SlideShare a Scribd company logo
1 of 16
QUALITY
ASSURANCE
MANGEMENT
PROCEDURES
8.1 COMMENCEMENT
DATE
10.1 ISSUE OF TAKING-OVER
CERTIFICATE
11.9 ISSUE OF THE PERFORMANCE
CERTIFICATE
8.2 TIME OF
COMPLETION 1
DELAYS
DEFECTS
NOTIFICATION
PERIOD 3
9.1 TESTS ON
COMPLETION
2
REMEDYING OF
DEFECTS
11 NOTIFYING
OF DEFECTS
21 DAYS
4.2 RETURN OF
PERFORMANCE
SECURITY
PRINCIPAL EVENTS
DURING CONTRACT ADMINISTRATION
(FIDIC)
(CALENDAR DAYS) 28 DAYS
28 DAYS
(21 DAYS NOTICE) (12 MONTHS)
14.3 CONTRACTOR SUBMITS
STATEMENT TO THE ENGINNER
14.6 ENGINEER ISSUES
INTERIM
PAYMENT CERTIFICATE
14.7 EMPLOYER MAKES THE PAYMENT
TO THE CONTRACTOR
28 DAYS
56 DAYS
28 DAYS 56 DAYS
ENGINEER VERIFIES THE STATEMENT,
CONTRACTOR SUBMITS INFORMATION
14.11 CONTRACTOR SUBMITS DRAFT
FINAL STATEMENT TO THE ENGINEER
14.11 CONTRACTOR SUBMITS
DRAFT FINAL STATEMENT AND
THE 14.12 DISCHARGE 14.7 EMPLOYER
MAKES PAYMENT
EACH OF THE
MONTHLY (OR
OTHERWISE)
INTERIM
PAYMENTS
(MIN.P20 MILLION)
THE FINAL
PAYMENT
14.7 EMPLOYER
MAKES PAYMENT
14.13 ENGINEER ISSUES
FINAL PAYMENT
CERTIFICATE
PAYMENT EVENTS
(FIDIC)
CONTRACTOR SENIOR/FIELD INSPECTOR RESIDENT ENGINEER PROGRAM MANAGER MCA-P
FLOW CHART
PROCESSING OF CONTRACTOR’S INTERM PAYMENT CERTIFICATE
START
PREPARE & SUBMIT DRAFT
INTERIM PAYMENT
CERTIFICATE
7 DAYS 7 DAYS 7 DAYS
STAMP & RECORD INTERIM
PAYMENT CERTIFICATE FOR
APPROPRIATE ACTION
ISSUE INSTRUCTIONS
TO CHECK & VERIFY
QUANTITIES & UNIT
RATES OF WORK ITEMS
VERIFY QUANTITIES
ACCOMPLISHED
AGAINST ITEM LOG &
CHECK UNIT RATES OF
WORKS ITEMS
JOINT ANALYSIS & EVALUATION TO ELIMINATE
DISAGREEMENT, THEN FINALIZE AND SIGN AGREED
RESULTS
CHECK & REVIEW
RESULTS OF JOINT
ANALYSIS AND
EVALUATION
RECOMMEND FOR
APPROVAL AND
CONCURRENCE
APPROVE
FURNISH COPY
RECEIVED
FILE FILE
END
YES
YES
NO
NO
FLOW CHART
PROCESSING OF CONTRACTOR’S INTERM PAYMENT CERTIFICATE
• That the respective Resident Engineers/ Quantity Engineers should strictly ensure the
following prior to endorsing the said Contractor’s Progress Billing/ Interim Payment
Certificate Application (IPC-A) to PMC (Borogan Office).
– That the Contractor’s submitted Statement of Work Accomplished (SWA) have been
carefully reviewed and checked.
– That all necessary supporting documents as required have been carefully reviewed and
checked to be in order and correct.
• That upon receipt by PMC Borogan Office of the Contractor’s Progress Billing/ IPC-A with the
Statement (SWA) signed by both the Contractor and Resident Engineer together with the
complete supporting documents. The PMC Borongan Office would spot check the
completeness and correctness of the Progress Billing/ IPC-A. That the date of receipt of such
complete and correct Progress Billing/ IPC-A by the Resident Engineer from the Contractor is
consider the acceptance of the Progress Billing/ IPC-A of the Contractor pursuant to FIDIC
Sub-clause 14.3 of the General Conditions of Contract.
• Upon reviewed by PMC Borogan Office such Progress Billing/ IPC-A endorsed by the Resident
Engineer, if no inconsistencies were found the Interim Payment Certificate (IPC) and
Statement would be signed off by the Deputy Team Leader and Team Leader. However, if a
major inconsistency is discovered such Progress Billing/ IPC-A would be returned back to the
Contractor thru the Resident Engineer for correction and re-submission. In such case the
Progress Billing/ Interim Payment Certificate Application could not be considered the date of
receipt of the Progress Billing/ IPC-A in accordance with FIDIC Sub-clause 14.3 of the General
Conditions of Contract.
• Only after receipt of the Resident Engineer of the re-submitted corrected documents, the
Progress Billing/ IPC-A could be considered the acceptance of the Progress Billing/ IPC-A of
the Contractor pursuant to FIDIC Sub-clause 14.3 of the General Conditions of Contract.
• The signed off ‘IPC/ SWA’ with supporting documents and including PMC’s Endorsement
