SlideShare a Scribd company logo
1 of 2
Download to read offline
BUILDING DEVELOPMENT PROCESS
STEPS APPLICANT WASA
Application
Application submitted with non-refundable fee ($2,500.00)
and required attachments as follows:
1. Completed application form
2. Town and Country Outline Approval
3. Topography Map
4. Location Map
5. Lotification Layout
6. Certificate of Environmental Clearance
7. Receipt for non-refundable Application Fee
Receives application and
issues reference number
Outline
Approval
Conducts Water Supply and
Wastewater feasibilities,
identifying conditions for
designs.
Issues Outline Approval.
Note: Where it is not feasible
to provide a water supply to
development a letter
indicating reasons will be
issued. Applicants will be
advised when to re-apply.
Design
Approval
Applicant submits designs as follows:
1. Four (4) copies of Water Reticulation Layout
2. Four (4) copies of Water Reticulation details
3. Four (4) copies of Wastewater Disposal System (for
treatment plants – detailed designs and calculation
are required)
4. Four (4) copies of Sewer Collections System design,
if applicable (layout and profile)
5. Preliminary Fire Approval (drawing and approval
letter)
6. Design submission review fee (refer to fee
schedule).
Note: Designs must be submitted on A1 size sheets (24” *
36”)
Where designs conform to
requirements a Design
Approval is issued.
Where designs do not
conform to requirements of
the Authority a Defects Letter
is issued specifying reasons
why designs cannot be
approved.
Note: Where designs are
rejected a resubmission fee is
applicable. Applicants must
make required corrections to
designs and resubmit with
applicable fee.
Inspection
and Testing
Applicant installs infrastructure as per approved designs and
submits the following:
INSPECTION
1. Inspection fees as per schedule
2. Inspection request form
INSPECTION
Inspections are conducted to
ensure water reticulation
infrastructure is installed in
PRESSURE TEST
1. Applicant submits pressure test fee as per schedule
2. Applicant pressures water reticulation system to
150PSI for date as indicated by WASA
METER INSPECTION
1. Applicant installs water service meters
2. Applicant submits request for meter inspection
accordance with approved
designs and using materials
required by WASA.
Note: Where installation is
not satisfactorily installed a re-
inspection fee equivalent to
initial fee will become payable
before re-inspections are
carried out
PRESSURE TEST
1. Applicant is advised
of date when
pressure test is to be
conducted
2. WASA Technician
visits site and installs
logger on water
reticulation system to
ensure there is no
pressure loss in
system (test can
either be 2 hours or
24 hours)
Note: Where pressure test
fails, Applicant must pay
another pressure test fee
before system is pressure
tested again.
METER INSPECTION
WASA Technician visits site
to inspect and test water
service meters. Once water
service meters are
satisfactorily installed
information for establishment
of accounts are recorded.
Completion
Certificate
Applicant submits payment for interconnection as per
WASA Estimate
WASA issues Completion
Certificate

More Related Content

Similar to WASA New Services Building Development process

TG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).docTG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).docjennbarroga7
 
Frontline services @website
Frontline services @websiteFrontline services @website
Frontline services @websiteValerie Alarcon
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013leo040490
 
InstallerTraining11_14_2014Final _
InstallerTraining11_14_2014Final _InstallerTraining11_14_2014Final _
InstallerTraining11_14_2014Final _Jeremiah Diaz
 
Three County Fairgrounds Stormwater Drainage Report 11-03-2010
Three County Fairgrounds Stormwater Drainage Report 11-03-2010Three County Fairgrounds Stormwater Drainage Report 11-03-2010
Three County Fairgrounds Stormwater Drainage Report 11-03-2010Adam Cohen
 
Understanding the Retro-Commissioning Process and its Benefits
Understanding the Retro-Commissioning Process and its BenefitsUnderstanding the Retro-Commissioning Process and its Benefits
Understanding the Retro-Commissioning Process and its Benefitsjasmine1020
 
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98osers
 
1 and 2 SRK WUL workshop introduction objectives and eWULAAS
1 and 2 SRK WUL workshop introduction objectives and eWULAAS1 and 2 SRK WUL workshop introduction objectives and eWULAAS
1 and 2 SRK WUL workshop introduction objectives and eWULAASsrkconsulting
 
