Fall 2015--DEC Upated on Spring Creek Restoration Project

1
Spring Creek South
Hazard Mitigation Grant Program
(HMGP) Update
Presentation to Jamaica Bay Task Force
State of the Bay Meeting
Venetia Lannon
R2 Regional Director
October 29, 2015
2
FEMA Hazard Mitigation Grant
Federal Funds: 75%
Local Funds: 25%
Goal: Reduce future
disaster damages
3
Project Area: National Park Service
Gateway National Recreation Area
Jamaica Bay Unit – Spring Creek
4
Project Area: Spring Creek
5
Project Goals
• Natural/nature-based
features to manage coastal
storm risk
• Improve sustainability and
resilience of area
• Integrated approach to
provide storm protection and
ecosystem restoration
benefits
• Consistent with NPS
management goals
6
HMGP Award: Two Phases
Phases
• I: Engineering & Design
Total: $3.3M (Share: $2.5M + $0.8M)
• II: Construction
Total: $65.8M (Share: $49.3M + $16.5M)
Schedule: 18-month build
7
Phase 1 Status Progress
• Agreements between USACE and NYSDEC executed
and sampling permits obtained
• Scope of Work and contract awarded to Consultant
Team
Princeton Hydro
Parsons Brinckerhoff
HDR
• Field work for Baseline Conditions and Concept Design
development over the next 2-3 months
8
Baseline Data Collection
October- November
Wetland Delineation
Bathymetry
9
Baseline Data Collection: Geotechnical
Investigation - Soil Borings
November-December
 Delivery of ATV Rig and
Water Truck to remain on-
site
 Work Hours: 7AM-3PM +/-
 One Pick-up Truck on 165th
Street (at 7AM and 3PM)
 Duration: 2-3 weeks from
start
10
Baseline Data Collection: Contaminant
Characterization - Soil Sampling
November-December
 Delivery of Geoprobe and
brush hog on-site
 Operational hours and
traffic same as Geotech
 Duration: 5-6 weeks from
start
11
Baseline Data Collection:
October-December
Biological surveys
Aerial
surveys
Tide gauges and
current meters
12
Previous
USACE
Ecosystem
Restoration
Conceptual
Design
Concept Plan Development
13
Conceptual Designs
14
Concept Designs Evaluated
Coastal Storm Modeling
Cost Estimates
 Concept Plan Selected
 Designs
 National Environmental Policy Act (NEPA)
Environmental Assessment
15
Detailed Designs and Cost Estimates and
NEPA Compliance
 Cost Benefit Analysis
 Detailed designs
 Detailed cost estimates
 Plans and specifications
 Updated NEPA Environmental Assessment
and Compliance
16
Complementary Projects: USACE Rockaway
Reformulation Study
17
Complementary Projects: Spring Creek
North and New York Rising
Spring Creek
North
(USACE/NYC
Parks
Restoration
Project)
NY Rising
Priority
Projects
18
Community and Partner Input
 Adjacent landowner requirements
 Partner agencies considerations
 Complementary projects
 Public access & amenities
 Community Involvement:
 Information sessions
 Draft Environmental Assessment Review/Comment
 Potential outreach portals (webpage, library, press,
signage, info sheets, email updates)
19
FEMA Approval of Phase 1
Advancement to Phase 2
 Final plans and specifications for construction
 Construction
20
21
Thank You
Lisa Baron
Project Manager, USACE
Lisa.a.baron@usace.army.mil
917-790-8306
Joanna Field
Marine Resources Biologist
Region 2, LIC
joanna.field@dec.ny.gov
718-482-4057
Connect with us:
Facebook:
www.facebook.com/NYSDEC
Twitter: twitter.com/NYSDEC
Flickr: www.flickr.com/photos/nysdec
1 of 21

