions concerned. Short term and partial studies by consultants are neither a cost-effective nor a file:///Y|/DFID_Original/Eval Report/ev_s392.htm (2 of 3) [22/07/2004 14:49:23]
  • 3. - VICTORIA PROJECT: SRI LANKA professionally adequate substitute. In this instance there was not much alternative given the severe time constraints. ● Long term planning and project preparation by both recipient institutions and aid agencies might help avoid similar predicaments in the future, and thereby secure higher rates of return. ● Projects such as Victoria require detailed attention to social and environmental matters at the appraisal stage. A lack of knowledge and understanding about them involves a degree of risk. ● Inadequate attention to social matters reduces the efficiency with which resettlement programmes can be implemented and impose unnecessary cost on evacuees and governments. This could cause financial crisis and lead to projects being halted. ● Clear understanding of the environmental issues at appraisal facilitates better arrangements for dealing with a range of problems (such as weed control and malaria prevention) and provides a better basis for exploiting the environmental benefits. file:///Y|/DFID_Original/Eval Report/ev_s392.htm (3 of 3) [22/07/2004 14:49:23]