SlideShare a Scribd company logo
1 of 40
Pipeline Abandonments and ConversionsPipeline Abandonments and Conversions
2014 FEPA Summer Symposium2014 FEPA Summer Symposium
July 24, 2014July 24, 2014
Berne L. Mosley, Energy Projects Consulting, LLCBerne L. Mosley, Energy Projects Consulting, LLC
Complete Partial
•Remove facilities
•Isolate and abandon in place
•Capacity lease
•Sell
•Downrate (pipeline MAOP or
turbine hp for example)
•Downsize (smaller diameter)
•Limit service schedule
2
Personal Rule of Thumb:
Action taken to temporarily inactivate a facility which can be
reversed in a short period of time to restore service upon
demand and with little/no ground disturbed is not
abandonment.
Examples: closing and locking valves or removing EFM
equipment from meters
3
FERC
Regulatory approval
followed by
physical
disconnection
BSEE
90 days of no flow
if no SOP approved
DOT
Purge
hydrocarbons
STATE
PERMITS
(i.e., Louisiana )
Inactive
12 months
Unintended
Abandonment?
4
Automatic
Blanket
Prior Notice
Blanket
Section 7
Excluded
Facilities
LNG take-away
Mainline
Storage field ∆ cap.
Leased mainline
Default mechanism for
all facilities
Replication
Cost (2013)
<$11 M $11M - $31.4M > $31.4M
Environment
“No effect” -and-
FERC Plan /
Procedures
“No effect” -and-
FERC Plan / Procedures
Public good outweighs
impacts.
Mitigation required
Misc.
Inactive 12 mos. or
consent req’d
No FT contract
Written consent if
service w/in 12 mos.
No protests
Considers protests and
alternatives
Pipeline Issues Creative Responses
•“Death spiral” from rising O&M
costs and falling revenue
volumes
•Declining revenue throughput so
no incentive for FT. Majority of
volumes flow on IT at discount
•New supply sources strand pipe
segments and compression.
•Policies and regulations from
other agencies
•Spin-down / spin-off of assets to
form stand-alone regional
pipeline
•Conversion to transport liquids or
other energy forms
•Create gathering system for gas
supply from new basins (i.e.,
shale)
•Traditional sale to third party
with lower cost structure
5
6
7
Producers “free to the pool” or with deeply discounted rates
may have to negotiate contracts with new owner. If producers
not currently paying for transport of the affected gas, FERC
regulations do not give them much weight in the analysis.
When abandoning regional assets to new company, shippers
may now have multiple rates for single haul. If these are
IT/FT shippers, proposed new company needs to settle with
affected customers to avoid protests.
Offshore producers may argue that their production will be
stranded upon abandonment. Possible claim onshore as well,
but it is not as expensive to establish new outlet. FERC takes
this issue very seriously if the offshore platform is not dually
connected and no other pipelines are in the vicinity.
8
End user concerns in cases of physical abandonment or
conversion to other energy transport include operational reliability
of the existing pipeline they contracted with.
On the other hand, FT customers may be pushing for
abandonment and will support application in order to reduce rates
by removing these assets and associated O&M from the pipeline
rate base.
Landowners have significant rights regarding physical
abandonment across their property. If they want complete
removal, but pipeline and environmental assets favor abandoning
in place, FERC will balance the competing valid arguments.
Landowners in general are more sophisticated, partly due to
FERC outreach process, in negotiating for the method of
abandonment and mitigation they expect.
9
10
Environmental groups that were focused on E&P activities
now view the pipeline application process as a vehicle to
thwart further shale development, including protests against
gathering system designation.
State and federal agencies have become more involved in the
future obligations regarding disposal of pipeline assets.
The abandonment of pipelines in traditional producing basins
impact state and regional public policy, including issues such
as jobs, tax revenues, future site cleanup, and national energy
policy.
With aging infrastructure, and more stringent integrity and
testing requirements, there is increased pressure to
abandon interstate pipelines.
Pipeline companies will increase efforts to find creative
alternatives to traditional pipeline removal or abandonment
in place.
FERC regulations, and those of other agencies having over-
sight, will add to the complexity of the decision of when,
and how, to abandon pipeline assets.
11
INFRASTRUCTURE
HIGHWAY
Traditional Production
Flow
Shale Production Flow
N
S
12
 FERC Regulation of Natural Gas and Oil
 Converting Pipelines from Transporters of
Natural Gas to Transporters of Oil and
Petroleum Products…and Why Now?
 FERC’s Role in Such Conversions – Two Case
Studies (and info on a third)
 Challenges to Accomplishing Such Conversions
13
FERC Regulation of
Natural Gas and Oil
14
The Commission's responsibilities include:
 Regulation of pipeline, storage, and liquefied natural gas
facility construction
 Regulation of natural gas transportation in interstate
commerce
 Issuance of certificates of public convenience and necessity
to prospective companies providing energy services or
constructing and operating interstate pipelines and storage
facilities
 Regulation of facility abandonment
 Oversight of the construction and operation of pipeline
facilities at U.S. points of entry for the import or export of
natural gas
15
With respect to Natural Gas projects, FERC safeguards the environment
by: 
 Disclosing, analyzing and minimizing impacts where it is feasible and
reasonable to do so
 Encourage applicants to communicate with relevant federal and state
natural resources agencies, Indian tribes, and state water quality
agencies, prior to submitting an application
 Ensuring that all applicants perform the necessary studies to make an
informed decision on the project
 Issuing environmental assessments (EA) or draft and final
environmental impact statement (EIS) for comment on most projects
 Including requirements with any certificate issued to reduce
environmental impacts
 Visiting proposed project areas to determine the range of environmental
issues requiring analysis and holding scoping meetings as appropriate
16
The Commission's responsibilities include:
 Regulation of rates and practices of oil pipeline
companies engaged in interstate transportation;
 Establishment of equal service conditions to provide
shippers with equal access to pipeline transportation;
and
 Establishment of reasonable rates for transporting
petroleum and petroleum products by pipeline.*
FERC has no jurisdiction over construction or
maintenance of production wells, oil
pipelines, refineries, or storage facilities!!!
* See Declaratory Order (OR13-29) for jurisdictional discussion on Ethane
transportation. 17
Converting Pipelines from
Transporters of Natural Gas to
Transporters of Oil and Petroleum
Products…and Why Now?
18
Higher crude oil-to-natural gas ratio encourages drilling for oil in preference to
natural gas and makes natural gas liquids developments (e.g., ethane) relatively
more attractive than the development of dry natural gas resources.
19Source: http://www.eia.gov/todayinenergy/detail.cfm?id=5830
Natural gas is a combustible mixture of hydrocarbon gases. While
natural gas is formed primarily of methane, it can also include
ethane, propane, butane and pentane, and other constituents
Source: http://www.naturalgas.org/overview/background.asp 20
21
 Nearly half of the world’s ethylene will be
produced from ethane and liquefied petroleum
gas (LPG) by 2023, mostly at the expense of
naphtha.
 The feedstock shift is most dramatic in North
America, where prolific shale gas
production yields cheap ethane in the US and
