SlideShare a Scribd company logo
1 of 11
Download to read offline
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 46 | P a g e
Analysis and Design of Marine Berthing Structure
T.Vivek1
, R.Durga prasad2
1
P.G. Student, Department of Civil Engineering, Swamy Vivekananda Engineering college, Kalavarai, bobbili,
vizianagaram, Andhra Pradesh, India.
2
Assistant Professor, Department of Civil Engineering, Swamy Vivekananda Engineering college, Kalavarai,
bobbili, vizianagaram, Andhra Pradesh, India.
ABSTRACT
In the present dissertation a berthing structure was analyzed and designed using different load conditions and the
best possible way to construct a new berthing structure was described. All the suitable and useful data was
adopted from the proposed site location at Visakhapatnam Port and studied carefully before designing the
structure. The proposed berthing structure was modeled with suitable geometry using STAADPRO, after which
all considerable loads on the structure were induced and analyzed carefully. Different sectional dimensions were
trialed during the analysis and the most acceptable structure was designed with providing all structural members
with suitable reinforcement and satisfying all marine safety conditions.
I. INTRODUCTION
The berthing structures are constructed for the berthing and mooring of vessels to enable loading and
unloading of cargo and for embarking and disembarking of passengers, conveyances etc. The orchestrating and
design of berthing structures depend on sundry factors. In the present study of the project, we described a
felicitous way to design an incipient berthing structure with example of one of the proposed berthing structure in
Visakhapatnam port. So afore analyzing and designing, the influence factors which effected on the structure
were taken into consideration such as soil characteristics of the proposed location, environmental conditions and
range of traffic.
All the rudimental Data was adopted from Visakhapatnam port which were supposed to be utilized in
the project such as geotechnical data, environmental data, and traffic forecasting data. The entire Berth length of
100m was divided into 3 units of each 33.33 in length with an expansion joint of 40mm between successive
units and proposed in the inner harbour, designated for handling liquid cargo like Sulphuric acid, Phosphoric
acid, phosphoric acid, edible oils etc. The details of the structural element are discussed under the conceptual
design. The design dredge level is taken as -16.10m.
A berthing structure is a capital injuctively authorizing project, thereby; optimum utilization of both
space and capital becomes essential. This denotes that felicitous orchestrating of the sundry units undergo from
congestion or inflexibility due to short comings in orchestrating or due to erroneous estimate of the traffic and or
land requisite. Berthing structures vary generally from port to port. The number of berths will depend upon the
number of ships to utilize the port and the time it will take to ejection and take on cargo or passengers. Berthing
structures should be located in the most bulwarked part of the harbor or along the the wind and waves as
possible.
II. DESIGN PARAMETERS OF BERTHING STRUCTURES
2.1.1 PLACE OF CONSTRUCTION
The determination of location influenced by easy accessibility for ships, sufficient draft availability during the
year, favorable metrological and wave hydro dynamic conditions. Amount of the forces on marine structure
depends on last two factors.
2.1.2 TYPES
After determination of the location for structure, have to select the kind of structure for construction and the
factors controlling the selection of the kind of structure are depending on the conditions of water flowing and
Geotechnical properties of soil.
Classifications of berthing structure are basically Piers and Wharfs
1) Wharf – A berthing structure which is parallel to shore line. It is generally adjacent to the shore, and may not
be very near to shore
RESEARCH ARTICLE OPEN ACCESS
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 47 | P a g e
2) Pier - A berthing structure which is project into water that means perpendicular to shore. This structure need
not be exactly perpendicular to shore; it may be with some angle to shore. These structures also are like T or L
shape.
2.1.3 WAY OF SELECTION TO CONSTRUCT BERTHING STRUCTURES
Type of berthing structure and utilized material for construction depend on various factors
Local customs and practice: for suppose, Europe used the massive quays, whereas, America used the open and
light structures.
 Material availability
 Construction cost.
 Method of construction.
 Dimension and mass of ships handled in the port.
2.1.4 REQUIRED NUMBER OF BERTHS
The determination of number of berths depends on handling of traffic in port .the planning of a new terminal
was influenced by initial investment.
The approximate relations used for the determination of the required number of berths are:
N1= W/ R* H * D
Where,
N1= essential amount of berths for a certain cargo.
W = yearly amount of this cargo imported and exported(T/year).
R = handling rate of this cargo on the berth. (T/ hour) H = number of working hours per day. (Hour/ day) D =
amount of working days per year. (Day/ year)
N1 is calculated for each kind of cargo, and the overall number of berths in the port N for all types of cargo is:
N = N1 + N2 + N3 +……..
2.1.5 LONGITUDINAL DIMENSION OF BERTH
The function of the terminal and size of vessel determines the berth length and ships calling to port also
influence the length
Berth length required for main line vessels is 275+25=300m
Berth length required for feeder vessels is 150 +50 = 200m
2.1.6 REQUIRED AREA OF BERTH
Berthing territory ought to be focused around the length and broadness of the biggest size of boat
utilizing for the berths. Berthing range is the zone before the berthing structure needed for berthing vessels
furthermore suits the administration vessels. Length needed for berthing a vessel and its surging developments
because of wave and momentums are for the most part defined as 10% of boats length, subject to at least 15m.
d1 ought not be short of what (L1+l2)/20 and d2 >= (L2+l3)/20 where there are solid obstructions, the safe
separation of d0 = 25 – 30 m is permitted. The width of the berthing zone ought to be 1.15 B + b where B is the
shaft width of the outline vessel and b is the width of the attending craft.
2.1.7 DRAFT MAINTENANCE ALONG THE BERTH
The third era holder vessels have a draft of 12.5 m. Subsequently a depth of 13.5 m must be kept up close by the
quay amid all conditions permitting sufficient depth for different remittances. Depth at the compartment ought
to be 10% in abundance of most extreme stacked draft of configuration vessel to consider silting and vertical
movement.
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 48 | P a g e
Fig: 2.1.7 draft representation along the berth
2.1.8 WIDTH OF BERTH APRON
Cover width of a quay is reliant on the sort of equipment utilized for stacking and exhausting
operations. The apron width is picked focused around the facilities gave. The width of the berth will in a general
sense rely on upon space prerequisites of substantial obligation boat to shore cranes which must have versatility
all through the length of berth. The necessity, for the width of apron varies with the separation from berthing
line to the first rail track of the gantry crane and with the back compass of the crane. Measurements of the
holder cranes may shift appropriately to the outline and limit of the crane. Obliged width of the cover for
commonplace compartment crane is 2 to 4 m for the separation from water front to the first rail, 20 to 35 m for
the track width of the crane and 8 to 16 m for back achieve, making a sum of 30 to 55 m towards back.
2.1.9 ELEVATION OF DECK
Deck elevation is fine-tuned at or above the highest high spring dihydrogen monoxide level plus half the wave
height near the berth plus a free board of 1m. The maximum distance of quay edge inclusive of fine-tuned
fenders from the outer track of the crane is about 2.65m.
2.1.10 TURNING CIRCLE
Measurements of turning loop are subject to the predominating power of wind, current and the force of tugs
accessible for aid. The accompanying criteria may be followed in either case for figuring the radius of the circle:
i) Without tug support - 1.7 l
ii) With tug support - 0.85 L
The third era boats will have a draft of 12.2 m. Consequently a navigational channel which can suit these boats
is important with a base depth of 13.5 m.
2.1.11 AREA REQUIRED FOR STACKING PURPOSE
The zone needed for capacity of holder inside the terminal relies on upon the accompanying elements
1) Throughput anticipated that will pass through the terminal for every annum.
2) Dwell time of containers inside the terminal. This is the mundane time a container would utilize in the yard
after import and afore re-trade in a transit terminal.
3) The kind of container handling equipment utilized for stacking.
4) Average stacking height: Containers are not stacked to the most extreme tallness in all the spaces inside the
stacking region. This is obliged to empower the taking care of supplies to get the lower holders in the stack
for release. Moreover, containers need to be isolated by end, weight class, and direction of peregrinate in
some cases by sorts and frequently shipping line or accommodation. Subsequently there is dependably a
proportion between the mundane stacking stature and most extreme stacking tallness
5) Peaking factor: This is the degree of the crest activity to the average traffic, generally taken in the middle of
1.3 to 1.4.
6) Ratio of working slots: All the slots gave on the ground can't be accessible for stacking because of different
reasons. The degree of working spaces to general apertures is generally taken as 0.8.
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 49 | P a g e
III. INDUCED LOADS ON BERTHING STRUCTURE
The whole EQ (Eastern Quay)-10 berth length of 100.07 m is separated into 3 units of every 33.33 long
with an expansion joint of 40mm between progressive units
The proposed EQ-10 berth is implied for taking care of fluid freight like Sulphuric corrosive, Phosphoric
corrosive, phosphoric corrosive, eatable oils and so on the subtle elements of the structural component are talked
about under the applied configuration .in spite of the fact that the concession understanding accommodates
dredging must be conveyed up to -16.10m .henceforth the outline dredging level is taken as -16.10m
IV. ANALYSIS OF INDUCED LOADS
4.1.1 DEAD LOAD
Fig: 4.1.1 Dead load representation on structure
All dead loads of and on structures identifying with docks and harbor ought to be evaluated and
included in the design configuration. Dead loads comprise of the weight of all parts of the structure and also the
weight of all permanent connections. The DL of a port related marine structure constitutes a relative little rate of
the total burden acting up on the structure.
Wearing coat (Apron) = 0.20 X 25 = 5 kN/m2
(density of the concrete is taken 25 kN/m3
)
Slab weight = 0.30 X 25 = 7.55 kN/m2
Beams
Transverse beams = 1.10 X 1.80 X25 = 50kN/m
Longitudinal beam = 1.10 X 0.60 X 25 =16.5 kN/m
Pile =1.70X21.65X25=920.12 kN/m
4.1.2 LIVE LOAD
Fig: 4.1.2 Live load representation on structure Additional charges because of put away and stacked
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 50 | P a g e
material, for example, general load, mass freight, holders and burdens from vehicular movement of assorted
types, including trucks, trailers, track, and cranes, containers handling equipment and development plant
constitute vertical1ive loads. Vertical LL comprise of the weight of all versatile equipment’s on the structure
Serial Functioning Truck Uniform
number berth loading vertical
LL(T/m2
)
1 Passenger berth B 1.0
2 Bulk unloading A 1.0 to 1.5
and unloading
berths
3 Container berths A or AA 3 to 5
or 70R
4 Cargo berth A or AA 2.5 to 3.5
or 70R
5 Heavy cargo A or AA 5 or 6
berth or 70R
6 Small boat berth B 0.5
7 Fishing berth B 1.0
The function of berth related to Truck loading A or AA or 70R (Heavy cargo berth) so we are adopted 50
kN/m2
.
4.1.3 BERTHING LOAD
Fig: 4.1.3 berthing load representation on structure
Berthing Energy - When an approaching vessel strikes a berth a level power follows up on the
compartment. The magnitude of this power Depends on the kinetic energy that can be ingested by the Fendering
framework. The response energy for which the berth is to be composed can be acquired and Deflection-response
outlines of the fendering framework picked. These outlines are realistic from bumper producers the Kinetic
energy E, bestowed to a fendering framework, by a vessel moving with speed V m/s is given by:
W V 2
E  2
D
g (Cm )(Ce )(Cs )
WD = displacement tonnage (DT) of the vessel
V = velocity of vessel in m/s, normal to the berth g = acceleration due to gravity in m/s2
Cm = mass coefficient
Ce = eccentricity coefficient
Cs = soft coefficient
E  200000X 0.102
X 0.51X1.60X 0.95 =80kN.m
2 X 9.81
27 kNm/33m for 1unit of berth (33 meters)
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 51 | P a g e
4.1.4 MOORING LOAD
Fig: 4.1.4 mooring load representation on structure
The mooring burdens are the lateral loads brought about by the mooring lines when they pull the boat
into or along the dock or hold it against the powers of wind or current. The most extreme mooring burdens are
because of the wind compels on uncovered range on the open side of the boat in light condition
F  Cw Aw P
F = force due to wind in Kg Cw = shape factor = 1.3 to 1.6
Aw = wind age area in m2
P = wind age pressure in m2
to be taken in accordance with IS: 875-1964
The wind age area (Aw) can be predictable as follows: Aw= 1.175Lp (DM-DL)
Where
Lp= length between perpendicular in meter DM= mould depth in m, and
DL=average light draft in m.
Actual this is the definite procedure but port engineers suggested that bollard pull =900kN is adopted (Design
load) Generally mooring load act in various angle of forces so we have to resolve on the mooring point while
designing the berth. And spacing taken as bollard to bollard is 15m c/c ,if suppose we fixed 7 bollards then the
load on each bollard is 900/7 =F =128kN
Resolving of forces on mooring points are
Horizontal component = Fcos = 90kN
Vertical component = FSin = 90kN
Generally angle is taken as 450
here if necessary need to calculate at different angles as per maximum ship
moment observations.
4.1.5 CURRENT LOAD
Fig: 4.1.5 Current load representations on structure
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 52 | P a g e
Loads because of Current - Pressure because of flow will be connected to the zone of the vessel
beneath the water line when completely stacked. It is roughly equivalent to w v2
/2 g per square meter of range,
where v is the velocity in m/s and ID is the unit weight of water in tones/ml. The boat is for the most part
berthed parallel to the current with powerful currents and where berth arrangement really goes astray from the
bearing of the current, the' likely force should be considered by any familiar method and taken into account.
F= w v2
/2 g
=1.025 tonnes/m3
Unit weight of water ( w)
Velocity of current ( v) =0.26m/s
Acceleration due to gravity = 9.81m/s2
F = 0.035kN/m2
For 1 unit of berth F = 0.035X33X21.65 =25kN
25kN for 12 piles for each pile F = 2.02 kN
Load distribution is converted as uniform on pile F= 2.02/21.65 =0.096KN/m
4.1.6 WIND LOAD
Wind contributes primarily to the lateral loading on a pier. It blows from many directions and can vary
without detect. The wind impinging upon a surface increases the pressure on that surface and results in a force
loading. However, given the construction characteristics of an open pier, the loading on the structure itself is
minor compared with the wind effects of the ship moored along side. The exposed, directional, surface region of
the ship is susceptible to wind loading which is then transferred to the pier. When designing a pier, historical
wind data, along with the design ship size, is analyzed to size the structural members according to the
predominant wind direction.
Design wind speed (Vz) = Vb k1k2 k3
Vb = basic wind speed
k 1= probability factor (Risk coefficient) K2= terrain, height and structure size factor K3= topography factor
Vz = (50)(0.92)(1.05)(1) =48.3m/sec
Design wind pressure = 0.6(vz)2
p=1400N/m2
=1.4kN/ m2
Now the design wind pressure is resolved as nodal loads on structure
=1.4X 33X1 =46.2/12 =3.85 kN
4.1.7 SESMIC LOAD
Fig: 4.1.7 Lateral load representation on structure
Design seismic base shear VB= AhW
Ah = horizontal seismic coefficient
W = seismic weight of structure
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 53 | P a g e
4.1.8 EARTH PRESSURE
Fig: 4.1.8 Earth Pressure representation on structure
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 54 | P a g e
4.1.9 HYDROSTATIC PRESSURE
On account of waterfront structures with inlay, the weight created by distinction in water level at the
fill side and waterside must be considered in design configuration. The magnitude of hydrostatic pressure is
affected by the tidal extent, free water variances, the ground water deluge, the porousness of the establishment
of foundation soil and the structure and also the proficiency of accessible refill drainage
Fig: 4.1.9 hydrostatic load representation on structure
P= h
 =unit weight of water=10kN/m3
H= water head on structure; m P=10 X 18 =180kN/m2
= 180X1.57=270kN/m on every pile
 BASIC LOAD COMBINATIONS
 1.5DL+1.5LL+1(EARTHPRESSURE)+1(HY
DROSTATICPRESSURE)+1.5(BERTHING LOAD)+1.5(MOORING LOAD)
 1.2DL+1.2LL+1E.P+1.2H.P
 1.2DL+1.2LL+1EP+1HP+1.5(WIND LOAD)
 1.2DL+1.2LL+EP+1HP+1.5(SEISMIC

