SlideShare a Scribd company logo
1 of 9
Download to read offline
Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42
www.ijera.com 34|P a g e
An Approach for Measurement of Non-Technical losses of 11KV
feeder and its Minimization
Dharam Singh Dr. Sudhir Sharma Sh. Gagandeep Sharma
Student, M.Tech (Electrical) Associate Professor & Head Assistant Professor
Department of Elect. Engg. Department of Elect. Engg. Department of Elect. Engg.
DAVIET, Jalandhar, Punjab DAVIET, Jalandhar, Punjab DAVIET, Jalandhar, Punjab
Abstract
Distribution losses comprise Technical & Non-Technical losses. In this paper technical losses calculation of
11KV Kochar Urban Gohlwar, TarnTaran feeder by load power flow analysis using technical data with utility
has been presented. Non technical losses of this feeder have been arrived at by subtracting technical losses from
total distribution losses. As non technical losses are on higher side, new proposals for minimization of non
technical losses have been suggested which include checking of technically rejected temporary tubewell
connections during paddy season and seasonal factories such as rice shellers and ice factories to avoid
accumulation of consumption units.
Keywords- Bus Bar, current Transformer, Distribution Transformer, Energy Meter, Power Plant, Shunt
Capacitor, Transmission Line.
I. Introduction-
In power system, all the power generated at
power plant is unable to reach the consumer end. A
very high percentage of power is wasted as T&D
losses.80% of the total losses are distribution losses.
In Punjab distribution losses amounts to Rs.3667.46
crores (6234MU) as per the latest data of PSERC [1].
So a lot of scope is still there to solve this problem of
undesirable loss to Power sector. These losses very
much affect the economy of the country which
cannot be tolerated. To cover up these losses the
power plant has to generate more energy. The energy
required for covering up the transmission and
distribution losses will also be transmitted through
the transmission and distribution system which will
also add energy losses to the system concerned.
These losses affect the determinations of tariff which
will be on higher side to recover the amount due to
excess distribution losses. So it is utmost necessary
for the utility to reduce the losses wherever practical.
Transmission and Distribution system acts as a link
between generation of power supply at power plant
and its consumption at the consumer side.
Transmission system is expended after the technical
study of all required transmission data and
transmission line routes with planed manner but
expansion of distribution system is done as and when
required, on the emergent demand basis. So no
planning is involved in the expansion of distribution
system. Due to these reason there is increase in T&D
losses and reliability of power supply is minimum.
End users are dissatisfied and are burdened with high
tariff due to high distribution losses. So focus has
rightly been shifted to improvement in distribution
system to reduce distribution losses.
Minimization of distribution losses is not a new
topic for dissertation. A lot of work has already been
done in this regard by different authors/agencies.
New techniques are being developed in a effort that
maximum part of generated energy should reach to
the consumer end. Some of the techniques such as
replacing disc type energy meter with electronics
meters, use of aerial bunched cables, power factor
improvement by installing capacitor units at
substation [2], 11KV feeder and the motor terminals,
HVDS system for agriculture connections, load
balancing on each phase, checking of connections by
flying squads of utilities and levying heavy penalty,
high tariff/penalty for peak load hours, placing
transformer at load centre etc are being adopted by
utilities. In spite of the best effort done by utilities we
are not close to the developed countries of the world
such as, USA, Japan & South Korea on this issue [3].
From practical experience of electrical field, more
efforts can be done in this regard. New suggestions
have been made in this paper, along with
Comprehensive analysis of already prevailing
techniques for minimization of non technical losses
in distribution system.
For calculating non-technical losses, a case study
of 11KV Gohlwar, TarnTaran feeder has been
undertaken. The first step is to calculate distribution
losses from the feeder data of billed energy units &
incoming energy units of the feeder. Technical losses
have been calculated by load flow analysis by
Newton Raphson method using MiPower Software.
RESEARCH ARTICLE OPEN ACCESS
Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42
www.ijera.com 35|P a g e
Non technical losses are calculated by subtracting
technical losses from total distribution losses. In the
end, some new techniques have been suggested for
minimization of losses. In India T&D losses are
officially declared as 24% [4], but different agencies
including TERI (The Energy Research Institute) has
estimated the T&D losses as high as 50% from their
sample study carried out. This paper presents a case
study of calculation of distribution losses of 11KV
Kochar Urban feeder emanating from 66KV
substation Gohlwar, TarnTararn Punjab.
II. A Case Study
In this Paper, a case study of 11KV Kochar
Urban feeder emanating from 66KV substation,
Gohlwar is under taken..
Fig.1 Sketch of 11KV Kochar Urban Feeder
Gohlwar village is located at a distance of about 12 KMs from TarnTaran district headquarters. This substation
has two nos. 66/11KV step down power transformer. The key diagram of 11KV Kochar Urban feeder is shown
as per figure 1.
This feeder has 32 number mixed categories of consumers, namely large
supply (LS), small power (SP), non-residential supply (NRS) and domestic supply (DS). The major power
consumption is of large supply & small power connections.
2.1 Methodology
The distribution losses of 11KV Kochar urban feeder have been calculated by subtracting energy units billed in
the area of this feeder from the units supplied to this feeder from substation as recorded by energy meter
installed at the start of the feeder. The Punjab State Power Com Limited has all the records of energy incoming
and outgoing from the substation duly recorded in log sheet Performa. The methodology adapted [5] for the loss
calculation has been shown as per figure 2.
Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42
www.ijera.com 36|P a g e