Recommended

Public meeting # 1 for website by
Public meeting # 1   for websitePublic meeting # 1   for website
Public meeting # 1 for websitepixellence
240 views20 slides
C Arias EA Current_WEM3 2015 Paddock Wood by
C Arias EA Current_WEM3 2015 Paddock WoodC Arias EA Current_WEM3 2015 Paddock Wood
C Arias EA Current_WEM3 2015 Paddock WoodArias Christian
86 views1 slide
2006 AEG Godwin presentation by
2006 AEG Godwin presentation2006 AEG Godwin presentation
2006 AEG Godwin presentationWilliam Godwin
55 views62 slides
Moffett Site 1, 22, 26, and 28 Five Year Review by
Moffett Site 1, 22, 26, and 28 Five Year ReviewMoffett Site 1, 22, 26, and 28 Five Year Review
Moffett Site 1, 22, 26, and 28 Five Year ReviewSteve Williams
850 views23 slides
Arcadis Design Lake Accotink Dredging Public Meeting December 2020 by
Arcadis Design Lake Accotink Dredging Public Meeting December 2020 Arcadis Design Lake Accotink Dredging Public Meeting December 2020
Arcadis Design Lake Accotink Dredging Public Meeting December 2020 Fairfax County
737 views10 slides

More Related Content

What's hot

Gude Landfill Remediation update by
Gude Landfill Remediation updateGude Landfill Remediation update
Gude Landfill Remediation updateRecycling and Resource Management Division
1.6K views25 slides
Creating A Paradigm Shift, Putting the Buffalo River First: Usace by
Creating A Paradigm Shift, Putting the Buffalo River First: UsaceCreating A Paradigm Shift, Putting the Buffalo River First: Usace
Creating A Paradigm Shift, Putting the Buffalo River First: UsaceHealthy Lakes, Healthy Lives
280 views8 slides
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ... by
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...
Bay Delta Conservation Plan - Paul Helliker, Department of Water Resources - ...San Diego County Water Authority
1.7K views11 slides
TGS Bain Geo by
TGS Bain GeoTGS Bain Geo
TGS Bain GeoTGS
267 views2 slides
Lake Accotink Dredging Public Meeting Presentation December 2020 by
Lake Accotink Dredging Public Meeting Presentation December 2020Lake Accotink Dredging Public Meeting Presentation December 2020
Lake Accotink Dredging Public Meeting Presentation December 2020Fairfax County
873 views11 slides
Professional Geologist Work Experience by
Professional Geologist Work ExperienceProfessional Geologist Work Experience
Professional Geologist Work ExperienceWilliamOlsenPG
24 views4 slides

What's hot(16)

TGS Bain Geo by TGS
TGS Bain GeoTGS Bain Geo
TGS Bain Geo
TGS267 views
Lake Accotink Dredging Public Meeting Presentation December 2020 by Fairfax County
Lake Accotink Dredging Public Meeting Presentation December 2020Lake Accotink Dredging Public Meeting Presentation December 2020
Lake Accotink Dredging Public Meeting Presentation December 2020
Fairfax County873 views
Professional Geologist Work Experience by WilliamOlsenPG
Professional Geologist Work ExperienceProfessional Geologist Work Experience
Professional Geologist Work Experience
WilliamOlsenPG24 views
K5 4 Wells Portal Success Story by Daljit Brar
K5 4 Wells Portal Success StoryK5 4 Wells Portal Success Story
K5 4 Wells Portal Success Story
Daljit Brar258 views
20151210_GasReservesCookInlet_v2 by Theia Marketing
20151210_GasReservesCookInlet_v220151210_GasReservesCookInlet_v2
20151210_GasReservesCookInlet_v2
Theia Marketing375 views
Impacts of Climate Change in sustainability of hydropower in Nepal by Qust04
Impacts of Climate Change in sustainability of hydropower in NepalImpacts of Climate Change in sustainability of hydropower in Nepal
Impacts of Climate Change in sustainability of hydropower in Nepal
Qust04662 views
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5... by Fairfax County
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Lake Accotink Dredge Public Meeting Combined Presentation July 29 & aug 5...
Fairfax County566 views
25 decovalex 2019 geochemical and reactive transport evaluations with relevan... by leann_mays
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
25 decovalex 2019 geochemical and reactive transport evaluations with relevan...
leann_mays189 views

