1. I t lR t fR t
Internal Rate of Return
f f j
Internal rate of return of a project is that discount rate
which equates the aggregate present value of the cash
inflows (CFAT) of the project with the aggregate
present value of cash outflows of the project
The decision rule is :
Accept project only if IRR > required return
Steps to computing IRR –
1. Determine the project cash outflow and inflows
2. Take initial guestimate of the probable IRR rate
3. Compute NPV for such initial rates
4. Use intrapolation whenever needed
narain@fms.edu
2. Ill t ti
Illustration
A firm is considering following two projects for the
purpose of adoption in the next budget year. Their
f d i i h b d Th i
cash flow estimates are given below:
Year 0 1 2 3 4
Project A (45,555) 15,000 15,000 15,000 15,000
Project B (64,320) 20,000 25,000 28,000 24,000
Calculate the internal rate of return of both the projects
if required rate of return on the projects are 10%.
narain@fms.edu
4. Illustration
A firm is considering two projects, with a capital outlay
of Rs. 1,00,000 each and the following cash inflows.
Compute their internal rates of returns
returns.
Year 1 2 3 4
Project A 33,620 33,620 33,620 33,620
Project B - - - 1,36,050
narain@fms.edu
5. Exercise
You are required to analyse following two projects, each
with a cost of Rs. 10,000 and cost of capital is 5 The
p 5%.
projects’ expected net cash flows are as follows:
Year 1 2 3 4
Project X 6,500 3,000 3,000 1,000
Project Y 3,500 3,500 3,500 3,500
What is their Internal rate of return?
Which project should be accepted if they are
p j p y
independent?
Which project should be accepted if they are mutually
exclusive?
narain@fms.edu
6. Evaluating IRR method
It has intuitive appeal to those who want to analyse the
project in terms of rate of return
DDetermination of IRR does not depend on the
i i f IRR d d d h
required rate of return
It is consistent with NPV method for a single project
IRR method is based on the reinvestment assumption
by which cash flows of the project are reinvested at the
IRR itself: use MIRR
narain@fms.edu
7. Pitfalls of IRR
1. It is a relative measure of evaluation, not the absolute
one.
Projects Outflow Inflow IRR NPV @ 10%
A ‐1,000 +1,500 50% +364
B +1,000
+1 000 ‐1,500
1 500 50% ‐364
364
We need to modify the acceptance criterion for
borrowing and lending Projects
What to do in case project is both borrowing & lending?
Period 0 1 2 3
Cash Flows +1,000 ‐3,600 +4,320 ‐1,728
Min.
Min return 10% IRR=20% NPV=‐0.75
NPV= 0 75
narain@fms.edu
8. Pitf ll 2 C t ti lH d
Pitfall 2: Computational Hazards
Multiple rate of IRR
Period 0 1 2
Cash
‐1,600 1,000 ‐1,000
flow
IRR= 25% and 400% NPV at 10% = ‐1,517
No IRR
Period 0 1 2
Cash flows 1,000 3
‐3,000 2,500
5
narain@fms.edu
9. Pitfall 3: Mutually exclusive projects
Pitf ll 3 M t ll l i j t
Mutually exclusive projects are those projects from
which only one of them is to be chosen
T h i ll Fi
Technically or Financially
i ll
Inconsistent ranking of projects based on the IRR
criterion and other evaluation criterion
Size‐disparity
Time‐disparity
Life‐disparity
narain@fms.edu
10. Size Disparity Problem
Size Disparity Problem
Try this:
Printer
P i Outlay
O l CFAT IRR NPV @ 10%
NPV %
Inkjet 10,000 20,000 100% 8,182
LaserJet 20,000
20 000 35,000
35 000 75% 11,818
11 818
Which project will you prefer?
The difference lies in the implicit compounding rate of
interest
IRR – funds are compounded at the project IRR
NPV – funds are compounded at the discount rate
Use incremental project analysis if IRR has to be computed
narain@fms.edu