1. TIME SCHEDULLE
KEGIATAN : PEMBANGUNAN SALURAN DRAINASE / GORONG - GORONG KECAMATAN BENGKALIS
PEKERJAAN : #REF!
LOKASI : KEC. BENGKALIS
BOBOT
No. URAIAN PEKERJAAN %
1 2 3 4 5 6 7 8 9 10 11 12 13 14
UMUM 1.06 0.33 0.33
PEKERJAAN TANAH 4.14 2.02 2.02
STRUKTUR 94.80 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91 7.91
JUMLAH BOBOT 100.00
BOBOT RENCANA 0 0.3 2.4 2.0 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9 7.9
BOBOT KOMULATIEF 0.3 2.7 5 13 21 29 37 45 53 61 69 77 85 93
BOBOT REALISASI 0 1.52 1.7 1.91 7.50
Jangaka waktu pelaksanaan selama 120 (seratus dua puluh hari) kalender
Bengkalis, 20 Juli 2008
Di Buat Oleh:
Di Periksa Oleh: KONSULTAN PENGAWAS
PEJABAT PELAKSANA TEKNIS KEGIATAN CV. LINGKAR BUANA KONSULTAN
(PPTK)
FIRDAUS, Sst SUHAIMI, Amd
Nip.420011593 Supervision Engineering
BULAN I BULAN II BULAN III
W A K T U P E L A K S A N A N