is driving a petrochemical resurgence.
Source: http://www.hydrocarbonprocessing.com/Article/3257517/Ethane-LPG-
to-trump-naphtha-as-preferred-ethylene-feedstocks.html 22
The ethane can be removed from natural gas,
but for petrochemical uses it must first be
“cracked”, typically using steam…
 There are few crackers in and around the
Marcellus and Utica Shale Plays…
 There are many crackers in the Gulf Coast…
 There is unused / spare capacity on
traditional South-to-North long haul
pipelines…
Hence the gas-to-liquids pipeline conversions!
23
FERC’s Role in Such Conversions
24
25
Tallgrass was authorized to abandon approximately 432.4 miles of
mainline pipeline facilities for the purpose of re-converting the facilities
into crude oil pipeline facilities, and to construct and operate certain
replacement facilities in order to continue natural gas transportation
service to its existing firm customers.
To satisfy NEPA, FERC issued an EA (not an EIS) that addressed
geology, soils, water resources, wetlands, vegetation, fisheries, wildlife,
threatened and endangered species, land use, recreation, visual
resources, cultural resources, air quality, noise, safety, cumulative
impacts, and alternatives. In addition, section B.9 of the EA discussed
the cumulative impacts of the conversion to oil -- the construction of:
 260 miles of 24-inch-diameter pipeline (Cushing Lateral) from KS to OK
that would connect to Tallgrass (Pony Express) Pipeline from Lincoln
County, Kansas to Cushing, Oklahoma;
 16 span replacements and eight electric oil pump stations along the
existing Pony Express Pipeline segment;
 2 electric oil pump stations along the Cushing Lateral.
26
27
The abandonment by transfer of the 432.4 miles of PXP would have no
ground disturbance and is not addressed further. The abandonment
and/or modification of aboveground facilities would cause minimal
disturbance entirely within existing work areas or existing right-of-way.
Regarding the cumulative impacts of the Cushing Lateral…“[s]ince the
FERC does not regulate the sitting of oil pipelines, we do not have
detailed information concerning the environmental impacts of the
planned Cushing Lateral, other than what TIGT has provided, as
discussed above. The environmental review would be subject to the
regulations of the USACE and other applicable Kansas and Oklahoma
state permitting agencies. We conclude that the Project would represent
a negligible contribution to the overall cumulative impacts of the
combined oil transportation project discussed above."
Relevant Language from the EA:
28
Trunkline was authorized to abandon by sale to an affiliate
approximately 770 miles of mainline transmission pipeline and
appurtenant facilities for conversion to oil pipeline
transmission service, and to abandon in place certain
mainline compression facilities that it would no longer need
after the pipeline facilities are abandoned, while still
maintaining natural gas service to its firm customers.
To satisfy NEPA, FERC issued an EA (again, NOT an EIS)
that addressed geology, soils, water resources, wetlands,
vegetation, fisheries, wildlife, threatened and endangered
species, land use, recreation, visual resources, cultural
resources, air quality, noise, safety, cumulative impacts, and
alternatives.
29
Relevant Language from the EA:
“After the abandonment, Trunkline would no longer be responsible for
the facilities and the Commission will have no remaining jurisdiction.
Thus, the EA did not include a detailed analysis of the impacts that could
occur after the abandonment. However, the EA did provide available
information about the anticipated conversion and about potential
cumulative impacts associated with the construction of facilities to
support the proposed future use.”
and
“In the event that the abandoned pipeline is converted for use in oil
transportation, the relevant authorizing and permitting state and federal
agencies, including the U.S. Department of Transportation, are
responsible for addressing environmental and safety matters.”
30
31
From the application:
• Texas Gas sought authority to abandon approximately 623 miles of
natural gas pipeline segments from Eunice, Louisiana to Hardinsburg,
Kentucky and associated facilities.
• All of Texas Gas’s installed facilities south of Eunice and north of
Hardinsburg would remain in interstate natural gas transportation service.
FERC issued an Environmental Assessment
[emphasis added] on February 14, 2014, but
project was withdrawn on June 3, 2014…
• Following abandonment, Texas Gas would
continue to provide natural gas transportation service
on its remaining pipeline facilities.
• After receipt of abandonment authority, the
pipeline segments will be taken out of natural gas
service and repurposed for use in natural gas liquids
(“NGL”) service.
Challenges to Accomplishing Such
Conversions
32
As Noted Above:
FERC has no jurisdiction over construction or maintenance of
production wells, oil pipelines, refineries, or storage facilities
This means:
Products pipelines are “sited” on a State-by-State basis (if a
pipeline crosses 10 states, then 10 different siting agencies may
be involved)
This doesn’t mean:
Products Pipelines are exempt from other Federal agency
requirements, or requirements of State agencies administering
Federal requirements (i. e., CZMA, CWA, CAA, etc.)
33
 Natural Gas is transported by being compressed by large
reciprocating or turbine motors at compressor stations
 Compressor stations are sited along the length of a
pipeline based on flow engineering analysis of
transportation distances, transportation volumes and
operating & delivery pressures
 Liquids are “pumped” and pumping stations are sited
along the liquids pipeline based on hydraulic analysis
The locations of historic compressor station
sites may not align with the required pumping
station sites, leading to new, and possibly
significant, construction for gas-to-liquid
conversion projects!
34
 The trend to convert unused natural gas
pipelines to oil- and products-pipelines will
continue, owing to higher oil-to-gas prices, and
the market for NGLs
 FERC will continue to assert economic
jurisdiction on such pipelines
 FERC’s NEPA role in conversion projects will be
limited
 Project proponents for conversion projects will
still be subject to certain Federal and State
oversight
35
Contact Information:
Berne L. Mosley, President
Energy Projects Consulting, LLC
bernemosley@yahoo.com
FERC – Federal Energy Regulatory Commission;
the agency responsible for interstate and some
offshore transportation of natural gas, oil and
“oil products”
NGA – Natural Gas Act; law that gives natural
gas companies authority to construct & operate
(Sec 7(c)) and abandon (Sec 7(b)) interstate
natural gas facilities
DOT – Department of Transportation; regulatory
agency with safety authority over interstate gas
and oil facilities
BSEE – Bureau of Safety and Environmental
Enforcement; regulatory agency responsible for
safety, environment and conservation of
offshore oil and natural gas resources
Blanket Certificate Program – a subprogram
of a Section 7(c) application, comprising
“automatic” and “prior notice”
Blanket Certificate Program – a subprogram
of a Section 7(c) application, comprising
“automatic” and “prior notice”
FT – Firm Transportation; transportation
guaranteed at full contract level of service
IT – Interruptible Transportation; transportation
provided on an “as available basis” with no
level-of-service guarantees
MAOP – Maximum Allowable Operating Pressure;
the pressure, in PSI, at which a pipeline is
allowed to operate, based on the yield strength
of the steel and DOT requirements
EFM – Electronic Flow Meters; meters that
measure the amount of gas flowing through a
pipe