BASIX-Project-First-Report-FINAL
BASIX-Project-First-Report-FINALBASIX-Project-First-Report-FINAL
BASIX-Project-First-Report-FINALKatherine Schwartz
 
Quality Assurance Procedures fro MCAP.ppt
Quality Assurance Procedures fro MCAP.pptQuality Assurance Procedures fro MCAP.ppt
Quality Assurance Procedures fro MCAP.pptknownet
 
West virginia qci check list
West virginia qci check listWest virginia qci check list
West virginia qci check listDanielle Amasia
 
Major Subdivision Review Process
Major Subdivision  Review ProcessMajor Subdivision  Review Process
Major Subdivision Review Processgscplanning
 
2017 NYC Apartment Management Checklist Free Chapter - Backflow Prevention De...
2017 NYC Apartment Management Checklist Free Chapter - Backflow Prevention De...2017 NYC Apartment Management Checklist Free Chapter - Backflow Prevention De...
2017 NYC Apartment Management Checklist Free Chapter - Backflow Prevention De...VendomeRealEstateMedia
 
Apartment Management Checklist 2017 - Publishing November 2016 - Chapter 4 Ex...
Apartment Management Checklist 2017 - Publishing November 2016 - Chapter 4 Ex...Apartment Management Checklist 2017 - Publishing November 2016 - Chapter 4 Ex...
Apartment Management Checklist 2017 - Publishing November 2016 - Chapter 4 Ex...VendomeRealEstateMedia
 
Wagstaff and Cartmell stairs
Wagstaff and Cartmell stairsWagstaff and Cartmell stairs
Wagstaff and Cartmell stairsRichard Clark
 
jordan updated resume 2015
jordan updated resume 2015jordan updated resume 2015
jordan updated resume 2015Manolito Jordan
 
Department X (DEPARTMENT X)Quality Management (QM)Project .docx
Department X (DEPARTMENT X)Quality Management (QM)Project .docxDepartment X (DEPARTMENT X)Quality Management (QM)Project .docx
Department X (DEPARTMENT X)Quality Management (QM)Project .docxsalmonpybus
 

Similar to WASA New Services Building Development process (20)

TG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).docTG-15595- report-and-analysis_powerpointviewer(1).doc
TG-15595- report-and-analysis_powerpointviewer(1).doc
 
Frontline services @website
Frontline services @websiteFrontline services @website
Frontline services @website
 
Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013Presentacion asme seccion viii division 2 2013
Presentacion asme seccion viii division 2 2013
 
InstallerTraining11_14_2014Final _
InstallerTraining11_14_2014Final _InstallerTraining11_14_2014Final _
InstallerTraining11_14_2014Final _
 
Mohamed elsayed updated
Mohamed elsayed updatedMohamed elsayed updated
Mohamed elsayed updated
 
Three County Fairgrounds Stormwater Drainage Report 11-03-2010
Three County Fairgrounds Stormwater Drainage Report 11-03-2010Three County Fairgrounds Stormwater Drainage Report 11-03-2010
Three County Fairgrounds Stormwater Drainage Report 11-03-2010
 
Understanding the Retro-Commissioning Process and its Benefits
Understanding the Retro-Commissioning Process and its BenefitsUnderstanding the Retro-Commissioning Process and its Benefits
Understanding the Retro-Commissioning Process and its Benefits
 
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
Spec05 pro-ka-kc151a -contractor_quality_control_dated_10-19-98
 
1 and 2 SRK WUL workshop introduction objectives and eWULAAS
1 and 2 SRK WUL workshop introduction objectives and eWULAAS1 and 2 SRK WUL workshop introduction objectives and eWULAAS
1 and 2 SRK WUL workshop introduction objectives and eWULAAS
 
Kd6
Kd6Kd6
Kd6
 
Presentation QMC
Presentation QMCPresentation QMC
Presentation QMC
 
BASIX-Project-First-Report-FINAL
BASIX-Project-First-Report-FINALBASIX-Project-First-Report-FINAL
BASIX-Project-First-Report-FINAL
 
Quality Assurance Procedures fro MCAP.ppt
Quality Assurance Procedures fro MCAP.pptQuality Assurance Procedures fro MCAP.ppt
Quality Assurance Procedures fro MCAP.ppt
 
West virginia qci check list
West virginia qci check listWest virginia qci check list
West virginia qci check list
 
Major Subdivision Review Process
Major Subdivision  Review ProcessMajor Subdivision  Review Process
Major Subdivision Review Process
 
2017 NYC Apartment Management Checklist Free Chapter - Backflow Prevention De...
2017 NYC Apartment Management Checklist Free Chapter - Backflow Prevention De...2017 NYC Apartment Management Checklist Free Chapter - Backflow Prevention De...
2017 NYC Apartment Management Checklist Free Chapter - Backflow Prevention De...
 