LOAD)
5.DESIGN
5.1DESIGN OF BEAM
TRANSVERSE BEAM
 Pile cap beam
 Grade of concrete:M40
 Grade of steel:Fe415
 Size of the bar:32mm
 Spacing between bars:238mm
 Cover:50mm
LONGITUDUNAL BEAM
 Grade of concrete:M30
 Grade of steel:Fe415
 Size of the bar:20mm
 Spacing between bars:125mm
 Cover:50mm
 Shear reinforcement:12mm@150mm/cc
 Size:600mm x 1100mm
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 55 | P a g e
5.2DESIGN OF SLAB
 Thickness of slab:300mm
 Effective depth:217mm
 Effective cover:75mm
 Grade of concrete:M40
 Grade of steel:Fe415
5.3DESIGN OF PILE
 Grade of concrete:M40
 Grade of steel:Fe415
 Dia of the pile:1700mm
 Size of bar:40mm
 Spacing between bars:76mm
 Cover:50mm
 Tie reinforcement:16mm@300mm/cc
V. CONCLUSION
Different factors are to be considered while analyzing and designing the berthing structure. Lateral
loads on the berthing structures are more eminent than those on land– based structures. Congruous
environmental data, traffic forecasting and soil data ought to be received from the proposed site location, typical
load distribution is induced on the shore line structures, so need to utilize STAAD Pro software for the analysis
and design.
The structure was analyzed and designed satisfying various loading conditions and dimension analysis
for economical aspect was additionally taken care of without exceeding the structural safety. Afore going for
designing or orchestrating a berthing structure, all the present and future optimistic conditions regarding traffic
data, hinterland expansion and industrialization of that particular hinterland are to be studied, which additionally
play a major role in shaping the project inception at the first place.
REFERENCES
[1]. Krishna Raju.N, “Advanced Reinforced Concrete Design”, 2nd
Edition, Cbs Publication & Distributors
Pvt .Ltd, Newdelhi, 2012.
[2]. Muthukkumaran.K, Sundaravadivelu and Gandhi.S.R, “Effect of Dredging and Axial Load on a Berthing
Structure”, Geotechnical conference, 2006.
[3]. Premalatha P.V, Muthukkumaran. K & Jayabalan
[4]. P,“Behaviour of piles supported berthing structure under lateral loads”, Geotechnical conference, 2011.
[5]. Ramamrutham.S, “Design of Reinforced Concrete Structures”, 16th Edition, Dhanpat Rai Publications
Company, Newdelhi, 2009.
[6]. Sanil Kuma.R, K. Ashok Kumar and N. S. N. Raju, “Wave characteristics off Visakhapatnam coast
during a cyclone “, research article 1524 current science, 2004, vol. 86, no. 11
[7]. Shanthal. B, Subba rao,katta Henkatramana And
[8]. Harish, “ Analysis of berthing structures for wave induced Forces”,
International journal of earth sciences and engineering,2011,vol. 4,No 1, pp. 112-121.
[9]. SP16,“Code Of Practice Criteria For Design Aids For Reinforced Concrete To IS: 456-2000”, Fourth
Revision, Bureau of Indian Standards, New Delhi.
[10]. Thomos dawson. H, “Offshore Structural Engineering”, 2nd
Edition, Prentice –hall, New Jersey, 2010
[11]. Thandava Moorty, T.S, “Analysis of Structures”, 6th
Edition, Oxford University Press, Newdelhi, 2005.
[12]. www.vizagport.com
[13]. Kavitha.P.E, Dr.Narayanan.K.P, Dr. Sudheer.C.B., “Software Development for the Analysis and Design
of Ship Berthing Structures”, ACEEE Int. J. On Transportation and Urban Development, 2011, Vol.1,
No. 1.
[14]. Yasser E. Mostafa, “Design Considerations for Pile Groups Supporting Marine Structures with Respect
to Scour”, (http://www.scirp.org/journal/eng), 2012, No 4, pp.833-842.
[15]. IS 456: 2000, “Code of Practice for Plain And Reinforced Concrete Code Of Practice”, Ninth Revision,
[16]. Bureau of Indian Standards, New Delhi.
T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com
ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56
www.ijera.com 56 | P a g e
[17]. IS: 875 (Part 1) – 1987, “Code of Practice for Design Loads (Other than Earthquake) For Buildings and
Structures Part 1 Dead Loads — Unit Weights Of Building Materials and Stored Material”, Second
Revision, Bureau of Indian Standards, New Delhi.
[18]. Structures Part 5 Special Loads and Combinations”, Second Revision, Bureau of Indian Standards,
New Delhi.
[19]. IS: 875 (Part 2) – 1987, “Code of Practice for Design Loads (Other Than Earthquake) For Buildings and
Structures Part 2 Imposed Loads", Second Revision, Bureau of Indian Standards, New Delhi.
[20]. IS: 875 (Part 3) – 1987,” Code of Practice for Design Loads (Other Than Earthquake) For Buildings and
[21]. Structures Part 3 Wind Loads”, Second Revision, Bureau of Indian Standards, New Delhi.
[22]. IS: 875 (Part 5) – 1997, “Code of Practice for Design Loads (Other Than Earthquake) for Buildings and
Structures Part 5 Special Loads and Combinations”,
[23]. Second Revision, Bureau of Indian Standards, New Delhi.
[24]. IS: 1893-1984, “Code of Practice Criteria for
[25]. Earthquake Resistant Design of Structures”, Fourth Revision, Bureau of Indian Standards, New
Delhi.
[26]. IS 4651 (Part IV): 1989, “Code of Practice for General Design Considerations”, Second Revision,
Bureau of Indian Standards, New Delhi.
[27]. IS: 4851 (Part III) – 1974, “Code Of Practice For Planning and Design Of Ports and Harbours “, First
Revision, Bureau of Indian Standards, New Delhi.
[28]. IS 14238:1995, “Code of Practice for Inland vessels – Selection of rubber Fenders for berthing structures
code of practice”, second Revision, Bureau of Indian Standards, New Delhi.

