SlideShare a Scribd company logo
1 of 1
Site Instructions Issued by RE, Detailsfor section – II (km 113+000 to km 244+120):

Sr.   Date                 Details
No.
1     05.10.2012           Lab instrument used for field density checking must be
                           calibrated every month like sand pouring cylinder. Moisture
                           meter and sand used for density checking it also need to check
                           the density of sand if we found the gradation of sand in
                           changed due to use of it or change the source of sand.
2     31.10.2012           I, More crash barriers (Concrete or steel sheet) with reflective
                           tape is required at km 141+000 to sukhadi river existing bridge
                           on both the side that will guide to road user in night also for
                           safe driving.
                           II, DBM work is in progress at km 143+850. Observed the joint
                           cutting of DBM layer was done by the drilled machine and it
                           was uneven that joint cutting should be done by sharp cutter
                           instrument and it should be smooth and straight line.
                           III, Excavation soil stacked on existing road shoulder at km
                           227+000 RHS. That is break the road user visibility and it may
                           cause for accident. So, you are required to remove the same
                           as soon as possible.
3     22.01.2013           New Carriageway Construction at km 158+400 to km 160+500
                           LHS inspected before open for traffic. In this stretch, 7-
                           Locations of construction joint not good riding quality over the
                           DBM top level, when drive the vehicle over DBM surface,
                           surface giving jerks, concessionaire need to rectify the same
                           location mansion below; 1) km 158+750 LHS, 2) km 158+870
                           LHS, 3) 159+120 LHS, 4) km 159+320 LHS, 5) 159+530 LHS, 6)
                           km 159+580 LHS, 7) km 160+320 LHS.
4     02.02.2013           Kerbing work is in progress but cut on the kerb was not as per
                           standard engineering practice (Cut was not vertical and also
                           not as per general practice depth). That is need to rectify as
                           early and improve in further same type of work.
                           1, km 119+700 to km 120+000 LHS. 2, km 120+240 to km
                           121+800 LHS. 3, km 122+100 to km 124+000 LHS. 4, km
                           124+150 to km 124+550 LHS.

More Related Content

Viewers also liked (16)

Untitled Presentation
Untitled PresentationUntitled Presentation
Untitled Presentation
 
Los servicios
Los serviciosLos servicios
Los servicios
 
Tramites informáticos
Tramites informáticosTramites informáticos
Tramites informáticos
 
Formato de autoevaluacion sesion 5
Formato de autoevaluacion sesion 5Formato de autoevaluacion sesion 5
Formato de autoevaluacion sesion 5
 
FC05 Datasheet
FC05 DatasheetFC05 Datasheet
FC05 Datasheet
 
Poster NBC-15-487_Lu
Poster NBC-15-487_LuPoster NBC-15-487_Lu
Poster NBC-15-487_Lu
 
Manutenção de caixa de água
Manutenção de caixa de águaManutenção de caixa de água
Manutenção de caixa de água
 
letter2
letter2letter2
letter2
 
มติ กพ เรียกเงิน
มติ กพ  เรียกเงินมติ กพ  เรียกเงิน
มติ กพ เรียกเงิน
 
Final Resume 2015
Final Resume 2015Final Resume 2015
Final Resume 2015
 
CV MARIA GIL RUIZ
CV MARIA GIL RUIZCV MARIA GIL RUIZ
CV MARIA GIL RUIZ
 
Hosted-Voice
Hosted-VoiceHosted-Voice
Hosted-Voice
 
MAGISTER - U PACIFICO (2)
MAGISTER - U PACIFICO (2)MAGISTER - U PACIFICO (2)
MAGISTER - U PACIFICO (2)
 
ISI Technology - Company one pager
ISI Technology - Company   one pager ISI Technology - Company   one pager
ISI Technology - Company one pager
 
SENIOR LECTURER_UCT
SENIOR LECTURER_UCTSENIOR LECTURER_UCT
SENIOR LECTURER_UCT
 
Actividad de aprendizaje 1
Actividad de aprendizaje 1Actividad de aprendizaje 1
Actividad de aprendizaje 1
 

Similar to Site instructions details for section – ii (km 113+000 to km 244+120)

Village networking ppt
Village networking pptVillage networking ppt
Village networking pptPatel Tapan
 