Apartment Management Checklist 2017 - Publishing November 2016 - Chapter 4 Ex...
Apartment Management Checklist 2017 - Publishing November 2016 - Chapter 4 Ex...Apartment Management Checklist 2017 - Publishing November 2016 - Chapter 4 Ex...
Apartment Management Checklist 2017 - Publishing November 2016 - Chapter 4 Ex...
 
Wagstaff and Cartmell stairs
Wagstaff and Cartmell stairsWagstaff and Cartmell stairs
Wagstaff and Cartmell stairs
 
jordan updated resume 2015
jordan updated resume 2015jordan updated resume 2015
jordan updated resume 2015
 
Department X (DEPARTMENT X)Quality Management (QM)Project .docx
Department X (DEPARTMENT X)Quality Management (QM)Project .docxDepartment X (DEPARTMENT X)Quality Management (QM)Project .docx
Department X (DEPARTMENT X)Quality Management (QM)Project .docx
 

More from Jeffrey James

Ttfs fire hydrant info
Ttfs fire hydrant infoTtfs fire hydrant info
Ttfs fire hydrant infoJeffrey James
 
Profile of a professional plumber jeffrey james
Profile of a professional plumber   jeffrey jamesProfile of a professional plumber   jeffrey james
Profile of a professional plumber jeffrey jamesJeffrey James
 
Preliminary application form (1 a) fire services
Preliminary application form (1 a) fire servicesPreliminary application form (1 a) fire services
Preliminary application form (1 a) fire servicesJeffrey James
 
Wasa new services fee schedule
Wasa new services   fee scheduleWasa new services   fee schedule
Wasa new services fee scheduleJeffrey James
 
Executive leadership 2012
Executive leadership  2012Executive leadership  2012
Executive leadership 2012Jeffrey James
 
WASA Wastewater and Potable Water Design Requirements
WASA Wastewater and Potable Water Design RequirementsWASA Wastewater and Potable Water Design Requirements
WASA Wastewater and Potable Water Design RequirementsJeffrey James
 
The Water and Sewerage act of Trinidad and Tobago (1980)
The Water and Sewerage act of Trinidad and Tobago  (1980)The Water and Sewerage act of Trinidad and Tobago  (1980)
The Water and Sewerage act of Trinidad and Tobago (1980)Jeffrey James
 
Draft policy on the Regulation of the Plumbing Sector in Trinidad and Tobago ...
Draft policy on the Regulation of the Plumbing Sector in Trinidad and Tobago ...Draft policy on the Regulation of the Plumbing Sector in Trinidad and Tobago ...
Draft policy on the Regulation of the Plumbing Sector in Trinidad and Tobago ...Jeffrey James
 
WOM Wastewater Management project
WOM Wastewater Management projectWOM Wastewater Management project
WOM Wastewater Management projectJeffrey James
 
Tpatt membership application form
Tpatt membership application formTpatt membership application form
Tpatt membership application formJeffrey James
 
Congratulations to Madame Prime Minister
Congratulations to Madame Prime MinisterCongratulations to Madame Prime Minister
Congratulations to Madame Prime MinisterJeffrey James
 

More from Jeffrey James (13)

Ttfs fire hydrant info
Ttfs fire hydrant infoTtfs fire hydrant info
Ttfs fire hydrant info
 
Profile of a professional plumber jeffrey james
Profile of a professional plumber   jeffrey jamesProfile of a professional plumber   jeffrey james
Profile of a professional plumber jeffrey james
 
Preliminary application form (1 a) fire services
Preliminary application form (1 a) fire servicesPreliminary application form (1 a) fire services
Preliminary application form (1 a) fire services
 
Wasa new services fee schedule
Wasa new services   fee scheduleWasa new services   fee schedule
Wasa new services fee schedule
 