Viewers also liked

5 dep presentation to jbtf-fall 2015 by
5 dep presentation to jbtf-fall 20155 dep presentation to jbtf-fall 2015
5 dep presentation to jbtf-fall 2015ecowatchers
1.9K views12 slides
Army Corps of Engineers Report on Restoration Planning in Jamaica bay by
Army Corps of Engineers Report on Restoration Planning in Jamaica bayArmy Corps of Engineers Report on Restoration Planning in Jamaica bay
Army Corps of Engineers Report on Restoration Planning in Jamaica bayecowatchers
1.1K views29 slides
Nov 16 2016 nps presentation west pond[2995] by
Nov 16 2016 nps presentation west pond[2995]Nov 16 2016 nps presentation west pond[2995]
Nov 16 2016 nps presentation west pond[2995]ecowatchers
762 views21 slides
Jamaica Bay Greenway by
Jamaica Bay GreenwayJamaica Bay Greenway
Jamaica Bay Greenwayecowatchers
1.4K views31 slides
Sunset cove phase 2 advocacy by
Sunset cove phase 2 advocacySunset cove phase 2 advocacy
Sunset cove phase 2 advocacyecowatchers
778 views34 slides
Blackwall island planting project by
Blackwall island planting projectBlackwall island planting project
Blackwall island planting projectecowatchers
1.1K views44 slides

Viewers also liked(20)

5 dep presentation to jbtf-fall 2015 by ecowatchers
5 dep presentation to jbtf-fall 20155 dep presentation to jbtf-fall 2015
5 dep presentation to jbtf-fall 2015
ecowatchers1.9K views
Army Corps of Engineers Report on Restoration Planning in Jamaica bay by ecowatchers
Army Corps of Engineers Report on Restoration Planning in Jamaica bayArmy Corps of Engineers Report on Restoration Planning in Jamaica bay
Army Corps of Engineers Report on Restoration Planning in Jamaica bay
ecowatchers1.1K views
Nov 16 2016 nps presentation west pond[2995] by ecowatchers
Nov 16 2016 nps presentation west pond[2995]Nov 16 2016 nps presentation west pond[2995]
Nov 16 2016 nps presentation west pond[2995]
ecowatchers762 views
Jamaica Bay Greenway by ecowatchers
Jamaica Bay GreenwayJamaica Bay Greenway
Jamaica Bay Greenway
ecowatchers1.4K views
Sunset cove phase 2 advocacy by ecowatchers
Sunset cove phase 2 advocacySunset cove phase 2 advocacy
Sunset cove phase 2 advocacy
ecowatchers778 views
Blackwall island planting project by ecowatchers
Blackwall island planting projectBlackwall island planting project
Blackwall island planting project
ecowatchers1.1K views
Dep head of bay oyster project jam bay task force fall 2017 update by ecowatchers
Dep head of bay oyster project jam bay task force fall 2017 updateDep head of bay oyster project jam bay task force fall 2017 update
Dep head of bay oyster project jam bay task force fall 2017 update
ecowatchers604 views
Nps presentaion on horshoe crabs in jamaica bay by ecowatchers
Nps presentaion on horshoe crabs in jamaica bayNps presentaion on horshoe crabs in jamaica bay
