SlideShare a Scribd company logo
1 of 10
Booking Sheets Rise & Fall Method
Recording your levels – Rise & Fall Method – copy readings on a piece of paper BM –1st  reading taken was 2.250 (this is a back sight) (D) Last reading taken was .486(which is a foresight) (C) 5th  reading taken was 2.400( a foresight) 2nd  reading taken of  2.825 (this is a intermediate site) BM C D A (B) 3rd  reading taken was 1.976(which is a foresight) (C) 6th reading taken new instrument position was 1.880 (which is a back sight) B (B) 4th  reading taken new position of instrument was 2.120 (which is a back sight) Now we’ll have a look at how they go onto a booking sheet Triangles indicate instrument positions Letters indicate staff positions
Completed booking sheet example
First Remember the rules for completing the booking sheet The first reading you take is always a Backsight (BS) The last reading you take is always a Foresight (FS) The readings you take in between are Intermediate sights (IS)
Completing the sheet – step 1 ,[object Object]
 back sight at BM first
 Then intermediate site, one line down
 Then foresight one line down again
Then our instrument is moved (c.p. change point), our first reading from here is a backsight, but still goes on the line for staff reading B – etc. complete the rest
 In the remarks column you can also note the staff reading points, A,B,C, etc.,[object Object]

More Related Content

What's hot

Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)
Sheng Zhe
 
S2 6 theodolites
S2 6 theodolitesS2 6 theodolites
S2 6 theodolites
Est
 
Site surveying report1
Site surveying report1Site surveying report1
Site surveying report1
Est
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveying
stooty s
 
Profile and cross section
Profile and cross section Profile and cross section
Profile and cross section
Bahzad5
 
Traverse Computations
Traverse ComputationsTraverse Computations
Traverse Computations
Bahzad5
 
Leveling surveying
Leveling surveyingLeveling surveying
Leveling surveying
Mohammed_82
 
Total station topcon exp procedures
Total station topcon exp proceduresTotal station topcon exp procedures
Total station topcon exp procedures
NAGESH KUMAR GUTURU
 
Site survey Fieldwork 2 traversing
Site survey Fieldwork 2 traversingSite survey Fieldwork 2 traversing
Site survey Fieldwork 2 traversing
Sheng Zhe
 
Location horizontal and vertical curves Theory
Location horizontal and vertical curves Theory Location horizontal and vertical curves Theory
Location horizontal and vertical curves Theory
Bahzad5
 

What's hot (20)

Site Surveying Levelling
Site Surveying Levelling Site Surveying Levelling
Site Surveying Levelling
 
Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)Site survey Fieldwork1 (levelling)
Site survey Fieldwork1 (levelling)
 
S2 6 theodolites
S2 6 theodolitesS2 6 theodolites
S2 6 theodolites
 
Site surveying report1
Site surveying report1Site surveying report1
Site surveying report1
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveying
 
Projection of planes
Projection of planesProjection of planes
Projection of planes
 
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE) Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
 
Profile and cross section
Profile and cross section Profile and cross section
Profile and cross section
 
Traverse Computations
Traverse ComputationsTraverse Computations
Traverse Computations
 
Leveling surveying
Leveling surveyingLeveling surveying
Leveling surveying
 
Profile and Cross-Section - Report
Profile and Cross-Section - ReportProfile and Cross-Section - Report
Profile and Cross-Section - Report
 
Leveling
Leveling Leveling
Leveling
 
Site surveying report 1
Site surveying report 1Site surveying report 1
Site surveying report 1
 
Total station topcon exp procedures
Total station topcon exp proceduresTotal station topcon exp procedures
Total station topcon exp procedures
 
Site survey Fieldwork 2 traversing
Site survey Fieldwork 2 traversingSite survey Fieldwork 2 traversing
Site survey Fieldwork 2 traversing
 
Levelling
LevellingLevelling
Levelling
 
Location horizontal and vertical curves Theory
Location horizontal and vertical curves Theory Location horizontal and vertical curves Theory
Location horizontal and vertical curves Theory
 
Setting out of bridges unit 6
Setting out of bridges unit 6Setting out of bridges unit 6
Setting out of bridges unit 6
 
Scales
ScalesScales
Scales
 
Open channel Flow - Uniform Flow
Open channel Flow - Uniform FlowOpen channel Flow - Uniform Flow
Open channel Flow - Uniform Flow
 

More from jbusse

CPCCCA3009A Construct Advanced Roofs Octagonal end roof
CPCCCA3009A Construct Advanced Roofs Octagonal end roofCPCCCA3009A Construct Advanced Roofs Octagonal end roof
CPCCCA3009A Construct Advanced Roofs Octagonal end roof
jbusse
 
CPCCCA3009A Construct Advanced Roofs Oblique roof
CPCCCA3009A Construct Advanced Roofs Oblique roofCPCCCA3009A Construct Advanced Roofs Oblique roof
CPCCCA3009A Construct Advanced Roofs Oblique roof
jbusse
 