Fig.2 Flow Chart of Methodology
At first the data related to the consumption/ billed units of all consumers of this 11KV feeder is taken from the
consumer ledger is taken to calculate the consumption of units & total load. The consumption data as collected
has been shown as per table no.1
Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42
www.ijera.com 37|P a g e
Table no.1 Consumption Data of 11KV Kochar Urban feeder for the month of October, 2014
S.No. Name of transformer
Connection
A/C no.
Type of
Connection Consumption in KWH
Load
(KW)
1 25KVA Mohinder Singh GW33/1312 DS 1058 1.42
2 25KVA Mohinder Singh GW33/1313 DS 1500 1.42
3 25KVA Mohinder Singh GW33/1314 DS 638 1.42
4 25KVA Mohinder Singh GW33/1315 DS 0 1.42
5 25KVA Mohinder Singh GW33/1316 DS 686 1.42
6 25KVA Mohinder Singh GW33/1317 DS 0 1.42
7 25KVA Mohinder Singh GW33/1318 DS 1021 1.42
8 25KVA Mohinder Singh GW33/1319 DS 963 1.42
9 25KVA Mohinder Singh GW33/1320 DS 675 1.42
10 25KVA Mohinder Singh GW33/1338 DS 1017 5
11 10KVA Single Phase Transformer VP14/1812 NRS 236 1.46
12 10KVA Single Phase Transformer VP14/1872 DS 362 1.7
13
750KVA-2nos. Karam Singh &
Raghbir Singh
LS01/006 LS 304436 1300.439
14 2000KVA LT food Pvt. Ltd. LS01/007 LS 271294 1678.822
15 100KVA Sandeep Singh Bala Chack SP55/145 SP 411 17.65
16 100KVA Sandeep Singh Bala Chack SP55/156 SP 679 4.99
17 100KVA Sandeep Singh Bala Chack SP55/181 SP 517 14.94
18 100KVA Sandeep Singh Bala Chack SP55/196 SP 1318 14.93
19 63KVA Vijay Kumar SP55/15 SP 121 3.95
20 63KVA Vijay Kumar SP55/146 SP 216 12.76
21 63KVA Vijay Kumar BC37/483 DS 179 2.13
22 63KVA Vijay Kumar BC37/708 DS 183 2.83
23 63KVA Vijay Kumar BC37/1144 DS 224 1.53
24 63KVA Vijay Kumar BC37/1248 DS 364 0.46
25 63KVA Vijay Kumar BC37/1252 DS 255 1.92
26 63KVA Vijay Kumar BC37/1263 NRS 93 0.94
27 63KVA Vijay Kumar BC37/1282 DS 180 1.34
28 63KVA Vijay Kumar BC37/1283 DS 223 2.55
29 63KVA Vijay Kumar BC37/1292 NRS 121 0.8
30 63KVA Vijay Kumar BC37/1299 DS 11 0.96
31 63KVA Vijay Kumar BC37/1344 DS 224 1.78
32 315KVA KK Agro food LS01/0010 LS 6860 193.994
596065 3280.655
Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42
www.ijera.com 38|P a g e
2.2 Distribution Losses Calculations (Technical Losses & Non technical Losses)
For distribution losses calculation the readings of energy meter installed at substation have been recorded for
one month which are given as per table 2.
Table 2 Energy Meter reading of 11KV Kochar Urban feeder for the month of Oct.2014
S.No.
Description
of feeder
Reading taken
on 31/10/14
Reading taken
on 30/9/14
Difference
of energy
meter
readings
M.F of
energy
meter
Total energy
sent in
KWH
1 11KV
Kochar
Urban feeder
16763.25 15999.85 763.4 1000 763400
Total incoming units = 763400 KWH
Total consumption/Billed units = 596065 KWH
Distribution Losses = Total Incoming Units - Total Billed Units
= (763400 – 596065) =166925 KWH
= 21.88% (1)
Technical and nontechnical losses are the main two parts of distribution losses. Physical properties of all the
components of power system cause technical losses. Power dissipation in transmission line and transformer due
to load is the most oblivious example of these losses. Technical losses are naturally occurring losses and cannot
be eliminated. These losses occur due to action internal to the power system consisting of transmission lines,
substations, transformers, measurement and protection equipments. If we are provided with complete data
regarding running load, length and conductor sizes, these losses can be computed and controlled easily.
Technical losses in distribution system include copper losses in 11KV lines, LT lines, service drops and energy
meters. These losses also include core losses in distribution transformers. These losses are inherent in the power
supply distribution system and cannot be avoided.
Theft of energy by consumers / non consumers in one or the other way is the main cause of
Non technical losses. These can be calculated by subtracting technical losses from the total distribution losses of
the 11KV feeder.
2.3 Calculation of Technical Losses
Technical losses of 11KV feeder can be calculated by analytical method using load factor and load loss
factor and by load power flow analysis by different software available. For this, complete data of 11KV feeder
along with distribution transformers installed on it is required.
2.3.1 Loading Data of Distribution Transformers
Table no.3 Loading Data of Transformers on 11KV Kochar Urban feeder
S.No Transformer rating
KVA
Qty. Total KVA Transformer Load
(KW)
1
10 1 10 003.160
2
25 1 25 017.780
3
63 1 63 033.950
4 100 1 100 052.510
5
315 1 315 193.994
6 750 2 1500 1300.439
7
2000 1 2000 1678.822
Total 8 4013 KVA 3280.655
2.3.2 11KV Transmission Line Data
Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42
www.ijera.com 39|P a g e
Table 4 ACSR Conductor Details
S no. Description of Conductor Length(KM)
1 50mm2
ACSR Conductor 1.6
2 35mm2
ACSR Conductor 1.8
3 25mm2
ACSR Conductor 0.9
Total 4.3 KM
The Resistance of 11KV line Conductor has been taken for single conductor as per Table 5
50mm2
= 0.640146 Ohm/Km
35mm2
= 0.919246 Ohm/Km
25mm2
= 1.274624 Ohm/Km
Table 5 Sequence Impedance for 11KV Aluminum Conductor
ITEM Conductor Size
A.C.Resistance
Ohm/Cond./KM
Impedance Ohm/Cond./KM
mm2
Dia of
Str.mm/No. of
Str.
20o
c 50o
c Single Circuit Double Circuit
X1=X2 Ro+jxo X1=X2 Ro+jxo
1 25 2.14/7 1.137143 1.274624 0.401496 1.422624+
j1.628310
0.41662 1.570624 +
j2.755995
2 35 2.52/7 0.820096 0.919246 0.391226 1.067246+
j1.618040
0.40635 1.215246 +
j2.745725
3 50 3.02/7 0.571100 0.640146 0.379854 0.788146 +
j1.606667
0.39498 0.936146 +
j2.734352
4 70 2.15/19 0.421161 0.472079 0.366401 0.620079 +
j1.593214
0.38153 0.766079 +
j2.720099
5 95 2.52/19 0.303853 0.340589 0.356424 0.488589 +
j1.583237
0.37155 0.636589 +
j2.710922
6 120 2.85/19 0.237695 0.266432 0.348692 0.414432 +
j1.575505
0.36382 0.562432 +
j2.703190
7 185 2.52/37 0.156761 0.175713 0.334439 0.323713 +
j1.561251
0.34957 0.471713 +
j2.688937
Maximum Current on feeder = 138Amp. (On 18/10/2014 at 1.00hrs)
2.3.3 Technical Losses calculation by power load flow study method.
We are having all the data necessary for calculation of the distribution losses by Newton Raphson method of
load flow study. As shown in figure 4 of power flow diagram of 11KV feeder, we have 16nos. of buses including
66KV, 11KV and 0.415KV buses.
Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42
www.ijera.com 40|P a g e