Letter to MCA-P would be returned back to the Contractor for six (6) set photocopying prior
to sending the complete IPC to PMC (Manila Office) for transmitting to MCA-P. That PMC
Borongan Office to include from now on within the IPC Endorsement Letter such payment
event dates as requested by MCA-P.
FLOW CHART
PROCESSING OF CONTRACTOR’S INTERM PAYMENT CERTIFICATE
• The signed off ‘IPC/ SWA’ with supporting documents and including PMC’s Endorsement
Letter to MCA-P would be returned back to the Contractor for six (6) set photocopying prior
to sending the complete IPC to PMC (Manila Office) for transmitting to MCA-P. That PMC
Borongan Office to include from now on within the IPC Endorsement Letter such payment
event dates as requested by MCA-P.
• That the Resident Engineer should be aware of the minimum IPC amount requirement as
provided within Appendix to Bid of the Contract Documents. The minimum IPC amount is on
basis after considering all deductions for Retention (Appendix to Bid), repayment of Advance
(FIDIC Sub-clause 14.2), deductions for Plant and Materials (FIDIC Sub-clause 14.5) and any
deductions that may become due under the Contract.
• The Contractor should ensure that such IPC is received by PMC (Manila Office) well in
advance or before the 28th day after receipt of the Progress Billing/ IPC-A by the Resident
Engineer in accordance with FIDIC Sub-clause 14.3 of the General Conditions of Contract.
• Likewise PMC (Manila Office) should ensure that MCA-P (Manila Office) receives the IPC on
or before the 28th day after receipt of the Progress Billing/ IPC-A by the Resident Engineer in
accordance with FIDIC Sub-clause 14.3 of the General Conditions of Contract. Such timing is
strictly in accordance with FIDIC Sub-clause 14.6 of the General Conditions of Contract.
• MCA-P on or before the 56th day after receipt of the Progress Billing/ IPC-A in accordance
with FIDIC Sub-clause 14.3 of the General Conditions of Contract shall make a payment to the
Contractor in accordance with amount certified within the IPC.
FLOW CHART
PROCEDURE OF PROCESSING CONTRACTOR’S CLAIM
CONTRACTOR SENIOR/FIELD INSPECTOR RESIDENT ENGINEER ENGINEER
PROGRAM MANAGER
MCA-P
PREPARE AND SUBMIT NOTICE
OF INTENTION TO CLAIM
RECEIVE & STAMP REQUEST &
SEND TO RE FOR ACTION
CONFIRM THE MERITS AND
LACK OF MERITS OF THE CLAIM
ISSUE INSTRUCTION TO
VERIFY MERITS & LACK OF
MERITS OF THE CLAIM
RECOMMEND THE
PROCESSING OF
CLAIM
REVIEW & CONCUR
RECOMMENDATION TO
PROCESS THE CLAIM
YES
NO
ADVICE MCA-P OF THE
IMPENDING CLAIM
FINALIZE CLAIM & SUBMIT
REQUIRED DOCUMENTS
EXAMINE THE
COMPLETENESS OF
DOCUMENTS
COMPARATIVE ANALYSIS AND EVALUATION OF THE CLAIM WITH
CONTRACTOR TO ELIMINATE FUTURE DISAGREEMENT
PREPARE AGREED CLAIM &
SEND TO RE FOR REVIEW
CHECK & REVIEW
AGREED CLAIM
REVIEW AND RECOMMEND
FOR APPROVAL BY MCA-P
ACCEPT AND SIGN
CLAIM REQUEST
FILE
END
APPROVE
NO
YES
SEND COPY TO THE
FOLLOWING
ISSUE
OBJECTION/NO
OBJECTION
NO
FILE
FILE
START
FLOW CHART
PROCEDURE OF PROCESSING DESIGN REVISION
(INITIATED BY THE CONTRACTOR)
CONTRACTOR DESIGN ENGINEER RESIDENT ENGINEER (RE) ENGINEER
PROGRAM MANAGER (PM)
MCA-P
SUBMIT REQUEST FOR
DESIGN REVISION
START
STAMP AND RECORD
REQUEST AND SEND
TO RE FOR ACTION
ISSUE INSTRUCTION
TO ASSESS THE NEED
FOR DESIGN REVISION
ASSESS & CERTIFY THE
NEED FOR DESIGN
REVISON
EVALUATE RESULT OF
ASSESSMENT &
RECOMMEND PROPER
ACTION BY THE PM
REVIEW RESULT OF
ASSESSMENT &
RECOMMEND FOR
DESIGN CHANGES
VERIFY NEED FOR
REVISION OF PLAN &
DESIGN
APPROVE
REQUEST
ISSUE INSTRUCTION
TO DESIGN ENGINEER
TO PROCEED W/ THE
DESIGN REVISION
REVIEW REVISED PLAN
DESIGN AND SPECS.
FOR APPROVAL BY
MCA-P
CHECK REVISED PLAN
DESIGN AND
SPECIFICATION
PREPARE REVISED
PLAN, DESIGN AND
SPECIFICATION
CHECK REVISED PLAN
DESIGN AND
SPECIFICATION
APPROVE
REQUEST
GIVE COPIES
ACKNOWLEDGE
RECEIPT OF REVISED
PLAN, DESIGN AND
SPECIFICATION
FILE
END FILE FILE
YES
NO
NO YES
YES
YES
NO
NO
NO
YES
FLOW CHART