Executive leadership 2012
Executive leadership  2012Executive leadership  2012
Executive leadership 2012
 
WASA Wastewater and Potable Water Design Requirements
WASA Wastewater and Potable Water Design RequirementsWASA Wastewater and Potable Water Design Requirements
WASA Wastewater and Potable Water Design Requirements
 
The Water and Sewerage act of Trinidad and Tobago (1980)
The Water and Sewerage act of Trinidad and Tobago  (1980)The Water and Sewerage act of Trinidad and Tobago  (1980)
The Water and Sewerage act of Trinidad and Tobago (1980)
 
Draft policy on the Regulation of the Plumbing Sector in Trinidad and Tobago ...
Draft policy on the Regulation of the Plumbing Sector in Trinidad and Tobago ...Draft policy on the Regulation of the Plumbing Sector in Trinidad and Tobago ...
Draft policy on the Regulation of the Plumbing Sector in Trinidad and Tobago ...
 
WOM Wastewater Management project
WOM Wastewater Management projectWOM Wastewater Management project
WOM Wastewater Management project
 
TPATT
TPATTTPATT
TPATT
 
Tpatt membership application form
Tpatt membership application formTpatt membership application form
Tpatt membership application form
 
Congratulations to Madame Prime Minister
Congratulations to Madame Prime MinisterCongratulations to Madame Prime Minister
Congratulations to Madame Prime Minister
 
Tpatt's Executive
Tpatt's ExecutiveTpatt's Executive
Tpatt's Executive
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 

Recently uploaded (20)

young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 

WASA New Services Building Development process

  • 1. BUILDING DEVELOPMENT PROCESS STEPS APPLICANT WASA Application Application submitted with non-refundable fee ($2,500.00) and required attachments as follows: 1. Completed application form 2. Town and Country Outline Approval 3. Topography Map 4. Location Map 5. Lotification Layout 6. Certificate of Environmental Clearance 7. Receipt for non-refundable Application Fee Receives application and issues reference number Outline Approval Conducts Water Supply and Wastewater feasibilities, identifying conditions for designs. Issues Outline Approval. Note: Where it is not feasible to provide a water supply to development a letter indicating reasons will be issued. Applicants will be advised when to re-apply. Design Approval Applicant submits designs as follows: 1. Four (4) copies of Water Reticulation Layout 2. Four (4) copies of Water Reticulation details 3. Four (4) copies of Wastewater Disposal System (for treatment plants – detailed designs and calculation are required) 4. Four (4) copies of Sewer Collections System design, if applicable (layout and profile) 5. Preliminary Fire Approval (drawing and approval letter) 6. Design submission review fee (refer to fee schedule). Note: Designs must be submitted on A1 size sheets (24” * 36”) Where designs conform to requirements a Design Approval is issued. Where designs do not conform to requirements of the Authority a Defects Letter is issued specifying reasons why designs cannot be approved. Note: Where designs are rejected a resubmission fee is applicable. Applicants must make required corrections to designs and resubmit with applicable fee. Inspection and Testing Applicant installs infrastructure as per approved designs and submits the following: INSPECTION 1. Inspection fees as per schedule 2. Inspection request form INSPECTION Inspections are conducted to ensure water reticulation infrastructure is installed in
  • 2. PRESSURE TEST 1. Applicant submits pressure test fee as per schedule 2. Applicant pressures water reticulation system to 150PSI for date as indicated by WASA METER INSPECTION 1. Applicant installs water service meters 2. Applicant submits request for meter inspection accordance with approved designs and using materials required by WASA. Note: Where installation is not satisfactorily installed a re- inspection fee equivalent to initial fee will become payable before re-inspections are carried out PRESSURE TEST 1. Applicant is advised of date when pressure test is to be conducted 2. WASA Technician visits site and installs logger on water reticulation system to ensure there is no pressure loss in system (test can either be 2 hours or 24 hours) Note: Where pressure test fails, Applicant must pay another pressure test fee before system is pressure tested again. METER INSPECTION WASA Technician visits site to inspect and test water service meters. Once water service meters are satisfactorily installed information for establishment of accounts are recorded. Completion Certificate Applicant submits payment for interconnection as per WASA Estimate WASA issues Completion Certificate