Fig.4 Power Flow Diagram of 11KV Kochar Urban Feeder by Mipower Software
The base MVA has been taken as 100MVA and nominal system frequency 50Hzs. The 11KV feeder has three
sizes of ACSR conductor namely 50mm2
, 35mm2
and 25mm2
with total line length as 4.3 KMs. The number of
transformer loads, transmission lines and other detail has been given in the power flow diagram itself. Mipower
software has been used for power flow study by Newton Rephson method [6].
III. Summary of Results
TOTAL REAL POWER GENERATED : 3.622 MW
TOTAL REACTIVE POWER GENERATED : 1.716 MVAR
GENERATION Pf : 0.904
TOTAL REAL POWER LOAD : 3.279 MW
TOTAL REACT. POWER LOAD : 1.501 MVAR
LOAD PF : 0.909
TOTAL REAL POWER LOSS (AC+DC) : 0.342180 MW
% REAL LOSS (AC+DC) : 9.448
(2)
TOTAL REACT. POWER LOSS : 0.215114 MVAR
IV. Calculation of Non-Technical losses
As distribution losses comprises technical as well as non-technical losses [7]. So non technical losses can be
calculated subtracting technical losses from total distribution losses as under.
Distribution Losses as calculated (1) =21.88%
Technical Losses as calculated by Load
Flow Analysis by using MiPower Software (2) =9.448%
Non Technical Losses = Distribution Losses - Technical Losses
= (1) - (2)
Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42
www.ijera.com 41|P a g e
= 21.880% - 9.448%
= 12.432%
These losses are on very high side.
Non-Technical losses are basically due to theft of energy in one or the other way. Maximum permissible
limit for technical losses is 9% for urban and 10% for rural distribution system [8] but non technical losses are
not desirable at all. So it is very important to reduce these losses and save revenue as far as possible. This will
also lesson burden on consumers in the shape of lower electricity tariff.
V. Economic Consequences of Distribution Losses.
The economic consequences of distribution losses are far reaching. To cover up the lost energy, additional
generating capacity may be required. The power which is lost as T&D losses in distribution system is still to be
transmitted through these transmission lines substations etc which further adds to the energy losses already
existing in that system. These losses affect the determinations of tariff which will be on higher side to recover
the amount due to excess distribution losses.
VI. New Techniques suggested which are yet to be adopted or not being adopted vigorously.
 Mapping/ Data compilation of distribution feeders.
 Correct calculation/Computation of technical losses.
 Installation of energy meters on secondary side of each distribution transformers.
 Prepaid energy meters.
 Use of Aerial Bunched Cable.
 Installation of pillar-box for domestic/NRS connection energy meters.
 Checking of temporary tube well connections which have been rejected on technical ground during
paddy season.
 Repeated checking of tube well connection having H.P.tariff.
 Every tube well connection should have energy meter to access correct consumption.
 Repeated checking of seasonal factories i.e. Ice factories/ Rice shellers to avoid accumulation of
consumption units with the connivance of utility staff.
 Implementation of energy audit scheme.
 Mitigating power theft making theft of energy as cognizable offence with punishment up to 3 years
imprisonment.
VII. Conclusion
This paper demonstrates the capability of load power flow analysis system to calculate the technical losses
and there by non technical losses in 11KV feeder. For this Newton Raphson method of load power flow study
has been used through MiPower software. The data used is readily available with the engineers of power
distribution utility. The non technical losses calculated are 12.432% which are on very high side. As per survey
undertaken of this 11KV feeder there is Jhuggi Jhopri’s cluster under distribution area of 25KVA Mohinder
Singh Wala transformer and they directly tap the bare conductor of LT line. Two nos. energy meters are dead
stop and show zero consumption. Two connections of 10KVA single phase transformer are having energy
meters inside the commercial/ residential premises having no terminal plates. So pilferage of energy from
incoming terminals cannot be ruled out. Small power connections on 100KVA Sandeep Singh Bala Chack is
having naked joints in incoming cable so theft of energy by small power consumers may be there. All the
domestic / non residential supply connections on 63 KVA Vijay Kumar transformer are having energy meters
inside the respective premises and these have not been shifted outside in sealed pillar box. Thus calculation of
non-technical losses of this feeder will be beneficial to the utility to know the theft/pilferage going on in this
area. Removing naked joints from incoming cables, shifting of energy meters outside the premises in sealed
pillar boxes, replacement of slow/defective meters, proper sealing of terminal plates and meter boxes,
distribution of power supply to small power consumers having load more than 10 KW by HVDS system,
checking of temporary tube well connections rejected on technical ground during paddy season and continuous
checking of seasonal factories will definitely decrease the non technical losses of this feeder.
References
[1] Punjab State electricity Regulatory commission Tariff Order 2014-15 Volume-1 www.pserc.nic.in.
[2] Parmar Jigu Total losses in power distribution & transmission line published in Electrical Engg. Potel,
Aug19, 2013.
Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42
www.ijera.com 42|P a g e
[3] Singh Tejinder Analysis of Non Technical Losses and its economic consequences on power system, Master
Degree Thesis, Thapar University 2009.
[4] Wikipedia The free Encyclopedia (2015) Electricity Sector in India www.wikipedia.org.
[5] Pawar Rajneesh, Singh Jatinder Calculation of T&D Losses% Based on 11/0.4KV substation in a distribution
utility, Published in power India conference, 2012 IEEE Fifth.
[6] Volta River Authority Non-Technical Losses Reduction. A presentation during UPDEA Scientific committee
meeting in Durban, S.A, Thompson AGALAB (2010).
[7] Power Research and Development Consultant MiPowerTM
, How to Solve 2003.
[8] Jena B C “Distribution losses in power system” www.academia.edu Feb17, 2012.
[9] Ghosh Soham: Loss reduction and efficiency improvement: A critical Appraisal of Power distribution sector
in India. International journal of Modern Engineering Research (IJMER) volume-2, issue-5, September-
October-2012.PP3292-3297.’