PROCEDURE OF PROCESSING VARIATION ORDER
(INITIATED BY THE ENGINEER)
CONTRACTOR SENIOR/FIELD
INSPECTORS
RESIDENT ENGINEER ENGINEER
PROGRAM MANAGER
MCA-P
START
CONFIRM THE NEED FOR
VARIATION REQUEST
ISSUE INSTRUCTION TO
FIELD/SENIOR INSPECTOR TO
VERIFY NEED FOR VARIATION
REQUEST
RECOMMEND THE
PROCESSING OF
VARIATION REQUEST
REVIEW & APPROVE
RECOMMENDATION TO
PROCESS THE VARIATION
REQUEST
YES
NO
ADVICE MCA-P OF THE NEED
FOR VARIATION REQUEST
PREPARE AND SUBMIT
REQUIRED DOCUMENTS
CHECK & VERIFY
COMPLETENESS OF
DOCUMENTS
COMPARATIVE ANALYSIS & EVALUATION WITH CONTRACTOR TO
ELIMINATE FUTURE DISAGREEMENT
PREPARE AGREED VARIATION
REQUEST & SEND TO RE FOR
REVIEW
CHECK & REVIEW
AGREED VARIATION
REQUEST
REVIEW AND RECOMMEND
VARIATION REQUEST FOR
APPROVAL BY MCA-P
ACCEPT AND SIGN
VARIATION REQUEST
EXECUTE
FILE FILE
END
APPROVE
NO
YES
PROVIDE COPY TO
THE FOLLOWING
ISSUE OBJECTION/NO
OBJECTION TO
VARIATION REQUEST
NO
FINALIZE VARIATION REQUEST &
ASK CONTRACTOR TO SUBMIT
REQUIRED DOCUMENTS
ISSUE INSTRUCTION TO
CONTRACTOR
FLOW CHART
PROCEDURE OF PROCESSING VARIATION ORDER
(INITIATED BY THE CONTRACTOR)
CONTRACTOR SENIOR/FIELD
INSPECTORS
RESIDENT ENGINEER ENGINEER
PROGRAM MANAGER
MCA-P
START
PREPARE AND SUBMIT NOTICE
OF VARIATION
RECEIVE & STAMP REQUEST &
SEND TO RE FOR ACTION
CONFIRM THE NEED FOR
VARIATION REQUEST
ISSUE INSTRUCTION TO
FIELD/SENIOR INSPECTOR TO
VERIFY NEED FOR VARIATION
REQUEST
RECOMMEND THE
PROCESSING OF
VARIATION REQUEST
REVIEW & CONCUR
RECOMMENDATION TO PROCESS
THE VARIATION REQUEST
YES
NO
ADVICE MCA-P OF THE NEED FOR
VARIATION REQUEST
FINALIZE VARIATION
REQUEST & SUBMIT
REQUIRED DOCUMENTS
CHECK & VERIFY
COMPLETENESS OF
DOCUMENTS
COMPARATIVE ANALYSIS & EVALUATION WITH CONTRACTOR TO
ELIMINATE FUTURE DISAGREEMENT
PREPARE AGREED VARIATION
REQUEST & SEND TO RE FOR
REVIEW
CHECK & REVIEW
AGREED VARIATION
REQUEST
REVIEW AND RECOMMEND
VARIATION REQUEST FOR
APPROVAL
ACCEPT AND SIGN
VARIATION REQUEST
EXECUTE
FILE FILE
APPROVE
NO
YES
SEND COPY TO
THE FOLLOWING
ISSUE OBJECTION/NO
OBJECTION TO
VARIATION REQUEST
NO
END
ISSUE INSTRUCTION TO
CONTRACTOR
FLOW CHART
WORK REQUEST APPROVAL PROCEDURES
CONTRACTOR
ENGINEER
MCA-P
SENIOR/FIELD INSPECTORS RESIDENT ENGINEER MATERIALS ENGINEER SURVEYOR
PREPARE AND SUBMIT
INSPECTION REQUEST FOR
APPROVAL
REVIEW REQUEST AND ISSUE
INSTRUCTION TO VERIFY
REQUEST FOR INSPECTION
INSPECT WORK AREA &
VERIFY IF THE WORK MAY
PROCEED AS REQUESTED
FILE
APPROVED
REQUEST
YES
NO
START
RECEIVE APPROVED
REQUEST
SEND COPY OF APPROVED
REQUEST FOR EXECUTION
START
WORK
REQUEST FOR
TESTING & SURVEY
WORKS
ISSUE INSTRUCTION TO
CONDUCT TESTING &
SURVEY WORKS
CONDUCT SURVEY
WORKS
CONDUCT QUALITY
TESTING
REVIEW RESULTS OF TEST
AND SURVEY & GIVE A
COPY TO THE FOLLOWING
APPROVED
REQUEST
NO
FILE
SEND COPY OF THE
APPROVED REQUEST
FOR EXECUTION
RECEIVE APPROVED
REQUEST
YES
START
WORK
FILE
FILE FILE
FLOW CHART
PROCEDURE OF PROCESSING SHOP DRAWING
ENGINEER
CONTRACTOR KEY STAFF RESIDENT ENGINEER (RE) PROGRAM MANAGER (PM)
PREPARE & SUBMIT
REQUIRED SHOP
DRAWING
START
STAMP AND RECORD
SUBMISSION FOR
APPROPRIATE ACTION
SEND COPY TO RESPONSIBLE
KEY STAFF
CHECK DRAWINGS &
MARK APPROPRIATE
COMMENTS
REVIEW SHOP DRAWING &
APPROVE OR DISAPPROVE
SHOP DRAWING
NO YES
FINALIZE RETURN LETTER
AND TRANSMIT MARKED
SHOP DRAWINGS
GIVE COPIES TO ENGINEER’S
STAFF
ACKNOWLEDGE
RECEIPT OF
TRANSMITTAL
END
FILE FILE
MAKE NECESSARY
CORRECTIONS
FLOW CHART
MATERIAL TESTING PROCEDURES
CONTRACTOR LABORATORY TECHNICIAN MATERIALS ENGINEER ENGINEER
RESIDENT ENGINEER
PLAN AND ARRANGE
TESTING OF REQUIRED
MATERIALS
START
INFORM CONTRACTOR OF
THE SCHEDULE FOR
SAMPLING & TESTING
LABORATORY TECHNICIAN SHALL COLLECT SAMPLES AT RANDOM AND THE
CONTRACTOR SHALL PROVIDE NECESSARY LABOR EQUIPMENT FACILITIES FOR
SAMPLING AND TRANSPORT
EXAMINE SAMPLES AND
ISSUE INSTRUCTION TO
CONDUCT TEST
LABORATORY TECHNICIAN SHALL CONDUCT TEST IN THE
PRESENCE OF CONTRACTOR’S REPRESENTATIVE AND
CONCERNED SENIOR/FIELD CONTRACTOR