More Related Content

What's hot

Tecnologia de Veículos de Imersão Profunda para o século XXI
Tecnologia de Veículos de Imersão Profunda para o século XXITecnologia de Veículos de Imersão Profunda para o século XXI
Tecnologia de Veículos de Imersão Profunda para o século XXILeonam Guimarães
 
propulsion engineering-01-introduction 003 sm415-propulsion engineering-01-in...
propulsion engineering-01-introduction 003 sm415-propulsion engineering-01-in...propulsion engineering-01-introduction 003 sm415-propulsion engineering-01-in...
propulsion engineering-01-introduction 003 sm415-propulsion engineering-01-in...fahrenheit
 
Seismic Risk Assessment of Buried Pipelines in City Regions, Hamzeh SHAKIB
Seismic Risk Assessment of Buried Pipelines in City Regions, Hamzeh SHAKIBSeismic Risk Assessment of Buried Pipelines in City Regions, Hamzeh SHAKIB
Seismic Risk Assessment of Buried Pipelines in City Regions, Hamzeh SHAKIBGlobal Risk Forum GRFDavos
 
IRJET- Review on Seismic Analysis of Elevated Water Tanks with Different Shap...
IRJET- Review on Seismic Analysis of Elevated Water Tanks with Different Shap...IRJET- Review on Seismic Analysis of Elevated Water Tanks with Different Shap...
IRJET- Review on Seismic Analysis of Elevated Water Tanks with Different Shap...IRJET Journal
 
propulsion engineering-02-resistance of ships
propulsion engineering-02-resistance of shipspropulsion engineering-02-resistance of ships
propulsion engineering-02-resistance of shipsfahrenheit
 
weg-2016-vol-3-naval-systems
 weg-2016-vol-3-naval-systems weg-2016-vol-3-naval-systems
weg-2016-vol-3-naval-systemsTriplo Sof
 
Analysis of The Propulsion System Towards The Speed Reduction of Vessels Type...
Analysis of The Propulsion System Towards The Speed Reduction of Vessels Type...Analysis of The Propulsion System Towards The Speed Reduction of Vessels Type...
Analysis of The Propulsion System Towards The Speed Reduction of Vessels Type...IJERA Editor
 
Implications of the Second Generation Intact Stability Criteria When Applied ...
Implications of the Second Generation Intact Stability Criteria When Applied ...Implications of the Second Generation Intact Stability Criteria When Applied ...
Implications of the Second Generation Intact Stability Criteria When Applied ...IJMERJOURNAL
 
CMS Wave Model Project
CMS Wave Model ProjectCMS Wave Model Project
CMS Wave Model Projectbahar fahmi
 
Kuliah 3 tbk ukuran utama kapal
Kuliah 3 tbk ukuran utama kapalKuliah 3 tbk ukuran utama kapal
Kuliah 3 tbk ukuran utama kapalimamulfaizin
 
Introduction CMS (Coastal Modeling System) SMS
Introduction CMS (Coastal Modeling System) SMS Introduction CMS (Coastal Modeling System) SMS
Introduction CMS (Coastal Modeling System) SMS bahar fahmi
 
Navy Invests in New Mine Warfare Technology (UPDATED)
Navy Invests in New Mine Warfare Technology (UPDATED)Navy Invests in New Mine Warfare Technology (UPDATED)
Navy Invests in New Mine Warfare Technology (UPDATED)TJR Global
 

What's hot (20)

Tecnologia de Veículos de Imersão Profunda para o século XXI
Tecnologia de Veículos de Imersão Profunda para o século XXITecnologia de Veículos de Imersão Profunda para o século XXI
Tecnologia de Veículos de Imersão Profunda para o século XXI
 
propulsion engineering-01-introduction 003 sm415-propulsion engineering-01-in...
propulsion engineering-01-introduction 003 sm415-propulsion engineering-01-in...propulsion engineering-01-introduction 003 sm415-propulsion engineering-01-in...
propulsion engineering-01-introduction 003 sm415-propulsion engineering-01-in...
 