More Related Content

What's hot

Power electronic control of induction generator used in small hydro power system
Power electronic control of induction generator used in small hydro power systemPower electronic control of induction generator used in small hydro power system
Power electronic control of induction generator used in small hydro power systemIAEME Publication
 
Indian Wind Power - New-generation DFIG Power Converters for 6-8 MW Wind Turb...
Indian Wind Power - New-generation DFIG Power Converters for 6-8 MW Wind Turb...Indian Wind Power - New-generation DFIG Power Converters for 6-8 MW Wind Turb...
Indian Wind Power - New-generation DFIG Power Converters for 6-8 MW Wind Turb...Ingeteam Wind Energy
 
Flicker mitigation by individual pitch control of variable speed wind turbine...
Flicker mitigation by individual pitch control of variable speed wind turbine...Flicker mitigation by individual pitch control of variable speed wind turbine...
Flicker mitigation by individual pitch control of variable speed wind turbine...srikanth chandhupatla
 
Volume 2-issue-6-2085-2090
Volume 2-issue-6-2085-2090Volume 2-issue-6-2085-2090
Volume 2-issue-6-2085-2090Editor IJARCET
 
Study on transmission energy losses and finding the hazards using what if ana...
Study on transmission energy losses and finding the hazards using what if ana...Study on transmission energy losses and finding the hazards using what if ana...
Study on transmission energy losses and finding the hazards using what if ana...eSAT Publishing House
 
Improving Efficiency of Active Power Filter for Renewable Power Generation Sy...
Improving Efficiency of Active Power Filter for Renewable Power Generation Sy...Improving Efficiency of Active Power Filter for Renewable Power Generation Sy...
Improving Efficiency of Active Power Filter for Renewable Power Generation Sy...IRJET Journal
 

What's hot (7)

Power electronic control of induction generator used in small hydro power system
Power electronic control of induction generator used in small hydro power systemPower electronic control of induction generator used in small hydro power system
Power electronic control of induction generator used in small hydro power system
 
Indian Wind Power - New-generation DFIG Power Converters for 6-8 MW Wind Turb...
Indian Wind Power - New-generation DFIG Power Converters for 6-8 MW Wind Turb...Indian Wind Power - New-generation DFIG Power Converters for 6-8 MW Wind Turb...
Indian Wind Power - New-generation DFIG Power Converters for 6-8 MW Wind Turb...
 
Flicker mitigation by individual pitch control of variable speed wind turbine...
Flicker mitigation by individual pitch control of variable speed wind turbine...Flicker mitigation by individual pitch control of variable speed wind turbine...
Flicker mitigation by individual pitch control of variable speed wind turbine...
 
Volume 2-issue-6-2085-2090
Volume 2-issue-6-2085-2090Volume 2-issue-6-2085-2090
Volume 2-issue-6-2085-2090
 
J010346786
J010346786J010346786
J010346786
 
Study on transmission energy losses and finding the hazards using what if ana...
Study on transmission energy losses and finding the hazards using what if ana...Study on transmission energy losses and finding the hazards using what if ana...
Study on transmission energy losses and finding the hazards using what if ana...
 
Improving Efficiency of Active Power Filter for Renewable Power Generation Sy...
Improving Efficiency of Active Power Filter for Renewable Power Generation Sy...Improving Efficiency of Active Power Filter for Renewable Power Generation Sy...
Improving Efficiency of Active Power Filter for Renewable Power Generation Sy...
 

Viewers also liked

An Advanced Exploration on Fixture Design
An Advanced Exploration on Fixture DesignAn Advanced Exploration on Fixture Design
An Advanced Exploration on Fixture DesignIJERA Editor
 
Measuring Robustness on Generalized Gaussian Distribution
Measuring Robustness on Generalized Gaussian DistributionMeasuring Robustness on Generalized Gaussian Distribution
Measuring Robustness on Generalized Gaussian DistributionIJERA Editor
 
Stakeholder Perceptions of Fire and Haze
Stakeholder Perceptions of Fire and HazeStakeholder Perceptions of Fire and Haze
Stakeholder Perceptions of Fire and HazeCIFOR-ICRAF
 
Introduction to concrete curing effect on the early performance of modern con...
Introduction to concrete curing effect on the early performance of modern con...Introduction to concrete curing effect on the early performance of modern con...
Introduction to concrete curing effect on the early performance of modern con...IJERA Editor
 
Highway soft soil subgrade treatment research
Highway soft soil subgrade treatment researchHighway soft soil subgrade treatment research
Highway soft soil subgrade treatment researchIJERA Editor
 
Geotechnical Properties of Sabkha Soil in the southern part of Al-Khobar city...
Geotechnical Properties of Sabkha Soil in the southern part of Al-Khobar city...Geotechnical Properties of Sabkha Soil in the southern part of Al-Khobar city...
Geotechnical Properties of Sabkha Soil in the southern part of Al-Khobar city...IJERA Editor
 
An Ant colony optimization algorithm to solve the broken link problem in wire...
An Ant colony optimization algorithm to solve the broken link problem in wire...An Ant colony optimization algorithm to solve the broken link problem in wire...
An Ant colony optimization algorithm to solve the broken link problem in wire...IJERA Editor
 

Viewers also liked (10)

An Advanced Exploration on Fixture Design
An Advanced Exploration on Fixture DesignAn Advanced Exploration on Fixture Design
An Advanced Exploration on Fixture Design
 
Knowledge Electric Motors
Knowledge Electric MotorsKnowledge Electric Motors
Knowledge Electric Motors
 
05 ethics in research
05   ethics in research05   ethics in research
05 ethics in research
 
Measuring Robustness on Generalized Gaussian Distribution
Measuring Robustness on Generalized Gaussian DistributionMeasuring Robustness on Generalized Gaussian Distribution
Measuring Robustness on Generalized Gaussian Distribution
 
Stakeholder Perceptions of Fire and Haze
Stakeholder Perceptions of Fire and HazeStakeholder Perceptions of Fire and Haze
Stakeholder Perceptions of Fire and Haze
 
Introduction to concrete curing effect on the early performance of modern con...
Introduction to concrete curing effect on the early performance of modern con...Introduction to concrete curing effect on the early performance of modern con...
Introduction to concrete curing effect on the early performance of modern con...
 
Highway soft soil subgrade treatment research
Highway soft soil subgrade treatment researchHighway soft soil subgrade treatment research
Highway soft soil subgrade treatment research
 
Geotechnical Properties of Sabkha Soil in the southern part of Al-Khobar city...
Geotechnical Properties of Sabkha Soil in the southern part of Al-Khobar city...Geotechnical Properties of Sabkha Soil in the southern part of Al-Khobar city...
Geotechnical Properties of Sabkha Soil in the southern part of Al-Khobar city...
 
An Ant colony optimization algorithm to solve the broken link problem in wire...
An Ant colony optimization algorithm to solve the broken link problem in wire...An Ant colony optimization algorithm to solve the broken link problem in wire...
An Ant colony optimization algorithm to solve the broken link problem in wire...
 