More Related Content

What's hot

Texas Aquifer Exemptions - Clean Water Action august 2016
Texas Aquifer Exemptions - Clean Water Action august 2016Texas Aquifer Exemptions - Clean Water Action august 2016
Texas Aquifer Exemptions - Clean Water Action august 2016
John Noël
 
UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016
Charlie Bell
 
MASEFinalReport (2)
MASEFinalReport (2)MASEFinalReport (2)
MASEFinalReport (2)
Sunil Satish
 
drainagedesignonm25motorwaywideningprojectj16j23
drainagedesignonm25motorwaywideningprojectj16j23drainagedesignonm25motorwaywideningprojectj16j23
drainagedesignonm25motorwaywideningprojectj16j23
Anthony Jones
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014
Iain McGregor
 
1.DAM BREAK MODELLING OF PHOUPHONG DAM_PRADYUMNA MACHHKHAND
1.DAM BREAK MODELLING OF PHOUPHONG DAM_PRADYUMNA MACHHKHAND1.DAM BREAK MODELLING OF PHOUPHONG DAM_PRADYUMNA MACHHKHAND
1.DAM BREAK MODELLING OF PHOUPHONG DAM_PRADYUMNA MACHHKHAND
Pradyumna Machhkhand
 
Risk Assessment Project
Risk Assessment ProjectRisk Assessment Project
Risk Assessment Project
ashkan ezazi
 
2.FLOOD RISK ANALYSIS _PRADYUMNA MACHHKHAND - Copy
2.FLOOD RISK ANALYSIS _PRADYUMNA MACHHKHAND - Copy2.FLOOD RISK ANALYSIS _PRADYUMNA MACHHKHAND - Copy
2.FLOOD RISK ANALYSIS _PRADYUMNA MACHHKHAND - Copy
Pradyumna Machhkhand
 

What's hot (20)

Environmental Concerns Associated with Marcellus Midstream Development &amp; ...
Environmental Concerns Associated with Marcellus Midstream Development &amp; ...Environmental Concerns Associated with Marcellus Midstream Development &amp; ...
Environmental Concerns Associated with Marcellus Midstream Development &amp; ...
 
FERC Ruling on Ohio-Louisiana Access Project
FERC Ruling on Ohio-Louisiana Access ProjectFERC Ruling on Ohio-Louisiana Access Project
FERC Ruling on Ohio-Louisiana Access Project
 
Texas Aquifer Exemptions - Clean Water Action august 2016
Texas Aquifer Exemptions - Clean Water Action august 2016Texas Aquifer Exemptions - Clean Water Action august 2016
Texas Aquifer Exemptions - Clean Water Action august 2016
 
FERC_LNG
FERC_LNGFERC_LNG
FERC_LNG
 
UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016UU_Davyhulme_Modernisation_2016
UU_Davyhulme_Modernisation_2016
 
Ohio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to Gulf
Ohio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to GulfOhio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to Gulf
Ohio-Louisiana Access Project - Reverse Natural Gas Pipeline from NE to Gulf
 
MASEFinalReport (2)
MASEFinalReport (2)MASEFinalReport (2)
MASEFinalReport (2)
 
