1. Production Schedule
Week
Beginning
What needs to be done Location By Who Equipment Needed
01/10/18
Pre-production
Music industry task 1-3
Target audience avatars
Genre research
Me1 or Me2 CF Computer, internet
08/10/18 Pre-production
Annotated digipak and poster
research
Me1 or Me2 CF Computer, internet, pen, paper,
pencil, ruler.
15/10/18 Fonts research
Plans for image taking
Sketch/mock up
Production schedule
Me1 or Me2 CF Computer, internet, Paper, pen,
pencil, ruler.
22/10/18 HALF TERM
29/10/18
Pre-production
Permission letter
Legal and ethical research
Recce
Risk assessment
Me1 or Me2 CF Computer, internet
05/11/18 Production photoshoot, I will
take all my photos in an one
hour period during the sunset.
The mount in
poulner is my
one destination
CF Actors, camera, tripod, tobacco, sign,
12/11/18 Post production of digipak
Make front and back cover in
first 3 lessons
Make the inside covers in the
next 3 lessons
Me1 or Me2 CF Computer, photoshop
19/11/18 Post production of album
poster
Spend the whole of the six
lessons making my poster and
if I finish go back to my
digipack and see if there is
anything I can improve on
Me1 or Me2 CF Computer, photoshop
Deadline Fri 23rd
Nov CF