Fredyn
FredynFredyn
Fredyn
 
Seismic Risk Assessment of Buried Pipelines in City Regions, Hamzeh SHAKIB
Seismic Risk Assessment of Buried Pipelines in City Regions, Hamzeh SHAKIBSeismic Risk Assessment of Buried Pipelines in City Regions, Hamzeh SHAKIB
Seismic Risk Assessment of Buried Pipelines in City Regions, Hamzeh SHAKIB
 
IRJET- Review on Seismic Analysis of Elevated Water Tanks with Different Shap...
IRJET- Review on Seismic Analysis of Elevated Water Tanks with Different Shap...IRJET- Review on Seismic Analysis of Elevated Water Tanks with Different Shap...
IRJET- Review on Seismic Analysis of Elevated Water Tanks with Different Shap...
 
5.1 reservoir planning
5.1 reservoir planning5.1 reservoir planning
5.1 reservoir planning
 
DREDGING
DREDGINGDREDGING
DREDGING
 
propulsion engineering-02-resistance of ships
propulsion engineering-02-resistance of shipspropulsion engineering-02-resistance of ships
propulsion engineering-02-resistance of ships
 
weg-2016-vol-3-naval-systems
 weg-2016-vol-3-naval-systems weg-2016-vol-3-naval-systems
weg-2016-vol-3-naval-systems
 
Analysis of The Propulsion System Towards The Speed Reduction of Vessels Type...
Analysis of The Propulsion System Towards The Speed Reduction of Vessels Type...Analysis of The Propulsion System Towards The Speed Reduction of Vessels Type...
Analysis of The Propulsion System Towards The Speed Reduction of Vessels Type...
 
Martec 2010
Martec 2010Martec 2010
Martec 2010
 
ARMF 2014 USCG White Paper
ARMF 2014 USCG White PaperARMF 2014 USCG White Paper
ARMF 2014 USCG White Paper
 
putnam engineering geophysics 2007
putnam engineering geophysics 2007putnam engineering geophysics 2007
putnam engineering geophysics 2007
 
Implications of the Second Generation Intact Stability Criteria When Applied ...
Implications of the Second Generation Intact Stability Criteria When Applied ...Implications of the Second Generation Intact Stability Criteria When Applied ...
Implications of the Second Generation Intact Stability Criteria When Applied ...
 
Stream Gauging
Stream GaugingStream Gauging
Stream Gauging
 
CMS Wave Model Project
CMS Wave Model ProjectCMS Wave Model Project
CMS Wave Model Project
 
Kuliah 3 tbk ukuran utama kapal
Kuliah 3 tbk ukuran utama kapalKuliah 3 tbk ukuran utama kapal
Kuliah 3 tbk ukuran utama kapal
 
Introduction CMS (Coastal Modeling System) SMS
Introduction CMS (Coastal Modeling System) SMS Introduction CMS (Coastal Modeling System) SMS
Introduction CMS (Coastal Modeling System) SMS
 
Navy Invests in New Mine Warfare Technology (UPDATED)
Navy Invests in New Mine Warfare Technology (UPDATED)Navy Invests in New Mine Warfare Technology (UPDATED)
Navy Invests in New Mine Warfare Technology (UPDATED)
 
Structural Design of Drill Ships
Structural Design of Drill ShipsStructural Design of Drill Ships
Structural Design of Drill Ships
 

Viewers also liked

Riverside Population in Amazon: Culture, Environment and Construction Technique
Riverside Population in Amazon: Culture, Environment and Construction TechniqueRiverside Population in Amazon: Culture, Environment and Construction Technique
Riverside Population in Amazon: Culture, Environment and Construction TechniqueIJERA Editor
 
A Study on self-Compacting Concrete Using Portland Slag Cement with Partial R...
A Study on self-Compacting Concrete Using Portland Slag Cement with Partial R...A Study on self-Compacting Concrete Using Portland Slag Cement with Partial R...
A Study on self-Compacting Concrete Using Portland Slag Cement with Partial R...IJERA Editor
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...IJERA Editor
 
Graph-Based Algorithm for a User-Aware SaaS Approach: Computing Optimal Distr...
Graph-Based Algorithm for a User-Aware SaaS Approach: Computing Optimal Distr...Graph-Based Algorithm for a User-Aware SaaS Approach: Computing Optimal Distr...
Graph-Based Algorithm for a User-Aware SaaS Approach: Computing Optimal Distr...IJERA Editor
 
Battery Remaining Useful life Forecast Applied in Unmanned Aerial Vehicle.
Battery Remaining Useful life Forecast Applied in Unmanned Aerial Vehicle.Battery Remaining Useful life Forecast Applied in Unmanned Aerial Vehicle.
Battery Remaining Useful life Forecast Applied in Unmanned Aerial Vehicle.IJERA Editor
 
A Mobile-Cloud based Context-Aware and Interactive Framework for Diabetes Man...
A Mobile-Cloud based Context-Aware and Interactive Framework for Diabetes Man...A Mobile-Cloud based Context-Aware and Interactive Framework for Diabetes Man...
A Mobile-Cloud based Context-Aware and Interactive Framework for Diabetes Man...IJERA Editor
 
Thermal Preference: An analysis alternative approache to estimatethermalcomfo...
Thermal Preference: An analysis alternative approache to estimatethermalcomfo...Thermal Preference: An analysis alternative approache to estimatethermalcomfo...
Thermal Preference: An analysis alternative approache to estimatethermalcomfo...IJERA Editor
 
Magneto-transport properties of MnGeP2 and MnGeAs2 films
Magneto-transport properties of MnGeP2 and MnGeAs2 filmsMagneto-transport properties of MnGeP2 and MnGeAs2 films
Magneto-transport properties of MnGeP2 and MnGeAs2 filmsIJERA Editor
 
Acute Toxicity of Fluazifop-P-Butyl (Herbicide) on Daphnia magna (Straus, 1820)
Acute Toxicity of Fluazifop-P-Butyl (Herbicide) on Daphnia magna (Straus, 1820)Acute Toxicity of Fluazifop-P-Butyl (Herbicide) on Daphnia magna (Straus, 1820)
Acute Toxicity of Fluazifop-P-Butyl (Herbicide) on Daphnia magna (Straus, 1820)IJERA Editor
 
CS Based Channel Estimation for OFDM Systems under Long Delay Channels Using ...
CS Based Channel Estimation for OFDM Systems under Long Delay Channels Using ...CS Based Channel Estimation for OFDM Systems under Long Delay Channels Using ...
CS Based Channel Estimation for OFDM Systems under Long Delay Channels Using ...IJERA Editor
 
Design and Fem Analysis of Car Alloy Wheel
Design and Fem Analysis of Car Alloy WheelDesign and Fem Analysis of Car Alloy Wheel
Design and Fem Analysis of Car Alloy WheelIJERA Editor
 
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...An Experimental Study on Behavior of Partial Replacement of Cement with Groun...
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...IJERA Editor
 
Methods for assessment of a cooling tower plume size
Methods for assessment of a cooling tower plume sizeMethods for assessment of a cooling tower plume size
Methods for assessment of a cooling tower plume sizeIJERA Editor
 
Elaboration and sensory evaluation of pecan nut butter (Carya Illinoensis K) ...
Elaboration and sensory evaluation of pecan nut butter (Carya Illinoensis K) ...Elaboration and sensory evaluation of pecan nut butter (Carya Illinoensis K) ...
Elaboration and sensory evaluation of pecan nut butter (Carya Illinoensis K) ...IJERA Editor
 

Viewers also liked (14)

Riverside Population in Amazon: Culture, Environment and Construction Technique
Riverside Population in Amazon: Culture, Environment and Construction TechniqueRiverside Population in Amazon: Culture, Environment and Construction Technique
Riverside Population in Amazon: Culture, Environment and Construction Technique
 
A Study on self-Compacting Concrete Using Portland Slag Cement with Partial R...
A Study on self-Compacting Concrete Using Portland Slag Cement with Partial R...A Study on self-Compacting Concrete Using Portland Slag Cement with Partial R...
A Study on self-Compacting Concrete Using Portland Slag Cement with Partial R...
 
Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...Causes of delays on Construction Projects in Kuwait according to opinion of e...
Causes of delays on Construction Projects in Kuwait according to opinion of e...
 
Graph-Based Algorithm for a User-Aware SaaS Approach: Computing Optimal Distr...
Graph-Based Algorithm for a User-Aware SaaS Approach: Computing Optimal Distr...Graph-Based Algorithm for a User-Aware SaaS Approach: Computing Optimal Distr...
Graph-Based Algorithm for a User-Aware SaaS Approach: Computing Optimal Distr...
 
Battery Remaining Useful life Forecast Applied in Unmanned Aerial Vehicle.
Battery Remaining Useful life Forecast Applied in Unmanned Aerial Vehicle.Battery Remaining Useful life Forecast Applied in Unmanned Aerial Vehicle.
Battery Remaining Useful life Forecast Applied in Unmanned Aerial Vehicle.
 
A Mobile-Cloud based Context-Aware and Interactive Framework for Diabetes Man...
A Mobile-Cloud based Context-Aware and Interactive Framework for Diabetes Man...A Mobile-Cloud based Context-Aware and Interactive Framework for Diabetes Man...
A Mobile-Cloud based Context-Aware and Interactive Framework for Diabetes Man...
 
Thermal Preference: An analysis alternative approache to estimatethermalcomfo...
Thermal Preference: An analysis alternative approache to estimatethermalcomfo...Thermal Preference: An analysis alternative approache to estimatethermalcomfo...
Thermal Preference: An analysis alternative approache to estimatethermalcomfo...
 
Magneto-transport properties of MnGeP2 and MnGeAs2 films
Magneto-transport properties of MnGeP2 and MnGeAs2 filmsMagneto-transport properties of MnGeP2 and MnGeAs2 films
Magneto-transport properties of MnGeP2 and MnGeAs2 films
 
Acute Toxicity of Fluazifop-P-Butyl (Herbicide) on Daphnia magna (Straus, 1820)
Acute Toxicity of Fluazifop-P-Butyl (Herbicide) on Daphnia magna (Straus, 1820)Acute Toxicity of Fluazifop-P-Butyl (Herbicide) on Daphnia magna (Straus, 1820)
Acute Toxicity of Fluazifop-P-Butyl (Herbicide) on Daphnia magna (Straus, 1820)
 
CS Based Channel Estimation for OFDM Systems under Long Delay Channels Using ...
CS Based Channel Estimation for OFDM Systems under Long Delay Channels Using ...CS Based Channel Estimation for OFDM Systems under Long Delay Channels Using ...
CS Based Channel Estimation for OFDM Systems under Long Delay Channels Using ...
 
Design and Fem Analysis of Car Alloy Wheel
Design and Fem Analysis of Car Alloy WheelDesign and Fem Analysis of Car Alloy Wheel
Design and Fem Analysis of Car Alloy Wheel
 
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...An Experimental Study on Behavior of Partial Replacement of Cement with Groun...
An Experimental Study on Behavior of Partial Replacement of Cement with Groun...
 
Methods for assessment of a cooling tower plume size
Methods for assessment of a cooling tower plume sizeMethods for assessment of a cooling tower plume size
Methods for assessment of a cooling tower plume size
 
Elaboration and sensory evaluation of pecan nut butter (Carya Illinoensis K) ...
Elaboration and sensory evaluation of pecan nut butter (Carya Illinoensis K) ...Elaboration and sensory evaluation of pecan nut butter (Carya Illinoensis K) ...
Elaboration and sensory evaluation of pecan nut butter (Carya Illinoensis K) ...
 

Similar to Analysis and Design of Marine Berthing Structure

Software Development for the Analysis and Design of Ship Berthing Structures
Software Development for the Analysis and Design of Ship Berthing StructuresSoftware Development for the Analysis and Design of Ship Berthing Structures
Software Development for the Analysis and Design of Ship Berthing StructuresIDES Editor
 
IRJET- Analysis of Loads and Design of Passenger Boat Berthing Structure ...
IRJET-  	  Analysis of Loads and Design of Passenger Boat Berthing Structure ...IRJET-  	  Analysis of Loads and Design of Passenger Boat Berthing Structure ...
IRJET- Analysis of Loads and Design of Passenger Boat Berthing Structure ...IRJET Journal
 
IRJET- Analysis and Design of Berthing Structure
IRJET- Analysis and Design of Berthing StructureIRJET- Analysis and Design of Berthing Structure
IRJET- Analysis and Design of Berthing StructureIRJET Journal
 
IRJET- Preliminary Design of Floating Dry Dock
IRJET- Preliminary Design of Floating Dry DockIRJET- Preliminary Design of Floating Dry Dock
IRJET- Preliminary Design of Floating Dry DockIRJET Journal
 
A wave piercing catamaran ferry
A wave piercing catamaran ferryA wave piercing catamaran ferry
A wave piercing catamaran ferryKARIM KOTB
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623VATSAL PATEL
 
Challenges and prospects of Bay Container Terminal, Chittagong.
Challenges and prospects of Bay Container Terminal, Chittagong.Challenges and prospects of Bay Container Terminal, Chittagong.
Challenges and prospects of Bay Container Terminal, Chittagong.MOHIMENUL
 
harborengineering-200428164114 (1).pdf
harborengineering-200428164114 (1).pdfharborengineering-200428164114 (1).pdf
harborengineering-200428164114 (1).pdfjaswanthyadav12
 
REVIEW PAPER ON “HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
REVIEW PAPER ON “HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”REVIEW PAPER ON “HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
REVIEW PAPER ON “HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”IRJET Journal
 
Using Half Pipes as Permeable Breakwater
Using Half Pipes as Permeable BreakwaterUsing Half Pipes as Permeable Breakwater
Using Half Pipes as Permeable BreakwaterIRJET Journal
 
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET Journal
 
NON-LINEAR STATIC ANALYSIS OF A BERTHING STRUCTURE SUBJECTED TO VARIOUS CRANE...
NON-LINEAR STATIC ANALYSIS OF A BERTHING STRUCTURE SUBJECTED TO VARIOUS CRANE...NON-LINEAR STATIC ANALYSIS OF A BERTHING STRUCTURE SUBJECTED TO VARIOUS CRANE...
NON-LINEAR STATIC ANALYSIS OF A BERTHING STRUCTURE SUBJECTED TO VARIOUS CRANE...IRJET Journal
 
IRJET- Planning and Design of Container Terminal
IRJET-  	  Planning and Design of Container TerminalIRJET-  	  Planning and Design of Container Terminal
IRJET- Planning and Design of Container TerminalIRJET Journal
 
IRJET-Analysis of Offshore Jacket Structure
IRJET-Analysis of Offshore Jacket StructureIRJET-Analysis of Offshore Jacket Structure
IRJET-Analysis of Offshore Jacket StructureIRJET Journal
 
Hydraulic and-structural-design-of-navigational-locks-2165-784 x-1000297
Hydraulic and-structural-design-of-navigational-locks-2165-784 x-1000297Hydraulic and-structural-design-of-navigational-locks-2165-784 x-1000297
Hydraulic and-structural-design-of-navigational-locks-2165-784 x-1000297PRABIR DATTA
 
IRJET- A Study on Corrugated Bulkheads for Bulk Carriers
IRJET- A Study on Corrugated Bulkheads for Bulk CarriersIRJET- A Study on Corrugated Bulkheads for Bulk Carriers
IRJET- A Study on Corrugated Bulkheads for Bulk CarriersIRJET Journal
 

Similar to Analysis and Design of Marine Berthing Structure (20)

Software Development for the Analysis and Design of Ship Berthing Structures
Software Development for the Analysis and Design of Ship Berthing StructuresSoftware Development for the Analysis and Design of Ship Berthing Structures
Software Development for the Analysis and Design of Ship Berthing Structures
 
IRJET- Analysis of Loads and Design of Passenger Boat Berthing Structure ...
IRJET-  	  Analysis of Loads and Design of Passenger Boat Berthing Structure ...IRJET-  	  Analysis of Loads and Design of Passenger Boat Berthing Structure ...
IRJET- Analysis of Loads and Design of Passenger Boat Berthing Structure ...
 