Nps presentaion on horshoe crabs in jamaica bay
ecowatchers1.7K views
Oct 2016 public meeting presentation acoe reformulation plan by ecowatchers
Oct 2016 public meeting presentation acoe reformulation planOct 2016 public meeting presentation acoe reformulation plan
Oct 2016 public meeting presentation acoe reformulation plan
ecowatchers758 views
May 5 2016 NPS presentation-update on west pond breach repairs by ecowatchers
May 5 2016 NPS presentation-update on west pond breach repairsMay 5 2016 NPS presentation-update on west pond breach repairs
May 5 2016 NPS presentation-update on west pond breach repairs
ecowatchers1K views
Nps presentation on restoration plans for north and south garden by ecowatchers
Nps presentation on restoration plans for north and south gardenNps presentation on restoration plans for north and south garden
Nps presentation on restoration plans for north and south garden
ecowatchers921 views
Dep head of bay oyster project jam bay task force november 2016 by ecowatchers
Dep head of bay oyster project jam bay task force november 2016Dep head of bay oyster project jam bay task force november 2016
Dep head of bay oyster project jam bay task force november 2016
ecowatchers893 views
Usace new york harbor drift removal by ecowatchers
Usace new york harbor drift removalUsace new york harbor drift removal
Usace new york harbor drift removal
ecowatchers1.4K views
Rulers Bar/Blackwall island update 10 29 15 Elizabeth Manclarke-ALS by ecowatchers
Rulers Bar/Blackwall island update 10 29 15 Elizabeth Manclarke-ALSRulers Bar/Blackwall island update 10 29 15 Elizabeth Manclarke-ALS
Rulers Bar/Blackwall island update 10 29 15 Elizabeth Manclarke-ALS
ecowatchers1.9K views
9 jamaica bay wildlife refuge 2015 by ecowatchers
9 jamaica bay wildlife refuge 20159 jamaica bay wildlife refuge 2015
9 jamaica bay wildlife refuge 2015
ecowatchers1.1K views
Fall 2015-Sunset Cove Update by ecowatchers
Fall 2015-Sunset Cove UpdateFall 2015-Sunset Cove Update
Fall 2015-Sunset Cove Update
ecowatchers1.8K views
Stakeholder report -srijb-science and resiliency institute at jamaica bay- by ecowatchers
Stakeholder report -srijb-science and resiliency institute at jamaica bay-Stakeholder report -srijb-science and resiliency institute at jamaica bay-
Stakeholder report -srijb-science and resiliency institute at jamaica bay-
ecowatchers801 views
Ecowatcher's State of the bay -fall 2015 by ecowatchers
Ecowatcher's State of the bay -fall 2015Ecowatcher's State of the bay -fall 2015
Ecowatcher's State of the bay -fall 2015
ecowatchers998 views
Sunset cove restoration project -update by ecowatchers
Sunset cove restoration project -updateSunset cove restoration project -update
Sunset cove restoration project -update
ecowatchers1K views