EVALUATE/ANALYZE
AND INTERPRET
RESULTS OF TEST
REVIEW TEST RESULTS
& FINALIZE
TRANSMITTAL LETTER
TO CONTRACTOR
SEND COPIES OF TEST
RESULTS AND INFORM
CONTRACTOR OF THE
RESULT OF TEST
ACKNOWLEDGE
RECEIPT OF TEST
RESULTS
END FILE FILE
PREPARE & SUBMIT
REQUEST/SAMPLES
WITH SAMPLE CARD
PROCEDURES and GUIDELINES
NON-COMPLIANCE REPORT/ CORRECTIVE and PREVENTIVE ACTION
• In order to assure and monitor that all Contractor’s are complying with its
contractual requirements and obligations under the Contract, the
implementation of a ‘Non-Compliance Report/ Corrective and Preventive
Action’ reporting system would be implemented effective immediately by
the PMC. This Non-Compliance Reporting (NCR) system covers the following
groups/ or category: -
– Contractual requirements of the Project in accordance with the
approved Drawings and Specifications of the Contract including
materials and workmanship quality issues.
– Contractual obligations of the Contractor in accordance with the
relevant provisions of the Contract in respect of Health and Safety
issues.
– Contractual obligations of the Contractor in accordance with the
relevant provisions of the Contract in respect of Environmental issues.
– Contractual obligations of the Contractor in accordance with the
relevant provisions of the Contract in respect of Social and Gender
issues.
PROCEDURES and GUIDELINES
NON-COMPLIANCE REPORT/ CORRECTIVE and PREVENTIVE ACTION
• Part A [Non-Compliance/ Non Conformity Record] – this part
shall be completed and signed by the PMC personnel’s [i.e.
Resident Engineers/ Bridge Engineer/ Materials Engineers/ CE
Inspectors/ Development Program Manager/ Environmental
Specialist/ Road Safety Officers] identifying a non-complying
work or observing that a practice or construction activity that
may lead to non-conformity with the Project contractual
requirements. Specific procedures to be followed: -
– The PMC personnel completes’ Part A of the NCR form.
– The Contractor receives the completed Part A of the
NCR form.
– The PMC personnel photocopy the completed Part A of
the NCR form as file record and encoded in a registry.
Note that on a monthly basis the updated copy of the
NCR registry per group should be furnished to the Office
Engineer of PMC Borongan Office.
– The original completed Part A of the NCR form is sent to
the Contractor.
– The PMC personnel shall provide the relevant Resident
Engineer (who is responsible for his work area) another
copy of the completed Part A of the NCR form in respect
of NCR’s initiated by the Bridge Engineer, Development
Program Manager, Environmental Specialist, and Road
Safety Officer.
• Part B [Corrective and Preventive Action] – this part is to be
completed by the Contractor and submitted to Engineer.
• Part C [Engineer’s Review of proposed Corrective and
Preventive Action] – this part is to be completed by the Engineer
who shall review and/or inspect if compliance is now probable
or achieved. If the Engineer is satisfied the NCR is ‘closed out’
and the NCR close out form is copied to the Contractor. If the
Engineer is not satisfied the NCR form is returned back to the
Contractor to rectify the situation.
Non-Compliance Report/ Corrective and Preventive Action
Part A - Non-Complinace/ Non-Conformity Record
Attention: DMCI-CMPCI Joint Venture (Contractor)
From: Katahira & Engineer's International (Engineer)
Date Observed: Time Observed:
Work Location:
Details of Observation:
Full Name:
Designation:
Signature:
Date:
Time:
Engineer Received by:
Part B - Corrective and Preventive Action
Corrective and Preventive Action to be taken:
Full Name: Designation: Signature: Date: Time
Part C - Engineer's Review of Proposed Corrective and Preventive Action
Full Name: Designation: Signature: Date: Time
☐ ☐NCR Closed Out
Activity reviewed/ inspected and compliance is now probable/ achieved.
NCR No.: ______________
END OF
PRESENTATION
Thank you!!!!