IRJET- Analysis and Design of Berthing Structure
IRJET- Analysis and Design of Berthing StructureIRJET- Analysis and Design of Berthing Structure
IRJET- Analysis and Design of Berthing Structure
 
Ship Construction by Jayan Pillai
Ship Construction by Jayan PillaiShip Construction by Jayan Pillai
Ship Construction by Jayan Pillai
 
IRJET- Preliminary Design of Floating Dry Dock
IRJET- Preliminary Design of Floating Dry DockIRJET- Preliminary Design of Floating Dry Dock
IRJET- Preliminary Design of Floating Dry Dock
 
A wave piercing catamaran ferry
A wave piercing catamaran ferryA wave piercing catamaran ferry
A wave piercing catamaran ferry
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623
 
Challenges and prospects of Bay Container Terminal, Chittagong.
Challenges and prospects of Bay Container Terminal, Chittagong.Challenges and prospects of Bay Container Terminal, Chittagong.
Challenges and prospects of Bay Container Terminal, Chittagong.
 
harborengineering-200428164114 (1).pdf
harborengineering-200428164114 (1).pdfharborengineering-200428164114 (1).pdf
harborengineering-200428164114 (1).pdf
 
HARBOUR ENGINEERING
HARBOUR ENGINEERING HARBOUR ENGINEERING
HARBOUR ENGINEERING
 
REVIEW PAPER ON “HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
REVIEW PAPER ON “HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”REVIEW PAPER ON “HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
REVIEW PAPER ON “HYDRAULIC AND HYDROLOGICAL IMPACT ON BRIDGE”
 
Using Half Pipes as Permeable Breakwater
Using Half Pipes as Permeable BreakwaterUsing Half Pipes as Permeable Breakwater
Using Half Pipes as Permeable Breakwater
 
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
IRJET - Research on Design of Semi-Polygonal Segment of Submerged Floating Tu...
 
NON-LINEAR STATIC ANALYSIS OF A BERTHING STRUCTURE SUBJECTED TO VARIOUS CRANE...
NON-LINEAR STATIC ANALYSIS OF A BERTHING STRUCTURE SUBJECTED TO VARIOUS CRANE...NON-LINEAR STATIC ANALYSIS OF A BERTHING STRUCTURE SUBJECTED TO VARIOUS CRANE...
NON-LINEAR STATIC ANALYSIS OF A BERTHING STRUCTURE SUBJECTED TO VARIOUS CRANE...
 
IRJET- Planning and Design of Container Terminal
IRJET-  	  Planning and Design of Container TerminalIRJET-  	  Planning and Design of Container Terminal
IRJET- Planning and Design of Container Terminal
 
IRJET-Analysis of Offshore Jacket Structure
IRJET-Analysis of Offshore Jacket StructureIRJET-Analysis of Offshore Jacket Structure
IRJET-Analysis of Offshore Jacket Structure
 
Hydraulic and-structural-design-of-navigational-locks-2165-784 x-1000297
Hydraulic and-structural-design-of-navigational-locks-2165-784 x-1000297Hydraulic and-structural-design-of-navigational-locks-2165-784 x-1000297
Hydraulic and-structural-design-of-navigational-locks-2165-784 x-1000297
 
automation final
automation finalautomation final
automation final
 
Final ppt of ts
Final ppt of tsFinal ppt of ts
Final ppt of ts
 
IRJET- A Study on Corrugated Bulkheads for Bulk Carriers
IRJET- A Study on Corrugated Bulkheads for Bulk CarriersIRJET- A Study on Corrugated Bulkheads for Bulk Carriers
IRJET- A Study on Corrugated Bulkheads for Bulk Carriers
 