LNG as fuel innovation 220618
LNG as fuel innovation 220618LNG as fuel innovation 220618
LNG as fuel innovation 220618
 
drainagedesignonm25motorwaywideningprojectj16j23
drainagedesignonm25motorwaywideningprojectj16j23drainagedesignonm25motorwaywideningprojectj16j23
drainagedesignonm25motorwaywideningprojectj16j23
 
CCUS_Mobile
CCUS_MobileCCUS_Mobile
CCUS_Mobile
 
Bureau veritas
Bureau veritasBureau veritas
Bureau veritas
 
Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014Severn_Trent_Wanlip_Sludge_2014
Severn_Trent_Wanlip_Sludge_2014
 
1.DAM BREAK MODELLING OF PHOUPHONG DAM_PRADYUMNA MACHHKHAND
1.DAM BREAK MODELLING OF PHOUPHONG DAM_PRADYUMNA MACHHKHAND1.DAM BREAK MODELLING OF PHOUPHONG DAM_PRADYUMNA MACHHKHAND
1.DAM BREAK MODELLING OF PHOUPHONG DAM_PRADYUMNA MACHHKHAND
 
Overview
 Overview Overview
Overview
 
Risk Assessment Project
Risk Assessment ProjectRisk Assessment Project
Risk Assessment Project
 
Sneak preview - SMM presentation
Sneak preview - SMM presentationSneak preview - SMM presentation
Sneak preview - SMM presentation
 
Fsru conference fsru dam 21 nov 12
Fsru conference fsru dam 21 nov 12Fsru conference fsru dam 21 nov 12
Fsru conference fsru dam 21 nov 12
 
Delaware Riverkeeper Letter to DRBC Requesting Intervention to Stop PennEast ...
Delaware Riverkeeper Letter to DRBC Requesting Intervention to Stop PennEast ...Delaware Riverkeeper Letter to DRBC Requesting Intervention to Stop PennEast ...
Delaware Riverkeeper Letter to DRBC Requesting Intervention to Stop PennEast ...
 
2.FLOOD RISK ANALYSIS _PRADYUMNA MACHHKHAND - Copy
2.FLOOD RISK ANALYSIS _PRADYUMNA MACHHKHAND - Copy2.FLOOD RISK ANALYSIS _PRADYUMNA MACHHKHAND - Copy
2.FLOOD RISK ANALYSIS _PRADYUMNA MACHHKHAND - Copy
 
Sea Water Intrusion - 90 day work plan
Sea Water Intrusion - 90 day work planSea Water Intrusion - 90 day work plan
Sea Water Intrusion - 90 day work plan
 

Viewers also liked

2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas
FloridaPipeTalk
 
2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn
FloridaPipeTalk
 
2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley
FloridaPipeTalk
 
2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins
FloridaPipeTalk
 
2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris
FloridaPipeTalk
 
2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick
FloridaPipeTalk
 
Anthropocene and culture dec 2013 web
Anthropocene and culture dec 2013 webAnthropocene and culture dec 2013 web
Anthropocene and culture dec 2013 web
Owen Gaffney
 
2012 FEPA Presentation: Charlie Hall
2012 FEPA Presentation: Charlie Hall2012 FEPA Presentation: Charlie Hall
2012 FEPA Presentation: Charlie Hall
FloridaPipeTalk
 
Vertical: The City From Satellites to Bunkers Stephen Graham
Vertical: The City From Satellites to Bunkers Stephen Graham Vertical: The City From Satellites to Bunkers Stephen Graham
Vertical: The City From Satellites to Bunkers Stephen Graham
Stephen Graham
 

Viewers also liked (20)

2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas2012 FEPA Presentation: Jeff Didas
2012 FEPA Presentation: Jeff Didas
 
2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn2012 FEPA Presentation: Don Thorn
2012 FEPA Presentation: Don Thorn
 
2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley2012 FEPA Presentation: Berne Mosley
2012 FEPA Presentation: Berne Mosley
 
2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins2012 FEPA Presentation: Danny Kilcollins
2012 FEPA Presentation: Danny Kilcollins
 
2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris2012 FEPA Presentation: Donald Morris
2012 FEPA Presentation: Donald Morris
 
2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick2012 FEPA Presentation: Erik Kirkpatrick
2012 FEPA Presentation: Erik Kirkpatrick
 
Sunshine 811
Sunshine 811Sunshine 811
Sunshine 811
 
Pipeline Construction Safety
Pipeline Construction SafetyPipeline Construction Safety
Pipeline Construction Safety
 
Anthropocene and culture dec 2013 web
Anthropocene and culture dec 2013 webAnthropocene and culture dec 2013 web
Anthropocene and culture dec 2013 web
 
Sustainability advantage: The Natural Step as competitive edge (Stanley Nyoni...
Sustainability advantage: The Natural Step as competitive edge (Stanley Nyoni...Sustainability advantage: The Natural Step as competitive edge (Stanley Nyoni...
Sustainability advantage: The Natural Step as competitive edge (Stanley Nyoni...
 
Confronting The Intermediate Color Line
Confronting The Intermediate Color LineConfronting The Intermediate Color Line
Confronting The Intermediate Color Line
 
2012 FEPA Presentation: Charlie Hall
2012 FEPA Presentation: Charlie Hall2012 FEPA Presentation: Charlie Hall
2012 FEPA Presentation: Charlie Hall
 
Great acceleration
Great accelerationGreat acceleration
Great acceleration
 
Vertical: The City From Satellites to Bunkers Stephen Graham
Vertical: The City From Satellites to Bunkers Stephen Graham Vertical: The City From Satellites to Bunkers Stephen Graham
Vertical: The City From Satellites to Bunkers Stephen Graham
 
Building a Personal Learning Solution
Building a Personal Learning SolutionBuilding a Personal Learning Solution
Building a Personal Learning Solution
 
designing innovation, insitutions for social transformation D1s3 gupta anil i...
designing innovation, insitutions for social transformation D1s3 gupta anil i...designing innovation, insitutions for social transformation D1s3 gupta anil i...
designing innovation, insitutions for social transformation D1s3 gupta anil i...
 