More Related Content

Similar to Quality Assurance Procedures fro MCAP.ppt

Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTEuan Pirie
 
FINAL-GEP-PRESENTATION-1.pptx
FINAL-GEP-PRESENTATION-1.pptxFINAL-GEP-PRESENTATION-1.pptx
FINAL-GEP-PRESENTATION-1.pptxGabClaudio
 
Rules and regulation of Pakistan Engineering Council (PEC)
Rules and regulation of Pakistan Engineering Council (PEC)Rules and regulation of Pakistan Engineering Council (PEC)
Rules and regulation of Pakistan Engineering Council (PEC)Amir Khan
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
LECTURE - Planning.ppt
LECTURE - Planning.pptLECTURE - Planning.ppt
LECTURE - Planning.pptshinawaro27
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptxssuserb337ce1
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
Beyond Contract Series Article One
Beyond Contract Series   Article OneBeyond Contract Series   Article One
Beyond Contract Series Article OneMy own
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTYee Len Wan
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractAvinash Kumar Gupta
 
Item # 8 Sewer Rehab Contract - Ogden
Item # 8   Sewer Rehab Contract - OgdenItem # 8   Sewer Rehab Contract - Ogden
Item # 8 Sewer Rehab Contract - Ogdenahcitycouncil
 
COLD STORE PROJECT SCHEME.
COLD STORE PROJECT SCHEME.COLD STORE PROJECT SCHEME.
COLD STORE PROJECT SCHEME.CHARAK RAY
 

Similar to Quality Assurance Procedures fro MCAP.ppt (20)

Cl report final
Cl report finalCl report final
Cl report final
 
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
Claims and Counterclaims Preparation, Analysis, Assessment and Successful Set...
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPT
 
FINAL-GEP-PRESENTATION-1.pptx
FINAL-GEP-PRESENTATION-1.pptxFINAL-GEP-PRESENTATION-1.pptx
FINAL-GEP-PRESENTATION-1.pptx
 
Rules and regulation of Pakistan Engineering Council (PEC)
Rules and regulation of Pakistan Engineering Council (PEC)Rules and regulation of Pakistan Engineering Council (PEC)
Rules and regulation of Pakistan Engineering Council (PEC)
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
LECTURE - Planning.ppt
LECTURE - Planning.pptLECTURE - Planning.ppt
LECTURE - Planning.ppt
 
fidic-flow-chart.pptx
fidic-flow-chart.pptxfidic-flow-chart.pptx
fidic-flow-chart.pptx
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
Beyond Contract Series Article One
Beyond Contract Series   Article OneBeyond Contract Series   Article One
Beyond Contract Series Article One
 
Bihar rfp
Bihar rfpBihar rfp
Bihar rfp
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
Professional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOTProfessional Practice II - Presentation - Construction Delays & EOT
Professional Practice II - Presentation - Construction Delays & EOT
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
Item # 8 Sewer Rehab Contract - Ogden
Item # 8   Sewer Rehab Contract - OgdenItem # 8   Sewer Rehab Contract - Ogden
Item # 8 Sewer Rehab Contract - Ogden
 
COLD STORE PROJECT SCHEME.
COLD STORE PROJECT SCHEME.COLD STORE PROJECT SCHEME.
COLD STORE PROJECT SCHEME.
 