Recently uploaded

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 

Analysis and Design of Marine Berthing Structure

  • 1. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 46 | P a g e Analysis and Design of Marine Berthing Structure T.Vivek1 , R.Durga prasad2 1 P.G. Student, Department of Civil Engineering, Swamy Vivekananda Engineering college, Kalavarai, bobbili, vizianagaram, Andhra Pradesh, India. 2 Assistant Professor, Department of Civil Engineering, Swamy Vivekananda Engineering college, Kalavarai, bobbili, vizianagaram, Andhra Pradesh, India. ABSTRACT In the present dissertation a berthing structure was analyzed and designed using different load conditions and the best possible way to construct a new berthing structure was described. All the suitable and useful data was adopted from the proposed site location at Visakhapatnam Port and studied carefully before designing the structure. The proposed berthing structure was modeled with suitable geometry using STAADPRO, after which all considerable loads on the structure were induced and analyzed carefully. Different sectional dimensions were trialed during the analysis and the most acceptable structure was designed with providing all structural members with suitable reinforcement and satisfying all marine safety conditions. I. INTRODUCTION The berthing structures are constructed for the berthing and mooring of vessels to enable loading and unloading of cargo and for embarking and disembarking of passengers, conveyances etc. The orchestrating and design of berthing structures depend on sundry factors. In the present study of the project, we described a felicitous way to design an incipient berthing structure with example of one of the proposed berthing structure in Visakhapatnam port. So afore analyzing and designing, the influence factors which effected on the structure were taken into consideration such as soil characteristics of the proposed location, environmental conditions and range of traffic. All the rudimental Data was adopted from Visakhapatnam port which were supposed to be utilized in the project such as geotechnical data, environmental data, and traffic forecasting data. The entire Berth length of 100m was divided into 3 units of each 33.33 in length with an expansion joint of 40mm between successive units and proposed in the inner harbour, designated for handling liquid cargo like Sulphuric acid, Phosphoric acid, phosphoric acid, edible oils etc. The details of the structural element are discussed under the conceptual design. The design dredge level is taken as -16.10m. A berthing structure is a capital injuctively authorizing project, thereby; optimum utilization of both space and capital becomes essential. This denotes that felicitous orchestrating of the sundry units undergo from congestion or inflexibility due to short comings in orchestrating or due to erroneous estimate of the traffic and or land requisite. Berthing structures vary generally from port to port. The number of berths will depend upon the number of ships to utilize the port and the time it will take to ejection and take on cargo or passengers. Berthing structures should be located in the most bulwarked part of the harbor or along the the wind and waves as possible. II. DESIGN PARAMETERS OF BERTHING STRUCTURES 2.1.1 PLACE OF CONSTRUCTION The determination of location influenced by easy accessibility for ships, sufficient draft availability during the year, favorable metrological and wave hydro dynamic conditions. Amount of the forces on marine structure depends on last two factors. 2.1.2 TYPES After determination of the location for structure, have to select the kind of structure for construction and the factors controlling the selection of the kind of structure are depending on the conditions of water flowing and Geotechnical properties of soil. Classifications of berthing structure are basically Piers and Wharfs 1) Wharf – A berthing structure which is parallel to shore line. It is generally adjacent to the shore, and may not be very near to shore RESEARCH ARTICLE OPEN ACCESS
  • 2. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 47 | P a g e 2) Pier - A berthing structure which is project into water that means perpendicular to shore. This structure need not be exactly perpendicular to shore; it may be with some angle to shore. These structures also are like T or L shape. 2.1.3 WAY OF SELECTION TO CONSTRUCT BERTHING STRUCTURES Type of berthing structure and utilized material for construction depend on various factors Local customs and practice: for suppose, Europe used the massive quays, whereas, America used the open and light structures.  Material availability  Construction cost.  Method of construction.  Dimension and mass of ships handled in the port. 2.1.4 REQUIRED NUMBER OF BERTHS The determination of number of berths depends on handling of traffic in port .the planning of a new terminal was influenced by initial investment. The approximate relations used for the determination of the required number of berths are: N1= W/ R* H * D Where, N1= essential amount of berths for a certain cargo. W = yearly amount of this cargo imported and exported(T/year). R = handling rate of this cargo on the berth. (T/ hour) H = number of working hours per day. (Hour/ day) D = amount of working days per year. (Day/ year) N1 is calculated for each kind of cargo, and the overall number of berths in the port N for all types of cargo is: N = N1 + N2 + N3 +…….. 2.1.5 LONGITUDINAL DIMENSION OF BERTH The function of the terminal and size of vessel determines the berth length and ships calling to port also influence the length Berth length required for main line vessels is 275+25=300m Berth length required for feeder vessels is 150 +50 = 200m 2.1.6 REQUIRED AREA OF BERTH Berthing territory ought to be focused around the length and broadness of the biggest size of boat utilizing for the berths. Berthing range is the zone before the berthing structure needed for berthing vessels furthermore suits the administration vessels. Length needed for berthing a vessel and its surging developments because of wave and momentums are for the most part defined as 10% of boats length, subject to at least 15m. d1 ought not be short of what (L1+l2)/20 and d2 >= (L2+l3)/20 where there are solid obstructions, the safe separation of d0 = 25 – 30 m is permitted. The width of the berthing zone ought to be 1.15 B + b where B is the shaft width of the outline vessel and b is the width of the attending craft. 2.1.7 DRAFT MAINTENANCE ALONG THE BERTH The third era holder vessels have a draft of 12.5 m. Subsequently a depth of 13.5 m must be kept up close by the quay amid all conditions permitting sufficient depth for different remittances. Depth at the compartment ought to be 10% in abundance of most extreme stacked draft of configuration vessel to consider silting and vertical movement.
  • 3. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 48 | P a g e Fig: 2.1.7 draft representation along the berth 2.1.8 WIDTH OF BERTH APRON Cover width of a quay is reliant on the sort of equipment utilized for stacking and exhausting operations. The apron width is picked focused around the facilities gave. The width of the berth will in a general sense rely on upon space prerequisites of substantial obligation boat to shore cranes which must have versatility all through the length of berth. The necessity, for the width of apron varies with the separation from berthing line to the first rail track of the gantry crane and with the back compass of the crane. Measurements of the holder cranes may shift appropriately to the outline and limit of the crane. Obliged width of the cover for commonplace compartment crane is 2 to 4 m for the separation from water front to the first rail, 20 to 35 m for the track width of the crane and 8 to 16 m for back achieve, making a sum of 30 to 55 m towards back. 2.1.9 ELEVATION OF DECK Deck elevation is fine-tuned at or above the highest high spring dihydrogen monoxide level plus half the wave height near the berth plus a free board of 1m. The maximum distance of quay edge inclusive of fine-tuned fenders from the outer track of the crane is about 2.65m. 2.1.10 TURNING CIRCLE Measurements of turning loop are subject to the predominating power of wind, current and the force of tugs accessible for aid. The accompanying criteria may be followed in either case for figuring the radius of the circle: i) Without tug support - 1.7 l ii) With tug support - 0.85 L The third era boats will have a draft of 12.2 m. Consequently a navigational channel which can suit these boats is important with a base depth of 13.5 m. 2.1.11 AREA REQUIRED FOR STACKING PURPOSE The zone needed for capacity of holder inside the terminal relies on upon the accompanying elements 1) Throughput anticipated that will pass through the terminal for every annum. 2) Dwell time of containers inside the terminal. This is the mundane time a container would utilize in the yard after import and afore re-trade in a transit terminal. 3) The kind of container handling equipment utilized for stacking. 4) Average stacking height: Containers are not stacked to the most extreme tallness in all the spaces inside the stacking region. This is obliged to empower the taking care of supplies to get the lower holders in the stack for release. Moreover, containers need to be isolated by end, weight class, and direction of peregrinate in some cases by sorts and frequently shipping line or accommodation. Subsequently there is dependably a proportion between the mundane stacking stature and most extreme stacking tallness 5) Peaking factor: This is the degree of the crest activity to the average traffic, generally taken in the middle of 1.3 to 1.4. 6) Ratio of working slots: All the slots gave on the ground can't be accessible for stacking because of different reasons. The degree of working spaces to general apertures is generally taken as 0.8.
  • 4. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 49 | P a g e III. INDUCED LOADS ON BERTHING STRUCTURE The whole EQ (Eastern Quay)-10 berth length of 100.07 m is separated into 3 units of every 33.33 long with an expansion joint of 40mm between progressive units The proposed EQ-10 berth is implied for taking care of fluid freight like Sulphuric corrosive, Phosphoric corrosive, phosphoric corrosive, eatable oils and so on the subtle elements of the structural component are talked about under the applied configuration .in spite of the fact that the concession understanding accommodates dredging must be conveyed up to -16.10m .henceforth the outline dredging level is taken as -16.10m IV. ANALYSIS OF INDUCED LOADS 4.1.1 DEAD LOAD Fig: 4.1.1 Dead load representation on structure All dead loads of and on structures identifying with docks and harbor ought to be evaluated and included in the design configuration. Dead loads comprise of the weight of all parts of the structure and also the weight of all permanent connections. The DL of a port related marine structure constitutes a relative little rate of the total burden acting up on the structure. Wearing coat (Apron) = 0.20 X 25 = 5 kN/m2 (density of the concrete is taken 25 kN/m3 ) Slab weight = 0.30 X 25 = 7.55 kN/m2 Beams Transverse beams = 1.10 X 1.80 X25 = 50kN/m Longitudinal beam = 1.10 X 0.60 X 25 =16.5 kN/m Pile =1.70X21.65X25=920.12 kN/m 4.1.2 LIVE LOAD Fig: 4.1.2 Live load representation on structure Additional charges because of put away and stacked