Lecture2
Lecture2Lecture2
Lecture2
jbusse
 
Installation JB2011
Installation JB2011Installation JB2011
Installation JB2011
jbusse
 
4 internal lining
4 internal lining4 internal lining
4 internal lining
jbusse
 
4. associated issues
4. associated issues4. associated issues
4. associated issues
jbusse
 
3. application of timber in environmental building
3. application of timber in environmental building3. application of timber in environmental building
3. application of timber in environmental building
jbusse
 
2. timber as a sustainable building material
2. timber as a sustainable building material2. timber as a sustainable building material
2. timber as a sustainable building material
jbusse
 
1. ecologically sustainable development
1. ecologically sustainable development1. ecologically sustainable development
1. ecologically sustainable development
jbusse
 
Using span tables as1684 2
Using span tables   as1684 2Using span tables   as1684 2
Using span tables as1684 2
jbusse
 
Genral code sub floor
Genral code sub floorGenral code sub floor
Genral code sub floor
jbusse
 
Sub floor code
Sub floor codeSub floor code
Sub floor code
jbusse
 
Explosive power tools
Explosive power toolsExplosive power tools
Explosive power tools
jbusse
 
Roof framing cdujb
Roof framing cdujbRoof framing cdujb
Roof framing cdujb
jbusse
 

More from jbusse (14)

CPCCCA3009A Construct Advanced Roofs Octagonal end roof
CPCCCA3009A Construct Advanced Roofs Octagonal end roofCPCCCA3009A Construct Advanced Roofs Octagonal end roof
CPCCCA3009A Construct Advanced Roofs Octagonal end roof
 
CPCCCA3009A Construct Advanced Roofs Oblique roof
CPCCCA3009A Construct Advanced Roofs Oblique roofCPCCCA3009A Construct Advanced Roofs Oblique roof
CPCCCA3009A Construct Advanced Roofs Oblique roof
 
Lecture2
Lecture2Lecture2
Lecture2
 
Installation JB2011
Installation JB2011Installation JB2011
Installation JB2011
 
4 internal lining
4 internal lining4 internal lining
4 internal lining
 
4. associated issues
4. associated issues4. associated issues
4. associated issues
 
3. application of timber in environmental building
3. application of timber in environmental building3. application of timber in environmental building
3. application of timber in environmental building
 
2. timber as a sustainable building material
2. timber as a sustainable building material2. timber as a sustainable building material
2. timber as a sustainable building material
 
1. ecologically sustainable development
1. ecologically sustainable development1. ecologically sustainable development
1. ecologically sustainable development
 
Using span tables as1684 2
Using span tables   as1684 2Using span tables   as1684 2
Using span tables as1684 2
 
Genral code sub floor
Genral code sub floorGenral code sub floor
Genral code sub floor
 
Sub floor code
Sub floor codeSub floor code
Sub floor code
 
Explosive power tools
Explosive power toolsExplosive power tools
Explosive power tools
 
Roof framing cdujb
Roof framing cdujbRoof framing cdujb
Roof framing cdujb
 

Booking sheets, 2011 v1

  • 1. Booking Sheets Rise & Fall Method
  • 2. Recording your levels – Rise & Fall Method – copy readings on a piece of paper BM –1st reading taken was 2.250 (this is a back sight) (D) Last reading taken was .486(which is a foresight) (C) 5th reading taken was 2.400( a foresight) 2nd reading taken of 2.825 (this is a intermediate site) BM C D A (B) 3rd reading taken was 1.976(which is a foresight) (C) 6th reading taken new instrument position was 1.880 (which is a back sight) B (B) 4th reading taken new position of instrument was 2.120 (which is a back sight) Now we’ll have a look at how they go onto a booking sheet Triangles indicate instrument positions Letters indicate staff positions
  • 4. First Remember the rules for completing the booking sheet The first reading you take is always a Backsight (BS) The last reading you take is always a Foresight (FS) The readings you take in between are Intermediate sights (IS)
  • 5.
  • 6. back sight at BM first
  • 7. Then intermediate site, one line down
  • 8. Then foresight one line down again
  • 9. Then our instrument is moved (c.p. change point), our first reading from here is a backsight, but still goes on the line for staff reading B – etc. complete the rest
  • 10.
  • 11. This is simply deducting one reading from the previous and posting the answer in the rise & fall column
  • 12.
  • 13.
  • 14. Total the columns
  • 15. Take FS away from BS
  • 16. Take Fall away from Rise
  • 17.
  • 18. eg. 47.195 - .575 = 46.620
  • 19. 46.620 + .849 = 47.469 and so on
  • 21.
  • 22. Take the last RL away from the firstAgain All Answers should EQUAL !
  • 23. Review the completed booking sheet