Similar to Fall 2015--DEC Upated on Spring Creek Restoration Project

Brownfields Case Studies by
Brownfields Case Studies Brownfields Case Studies
Brownfields Case Studies nado-web
2.6K views32 slides
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat... by
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...Graeme Donaldson
217 views56 slides
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018 by
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Fairfax County
1.5K views42 slides
Scoping meeting presentation 4 29-13 by
Scoping meeting presentation 4 29-13Scoping meeting presentation 4 29-13
Scoping meeting presentation 4 29-13San Diego County Water Authority
2.3K views17 slides
Dead Run Segments 2/3 Stream Restoration Project Public Meeting by
Dead Run Segments 2/3 Stream Restoration Project Public MeetingDead Run Segments 2/3 Stream Restoration Project Public Meeting
Dead Run Segments 2/3 Stream Restoration Project Public MeetingFairfax County
724 views47 slides
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr... by
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...Deltares
424 views39 slides

Similar to Fall 2015--DEC Upated on Spring Creek Restoration Project(20)

Brownfields Case Studies by nado-web
Brownfields Case Studies Brownfields Case Studies
Brownfields Case Studies
nado-web2.6K views
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat... by Graeme Donaldson
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
Graeme Donaldson217 views
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018 by Fairfax County
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Hunting Creek at Fairchild MVCCA-Meeting March 7, 2018
Fairfax County1.5K views
Dead Run Segments 2/3 Stream Restoration Project Public Meeting by Fairfax County
Dead Run Segments 2/3 Stream Restoration Project Public MeetingDead Run Segments 2/3 Stream Restoration Project Public Meeting
Dead Run Segments 2/3 Stream Restoration Project Public Meeting
Fairfax County724 views
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr... by Deltares
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
DSD-INT 2019 Keynote - A National Flood-Guidance Programme for Canada - Pietr...
Deltares424 views
Regulatory Challenges to Alternative Energy by Kevin Haroff
Regulatory Challenges to Alternative EnergyRegulatory Challenges to Alternative Energy
Regulatory Challenges to Alternative Energy
Kevin Haroff359 views
Part 490 Presentation by Amanda Post
Part 490 PresentationPart 490 Presentation
Part 490 Presentation
Amanda Post213 views
Baron-Jamaica Bay Task force 17Nov22.pdf by ecowatchers
Baron-Jamaica Bay Task force 17Nov22.pdfBaron-Jamaica Bay Task force 17Nov22.pdf
Baron-Jamaica Bay Task force 17Nov22.pdf
ecowatchers19 views
Paul Spring Branch at Sherwood Hall Stream Restoration Project by Fairfax County
Paul Spring Branch at Sherwood Hall Stream Restoration ProjectPaul Spring Branch at Sherwood Hall Stream Restoration Project
Paul Spring Branch at Sherwood Hall Stream Restoration Project
Fairfax County1.9K views
Steve Nadeau, Honigman, Sediment Cleanup and Great Lakes Legacy Act, Midwest ... by Kevin Perry
Steve Nadeau, Honigman, Sediment Cleanup and Great Lakes Legacy Act, Midwest ...Steve Nadeau, Honigman, Sediment Cleanup and Great Lakes Legacy Act, Midwest ...
Steve Nadeau, Honigman, Sediment Cleanup and Great Lakes Legacy Act, Midwest ...
Kevin Perry989 views
Spring Creek South Update by ecowatchers
Spring Creek South UpdateSpring Creek South Update
Spring Creek South Update
ecowatchers269 views
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju... by Fairfax County
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Rabbit Branch at Collingham Drive Stream Restoration Information Meeting - Ju...
Fairfax County3.7K views
Dead Run Stream Restoration Public Meeting June 9, 2015 by Fairfax County
Dead Run Stream Restoration Public Meeting June 9, 2015Dead Run Stream Restoration Public Meeting June 9, 2015
Dead Run Stream Restoration Public Meeting June 9, 2015
Fairfax County1.8K views
Long Branch Central Watershed Management Area 03-03-2021 by Fairfax County
Long Branch Central Watershed Management Area 03-03-2021Long Branch Central Watershed Management Area 03-03-2021
Long Branch Central Watershed Management Area 03-03-2021
Fairfax County2.4K views

More from ecowatchers

NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf by
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfNPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfecowatchers
13 views12 slides
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf by
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdfNYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdfecowatchers
46 views26 slides
November 17 2022 Jam Bay Task Force.pdf by
November 17 2022 Jam Bay Task Force.pdfNovember 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdfecowatchers
8 views10 slides
Jamaica Bay Task Force_May 2022.pdf by
Jamaica Bay Task Force_May 2022.pdfJamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdfecowatchers
25 views36 slides
Jamaica Bay Task Force2- 10May22.pdf by
Jamaica Bay Task Force2- 10May22.pdfJamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdfecowatchers
25 views21 slides
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric... by
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...ecowatchers
25 views23 slides

More from ecowatchers(20)

NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf by ecowatchers
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdfNPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
NPS presentation Jamaica Bay Task Force Meeting 2022-11-17.pdf
ecowatchers13 views
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf by ecowatchers
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdfNYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
NYNJHAT Presentation slides for Jamaica Bay Task Force Meeting 17 Nov 22.pdf
ecowatchers46 views
November 17 2022 Jam Bay Task Force.pdf by ecowatchers
November 17 2022 Jam Bay Task Force.pdfNovember 17 2022 Jam Bay Task Force.pdf
November 17 2022 Jam Bay Task Force.pdf
ecowatchers8 views
Jamaica Bay Task Force_May 2022.pdf by ecowatchers
Jamaica Bay Task Force_May 2022.pdfJamaica Bay Task Force_May 2022.pdf
Jamaica Bay Task Force_May 2022.pdf
ecowatchers25 views
Jamaica Bay Task Force2- 10May22.pdf by ecowatchers
Jamaica Bay Task Force2- 10May22.pdfJamaica Bay Task Force2- 10May22.pdf
Jamaica Bay Task Force2- 10May22.pdf
ecowatchers25 views
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric... by ecowatchers
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
Spring 2022 Task Force Meeting presentation on Adjacent Sediment Slurry Enric...
ecowatchers25 views
Ribbed Mussel Study Status JBTF.pdf by ecowatchers
Ribbed Mussel Study Status JBTF.pdfRibbed Mussel Study Status JBTF.pdf
Ribbed Mussel Study Status JBTF.pdf
ecowatchers28 views
Weppler jam bay task force 3 nov 21 by ecowatchers
Weppler jam bay task force  3 nov 21Weppler jam bay task force  3 nov 21
Weppler jam bay task force 3 nov 21
ecowatchers149 views
Jb task force 2021 1103 by ecowatchers
Jb task force 2021 1103Jb task force 2021 1103
Jb task force 2021 1103
ecowatchers136 views
201130 west pond reduced by ecowatchers
201130 west pond reduced201130 west pond reduced
201130 west pond reduced
ecowatchers241 views
Jamaica bay ecowatchers task force presentation 12.9.2020 by ecowatchers
Jamaica bay ecowatchers task force presentation   12.9.2020Jamaica bay ecowatchers task force presentation   12.9.2020
Jamaica bay ecowatchers task force presentation 12.9.2020
ecowatchers412 views
Nyc parks marine debris removal by ecowatchers
Nyc parks marine debris removalNyc parks marine debris removal
Nyc parks marine debris removal
ecowatchers149 views
Raptor mgmt presentation12 09-2020 by ecowatchers
Raptor mgmt presentation12 09-2020Raptor mgmt presentation12 09-2020
Raptor mgmt presentation12 09-2020
ecowatchers170 views
20191113 jbfs presentation final by ecowatchers
20191113 jbfs presentation final20191113 jbfs presentation final
20191113 jbfs presentation final
ecowatchers300 views
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore... by ecowatchers
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
Jamaica Bay Wildlife refuge west pond proposal for protecting the south shore...
ecowatchers312 views
Ribbed Mussel ability to remove Nitrogen from water bodies. by ecowatchers
Ribbed Mussel ability to remove Nitrogen from water bodies.Ribbed Mussel ability to remove Nitrogen from water bodies.
Ribbed Mussel ability to remove Nitrogen from water bodies.
ecowatchers414 views
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies by ecowatchers
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodiesNYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
NYC DEP update on Ribbed Mussel potential for treating pathogens in water bodies
ecowatchers396 views
Shirley Chisholm State Park-Brooklyn Update on phase two work by ecowatchers
Shirley Chisholm State Park-Brooklyn Update on phase two workShirley Chisholm State Park-Brooklyn Update on phase two work
Shirley Chisholm State Park-Brooklyn Update on phase two work
ecowatchers418 views
Army Corps of Engineers updates on future Jamaica Bay Projects by ecowatchers
Army Corps of Engineers updates on future Jamaica Bay ProjectsArmy Corps of Engineers updates on future Jamaica Bay Projects
Army Corps of Engineers updates on future Jamaica Bay Projects
ecowatchers373 views
Sunset cove restoration project -update by ecowatchers
Sunset cove restoration project -updateSunset cove restoration project -update
Sunset cove restoration project -update
ecowatchers389 views

Recently uploaded

Smart Grids by
Smart GridsSmart Grids
Smart GridsDr. Salem Baidas
10 views30 slides
green manuring ppt.pptx by
green manuring ppt.pptxgreen manuring ppt.pptx
green manuring ppt.pptxShubham Temgire
6 views34 slides
ORAL_PRESENTATION.pdf by
ORAL_PRESENTATION.pdfORAL_PRESENTATION.pdf
ORAL_PRESENTATION.pdfahmadalfalasim
33 views5 slides
Climate Equality Report OXFAM by
Climate Equality Report OXFAMClimate Equality Report OXFAM
Climate Equality Report OXFAMQuotidiano Piemontese
19 views136 slides
Towards a just and regenerative aquaculture system by
Towards a just and regenerative aquaculture systemTowards a just and regenerative aquaculture system
Towards a just and regenerative aquaculture systemMartin Koehring
16 views15 slides
Smart Cities by
Smart CitiesSmart Cities
Smart CitiesDr. Salem Baidas
10 views40 slides

Recently uploaded(20)

