1.concretos mortero 179
- 1. 210 CONSTRUDATA
ACCESORIOS BAÑOS
ANÁLISIS UM CANT. BOGOTÁ CALI B/QUILLA MEDELLÍNANÁLISIS UM CANT. BOGOTÁ CALI B/QUILLA MEDELLÍN
DETALLADOS
GENERALES
ANÁLISIS UM CANT. BOGOTÁ CALI B/QUILLA MEDELLÍN ANÁLISIS UM CANT. BOGOTÁ CALI B/QUILLA MEDELLÍN
CONCRETOS
CONCRETO CORRIENTE GRAVA COMUN 1500 P.S.I. m³
AGUA lt 160.00 2,560 2,560 2,560 2,560
ARENA LAVADA DE PEÑA m³ 0.50 30,856 30,856 30,856 30,856
CEMENTO GRIS kg 210.00 119,700 115,500 111,720 115,500
GRAVA 1” m³ 1.00 46,400 34,500 59,508 41,800
HERRAMIENTA MENOR % 10.00 23,147 21,537 23,660 22,267
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
254,616 236,906 260,257 244,936
CONCRETO CORRIENTE GRAVA COMUN 2000 P.S.I. m³
AGUA lt 170.00 2,720 2,720 2,720 2,720
ARENA LAVADA DE PEÑA m³ 0.63 38,879 38,879 38,879 38,879
CEMENTO GRIS kg 260.00 148,200 143,000 138,320 143,000
GRAVA 1” m³ 0.84 38,976 28,980 49,987 35,112
HERRAMIENTA MENOR % 10.00 26,073 24,553 26,186 25,166
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
286,800 270,085 288,044 276,830
CONCRETO CORRIENTE GRAVA COMUN 2500 P.S.I. m³
AGUA lt 170.00 2,720 2,720 2,720 2,720
ARENA LAVADA DE PEÑA m³ 0.48 29,622 29,622 29,622 29,622
CEMENTO GRIS kg 300.00 171,000 165,000 159,600 165,000
GRAVA 1” m³ 0.95 44,080 32,775 56,533 39,710
HERRAMIENTA MENOR % 10.00 27,937 26,207 28,043 26,900
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
307,312 288,277 308,470 295,905
CONCRETO CORRIENTE GRAVA COMUN 3000 P.S.I. m³
AGUA lt 180.00 2,880 2,880 2,880 2,880
ARENA LAVADA DE PEÑA m³ 0.56 34,559 34,559 34,559 34,559
CEMENTO GRIS kg 350.00 199,500 192,500 186,200 192,500
GRAVA 1” m³ 0.84 38,976 28,980 49,987 35,112
HERRAMIENTA MENOR % 10.00 30,787 29,087 30,558 29,700
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
338,654 319,959 336,136 326,704
CONCRETO CORRIENTE GRAVA COMUN 3500 P.S.I. m³
AGUA lt 250.00 4,000 4,000 4,000 4,000
ARENA LAVADA DE PEÑA m³ 0.67 41,347 41,347 41,347 41,347
CEMENTO GRIS kg 420.00 239,400 231,000 223,440 231,000
GRAVA 1” m³ 0.67 31,088 23,115 39,870 28,006
HERRAMIENTA MENOR % 10.00 34,779 33,142 34,061 33,631
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
382,567 364,557 374,671 369,937
CONCRETO CORRIENTE GRAVA FINA 2000 P.S.I. m³
AGUA lt 170.00 2,720 2,720 2,720 2,720
ARENA FINA m³ 0.63 29,232 27,770 27,770 27,770
CEMENTO GRIS kg 260.00 148,200 143,000 138,320 143,000
GRAVA NO 7 - 1/2” m³ 0.84 49,987 33,743 49,987 49,987
HERRAMIENTA MENOR % 10.00 26,209 23,919 25,075 25,543
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
288,301 263,105 275,825 280,973
CONCRETO CORRIENTE GRAVA FINA 3000 P.S.I. m³
AGUA lt 180.00 2,880 2,880 2,880 2,880
ARENA FINA m³ 0.56 25,984 24,685 24,685 24,685
CEMENTO GRIS kg 350.00 199,500 192,500 186,200 192,500
GRAVA NO 7 - 1/2” m³ 0.84 49,987 33,743 49,987 49,987
HERRAMIENTA MENOR % 10.00 31,030 28,576 29,570 30,200
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
341,334 314,337 325,275 332,205
MORTEROS
MORTERO 1:2 m³
AGUA lt 250.00 4,000 4,000 4,000 4,000
ARENA FINA m³ 0.97 45,008 42,758 42,758 42,758
CEMENTO GRIS kg 610.00 347,700 335,500 324,520 335,500
HERRAMIENTA MENOR % 5.00 21,433 20,711 20,162 20,711