Recently uploaded

Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

Quality Assurance Procedures fro MCAP.ppt

  • 2. 8.1 COMMENCEMENT DATE 10.1 ISSUE OF TAKING-OVER CERTIFICATE 11.9 ISSUE OF THE PERFORMANCE CERTIFICATE 8.2 TIME OF COMPLETION 1 DELAYS DEFECTS NOTIFICATION PERIOD 3 9.1 TESTS ON COMPLETION 2 REMEDYING OF DEFECTS 11 NOTIFYING OF DEFECTS 21 DAYS 4.2 RETURN OF PERFORMANCE SECURITY PRINCIPAL EVENTS DURING CONTRACT ADMINISTRATION (FIDIC) (CALENDAR DAYS) 28 DAYS 28 DAYS (21 DAYS NOTICE) (12 MONTHS)
  • 3. 14.3 CONTRACTOR SUBMITS STATEMENT TO THE ENGINNER 14.6 ENGINEER ISSUES INTERIM PAYMENT CERTIFICATE 14.7 EMPLOYER MAKES THE PAYMENT TO THE CONTRACTOR 28 DAYS 56 DAYS 28 DAYS 56 DAYS ENGINEER VERIFIES THE STATEMENT, CONTRACTOR SUBMITS INFORMATION 14.11 CONTRACTOR SUBMITS DRAFT FINAL STATEMENT TO THE ENGINEER 14.11 CONTRACTOR SUBMITS DRAFT FINAL STATEMENT AND THE 14.12 DISCHARGE 14.7 EMPLOYER MAKES PAYMENT EACH OF THE MONTHLY (OR OTHERWISE) INTERIM PAYMENTS (MIN.P20 MILLION) THE FINAL PAYMENT 14.7 EMPLOYER MAKES PAYMENT 14.13 ENGINEER ISSUES FINAL PAYMENT CERTIFICATE PAYMENT EVENTS (FIDIC)
  • 4. CONTRACTOR SENIOR/FIELD INSPECTOR RESIDENT ENGINEER PROGRAM MANAGER MCA-P FLOW CHART PROCESSING OF CONTRACTOR’S INTERM PAYMENT CERTIFICATE START PREPARE & SUBMIT DRAFT INTERIM PAYMENT CERTIFICATE 7 DAYS 7 DAYS 7 DAYS STAMP & RECORD INTERIM PAYMENT CERTIFICATE FOR APPROPRIATE ACTION ISSUE INSTRUCTIONS TO CHECK & VERIFY QUANTITIES & UNIT RATES OF WORK ITEMS VERIFY QUANTITIES ACCOMPLISHED AGAINST ITEM LOG & CHECK UNIT RATES OF WORKS ITEMS JOINT ANALYSIS & EVALUATION TO ELIMINATE DISAGREEMENT, THEN FINALIZE AND SIGN AGREED RESULTS CHECK & REVIEW RESULTS OF JOINT ANALYSIS AND EVALUATION RECOMMEND FOR APPROVAL AND CONCURRENCE APPROVE FURNISH COPY RECEIVED FILE FILE END YES YES NO NO
  • 5. FLOW CHART PROCESSING OF CONTRACTOR’S INTERM PAYMENT CERTIFICATE • That the respective Resident Engineers/ Quantity Engineers should strictly ensure the following prior to endorsing the said Contractor’s Progress Billing/ Interim Payment Certificate Application (IPC-A) to PMC (Borogan Office). – That the Contractor’s submitted Statement of Work Accomplished (SWA) have been carefully reviewed and checked. – That all necessary supporting documents as required have been carefully reviewed and checked to be in order and correct. • That upon receipt by PMC Borogan Office of the Contractor’s Progress Billing/ IPC-A with the Statement (SWA) signed by both the Contractor and Resident Engineer together with the complete supporting documents. The PMC Borongan Office would spot check the completeness and correctness of the Progress Billing/ IPC-A. That the date of receipt of such complete and correct Progress Billing/ IPC-A by the Resident Engineer from the Contractor is consider the acceptance of the Progress Billing/ IPC-A of the Contractor pursuant to FIDIC Sub-clause 14.3 of the General Conditions of Contract. • Upon reviewed by PMC Borogan Office such Progress Billing/ IPC-A endorsed by the Resident Engineer, if no inconsistencies were found the Interim Payment Certificate (IPC) and Statement would be signed off by the Deputy Team Leader and Team Leader. However, if a major inconsistency is discovered such Progress Billing/ IPC-A would be returned back to the Contractor thru the Resident Engineer for correction and re-submission. In such case the Progress Billing/ Interim Payment Certificate Application could not be considered the date of receipt of the Progress Billing/ IPC-A in accordance with FIDIC Sub-clause 14.3 of the General Conditions of Contract. • Only after receipt of the Resident Engineer of the re-submitted corrected documents, the Progress Billing/ IPC-A could be considered the acceptance of the Progress Billing/ IPC-A of the Contractor pursuant to FIDIC Sub-clause 14.3 of the General Conditions of Contract. • The signed off ‘IPC/ SWA’ with supporting documents and including PMC’s Endorsement Letter to MCA-P would be returned back to the Contractor for six (6) set photocopying prior to sending the complete IPC to PMC (Manila Office) for transmitting to MCA-P. That PMC Borongan Office to include from now on within the IPC Endorsement Letter such payment event dates as requested by MCA-P.
  • 6. FLOW CHART PROCESSING OF CONTRACTOR’S INTERM PAYMENT CERTIFICATE • The signed off ‘IPC/ SWA’ with supporting documents and including PMC’s Endorsement Letter to MCA-P would be returned back to the Contractor for six (6) set photocopying prior to sending the complete IPC to PMC (Manila Office) for transmitting to MCA-P. That PMC Borongan Office to include from now on within the IPC Endorsement Letter such payment event dates as requested by MCA-P. • That the Resident Engineer should be aware of the minimum IPC amount requirement as provided within Appendix to Bid of the Contract Documents. The minimum IPC amount is on basis after considering all deductions for Retention (Appendix to Bid), repayment of Advance (FIDIC Sub-clause 14.2), deductions for Plant and Materials (FIDIC Sub-clause 14.5) and any deductions that may become due under the Contract. • The Contractor should ensure that such IPC is received by PMC (Manila Office) well in advance or before the 28th day after receipt of the Progress Billing/ IPC-A by the Resident Engineer in accordance with FIDIC Sub-clause 14.3 of the General Conditions of Contract. • Likewise PMC (Manila Office) should ensure that MCA-P (Manila Office) receives the IPC on or before the 28th day after receipt of the Progress Billing/ IPC-A by the Resident Engineer in accordance with FIDIC Sub-clause 14.3 of the General Conditions of Contract. Such timing is strictly in accordance with FIDIC Sub-clause 14.6 of the General Conditions of Contract. • MCA-P on or before the 56th day after receipt of the Progress Billing/ IPC-A in accordance with FIDIC Sub-clause 14.3 of the General Conditions of Contract shall make a payment to the Contractor in accordance with amount certified within the IPC.