  • 5. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 50 | P a g e material, for example, general load, mass freight, holders and burdens from vehicular movement of assorted types, including trucks, trailers, track, and cranes, containers handling equipment and development plant constitute vertical1ive loads. Vertical LL comprise of the weight of all versatile equipment’s on the structure Serial Functioning Truck Uniform number berth loading vertical LL(T/m2 ) 1 Passenger berth B 1.0 2 Bulk unloading A 1.0 to 1.5 and unloading berths 3 Container berths A or AA 3 to 5 or 70R 4 Cargo berth A or AA 2.5 to 3.5 or 70R 5 Heavy cargo A or AA 5 or 6 berth or 70R 6 Small boat berth B 0.5 7 Fishing berth B 1.0 The function of berth related to Truck loading A or AA or 70R (Heavy cargo berth) so we are adopted 50 kN/m2 . 4.1.3 BERTHING LOAD Fig: 4.1.3 berthing load representation on structure Berthing Energy - When an approaching vessel strikes a berth a level power follows up on the compartment. The magnitude of this power Depends on the kinetic energy that can be ingested by the Fendering framework. The response energy for which the berth is to be composed can be acquired and Deflection-response outlines of the fendering framework picked. These outlines are realistic from bumper producers the Kinetic energy E, bestowed to a fendering framework, by a vessel moving with speed V m/s is given by: W V 2 E  2 D g (Cm )(Ce )(Cs ) WD = displacement tonnage (DT) of the vessel V = velocity of vessel in m/s, normal to the berth g = acceleration due to gravity in m/s2 Cm = mass coefficient Ce = eccentricity coefficient Cs = soft coefficient E  200000X 0.102 X 0.51X1.60X 0.95 =80kN.m 2 X 9.81 27 kNm/33m for 1unit of berth (33 meters)
  • 6. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 51 | P a g e 4.1.4 MOORING LOAD Fig: 4.1.4 mooring load representation on structure The mooring burdens are the lateral loads brought about by the mooring lines when they pull the boat into or along the dock or hold it against the powers of wind or current. The most extreme mooring burdens are because of the wind compels on uncovered range on the open side of the boat in light condition F  Cw Aw P F = force due to wind in Kg Cw = shape factor = 1.3 to 1.6 Aw = wind age area in m2 P = wind age pressure in m2 to be taken in accordance with IS: 875-1964 The wind age area (Aw) can be predictable as follows: Aw= 1.175Lp (DM-DL) Where Lp= length between perpendicular in meter DM= mould depth in m, and DL=average light draft in m. Actual this is the definite procedure but port engineers suggested that bollard pull =900kN is adopted (Design load) Generally mooring load act in various angle of forces so we have to resolve on the mooring point while designing the berth. And spacing taken as bollard to bollard is 15m c/c ,if suppose we fixed 7 bollards then the load on each bollard is 900/7 =F =128kN Resolving of forces on mooring points are Horizontal component = Fcos = 90kN Vertical component = FSin = 90kN Generally angle is taken as 450 here if necessary need to calculate at different angles as per maximum ship moment observations. 4.1.5 CURRENT LOAD Fig: 4.1.5 Current load representations on structure
  • 7. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 52 | P a g e Loads because of Current - Pressure because of flow will be connected to the zone of the vessel beneath the water line when completely stacked. It is roughly equivalent to w v2 /2 g per square meter of range, where v is the velocity in m/s and ID is the unit weight of water in tones/ml. The boat is for the most part berthed parallel to the current with powerful currents and where berth arrangement really goes astray from the bearing of the current, the' likely force should be considered by any familiar method and taken into account. F= w v2 /2 g =1.025 tonnes/m3 Unit weight of water ( w) Velocity of current ( v) =0.26m/s Acceleration due to gravity = 9.81m/s2 F = 0.035kN/m2 For 1 unit of berth F = 0.035X33X21.65 =25kN 25kN for 12 piles for each pile F = 2.02 kN Load distribution is converted as uniform on pile F= 2.02/21.65 =0.096KN/m 4.1.6 WIND LOAD Wind contributes primarily to the lateral loading on a pier. It blows from many directions and can vary without detect. The wind impinging upon a surface increases the pressure on that surface and results in a force loading. However, given the construction characteristics of an open pier, the loading on the structure itself is minor compared with the wind effects of the ship moored along side. The exposed, directional, surface region of the ship is susceptible to wind loading which is then transferred to the pier. When designing a pier, historical wind data, along with the design ship size, is analyzed to size the structural members according to the predominant wind direction. Design wind speed (Vz) = Vb k1k2 k3 Vb = basic wind speed k 1= probability factor (Risk coefficient) K2= terrain, height and structure size factor K3= topography factor Vz = (50)(0.92)(1.05)(1) =48.3m/sec Design wind pressure = 0.6(vz)2 p=1400N/m2 =1.4kN/ m2 Now the design wind pressure is resolved as nodal loads on structure =1.4X 33X1 =46.2/12 =3.85 kN 4.1.7 SESMIC LOAD Fig: 4.1.7 Lateral load representation on structure Design seismic base shear VB= AhW Ah = horizontal seismic coefficient W = seismic weight of structure
  • 8. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 53 | P a g e 4.1.8 EARTH PRESSURE Fig: 4.1.8 Earth Pressure representation on structure
  • 9. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 54 | P a g e 4.1.9 HYDROSTATIC PRESSURE On account of waterfront structures with inlay, the weight created by distinction in water level at the fill side and waterside must be considered in design configuration. The magnitude of hydrostatic pressure is affected by the tidal extent, free water variances, the ground water deluge, the porousness of the establishment of foundation soil and the structure and also the proficiency of accessible refill drainage Fig: 4.1.9 hydrostatic load representation on structure P= h  =unit weight of water=10kN/m3 H= water head on structure; m P=10 X 18 =180kN/m2 = 180X1.57=270kN/m on every pile  BASIC LOAD COMBINATIONS  1.5DL+1.5LL+1(EARTHPRESSURE)+1(HY DROSTATICPRESSURE)+1.5(BERTHING LOAD)+1.5(MOORING LOAD)  1.2DL+1.2LL+1E.P+1.2H.P  1.2DL+1.2LL+1EP+1HP+1.5(WIND LOAD)  1.2DL+1.2LL+EP+1HP+1.5(SEISMIC  LOAD) 5.DESIGN 5.1DESIGN OF BEAM TRANSVERSE BEAM  Pile cap beam  Grade of concrete:M40  Grade of steel:Fe415  Size of the bar:32mm  Spacing between bars:238mm  Cover:50mm LONGITUDUNAL BEAM  Grade of concrete:M30  Grade of steel:Fe415  Size of the bar:20mm  Spacing between bars:125mm  Cover:50mm  Shear reinforcement:12mm@150mm/cc  Size:600mm x 1100mm
  • 10. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 55 | P a g e 5.2DESIGN OF SLAB  Thickness of slab:300mm  Effective depth:217mm  Effective cover:75mm  Grade of concrete:M40  Grade of steel:Fe415 5.3DESIGN OF PILE  Grade of concrete:M40  Grade of steel:Fe415  Dia of the pile:1700mm  Size of bar:40mm  Spacing between bars:76mm  Cover:50mm  Tie reinforcement:16mm@300mm/cc V. CONCLUSION Different factors are to be considered while analyzing and designing the berthing structure. Lateral loads on the berthing structures are more eminent than those on land– based structures. Congruous environmental data, traffic forecasting and soil data ought to be received from the proposed site location, typical load distribution is induced on the shore line structures, so need to utilize STAAD Pro software for the analysis and design. The structure was analyzed and designed satisfying various loading conditions and dimension analysis for economical aspect was additionally taken care of without exceeding the structural safety. Afore going for designing or orchestrating a berthing structure, all the present and future optimistic conditions regarding traffic data, hinterland expansion and industrialization of that particular hinterland are to be studied, which additionally play a major role in shaping the project inception at the first place. REFERENCES [1]. Krishna Raju.N, “Advanced Reinforced Concrete Design”, 2nd Edition, Cbs Publication & Distributors Pvt .Ltd, Newdelhi, 2012. [2]. Muthukkumaran.K, Sundaravadivelu and Gandhi.S.R, “Effect of Dredging and Axial Load on a Berthing Structure”, Geotechnical conference, 2006. [3]. Premalatha P.V, Muthukkumaran. K & Jayabalan [4]. P,“Behaviour of piles supported berthing structure under lateral loads”, Geotechnical conference, 2011. [5]. Ramamrutham.S, “Design of Reinforced Concrete Structures”, 16th Edition, Dhanpat Rai Publications Company, Newdelhi, 2009. [6]. Sanil Kuma.R, K. Ashok Kumar and N. S. N. Raju, “Wave characteristics off Visakhapatnam coast during a cyclone “, research article 1524 current science, 2004, vol. 86, no. 11 [7]. Shanthal. B, Subba rao,katta Henkatramana And [8]. Harish, “ Analysis of berthing structures for wave induced Forces”, International journal of earth sciences and engineering,2011,vol. 4,No 1, pp. 112-121. [9]. SP16,“Code Of Practice Criteria For Design Aids For Reinforced Concrete To IS: 456-2000”, Fourth Revision, Bureau of Indian Standards, New Delhi. [10]. Thomos dawson. H, “Offshore Structural Engineering”, 2nd Edition, Prentice –hall, New Jersey, 2010 [11]. Thandava Moorty, T.S, “Analysis of Structures”, 6th Edition, Oxford University Press, Newdelhi, 2005. [12]. www.vizagport.com [13]. Kavitha.P.E, Dr.Narayanan.K.P, Dr. Sudheer.C.B., “Software Development for the Analysis and Design of Ship Berthing Structures”, ACEEE Int. J. On Transportation and Urban Development, 2011, Vol.1, No. 1. [14]. Yasser E. Mostafa, “Design Considerations for Pile Groups Supporting Marine Structures with Respect to Scour”, (http://www.scirp.org/journal/eng), 2012, No 4, pp.833-842. [15]. IS 456: 2000, “Code of Practice for Plain And Reinforced Concrete Code Of Practice”, Ninth Revision, [16]. Bureau of Indian Standards, New Delhi.
  • 11. T.Vivek. Int. Journal of Engineering Research and Application www.ijera.com ISSN : 2248-9622, Vol. 6, Issue 12, ( Part -3) December 2016, pp.46-56 www.ijera.com 56 | P a g e [17]. IS: 875 (Part 1) – 1987, “Code of Practice for Design Loads (Other than Earthquake) For Buildings and Structures Part 1 Dead Loads — Unit Weights Of Building Materials and Stored Material”, Second Revision, Bureau of Indian Standards, New Delhi. [18]. Structures Part 5 Special Loads and Combinations”, Second Revision, Bureau of Indian Standards, New Delhi. [19]. IS: 875 (Part 2) – 1987, “Code of Practice for Design Loads (Other Than Earthquake) For Buildings and Structures Part 2 Imposed Loads", Second Revision, Bureau of Indian Standards, New Delhi. [20]. IS: 875 (Part 3) – 1987,” Code of Practice for Design Loads (Other Than Earthquake) For Buildings and [21]. Structures Part 3 Wind Loads”, Second Revision, Bureau of Indian Standards, New Delhi. [22]. IS: 875 (Part 5) – 1997, “Code of Practice for Design Loads (Other Than Earthquake) for Buildings and Structures Part 5 Special Loads and Combinations”, [23]. Second Revision, Bureau of Indian Standards, New Delhi. [24]. IS: 1893-1984, “Code of Practice Criteria for [25]. Earthquake Resistant Design of Structures”, Fourth Revision, Bureau of Indian Standards, New Delhi. [26]. IS 4651 (Part IV): 1989, “Code of Practice for General Design Considerations”, Second Revision, Bureau of Indian Standards, New Delhi. [27]. IS: 4851 (Part III) – 1974, “Code Of Practice For Planning and Design Of Ports and Harbours “, First Revision, Bureau of Indian Standards, New Delhi. [28]. IS 14238:1995, “Code of Practice for Inland vessels – Selection of rubber Fenders for berthing structures code of practice”, second Revision, Bureau of Indian Standards, New Delhi.