Mерење масе
Mерење масеMерење масе
Mерење масе
 

Similar to Measure and minimize non-technical power losses

An analytical approach for optimal placement of combined dg and capacitor in ...
An analytical approach for optimal placement of combined dg and capacitor in ...An analytical approach for optimal placement of combined dg and capacitor in ...
An analytical approach for optimal placement of combined dg and capacitor in ...IAEME Publication
 
2. power system losses evaluation
2. power system losses evaluation2. power system losses evaluation
2. power system losses evaluationYusuf A. KHALIL
 
Power loss reduction in radial distribution system by using plant growth simu...
Power loss reduction in radial distribution system by using plant growth simu...Power loss reduction in radial distribution system by using plant growth simu...
Power loss reduction in radial distribution system by using plant growth simu...Alexander Decker
 
Impact Analysis of Automatic Meter Reading (AMR) Meters
 Impact Analysis of Automatic Meter Reading (AMR) Meters Impact Analysis of Automatic Meter Reading (AMR) Meters
Impact Analysis of Automatic Meter Reading (AMR) MetersIJMREMJournal
 
Electrical energy auditing
Electrical energy auditingElectrical energy auditing
Electrical energy auditingPradeep DC
 
IRJET- Industrial Energy Audit
IRJET- Industrial Energy AuditIRJET- Industrial Energy Audit
IRJET- Industrial Energy AuditIRJET Journal
 
Micro Hydro Electricity Generation in S.T.P, A Case Study of S.T.P, Salawas-J...
Micro Hydro Electricity Generation in S.T.P, A Case Study of S.T.P, Salawas-J...Micro Hydro Electricity Generation in S.T.P, A Case Study of S.T.P, Salawas-J...
Micro Hydro Electricity Generation in S.T.P, A Case Study of S.T.P, Salawas-J...IRJET Journal
 
Optimum allocation of distributed generation by load flow analysis method a c...
Optimum allocation of distributed generation by load flow analysis method a c...Optimum allocation of distributed generation by load flow analysis method a c...
Optimum allocation of distributed generation by load flow analysis method a c...eSAT Publishing House
 
Project report-TATA Power
Project report-TATA PowerProject report-TATA Power
Project report-TATA PowerSHIVAM DWIVEDI
 
Mitigation of power quality problem due to starting of induction motor
Mitigation of power quality problem due to starting of induction motorMitigation of power quality problem due to starting of induction motor
Mitigation of power quality problem due to starting of induction motoreSAT Journals
 
IRJET- Analysis of Demand Side Management of Distribution Systems
IRJET-  	  Analysis of Demand Side Management of Distribution SystemsIRJET-  	  Analysis of Demand Side Management of Distribution Systems
IRJET- Analysis of Demand Side Management of Distribution SystemsIRJET Journal
 
Power Generation using T-Box and Fault Detection System using PLC
Power Generation using T-Box and Fault Detection System using PLCPower Generation using T-Box and Fault Detection System using PLC
Power Generation using T-Box and Fault Detection System using PLCIRJET Journal
 
Intership report akhil joseph
Intership report  akhil josephIntership report  akhil joseph
Intership report akhil josephVinay Vashisht
 
Design and Analysis of SPV-Diesel Hybrid System for Remote Areas
Design and Analysis of SPV-Diesel Hybrid System for Remote AreasDesign and Analysis of SPV-Diesel Hybrid System for Remote Areas
Design and Analysis of SPV-Diesel Hybrid System for Remote AreasBIBHUTI BHUSAN SAMANTARAY
 
Power loss reduction in radial distribution system by using plant growth simu...
Power loss reduction in radial distribution system by using plant growth simu...Power loss reduction in radial distribution system by using plant growth simu...
Power loss reduction in radial distribution system by using plant growth simu...Alexander Decker
 
11.power loss reduction in radial distribution system by using plant growth s...
11.power loss reduction in radial distribution system by using plant growth s...11.power loss reduction in radial distribution system by using plant growth s...
11.power loss reduction in radial distribution system by using plant growth s...Alexander Decker
 
IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...
IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...
IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...IRJET Journal
 
Final report soft copy
Final report soft copyFinal report soft copy
Final report soft copyVinay Vashisht
 
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...IAEME Publication
 

Similar to Measure and minimize non-technical power losses (20)

An analytical approach for optimal placement of combined dg and capacitor in ...
An analytical approach for optimal placement of combined dg and capacitor in ...An analytical approach for optimal placement of combined dg and capacitor in ...
An analytical approach for optimal placement of combined dg and capacitor in ...
 
2. power system losses evaluation
2. power system losses evaluation2. power system losses evaluation
2. power system losses evaluation
 
Power loss reduction in radial distribution system by using plant growth simu...
Power loss reduction in radial distribution system by using plant growth simu...Power loss reduction in radial distribution system by using plant growth simu...
Power loss reduction in radial distribution system by using plant growth simu...
 
Impact Analysis of Automatic Meter Reading (AMR) Meters
 Impact Analysis of Automatic Meter Reading (AMR) Meters Impact Analysis of Automatic Meter Reading (AMR) Meters
Impact Analysis of Automatic Meter Reading (AMR) Meters
 
P0450495100
P0450495100P0450495100
P0450495100
 
Electrical energy auditing
Electrical energy auditingElectrical energy auditing
Electrical energy auditing
 
IRJET- Industrial Energy Audit
IRJET- Industrial Energy AuditIRJET- Industrial Energy Audit
IRJET- Industrial Energy Audit
 
Micro Hydro Electricity Generation in S.T.P, A Case Study of S.T.P, Salawas-J...
Micro Hydro Electricity Generation in S.T.P, A Case Study of S.T.P, Salawas-J...Micro Hydro Electricity Generation in S.T.P, A Case Study of S.T.P, Salawas-J...
Micro Hydro Electricity Generation in S.T.P, A Case Study of S.T.P, Salawas-J...
 
Optimum allocation of distributed generation by load flow analysis method a c...
Optimum allocation of distributed generation by load flow analysis method a c...Optimum allocation of distributed generation by load flow analysis method a c...
Optimum allocation of distributed generation by load flow analysis method a c...
 
Project report-TATA Power
Project report-TATA PowerProject report-TATA Power
Project report-TATA Power
 
Mitigation of power quality problem due to starting of induction motor
Mitigation of power quality problem due to starting of induction motorMitigation of power quality problem due to starting of induction motor
Mitigation of power quality problem due to starting of induction motor
 
IRJET- Analysis of Demand Side Management of Distribution Systems
IRJET-  	  Analysis of Demand Side Management of Distribution SystemsIRJET-  	  Analysis of Demand Side Management of Distribution Systems
IRJET- Analysis of Demand Side Management of Distribution Systems
 
Power Generation using T-Box and Fault Detection System using PLC
Power Generation using T-Box and Fault Detection System using PLCPower Generation using T-Box and Fault Detection System using PLC
Power Generation using T-Box and Fault Detection System using PLC
 
Intership report akhil joseph
Intership report  akhil josephIntership report  akhil joseph
Intership report akhil joseph
 
Design and Analysis of SPV-Diesel Hybrid System for Remote Areas
Design and Analysis of SPV-Diesel Hybrid System for Remote AreasDesign and Analysis of SPV-Diesel Hybrid System for Remote Areas
Design and Analysis of SPV-Diesel Hybrid System for Remote Areas
 
Power loss reduction in radial distribution system by using plant growth simu...
Power loss reduction in radial distribution system by using plant growth simu...Power loss reduction in radial distribution system by using plant growth simu...
Power loss reduction in radial distribution system by using plant growth simu...
 