Lightning Talk #9: How UX and Data Storytelling Can Shape Policy by Mika Aldaba
Lightning Talk #9: How UX and Data Storytelling Can Shape Policy by Mika AldabaLightning Talk #9: How UX and Data Storytelling Can Shape Policy by Mika Aldaba
Lightning Talk #9: How UX and Data Storytelling Can Shape Policy by Mika Aldaba
 
Succession “Losers”: What Happens to Executives Passed Over for the CEO Job?
Succession “Losers”: What Happens to Executives Passed Over for the CEO Job? Succession “Losers”: What Happens to Executives Passed Over for the CEO Job?
Succession “Losers”: What Happens to Executives Passed Over for the CEO Job?
 
Test Driven Design - GDG DevFest Istanbul 2016
Test Driven Design - GDG DevFest Istanbul 2016Test Driven Design - GDG DevFest Istanbul 2016
Test Driven Design - GDG DevFest Istanbul 2016
 
The Great State of Design with CSS Grid Layout and Friends
The Great State of Design with CSS Grid Layout and FriendsThe Great State of Design with CSS Grid Layout and Friends
The Great State of Design with CSS Grid Layout and Friends
 

Similar to New Developments in the Natural Gas Industry

Fracking - AWMA Presentation
Fracking  - AWMA PresentationFracking  - AWMA Presentation
Fracking - AWMA Presentation
kwtght
 
LFG Strategic Plan v9 - Final
LFG Strategic Plan v9 - FinalLFG Strategic Plan v9 - Final
LFG Strategic Plan v9 - Final
Will Dickinson
 
Interstate Grid Electrification Improvement Project
Interstate Grid Electrification Improvement ProjectInterstate Grid Electrification Improvement Project
Interstate Grid Electrification Improvement Project
Margaret Puckette
 
PVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 FinalPVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 Final
Robert Potter
 
WEAO Influents Spring2015, Offsets
WEAO Influents Spring2015, OffsetsWEAO Influents Spring2015, Offsets
WEAO Influents Spring2015, Offsets
Edgar Tovilla
 
ILFI presentation on energy sector by ILFI National Council on Energy
ILFI presentation on energy sector by ILFI National Council on EnergyILFI presentation on energy sector by ILFI National Council on Energy
ILFI presentation on energy sector by ILFI National Council on Energy
ILFIindia
 

Similar to New Developments in the Natural Gas Industry (20)

Coal Combustion Residuals: Regulatory, Litigation, and Enforcement Update
 Coal Combustion Residuals: Regulatory, Litigation, and Enforcement Update Coal Combustion Residuals: Regulatory, Litigation, and Enforcement Update
Coal Combustion Residuals: Regulatory, Litigation, and Enforcement Update
 
Winter 2015 pioga meeting all4
Winter 2015 pioga meeting   all4Winter 2015 pioga meeting   all4
Winter 2015 pioga meeting all4
 
Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...
Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...
Decision by NH PUC to Deny Request by Eversource Energy to Strike a Long-Term...
 
20405_merged.pdf
20405_merged.pdf20405_merged.pdf
20405_merged.pdf
 
Swim Drink Fish's Preliminary Submission on Pickering Nuclear Generating Station
Swim Drink Fish's Preliminary Submission on Pickering Nuclear Generating StationSwim Drink Fish's Preliminary Submission on Pickering Nuclear Generating Station
Swim Drink Fish's Preliminary Submission on Pickering Nuclear Generating Station
 
Fracking - AWMA Presentation
Fracking  - AWMA PresentationFracking  - AWMA Presentation
Fracking - AWMA Presentation
 
Cle thur mou_arapahoe
Cle thur mou_arapahoeCle thur mou_arapahoe
Cle thur mou_arapahoe
 
LFG Strategic Plan v9 - Final
LFG Strategic Plan v9 - FinalLFG Strategic Plan v9 - Final
LFG Strategic Plan v9 - Final
 
Pipeline Safety Trust Land-Owners Guide_2016
Pipeline Safety Trust Land-Owners Guide_2016Pipeline Safety Trust Land-Owners Guide_2016
Pipeline Safety Trust Land-Owners Guide_2016
 
Interstate Grid Electrification Improvement Project
Interstate Grid Electrification Improvement ProjectInterstate Grid Electrification Improvement Project
Interstate Grid Electrification Improvement Project
 
International experience for regulation of exploration and production of unco...
International experience for regulation of exploration and production of unco...International experience for regulation of exploration and production of unco...
International experience for regulation of exploration and production of unco...
 
PA DEP White Paper: Utilization of Mine Influenced Water for Natural Gas Extr...
PA DEP White Paper: Utilization of Mine Influenced Water for Natural Gas Extr...PA DEP White Paper: Utilization of Mine Influenced Water for Natural Gas Extr...
PA DEP White Paper: Utilization of Mine Influenced Water for Natural Gas Extr...
 
