Fall 2015--DEC Upated on Spring Creek Restoration Project
1. 1
Spring Creek South
Hazard Mitigation Grant Program
(HMGP) Update
Presentation to Jamaica Bay Task Force
State of the Bay Meeting
Venetia Lannon
R2 Regional Director
October 29, 2015
2. 2
FEMA Hazard Mitigation Grant
Federal Funds: 75%
Local Funds: 25%
Goal: Reduce future
disaster damages
3. 3
Project Area: National Park Service
Gateway National Recreation Area
Jamaica Bay Unit – Spring Creek
5. 5
Project Goals
• Natural/nature-based
features to manage coastal
storm risk
• Improve sustainability and
resilience of area
• Integrated approach to
provide storm protection and
ecosystem restoration
benefits
• Consistent with NPS
management goals
7. 7
Phase 1 Status Progress
• Agreements between USACE and NYSDEC executed
and sampling permits obtained
• Scope of Work and contract awarded to Consultant
Team
Princeton Hydro
Parsons Brinckerhoff
HDR
• Field work for Baseline Conditions and Concept Design
development over the next 2-3 months
9. 9
Baseline Data Collection: Geotechnical
Investigation - Soil Borings
November-December
Delivery of ATV Rig and
Water Truck to remain on-
site
Work Hours: 7AM-3PM +/-
One Pick-up Truck on 165th
Street (at 7AM and 3PM)
Duration: 2-3 weeks from
start
10. 10
Baseline Data Collection: Contaminant
Characterization - Soil Sampling
November-December
Delivery of Geoprobe and
brush hog on-site
Operational hours and
traffic same as Geotech
Duration: 5-6 weeks from
start
17. 17
Complementary Projects: Spring Creek
North and New York Rising
Spring Creek
North
(USACE/NYC
Parks
Restoration
Project)
NY Rising
Priority
Projects
18. 18
Community and Partner Input
Adjacent landowner requirements
Partner agencies considerations
Complementary projects
Public access & amenities
Community Involvement:
Information sessions
Draft Environmental Assessment Review/Comment
Potential outreach portals (webpage, library, press,
signage, info sheets, email updates)
19. 19
FEMA Approval of Phase 1
Advancement to Phase 2
Final plans and specifications for construction
Construction
21. 21
Thank You
Lisa Baron
Project Manager, USACE
Lisa.a.baron@usace.army.mil
917-790-8306
Joanna Field
Marine Resources Biologist
Region 2, LIC
joanna.field@dec.ny.gov
718-482-4057
Connect with us:
Facebook:
www.facebook.com/NYSDEC
Twitter: twitter.com/NYSDEC
Flickr: www.flickr.com/photos/nysdec
Editor's Notes
New York Rising – we’re coordinating with the Howard Beach community’s priority projects to find efficiencies and achieve greater protection through combined efforts.