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
450,094 434,921 423,392 434,921
MORTERO 1:3 m³
AGUA lt 240.00 3,840 3,840 3,840 3,840
ARENA FINA m³ 1.09 50,576 48,047 48,047 48,047
CEMENTO GRIS kg 454.00 258,780 249,700 241,528 249,700
HERRAMIENTA MENOR % 5.00 17,257 16,677 16,268 16,677
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
362,406 350,217 341,637 350,217
MORTERO 1:3 IMPERMEABILIZADO m³
AGUA lt 240.00 3,840 3,840 3,840 3,840
ARENA FINA m³ 1.09 50,576 48,047 48,047 48,047
CEMENTO GRIS kg 454.00 258,780 249,700 241,528 249,700
HERRAMIENTA MENOR % 5.00 26,189 25,609 25,200 25,609
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
SIKA -1 (20 KG) kg 1.10 178,640 178,640 178,640 178,640
549,978 537,789 529,209 537,789
MORTERO 1:4 m³
AGUA lt 220.00 3,520 3,520 3,520 3,520
ARENA FINA m³ 1.16 53,824 51,133 51,133 51,133
CEMENTO GRIS kg 364.00 207,480 200,200 193,648 200,200
HERRAMIENTA MENOR % 5.00 14,839 14,340 14,013 14,340
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
311,616 301,146 294,266 301,146
MORTERO 1:4 IMPERMEABILIZADO m³
AGUA lt 220.00 3,520 3,520 3,520 3,520
ARENA FINA m³ 1.16 53,824 51,133 51,133 51,133
CEMENTO GRIS kg 364.00 207,480 200,200 193,648 200,200
HERRAMIENTA MENOR % 5.00 22,959 22,460 22,133 22,460
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
SIKA -1 (20 KG) kg 1.00 162,400 162,400 162,400 162,400
482,136 471,666 464,786 471,666
MORTERO 1:5 m³
AGUA lt 182.00 2,912 2,912 2,912 2,912
ARENA FINA m³ 1.20 55,680 52,896 52,896 52,896
CEMENTO GRIS kg 302.00 172,140 166,100 160,664 166,100
HERRAMIENTA MENOR % 5.00 13,134 12,693 12,421 12,693
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
275,819 266,554 260,846 266,554
MORTERO 1:6 m³
AGUA lt 158.00 2,528 2,528 2,528 2,528
ARENA FINA m³ 1.20 55,680 52,896 52,896 52,896
CEMENTO GRIS kg 261.00 148,770 143,550 138,852 143,550
HERRAMIENTA MENOR % 5.00 11,947 11,546 11,311 11,546
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MEZCLADORA DE TROMPO 3BT CON TOLVA d 0.13 12,818 12,818 12,818 12,818
250,878 242,473 237,540 242,473
PAÑETES
FILOS Y DILATACIONES m
HERRAMIENTA MENOR % 5.00 309 304 300 304
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.16 3,062 3,062 3,062 3,062
MORTERO 1:4 m³ 0.01 3,116 3,011 2,943 3,011
6,487 6,377 6,304 6,377
MALLA CON VENA BAJO ENTRAMADO m²
HERRAMIENTA MENOR % 5.00 565 565 565 565
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.40 7,654 7,654 7,654 7,654
MALLA CON VENA 0.60M X 2.00M un 0.83 3,569 3,569 3,569 3,569
PUNTILLA CON CABEZA 2” lb 0.04 84 84 84 84
11,872 11,872 11,872 11,872
PAÑETE BAJO ESTERILLA DE GUADUA 1:5 m²
HERRAMIENTA MENOR % 5.00 999 994 991 994
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.90 17,222 17,222 17,222 17,222
MORTERO 1:5 m³ 0.01 2,758 2,666 2,608 2,666
20,979 20,881 20,821 20,881
CONCRETOS y
MORTEROS
- 2. 211
ANÁLISIS UM CANT. BOGOTÁ CALI B/QUILLA MEDELLÍNANÁLISIS UM CANT. BOGOTÁ CALI B/QUILLA MEDELLÍN
DETALLADOS
GENERALES
EDICIÓN 179 JUNIO - AGOSTO 2016
CONCRETOS Y MORTEROS - PAÑETES
PAÑETE BAJO MALLA 1:4 m²
HERRAMIENTA MENOR % 5.00 1,173 1,162 1,155 1,162
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.90 17,222 17,222 17,222 17,222