Pipeline Operator Proposal PowerPoint Presentation Slides
Pipeline Operator Proposal PowerPoint Presentation SlidesPipeline Operator Proposal PowerPoint Presentation Slides
Pipeline Operator Proposal PowerPoint Presentation Slides
 
PVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 FinalPVN SOQ Presentation 2016 Final
PVN SOQ Presentation 2016 Final
 
AGDC Joint Resources Presentation October 16 2017
AGDC Joint Resources Presentation October 16 2017AGDC Joint Resources Presentation October 16 2017
AGDC Joint Resources Presentation October 16 2017
 
Unblocking the Roadblocks to Environmentally Beneficial Re-Mining ml
Unblocking the Roadblocks to Environmentally Beneficial Re-Mining mlUnblocking the Roadblocks to Environmentally Beneficial Re-Mining ml
Unblocking the Roadblocks to Environmentally Beneficial Re-Mining ml
 
WEAO Influents Spring2015, Offsets
WEAO Influents Spring2015, OffsetsWEAO Influents Spring2015, Offsets
WEAO Influents Spring2015, Offsets
 
Guidelines for Drainage Studies and Hydraulic Design (March 1999).pdf
Guidelines for Drainage Studies and Hydraulic Design (March 1999).pdfGuidelines for Drainage Studies and Hydraulic Design (March 1999).pdf
Guidelines for Drainage Studies and Hydraulic Design (March 1999).pdf
 
Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.Oil and Gas Undergrond Storage Keystone Project.
Oil and Gas Undergrond Storage Keystone Project.
 
ILFI presentation on energy sector by ILFI National Council on Energy
ILFI presentation on energy sector by ILFI National Council on EnergyILFI presentation on energy sector by ILFI National Council on Energy
ILFI presentation on energy sector by ILFI National Council on Energy
 

Recently uploaded

Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
Nauman Safdar
 
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
DUBAI (+971)581248768 BUY ABORTION PILLS IN ABU dhabi...Qatar
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
laloo_007
 

Recently uploaded (20)

Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165Lucknow Housewife Escorts  by Sexy Bhabhi Service 8250092165
Lucknow Housewife Escorts by Sexy Bhabhi Service 8250092165
 
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
Lundin Gold - Q1 2024 Conference Call Presentation (Revised)
 
Mckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for ViewingMckinsey foundation level Handbook for Viewing
Mckinsey foundation level Handbook for Viewing
 
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
Escorts in Nungambakkam Phone 8250092165 Enjoy 24/7 Escort Service Enjoy Your...
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
BeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdfBeMetals Investor Presentation_May 3, 2024.pdf
BeMetals Investor Presentation_May 3, 2024.pdf
 
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
Horngren’s Cost Accounting A Managerial Emphasis, Canadian 9th edition soluti...
 
Falcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial WingsFalcon Invoice Discounting: Tailored Financial Wings
Falcon Invoice Discounting: Tailored Financial Wings
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow ChallengesFalcon Invoice Discounting: Aviate Your Cash Flow Challenges
Falcon Invoice Discounting: Aviate Your Cash Flow Challenges
 
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdfTVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
TVB_The Vietnam Believer Newsletter_May 6th, 2024_ENVol. 006.pdf
 
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030Over the Top (OTT) Market Size & Growth Outlook 2024-2030
Over the Top (OTT) Market Size & Growth Outlook 2024-2030
 
New 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck TemplateNew 2024 Cannabis Edibles Investor Pitch Deck Template
New 2024 Cannabis Edibles Investor Pitch Deck Template
 
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
!~+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUD...
 
Putting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptxPutting the SPARK into Virtual Training.pptx
Putting the SPARK into Virtual Training.pptx
 
PHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation FinalPHX May 2024 Corporate Presentation Final
PHX May 2024 Corporate Presentation Final
 
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NSCROSS CULTURAL NEGOTIATION BY PANMISEM NS
CROSS CULTURAL NEGOTIATION BY PANMISEM NS
 
Falcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business GrowthFalcon Invoice Discounting: Empowering Your Business Growth
Falcon Invoice Discounting: Empowering Your Business Growth
 
Structuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdfStructuring and Writing DRL Mckinsey (1).pdf
Structuring and Writing DRL Mckinsey (1).pdf
 