11.power loss reduction in radial distribution system by using plant growth s...
11.power loss reduction in radial distribution system by using plant growth s...11.power loss reduction in radial distribution system by using plant growth s...
11.power loss reduction in radial distribution system by using plant growth s...
 
IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...
IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...
IRJET- Maximization of Net Profit by Optimal Placement and Sizing of DG in Di...
 
Final report soft copy
Final report soft copyFinal report soft copy
Final report soft copy
 
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...Optimal placement and sizing of ht shunt capacitors for transmission loss min...
Optimal placement and sizing of ht shunt capacitors for transmission loss min...
 

Recently uploaded

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Recently uploaded (20)

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 

Measure and minimize non-technical power losses

  • 1. Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42 www.ijera.com 34|P a g e An Approach for Measurement of Non-Technical losses of 11KV feeder and its Minimization Dharam Singh Dr. Sudhir Sharma Sh. Gagandeep Sharma Student, M.Tech (Electrical) Associate Professor & Head Assistant Professor Department of Elect. Engg. Department of Elect. Engg. Department of Elect. Engg. DAVIET, Jalandhar, Punjab DAVIET, Jalandhar, Punjab DAVIET, Jalandhar, Punjab Abstract Distribution losses comprise Technical & Non-Technical losses. In this paper technical losses calculation of 11KV Kochar Urban Gohlwar, TarnTaran feeder by load power flow analysis using technical data with utility has been presented. Non technical losses of this feeder have been arrived at by subtracting technical losses from total distribution losses. As non technical losses are on higher side, new proposals for minimization of non technical losses have been suggested which include checking of technically rejected temporary tubewell connections during paddy season and seasonal factories such as rice shellers and ice factories to avoid accumulation of consumption units. Keywords- Bus Bar, current Transformer, Distribution Transformer, Energy Meter, Power Plant, Shunt Capacitor, Transmission Line. I. Introduction- In power system, all the power generated at power plant is unable to reach the consumer end. A very high percentage of power is wasted as T&D losses.80% of the total losses are distribution losses. In Punjab distribution losses amounts to Rs.3667.46 crores (6234MU) as per the latest data of PSERC [1]. So a lot of scope is still there to solve this problem of undesirable loss to Power sector. These losses very much affect the economy of the country which cannot be tolerated. To cover up these losses the power plant has to generate more energy. The energy required for covering up the transmission and distribution losses will also be transmitted through the transmission and distribution system which will also add energy losses to the system concerned. These losses affect the determinations of tariff which will be on higher side to recover the amount due to excess distribution losses. So it is utmost necessary for the utility to reduce the losses wherever practical. Transmission and Distribution system acts as a link between generation of power supply at power plant and its consumption at the consumer side. Transmission system is expended after the technical study of all required transmission data and transmission line routes with planed manner but expansion of distribution system is done as and when required, on the emergent demand basis. So no planning is involved in the expansion of distribution system. Due to these reason there is increase in T&D losses and reliability of power supply is minimum. End users are dissatisfied and are burdened with high tariff due to high distribution losses. So focus has rightly been shifted to improvement in distribution system to reduce distribution losses. Minimization of distribution losses is not a new topic for dissertation. A lot of work has already been done in this regard by different authors/agencies. New techniques are being developed in a effort that maximum part of generated energy should reach to the consumer end. Some of the techniques such as replacing disc type energy meter with electronics meters, use of aerial bunched cables, power factor improvement by installing capacitor units at substation [2], 11KV feeder and the motor terminals, HVDS system for agriculture connections, load balancing on each phase, checking of connections by flying squads of utilities and levying heavy penalty, high tariff/penalty for peak load hours, placing transformer at load centre etc are being adopted by utilities. In spite of the best effort done by utilities we are not close to the developed countries of the world such as, USA, Japan & South Korea on this issue [3]. From practical experience of electrical field, more efforts can be done in this regard. New suggestions have been made in this paper, along with Comprehensive analysis of already prevailing techniques for minimization of non technical losses in distribution system. For calculating non-technical losses, a case study of 11KV Gohlwar, TarnTaran feeder has been undertaken. The first step is to calculate distribution losses from the feeder data of billed energy units & incoming energy units of the feeder. Technical losses have been calculated by load flow analysis by Newton Raphson method using MiPower Software. RESEARCH ARTICLE OPEN ACCESS
  • 2. Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42 www.ijera.com 35|P a g e Non technical losses are calculated by subtracting technical losses from total distribution losses. In the end, some new techniques have been suggested for minimization of losses. In India T&D losses are officially declared as 24% [4], but different agencies including TERI (The Energy Research Institute) has estimated the T&D losses as high as 50% from their sample study carried out. This paper presents a case study of calculation of distribution losses of 11KV Kochar Urban feeder emanating from 66KV substation Gohlwar, TarnTararn Punjab. II. A Case Study In this Paper, a case study of 11KV Kochar Urban feeder emanating from 66KV substation, Gohlwar is under taken.. Fig.1 Sketch of 11KV Kochar Urban Feeder Gohlwar village is located at a distance of about 12 KMs from TarnTaran district headquarters. This substation has two nos. 66/11KV step down power transformer. The key diagram of 11KV Kochar Urban feeder is shown as per figure 1. This feeder has 32 number mixed categories of consumers, namely large supply (LS), small power (SP), non-residential supply (NRS) and domestic supply (DS). The major power consumption is of large supply & small power connections. 2.1 Methodology The distribution losses of 11KV Kochar urban feeder have been calculated by subtracting energy units billed in the area of this feeder from the units supplied to this feeder from substation as recorded by energy meter installed at the start of the feeder. The Punjab State Power Com Limited has all the records of energy incoming and outgoing from the substation duly recorded in log sheet Performa. The methodology adapted [5] for the loss calculation has been shown as per figure 2.