MORTERO 1:4 m³ 0.02 6,232 6,023 5,885 6,023
24,627 24,407 24,262 24,407
PAÑETE BAJO MALLA 1:5 m²
HERRAMIENTA MENOR % 5.00 1,137 1,128 1,122 1,128
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.90 17,222 17,222 17,222 17,222
MORTERO 1:5 m³ 0.02 5,516 5,331 5,217 5,331
23,875 23,680 23,560 23,680
PAÑETE BAJO MALLA 1:6 m²
HERRAMIENTA MENOR % 5.00 1,112 1,104 1,099 1,104
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.90 17,222 17,222 17,222 17,222
MORTERO 1:6 m³ 0.02 5,018 4,849 4,751 4,849
23,351 23,175 23,071 23,175
PAÑETE IMPERMEABILIZADO MUROS 1:3 m²
HERRAMIENTA MENOR % 5.00 1,514 1,496 1,483 1,496
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.72 13,777 13,777 13,777 13,777
MORTERO 1:3 IMPERMEABILIZADO m³ 0.03 16,499 16,134 15,876 16,134
31,790 31,406 31,136 31,406
PAÑETE IMPERMEABILIZADO MUROS 1:4 m²
HERRAMIENTA MENOR % 5.00 1,412 1,396 1,386 1,396
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.72 13,777 13,777 13,777 13,777
MORTERO 1:4 IMPERMEABILIZADO m³ 0.03 14,464 14,150 13,944 14,150
29,653 29,324 29,107 29,324
PAÑETE LISO BAJO PLACA 1:4 m²
HERRAMIENTA MENOR % 5.00 1,017 1,012 1,008 1,012
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.90 17,222 17,222 17,222 17,222
MORTERO 1:4 m³ 0.01 3,116 3,011 2,943 3,011
21,355 21,245 21,172 21,245
PAÑETE LISO BAJO PLACA 1:5 m²
HERRAMIENTA MENOR % 5.00 999 994 991 994
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.90 17,222 17,222 17,222 17,222
MORTERO 1:5 m³ 0.01 2,758 2,666 2,608 2,666
20,979 20,881 20,821 20,881
PAÑETE LISO BAJO PLACA 1:6 m²
HERRAMIENTA MENOR % 5.00 987 982 980 982
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.90 17,222 17,222 17,222 17,222
MORTERO 1:6 m³ 0.01 2,509 2,425 2,375 2,425
20,717 20,629 20,577 20,629
PAÑETE LISO MUROS 1:3 m²
HERRAMIENTA MENOR % 5.00 1,051 1,039 1,030 1,039
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.72 13,777 13,777 13,777 13,777
MORTERO 1:3 m³ 0.02 7,248 7,004 6,833 7,004
22,077 21,821 21,640 21,821
PAÑETE LISO MUROS 1:4 m²
HERRAMIENTA MENOR % 5.00 1,000 990 983 990
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.72 13,777 13,777 13,777 13,777
MORTERO 1:4 m³ 0.02 6,232 6,023 5,885 6,023
21,010 20,790 20,646 20,790
PAÑETE LISO MUROS 1:5 m²
HERRAMIENTA MENOR % 5.00 965 955 950 955
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.72 13,777 13,777 13,777 13,777
MORTERO 1:5 m³ 0.02 5,516 5,331 5,217 5,331
20,258 20,064 19,944 20,064
PAÑETE LISO MUROS 1:6 m²
HERRAMIENTA MENOR % 5.00 940 931 926 931
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 0.72 13,777 13,777 13,777 13,777
MORTERO 1:6 m³ 0.02 5,018 4,849 4,751 4,849
19,734 19,558 19,454 19,558
PAÑETE RUSTICO BAJO PLACA 1:5 m²
HERRAMIENTA MENOR % 5.00 1,562 1,548 1,539 1,548
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.20 22,962 22,962 22,962 22,962
MORTERO 1:5 m³ 0.03 8,275 7,997 7,825 7,997
32,798 32,507 32,327 32,507
PAÑETE RUSTICO MUROS 1:5 m²
HERRAMIENTA MENOR % 5.00 1,370 1,357 1,348 1,357
HORA CUADRILLA AA ALBAÑILERÍA-PREST. hc 1.00 19,135 19,135 19,135 19,135
MORTERO 1:5 m³ 0.03 8,275 7,997 7,825 7,997
28,780 28,488 28,308 28,488