New Developments in the Natural Gas Industry

  • 1. Pipeline Abandonments and ConversionsPipeline Abandonments and Conversions 2014 FEPA Summer Symposium2014 FEPA Summer Symposium July 24, 2014July 24, 2014 Berne L. Mosley, Energy Projects Consulting, LLCBerne L. Mosley, Energy Projects Consulting, LLC
  • 2. Complete Partial •Remove facilities •Isolate and abandon in place •Capacity lease •Sell •Downrate (pipeline MAOP or turbine hp for example) •Downsize (smaller diameter) •Limit service schedule 2 Personal Rule of Thumb: Action taken to temporarily inactivate a facility which can be reversed in a short period of time to restore service upon demand and with little/no ground disturbed is not abandonment. Examples: closing and locking valves or removing EFM equipment from meters
  • 3. 3 FERC Regulatory approval followed by physical disconnection BSEE 90 days of no flow if no SOP approved DOT Purge hydrocarbons STATE PERMITS (i.e., Louisiana ) Inactive 12 months Unintended Abandonment?
  • 4. 4 Automatic Blanket Prior Notice Blanket Section 7 Excluded Facilities LNG take-away Mainline Storage field ∆ cap. Leased mainline Default mechanism for all facilities Replication Cost (2013) <$11 M $11M - $31.4M > $31.4M Environment “No effect” -and- FERC Plan / Procedures “No effect” -and- FERC Plan / Procedures Public good outweighs impacts. Mitigation required Misc. Inactive 12 mos. or consent req’d No FT contract Written consent if service w/in 12 mos. No protests Considers protests and alternatives
  • 5. Pipeline Issues Creative Responses •“Death spiral” from rising O&M costs and falling revenue volumes •Declining revenue throughput so no incentive for FT. Majority of volumes flow on IT at discount •New supply sources strand pipe segments and compression. •Policies and regulations from other agencies •Spin-down / spin-off of assets to form stand-alone regional pipeline •Conversion to transport liquids or other energy forms •Create gathering system for gas supply from new basins (i.e., shale) •Traditional sale to third party with lower cost structure 5
  • 6. 6
  • 7. 7 Producers “free to the pool” or with deeply discounted rates may have to negotiate contracts with new owner. If producers not currently paying for transport of the affected gas, FERC regulations do not give them much weight in the analysis. When abandoning regional assets to new company, shippers may now have multiple rates for single haul. If these are IT/FT shippers, proposed new company needs to settle with affected customers to avoid protests. Offshore producers may argue that their production will be stranded upon abandonment. Possible claim onshore as well, but it is not as expensive to establish new outlet. FERC takes this issue very seriously if the offshore platform is not dually connected and no other pipelines are in the vicinity.
  • 8. 8 End user concerns in cases of physical abandonment or conversion to other energy transport include operational reliability of the existing pipeline they contracted with. On the other hand, FT customers may be pushing for abandonment and will support application in order to reduce rates by removing these assets and associated O&M from the pipeline rate base. Landowners have significant rights regarding physical abandonment across their property. If they want complete removal, but pipeline and environmental assets favor abandoning in place, FERC will balance the competing valid arguments. Landowners in general are more sophisticated, partly due to FERC outreach process, in negotiating for the method of abandonment and mitigation they expect.
  • 9. 9
  • 10. 10 Environmental groups that were focused on E&P activities now view the pipeline application process as a vehicle to thwart further shale development, including protests against gathering system designation. State and federal agencies have become more involved in the future obligations regarding disposal of pipeline assets. The abandonment of pipelines in traditional producing basins impact state and regional public policy, including issues such as jobs, tax revenues, future site cleanup, and national energy policy.
  • 11. With aging infrastructure, and more stringent integrity and testing requirements, there is increased pressure to abandon interstate pipelines. Pipeline companies will increase efforts to find creative alternatives to traditional pipeline removal or abandonment in place. FERC regulations, and those of other agencies having over- sight, will add to the complexity of the decision of when, and how, to abandon pipeline assets. 11
  • 13.  FERC Regulation of Natural Gas and Oil  Converting Pipelines from Transporters of Natural Gas to Transporters of Oil and Petroleum Products…and Why Now?  FERC’s Role in Such Conversions – Two Case Studies (and info on a third)  Challenges to Accomplishing Such Conversions 13
  • 14. FERC Regulation of Natural Gas and Oil 14
  • 15. The Commission's responsibilities include:  Regulation of pipeline, storage, and liquefied natural gas facility construction  Regulation of natural gas transportation in interstate commerce  Issuance of certificates of public convenience and necessity to prospective companies providing energy services or constructing and operating interstate pipelines and storage facilities  Regulation of facility abandonment  Oversight of the construction and operation of pipeline facilities at U.S. points of entry for the import or export of natural gas 15
  • 16. With respect to Natural Gas projects, FERC safeguards the environment by:   Disclosing, analyzing and minimizing impacts where it is feasible and reasonable to do so  Encourage applicants to communicate with relevant federal and state natural resources agencies, Indian tribes, and state water quality agencies, prior to submitting an application  Ensuring that all applicants perform the necessary studies to make an informed decision on the project  Issuing environmental assessments (EA) or draft and final environmental impact statement (EIS) for comment on most projects  Including requirements with any certificate issued to reduce environmental impacts  Visiting proposed project areas to determine the range of environmental issues requiring analysis and holding scoping meetings as appropriate 16
  • 17. The Commission's responsibilities include:  Regulation of rates and practices of oil pipeline companies engaged in interstate transportation;  Establishment of equal service conditions to provide shippers with equal access to pipeline transportation; and  Establishment of reasonable rates for transporting petroleum and petroleum products by pipeline.* FERC has no jurisdiction over construction or maintenance of production wells, oil pipelines, refineries, or storage facilities!!! * See Declaratory Order (OR13-29) for jurisdictional discussion on Ethane transportation. 17
  • 18. Converting Pipelines from Transporters of Natural Gas to Transporters of Oil and Petroleum Products…and Why Now? 18
  • 19. Higher crude oil-to-natural gas ratio encourages drilling for oil in preference to natural gas and makes natural gas liquids developments (e.g., ethane) relatively more attractive than the development of dry natural gas resources. 19Source: http://www.eia.gov/todayinenergy/detail.cfm?id=5830
  • 20. Natural gas is a combustible mixture of hydrocarbon gases. While natural gas is formed primarily of methane, it can also include ethane, propane, butane and pentane, and other constituents Source: http://www.naturalgas.org/overview/background.asp 20
  • 21. 21
  • 22.  Nearly half of the world’s ethylene will be produced from ethane and liquefied petroleum gas (LPG) by 2023, mostly at the expense of naphtha.  The feedstock shift is most dramatic in North America, where prolific shale gas production yields cheap ethane in the US and is driving a petrochemical resurgence. Source: http://www.hydrocarbonprocessing.com/Article/3257517/Ethane-LPG- to-trump-naphtha-as-preferred-ethylene-feedstocks.html 22