  • 3. Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42 www.ijera.com 36|P a g e Fig.2 Flow Chart of Methodology At first the data related to the consumption/ billed units of all consumers of this 11KV feeder is taken from the consumer ledger is taken to calculate the consumption of units & total load. The consumption data as collected has been shown as per table no.1
  • 4. Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42 www.ijera.com 37|P a g e Table no.1 Consumption Data of 11KV Kochar Urban feeder for the month of October, 2014 S.No. Name of transformer Connection A/C no. Type of Connection Consumption in KWH Load (KW) 1 25KVA Mohinder Singh GW33/1312 DS 1058 1.42 2 25KVA Mohinder Singh GW33/1313 DS 1500 1.42 3 25KVA Mohinder Singh GW33/1314 DS 638 1.42 4 25KVA Mohinder Singh GW33/1315 DS 0 1.42 5 25KVA Mohinder Singh GW33/1316 DS 686 1.42 6 25KVA Mohinder Singh GW33/1317 DS 0 1.42 7 25KVA Mohinder Singh GW33/1318 DS 1021 1.42 8 25KVA Mohinder Singh GW33/1319 DS 963 1.42 9 25KVA Mohinder Singh GW33/1320 DS 675 1.42 10 25KVA Mohinder Singh GW33/1338 DS 1017 5 11 10KVA Single Phase Transformer VP14/1812 NRS 236 1.46 12 10KVA Single Phase Transformer VP14/1872 DS 362 1.7 13 750KVA-2nos. Karam Singh & Raghbir Singh LS01/006 LS 304436 1300.439 14 2000KVA LT food Pvt. Ltd. LS01/007 LS 271294 1678.822 15 100KVA Sandeep Singh Bala Chack SP55/145 SP 411 17.65 16 100KVA Sandeep Singh Bala Chack SP55/156 SP 679 4.99 17 100KVA Sandeep Singh Bala Chack SP55/181 SP 517 14.94 18 100KVA Sandeep Singh Bala Chack SP55/196 SP 1318 14.93 19 63KVA Vijay Kumar SP55/15 SP 121 3.95 20 63KVA Vijay Kumar SP55/146 SP 216 12.76 21 63KVA Vijay Kumar BC37/483 DS 179 2.13 22 63KVA Vijay Kumar BC37/708 DS 183 2.83 23 63KVA Vijay Kumar BC37/1144 DS 224 1.53 24 63KVA Vijay Kumar BC37/1248 DS 364 0.46 25 63KVA Vijay Kumar BC37/1252 DS 255 1.92 26 63KVA Vijay Kumar BC37/1263 NRS 93 0.94 27 63KVA Vijay Kumar BC37/1282 DS 180 1.34 28 63KVA Vijay Kumar BC37/1283 DS 223 2.55 29 63KVA Vijay Kumar BC37/1292 NRS 121 0.8 30 63KVA Vijay Kumar BC37/1299 DS 11 0.96 31 63KVA Vijay Kumar BC37/1344 DS 224 1.78 32 315KVA KK Agro food LS01/0010 LS 6860 193.994 596065 3280.655
  • 5. Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42 www.ijera.com 38|P a g e 2.2 Distribution Losses Calculations (Technical Losses & Non technical Losses) For distribution losses calculation the readings of energy meter installed at substation have been recorded for one month which are given as per table 2. Table 2 Energy Meter reading of 11KV Kochar Urban feeder for the month of Oct.2014 S.No. Description of feeder Reading taken on 31/10/14 Reading taken on 30/9/14 Difference of energy meter readings M.F of energy meter Total energy sent in KWH 1 11KV Kochar Urban feeder 16763.25 15999.85 763.4 1000 763400 Total incoming units = 763400 KWH Total consumption/Billed units = 596065 KWH Distribution Losses = Total Incoming Units - Total Billed Units = (763400 – 596065) =166925 KWH = 21.88% (1) Technical and nontechnical losses are the main two parts of distribution losses. Physical properties of all the components of power system cause technical losses. Power dissipation in transmission line and transformer due to load is the most oblivious example of these losses. Technical losses are naturally occurring losses and cannot be eliminated. These losses occur due to action internal to the power system consisting of transmission lines, substations, transformers, measurement and protection equipments. If we are provided with complete data regarding running load, length and conductor sizes, these losses can be computed and controlled easily. Technical losses in distribution system include copper losses in 11KV lines, LT lines, service drops and energy meters. These losses also include core losses in distribution transformers. These losses are inherent in the power supply distribution system and cannot be avoided. Theft of energy by consumers / non consumers in one or the other way is the main cause of Non technical losses. These can be calculated by subtracting technical losses from the total distribution losses of the 11KV feeder. 2.3 Calculation of Technical Losses Technical losses of 11KV feeder can be calculated by analytical method using load factor and load loss factor and by load power flow analysis by different software available. For this, complete data of 11KV feeder along with distribution transformers installed on it is required. 2.3.1 Loading Data of Distribution Transformers Table no.3 Loading Data of Transformers on 11KV Kochar Urban feeder S.No Transformer rating KVA Qty. Total KVA Transformer Load (KW) 1 10 1 10 003.160 2 25 1 25 017.780 3 63 1 63 033.950 4 100 1 100 052.510 5 315 1 315 193.994 6 750 2 1500 1300.439 7 2000 1 2000 1678.822 Total 8 4013 KVA 3280.655 2.3.2 11KV Transmission Line Data
  • 6. Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42 www.ijera.com 39|P a g e Table 4 ACSR Conductor Details S no. Description of Conductor Length(KM) 1 50mm2 ACSR Conductor 1.6 2 35mm2 ACSR Conductor 1.8 3 25mm2 ACSR Conductor 0.9 Total 4.3 KM The Resistance of 11KV line Conductor has been taken for single conductor as per Table 5 50mm2 = 0.640146 Ohm/Km 35mm2 = 0.919246 Ohm/Km 25mm2 = 1.274624 Ohm/Km Table 5 Sequence Impedance for 11KV Aluminum Conductor ITEM Conductor Size A.C.Resistance Ohm/Cond./KM Impedance Ohm/Cond./KM mm2 Dia of Str.mm/No. of Str. 20o c 50o c Single Circuit Double Circuit X1=X2 Ro+jxo X1=X2 Ro+jxo 1 25 2.14/7 1.137143 1.274624 0.401496 1.422624+ j1.628310 0.41662 1.570624 + j2.755995 2 35 2.52/7 0.820096 0.919246 0.391226 1.067246+ j1.618040 0.40635 1.215246 + j2.745725 3 50 3.02/7 0.571100 0.640146 0.379854 0.788146 + j1.606667 0.39498 0.936146 + j2.734352 4 70 2.15/19 0.421161 0.472079 0.366401 0.620079 + j1.593214 0.38153 0.766079 + j2.720099 5 95 2.52/19 0.303853 0.340589 0.356424 0.488589 + j1.583237 0.37155 0.636589 + j2.710922 6 120 2.85/19 0.237695 0.266432 0.348692 0.414432 + j1.575505 0.36382 0.562432 + j2.703190 7 185 2.52/37 0.156761 0.175713 0.334439 0.323713 + j1.561251 0.34957 0.471713 + j2.688937 Maximum Current on feeder = 138Amp. (On 18/10/2014 at 1.00hrs) 2.3.3 Technical Losses calculation by power load flow study method. We are having all the data necessary for calculation of the distribution losses by Newton Raphson method of load flow study. As shown in figure 4 of power flow diagram of 11KV feeder, we have 16nos. of buses including 66KV, 11KV and 0.415KV buses.