  • 7. FLOW CHART PROCEDURE OF PROCESSING CONTRACTOR’S CLAIM CONTRACTOR SENIOR/FIELD INSPECTOR RESIDENT ENGINEER ENGINEER PROGRAM MANAGER MCA-P PREPARE AND SUBMIT NOTICE OF INTENTION TO CLAIM RECEIVE & STAMP REQUEST & SEND TO RE FOR ACTION CONFIRM THE MERITS AND LACK OF MERITS OF THE CLAIM ISSUE INSTRUCTION TO VERIFY MERITS & LACK OF MERITS OF THE CLAIM RECOMMEND THE PROCESSING OF CLAIM REVIEW & CONCUR RECOMMENDATION TO PROCESS THE CLAIM YES NO ADVICE MCA-P OF THE IMPENDING CLAIM FINALIZE CLAIM & SUBMIT REQUIRED DOCUMENTS EXAMINE THE COMPLETENESS OF DOCUMENTS COMPARATIVE ANALYSIS AND EVALUATION OF THE CLAIM WITH CONTRACTOR TO ELIMINATE FUTURE DISAGREEMENT PREPARE AGREED CLAIM & SEND TO RE FOR REVIEW CHECK & REVIEW AGREED CLAIM REVIEW AND RECOMMEND FOR APPROVAL BY MCA-P ACCEPT AND SIGN CLAIM REQUEST FILE END APPROVE NO YES SEND COPY TO THE FOLLOWING ISSUE OBJECTION/NO OBJECTION NO FILE FILE START
  • 8. FLOW CHART PROCEDURE OF PROCESSING DESIGN REVISION (INITIATED BY THE CONTRACTOR) CONTRACTOR DESIGN ENGINEER RESIDENT ENGINEER (RE) ENGINEER PROGRAM MANAGER (PM) MCA-P SUBMIT REQUEST FOR DESIGN REVISION START STAMP AND RECORD REQUEST AND SEND TO RE FOR ACTION ISSUE INSTRUCTION TO ASSESS THE NEED FOR DESIGN REVISION ASSESS & CERTIFY THE NEED FOR DESIGN REVISON EVALUATE RESULT OF ASSESSMENT & RECOMMEND PROPER ACTION BY THE PM REVIEW RESULT OF ASSESSMENT & RECOMMEND FOR DESIGN CHANGES VERIFY NEED FOR REVISION OF PLAN & DESIGN APPROVE REQUEST ISSUE INSTRUCTION TO DESIGN ENGINEER TO PROCEED W/ THE DESIGN REVISION REVIEW REVISED PLAN DESIGN AND SPECS. FOR APPROVAL BY MCA-P CHECK REVISED PLAN DESIGN AND SPECIFICATION PREPARE REVISED PLAN, DESIGN AND SPECIFICATION CHECK REVISED PLAN DESIGN AND SPECIFICATION APPROVE REQUEST GIVE COPIES ACKNOWLEDGE RECEIPT OF REVISED PLAN, DESIGN AND SPECIFICATION FILE END FILE FILE YES NO NO YES YES YES NO NO NO YES
  • 9. FLOW CHART PROCEDURE OF PROCESSING VARIATION ORDER (INITIATED BY THE ENGINEER) CONTRACTOR SENIOR/FIELD INSPECTORS RESIDENT ENGINEER ENGINEER PROGRAM MANAGER MCA-P START CONFIRM THE NEED FOR VARIATION REQUEST ISSUE INSTRUCTION TO FIELD/SENIOR INSPECTOR TO VERIFY NEED FOR VARIATION REQUEST RECOMMEND THE PROCESSING OF VARIATION REQUEST REVIEW & APPROVE RECOMMENDATION TO PROCESS THE VARIATION REQUEST YES NO ADVICE MCA-P OF THE NEED FOR VARIATION REQUEST PREPARE AND SUBMIT REQUIRED DOCUMENTS CHECK & VERIFY COMPLETENESS OF DOCUMENTS COMPARATIVE ANALYSIS & EVALUATION WITH CONTRACTOR TO ELIMINATE FUTURE DISAGREEMENT PREPARE AGREED VARIATION REQUEST & SEND TO RE FOR REVIEW CHECK & REVIEW AGREED VARIATION REQUEST REVIEW AND RECOMMEND VARIATION REQUEST FOR APPROVAL BY MCA-P ACCEPT AND SIGN VARIATION REQUEST EXECUTE FILE FILE END APPROVE NO YES PROVIDE COPY TO THE FOLLOWING ISSUE OBJECTION/NO OBJECTION TO VARIATION REQUEST NO FINALIZE VARIATION REQUEST & ASK CONTRACTOR TO SUBMIT REQUIRED DOCUMENTS ISSUE INSTRUCTION TO CONTRACTOR
  • 10. FLOW CHART PROCEDURE OF PROCESSING VARIATION ORDER (INITIATED BY THE CONTRACTOR) CONTRACTOR SENIOR/FIELD INSPECTORS RESIDENT ENGINEER ENGINEER PROGRAM MANAGER MCA-P START PREPARE AND SUBMIT NOTICE OF VARIATION RECEIVE & STAMP REQUEST & SEND TO RE FOR ACTION CONFIRM THE NEED FOR VARIATION REQUEST ISSUE INSTRUCTION TO FIELD/SENIOR INSPECTOR TO VERIFY NEED FOR VARIATION REQUEST RECOMMEND THE PROCESSING OF VARIATION REQUEST REVIEW & CONCUR RECOMMENDATION TO PROCESS THE VARIATION REQUEST YES NO ADVICE MCA-P OF THE NEED FOR VARIATION REQUEST FINALIZE VARIATION REQUEST & SUBMIT REQUIRED DOCUMENTS CHECK & VERIFY COMPLETENESS OF DOCUMENTS COMPARATIVE ANALYSIS & EVALUATION WITH CONTRACTOR TO ELIMINATE FUTURE DISAGREEMENT PREPARE AGREED VARIATION REQUEST & SEND TO RE FOR REVIEW CHECK & REVIEW AGREED VARIATION REQUEST REVIEW AND RECOMMEND VARIATION REQUEST FOR APPROVAL ACCEPT AND SIGN VARIATION REQUEST EXECUTE FILE FILE APPROVE NO YES SEND COPY TO THE FOLLOWING ISSUE OBJECTION/NO OBJECTION TO VARIATION REQUEST NO END ISSUE INSTRUCTION TO CONTRACTOR
  • 11. FLOW CHART WORK REQUEST APPROVAL PROCEDURES CONTRACTOR ENGINEER MCA-P SENIOR/FIELD INSPECTORS RESIDENT ENGINEER MATERIALS ENGINEER SURVEYOR PREPARE AND SUBMIT INSPECTION REQUEST FOR APPROVAL REVIEW REQUEST AND ISSUE INSTRUCTION TO VERIFY REQUEST FOR INSPECTION INSPECT WORK AREA & VERIFY IF THE WORK MAY PROCEED AS REQUESTED FILE APPROVED REQUEST YES NO START RECEIVE APPROVED REQUEST SEND COPY OF APPROVED REQUEST FOR EXECUTION START WORK REQUEST FOR TESTING & SURVEY WORKS ISSUE INSTRUCTION TO CONDUCT TESTING & SURVEY WORKS CONDUCT SURVEY WORKS CONDUCT QUALITY TESTING REVIEW RESULTS OF TEST AND SURVEY & GIVE A COPY TO THE FOLLOWING APPROVED REQUEST NO FILE SEND COPY OF THE APPROVED REQUEST FOR EXECUTION RECEIVE APPROVED REQUEST YES START WORK FILE FILE FILE