  • 23. The ethane can be removed from natural gas, but for petrochemical uses it must first be “cracked”, typically using steam…  There are few crackers in and around the Marcellus and Utica Shale Plays…  There are many crackers in the Gulf Coast…  There is unused / spare capacity on traditional South-to-North long haul pipelines… Hence the gas-to-liquids pipeline conversions! 23
  • 24. FERC’s Role in Such Conversions 24
  • 25. 25
  • 26. Tallgrass was authorized to abandon approximately 432.4 miles of mainline pipeline facilities for the purpose of re-converting the facilities into crude oil pipeline facilities, and to construct and operate certain replacement facilities in order to continue natural gas transportation service to its existing firm customers. To satisfy NEPA, FERC issued an EA (not an EIS) that addressed geology, soils, water resources, wetlands, vegetation, fisheries, wildlife, threatened and endangered species, land use, recreation, visual resources, cultural resources, air quality, noise, safety, cumulative impacts, and alternatives. In addition, section B.9 of the EA discussed the cumulative impacts of the conversion to oil -- the construction of:  260 miles of 24-inch-diameter pipeline (Cushing Lateral) from KS to OK that would connect to Tallgrass (Pony Express) Pipeline from Lincoln County, Kansas to Cushing, Oklahoma;  16 span replacements and eight electric oil pump stations along the existing Pony Express Pipeline segment;  2 electric oil pump stations along the Cushing Lateral. 26
  • 27. 27 The abandonment by transfer of the 432.4 miles of PXP would have no ground disturbance and is not addressed further. The abandonment and/or modification of aboveground facilities would cause minimal disturbance entirely within existing work areas or existing right-of-way. Regarding the cumulative impacts of the Cushing Lateral…“[s]ince the FERC does not regulate the sitting of oil pipelines, we do not have detailed information concerning the environmental impacts of the planned Cushing Lateral, other than what TIGT has provided, as discussed above. The environmental review would be subject to the regulations of the USACE and other applicable Kansas and Oklahoma state permitting agencies. We conclude that the Project would represent a negligible contribution to the overall cumulative impacts of the combined oil transportation project discussed above." Relevant Language from the EA:
  • 28. 28
  • 29. Trunkline was authorized to abandon by sale to an affiliate approximately 770 miles of mainline transmission pipeline and appurtenant facilities for conversion to oil pipeline transmission service, and to abandon in place certain mainline compression facilities that it would no longer need after the pipeline facilities are abandoned, while still maintaining natural gas service to its firm customers. To satisfy NEPA, FERC issued an EA (again, NOT an EIS) that addressed geology, soils, water resources, wetlands, vegetation, fisheries, wildlife, threatened and endangered species, land use, recreation, visual resources, cultural resources, air quality, noise, safety, cumulative impacts, and alternatives. 29
  • 30. Relevant Language from the EA: “After the abandonment, Trunkline would no longer be responsible for the facilities and the Commission will have no remaining jurisdiction. Thus, the EA did not include a detailed analysis of the impacts that could occur after the abandonment. However, the EA did provide available information about the anticipated conversion and about potential cumulative impacts associated with the construction of facilities to support the proposed future use.” and “In the event that the abandoned pipeline is converted for use in oil transportation, the relevant authorizing and permitting state and federal agencies, including the U.S. Department of Transportation, are responsible for addressing environmental and safety matters.” 30
  • 31. 31 From the application: • Texas Gas sought authority to abandon approximately 623 miles of natural gas pipeline segments from Eunice, Louisiana to Hardinsburg, Kentucky and associated facilities. • All of Texas Gas’s installed facilities south of Eunice and north of Hardinsburg would remain in interstate natural gas transportation service. FERC issued an Environmental Assessment [emphasis added] on February 14, 2014, but project was withdrawn on June 3, 2014… • Following abandonment, Texas Gas would continue to provide natural gas transportation service on its remaining pipeline facilities. • After receipt of abandonment authority, the pipeline segments will be taken out of natural gas service and repurposed for use in natural gas liquids (“NGL”) service.
  • 32. Challenges to Accomplishing Such Conversions 32
  • 33. As Noted Above: FERC has no jurisdiction over construction or maintenance of production wells, oil pipelines, refineries, or storage facilities This means: Products pipelines are “sited” on a State-by-State basis (if a pipeline crosses 10 states, then 10 different siting agencies may be involved) This doesn’t mean: Products Pipelines are exempt from other Federal agency requirements, or requirements of State agencies administering Federal requirements (i. e., CZMA, CWA, CAA, etc.) 33
  • 34.  Natural Gas is transported by being compressed by large reciprocating or turbine motors at compressor stations  Compressor stations are sited along the length of a pipeline based on flow engineering analysis of transportation distances, transportation volumes and operating & delivery pressures  Liquids are “pumped” and pumping stations are sited along the liquids pipeline based on hydraulic analysis The locations of historic compressor station sites may not align with the required pumping station sites, leading to new, and possibly significant, construction for gas-to-liquid conversion projects! 34
  • 35.  The trend to convert unused natural gas pipelines to oil- and products-pipelines will continue, owing to higher oil-to-gas prices, and the market for NGLs  FERC will continue to assert economic jurisdiction on such pipelines  FERC’s NEPA role in conversion projects will be limited  Project proponents for conversion projects will still be subject to certain Federal and State oversight 35
  • 36. Contact Information: Berne L. Mosley, President Energy Projects Consulting, LLC bernemosley@yahoo.com
  • 37. FERC – Federal Energy Regulatory Commission; the agency responsible for interstate and some offshore transportation of natural gas, oil and “oil products” NGA – Natural Gas Act; law that gives natural gas companies authority to construct & operate (Sec 7(c)) and abandon (Sec 7(b)) interstate natural gas facilities DOT – Department of Transportation; regulatory agency with safety authority over interstate gas and oil facilities
  • 38. BSEE – Bureau of Safety and Environmental Enforcement; regulatory agency responsible for safety, environment and conservation of offshore oil and natural gas resources Blanket Certificate Program – a subprogram of a Section 7(c) application, comprising “automatic” and “prior notice”
  • 39. Blanket Certificate Program – a subprogram of a Section 7(c) application, comprising “automatic” and “prior notice” FT – Firm Transportation; transportation guaranteed at full contract level of service IT – Interruptible Transportation; transportation provided on an “as available basis” with no level-of-service guarantees
  • 40. MAOP – Maximum Allowable Operating Pressure; the pressure, in PSI, at which a pipeline is allowed to operate, based on the yield strength of the steel and DOT requirements EFM – Electronic Flow Meters; meters that measure the amount of gas flowing through a pipe