  • 7. Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42 www.ijera.com 40|P a g e Fig.4 Power Flow Diagram of 11KV Kochar Urban Feeder by Mipower Software The base MVA has been taken as 100MVA and nominal system frequency 50Hzs. The 11KV feeder has three sizes of ACSR conductor namely 50mm2 , 35mm2 and 25mm2 with total line length as 4.3 KMs. The number of transformer loads, transmission lines and other detail has been given in the power flow diagram itself. Mipower software has been used for power flow study by Newton Rephson method [6]. III. Summary of Results TOTAL REAL POWER GENERATED : 3.622 MW TOTAL REACTIVE POWER GENERATED : 1.716 MVAR GENERATION Pf : 0.904 TOTAL REAL POWER LOAD : 3.279 MW TOTAL REACT. POWER LOAD : 1.501 MVAR LOAD PF : 0.909 TOTAL REAL POWER LOSS (AC+DC) : 0.342180 MW % REAL LOSS (AC+DC) : 9.448 (2) TOTAL REACT. POWER LOSS : 0.215114 MVAR IV. Calculation of Non-Technical losses As distribution losses comprises technical as well as non-technical losses [7]. So non technical losses can be calculated subtracting technical losses from total distribution losses as under. Distribution Losses as calculated (1) =21.88% Technical Losses as calculated by Load Flow Analysis by using MiPower Software (2) =9.448% Non Technical Losses = Distribution Losses - Technical Losses = (1) - (2)
  • 8. Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42 www.ijera.com 41|P a g e = 21.880% - 9.448% = 12.432% These losses are on very high side. Non-Technical losses are basically due to theft of energy in one or the other way. Maximum permissible limit for technical losses is 9% for urban and 10% for rural distribution system [8] but non technical losses are not desirable at all. So it is very important to reduce these losses and save revenue as far as possible. This will also lesson burden on consumers in the shape of lower electricity tariff. V. Economic Consequences of Distribution Losses. The economic consequences of distribution losses are far reaching. To cover up the lost energy, additional generating capacity may be required. The power which is lost as T&D losses in distribution system is still to be transmitted through these transmission lines substations etc which further adds to the energy losses already existing in that system. These losses affect the determinations of tariff which will be on higher side to recover the amount due to excess distribution losses. VI. New Techniques suggested which are yet to be adopted or not being adopted vigorously.  Mapping/ Data compilation of distribution feeders.  Correct calculation/Computation of technical losses.  Installation of energy meters on secondary side of each distribution transformers.  Prepaid energy meters.  Use of Aerial Bunched Cable.  Installation of pillar-box for domestic/NRS connection energy meters.  Checking of temporary tube well connections which have been rejected on technical ground during paddy season.  Repeated checking of tube well connection having H.P.tariff.  Every tube well connection should have energy meter to access correct consumption.  Repeated checking of seasonal factories i.e. Ice factories/ Rice shellers to avoid accumulation of consumption units with the connivance of utility staff.  Implementation of energy audit scheme.  Mitigating power theft making theft of energy as cognizable offence with punishment up to 3 years imprisonment. VII. Conclusion This paper demonstrates the capability of load power flow analysis system to calculate the technical losses and there by non technical losses in 11KV feeder. For this Newton Raphson method of load power flow study has been used through MiPower software. The data used is readily available with the engineers of power distribution utility. The non technical losses calculated are 12.432% which are on very high side. As per survey undertaken of this 11KV feeder there is Jhuggi Jhopri’s cluster under distribution area of 25KVA Mohinder Singh Wala transformer and they directly tap the bare conductor of LT line. Two nos. energy meters are dead stop and show zero consumption. Two connections of 10KVA single phase transformer are having energy meters inside the commercial/ residential premises having no terminal plates. So pilferage of energy from incoming terminals cannot be ruled out. Small power connections on 100KVA Sandeep Singh Bala Chack is having naked joints in incoming cable so theft of energy by small power consumers may be there. All the domestic / non residential supply connections on 63 KVA Vijay Kumar transformer are having energy meters inside the respective premises and these have not been shifted outside in sealed pillar box. Thus calculation of non-technical losses of this feeder will be beneficial to the utility to know the theft/pilferage going on in this area. Removing naked joints from incoming cables, shifting of energy meters outside the premises in sealed pillar boxes, replacement of slow/defective meters, proper sealing of terminal plates and meter boxes, distribution of power supply to small power consumers having load more than 10 KW by HVDS system, checking of temporary tube well connections rejected on technical ground during paddy season and continuous checking of seasonal factories will definitely decrease the non technical losses of this feeder. References [1] Punjab State electricity Regulatory commission Tariff Order 2014-15 Volume-1 www.pserc.nic.in. [2] Parmar Jigu Total losses in power distribution & transmission line published in Electrical Engg. Potel, Aug19, 2013.
  • 9. Dharam Singh et al.Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 6, ( Part -3) June 2015, pp.34-42 www.ijera.com 42|P a g e [3] Singh Tejinder Analysis of Non Technical Losses and its economic consequences on power system, Master Degree Thesis, Thapar University 2009. [4] Wikipedia The free Encyclopedia (2015) Electricity Sector in India www.wikipedia.org. [5] Pawar Rajneesh, Singh Jatinder Calculation of T&D Losses% Based on 11/0.4KV substation in a distribution utility, Published in power India conference, 2012 IEEE Fifth. [6] Volta River Authority Non-Technical Losses Reduction. A presentation during UPDEA Scientific committee meeting in Durban, S.A, Thompson AGALAB (2010). [7] Power Research and Development Consultant MiPowerTM , How to Solve 2003. [8] Jena B C “Distribution losses in power system” www.academia.edu Feb17, 2012. [9] Ghosh Soham: Loss reduction and efficiency improvement: A critical Appraisal of Power distribution sector in India. International journal of Modern Engineering Research (IJMER) volume-2, issue-5, September- October-2012.PP3292-3297.’