Roads design as per IRC 37
Roads design as per IRC 37Roads design as per IRC 37
Roads design as per IRC 37Amardeep Singh
 
Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...Johan Granlund
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - ISachin Kulkarni
 
Six week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNSix week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNTarun2222
 
P07011_Gupta_et_al
P07011_Gupta_et_alP07011_Gupta_et_al
P07011_Gupta_et_alPankaj Gupta
 
Project presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash GargProject presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash Gargharshit315
 
All in a Weekend's Work
All in a Weekend's WorkAll in a Weekend's Work
All in a Weekend's WorkDon Talend
 
Design and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDesign and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDevesh Chaurasia
 
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)Utsav Tripathy
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)alamrintu
 
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...IRJET Journal
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
 

Similar to Site instructions details for section – ii (km 113+000 to km 244+120) (20)

Training PPT
Training PPTTraining PPT
Training PPT
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Roads design as per IRC 37
Roads design as per IRC 37Roads design as per IRC 37
Roads design as per IRC 37
 
Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
Roadex Iv Presentation Final Sem Inverness 2012 05 22 Vectura On Ride Vibrati...
 
Road construction
Road constructionRoad construction
Road construction
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - I
 
Road of construction
Road of construction Road of construction
Road of construction
 
Six week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUNSix week industrial training presentation BY GUPTA TARUN
Six week industrial training presentation BY GUPTA TARUN
 
P07011_Gupta_et_al
P07011_Gupta_et_alP07011_Gupta_et_al
P07011_Gupta_et_al
 
Project presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash GargProject presentation on flexible pavement by Harshit Prakash Garg
Project presentation on flexible pavement by Harshit Prakash Garg
 
All in a Weekend's Work
All in a Weekend's WorkAll in a Weekend's Work
All in a Weekend's Work
 
Design and analysis of flexible pavemeT
Design and analysis of flexible pavemeTDesign and analysis of flexible pavemeT
Design and analysis of flexible pavemeT
 
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
BEST PPT ON TRAINNING ON CONTRUCTION AT INDIAN RAILWAY (DFCC)
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)
 
Presentation sayed
Presentation sayedPresentation sayed
Presentation sayed
 
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...
Strengthening and Maintenance of a Flexible Road Pavement Using Benkelman Bea...
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Dragline ppt
Dragline pptDragline ppt
Dragline ppt
 

Site instructions details for section – ii (km 113+000 to km 244+120)

  • 1. Site Instructions Issued by RE, Detailsfor section – II (km 113+000 to km 244+120): Sr. Date Details No. 1 05.10.2012 Lab instrument used for field density checking must be calibrated every month like sand pouring cylinder. Moisture meter and sand used for density checking it also need to check the density of sand if we found the gradation of sand in changed due to use of it or change the source of sand. 2 31.10.2012 I, More crash barriers (Concrete or steel sheet) with reflective tape is required at km 141+000 to sukhadi river existing bridge on both the side that will guide to road user in night also for safe driving. II, DBM work is in progress at km 143+850. Observed the joint cutting of DBM layer was done by the drilled machine and it was uneven that joint cutting should be done by sharp cutter instrument and it should be smooth and straight line. III, Excavation soil stacked on existing road shoulder at km 227+000 RHS. That is break the road user visibility and it may cause for accident. So, you are required to remove the same as soon as possible. 3 22.01.2013 New Carriageway Construction at km 158+400 to km 160+500 LHS inspected before open for traffic. In this stretch, 7- Locations of construction joint not good riding quality over the DBM top level, when drive the vehicle over DBM surface, surface giving jerks, concessionaire need to rectify the same location mansion below; 1) km 158+750 LHS, 2) km 158+870 LHS, 3) 159+120 LHS, 4) km 159+320 LHS, 5) 159+530 LHS, 6) km 159+580 LHS, 7) km 160+320 LHS. 4 02.02.2013 Kerbing work is in progress but cut on the kerb was not as per standard engineering practice (Cut was not vertical and also not as per general practice depth). That is need to rectify as early and improve in further same type of work. 1, km 119+700 to km 120+000 LHS. 2, km 120+240 to km 121+800 LHS. 3, km 122+100 to km 124+000 LHS. 4, km 124+150 to km 124+550 LHS.