  • 12. FLOW CHART PROCEDURE OF PROCESSING SHOP DRAWING ENGINEER CONTRACTOR KEY STAFF RESIDENT ENGINEER (RE) PROGRAM MANAGER (PM) PREPARE & SUBMIT REQUIRED SHOP DRAWING START STAMP AND RECORD SUBMISSION FOR APPROPRIATE ACTION SEND COPY TO RESPONSIBLE KEY STAFF CHECK DRAWINGS & MARK APPROPRIATE COMMENTS REVIEW SHOP DRAWING & APPROVE OR DISAPPROVE SHOP DRAWING NO YES FINALIZE RETURN LETTER AND TRANSMIT MARKED SHOP DRAWINGS GIVE COPIES TO ENGINEER’S STAFF ACKNOWLEDGE RECEIPT OF TRANSMITTAL END FILE FILE MAKE NECESSARY CORRECTIONS
  • 13. FLOW CHART MATERIAL TESTING PROCEDURES CONTRACTOR LABORATORY TECHNICIAN MATERIALS ENGINEER ENGINEER RESIDENT ENGINEER PLAN AND ARRANGE TESTING OF REQUIRED MATERIALS START INFORM CONTRACTOR OF THE SCHEDULE FOR SAMPLING & TESTING LABORATORY TECHNICIAN SHALL COLLECT SAMPLES AT RANDOM AND THE CONTRACTOR SHALL PROVIDE NECESSARY LABOR EQUIPMENT FACILITIES FOR SAMPLING AND TRANSPORT EXAMINE SAMPLES AND ISSUE INSTRUCTION TO CONDUCT TEST LABORATORY TECHNICIAN SHALL CONDUCT TEST IN THE PRESENCE OF CONTRACTOR’S REPRESENTATIVE AND CONCERNED SENIOR/FIELD CONTRACTOR EVALUATE/ANALYZE AND INTERPRET RESULTS OF TEST REVIEW TEST RESULTS & FINALIZE TRANSMITTAL LETTER TO CONTRACTOR SEND COPIES OF TEST RESULTS AND INFORM CONTRACTOR OF THE RESULT OF TEST ACKNOWLEDGE RECEIPT OF TEST RESULTS END FILE FILE PREPARE & SUBMIT REQUEST/SAMPLES WITH SAMPLE CARD
  • 14. PROCEDURES and GUIDELINES NON-COMPLIANCE REPORT/ CORRECTIVE and PREVENTIVE ACTION • In order to assure and monitor that all Contractor’s are complying with its contractual requirements and obligations under the Contract, the implementation of a ‘Non-Compliance Report/ Corrective and Preventive Action’ reporting system would be implemented effective immediately by the PMC. This Non-Compliance Reporting (NCR) system covers the following groups/ or category: - – Contractual requirements of the Project in accordance with the approved Drawings and Specifications of the Contract including materials and workmanship quality issues. – Contractual obligations of the Contractor in accordance with the relevant provisions of the Contract in respect of Health and Safety issues. – Contractual obligations of the Contractor in accordance with the relevant provisions of the Contract in respect of Environmental issues. – Contractual obligations of the Contractor in accordance with the relevant provisions of the Contract in respect of Social and Gender issues.
  • 15. PROCEDURES and GUIDELINES NON-COMPLIANCE REPORT/ CORRECTIVE and PREVENTIVE ACTION • Part A [Non-Compliance/ Non Conformity Record] – this part shall be completed and signed by the PMC personnel’s [i.e. Resident Engineers/ Bridge Engineer/ Materials Engineers/ CE Inspectors/ Development Program Manager/ Environmental Specialist/ Road Safety Officers] identifying a non-complying work or observing that a practice or construction activity that may lead to non-conformity with the Project contractual requirements. Specific procedures to be followed: - – The PMC personnel completes’ Part A of the NCR form. – The Contractor receives the completed Part A of the NCR form. – The PMC personnel photocopy the completed Part A of the NCR form as file record and encoded in a registry. Note that on a monthly basis the updated copy of the NCR registry per group should be furnished to the Office Engineer of PMC Borongan Office. – The original completed Part A of the NCR form is sent to the Contractor. – The PMC personnel shall provide the relevant Resident Engineer (who is responsible for his work area) another copy of the completed Part A of the NCR form in respect of NCR’s initiated by the Bridge Engineer, Development Program Manager, Environmental Specialist, and Road Safety Officer. • Part B [Corrective and Preventive Action] – this part is to be completed by the Contractor and submitted to Engineer. • Part C [Engineer’s Review of proposed Corrective and Preventive Action] – this part is to be completed by the Engineer who shall review and/or inspect if compliance is now probable or achieved. If the Engineer is satisfied the NCR is ‘closed out’ and the NCR close out form is copied to the Contractor. If the Engineer is not satisfied the NCR form is returned back to the Contractor to rectify the situation. Non-Compliance Report/ Corrective and Preventive Action Part A - Non-Complinace/ Non-Conformity Record Attention: DMCI-CMPCI Joint Venture (Contractor) From: Katahira & Engineer's International (Engineer) Date Observed: Time Observed: Work Location: Details of Observation: Full Name: Designation: Signature: Date: Time: Engineer Received by: Part B - Corrective and Preventive Action Corrective and Preventive Action to be taken: Full Name: Designation: Signature: Date: Time Part C - Engineer's Review of Proposed Corrective and Preventive Action Full Name: Designation: Signature: Date: Time ☐ ☐NCR Closed Out Activity reviewed/ inspected and compliance is now probable/ achieved. NCR No.: ______________