Towards a just and regenerative aquaculture system by Martin Koehring
Towards a just and regenerative aquaculture systemTowards a just and regenerative aquaculture system
Towards a just and regenerative aquaculture system
Martin Koehring16 views
Climate Change, Biodiversity & Health - IPBES Perspectives by ipcc-media
Climate Change, Biodiversity & Health - IPBES PerspectivesClimate Change, Biodiversity & Health - IPBES Perspectives
Climate Change, Biodiversity & Health - IPBES Perspectives
ipcc-media48 views
Citizen science of the Great Barrier Reef and Coral Sea Expedition by Dr Adam Smith
Citizen science of the Great Barrier Reef and Coral Sea ExpeditionCitizen science of the Great Barrier Reef and Coral Sea Expedition
Citizen science of the Great Barrier Reef and Coral Sea Expedition
Dr Adam Smith46 views
Physical Science Challenges for AR7 by ipcc-media
Physical Science Challenges for AR7Physical Science Challenges for AR7
Physical Science Challenges for AR7
ipcc-media206 views
Climate Change and Health by ipcc-media
Climate Change and HealthClimate Change and Health
Climate Change and Health
ipcc-media50 views
Activity 9 Sustainability System.pptx by AkarshSingh57
Activity 9 Sustainability System.pptxActivity 9 Sustainability System.pptx
Activity 9 Sustainability System.pptx
AkarshSingh578 views
climate and the world by Basel Ahmed
climate and the worldclimate and the world
climate and the world
Basel Ahmed35 views
Low-emission food system perspectives in Viet Nam by CIFOR-ICRAF
Low-emission food system perspectives in Viet NamLow-emission food system perspectives in Viet Nam
Low-emission food system perspectives in Viet Nam
CIFOR-ICRAF7 views
PROGRAMMES OF ENVIRONMENTAL EDUCATION.pptx by DrHafizKosar
PROGRAMMES OF ENVIRONMENTAL EDUCATION.pptxPROGRAMMES OF ENVIRONMENTAL EDUCATION.pptx
PROGRAMMES OF ENVIRONMENTAL EDUCATION.pptx
DrHafizKosar133 views

Fall 2015--DEC Upated on Spring Creek Restoration Project

  • 1. 1 Spring Creek South Hazard Mitigation Grant Program (HMGP) Update Presentation to Jamaica Bay Task Force State of the Bay Meeting Venetia Lannon R2 Regional Director October 29, 2015
  • 2. 2 FEMA Hazard Mitigation Grant Federal Funds: 75% Local Funds: 25% Goal: Reduce future disaster damages
  • 3. 3 Project Area: National Park Service Gateway National Recreation Area Jamaica Bay Unit – Spring Creek
  • 5. 5 Project Goals • Natural/nature-based features to manage coastal storm risk • Improve sustainability and resilience of area • Integrated approach to provide storm protection and ecosystem restoration benefits • Consistent with NPS management goals
  • 6. 6 HMGP Award: Two Phases Phases • I: Engineering & Design Total: $3.3M (Share: $2.5M + $0.8M) • II: Construction Total: $65.8M (Share: $49.3M + $16.5M) Schedule: 18-month build
  • 7. 7 Phase 1 Status Progress • Agreements between USACE and NYSDEC executed and sampling permits obtained • Scope of Work and contract awarded to Consultant Team Princeton Hydro Parsons Brinckerhoff HDR • Field work for Baseline Conditions and Concept Design development over the next 2-3 months
  • 8. 8 Baseline Data Collection October- November Wetland Delineation Bathymetry
  • 9. 9 Baseline Data Collection: Geotechnical Investigation - Soil Borings November-December  Delivery of ATV Rig and Water Truck to remain on- site  Work Hours: 7AM-3PM +/-  One Pick-up Truck on 165th Street (at 7AM and 3PM)  Duration: 2-3 weeks from start
  • 10. 10 Baseline Data Collection: Contaminant Characterization - Soil Sampling November-December  Delivery of Geoprobe and brush hog on-site  Operational hours and traffic same as Geotech  Duration: 5-6 weeks from start
  • 11. 11 Baseline Data Collection: October-December Biological surveys Aerial surveys Tide gauges and current meters
  • 14. 14 Concept Designs Evaluated Coastal Storm Modeling Cost Estimates  Concept Plan Selected  Designs  National Environmental Policy Act (NEPA) Environmental Assessment
  • 15. 15 Detailed Designs and Cost Estimates and NEPA Compliance  Cost Benefit Analysis  Detailed designs  Detailed cost estimates  Plans and specifications  Updated NEPA Environmental Assessment and Compliance
  • 16. 16 Complementary Projects: USACE Rockaway Reformulation Study
  • 17. 17 Complementary Projects: Spring Creek North and New York Rising Spring Creek North (USACE/NYC Parks Restoration Project) NY Rising Priority Projects
  • 18. 18 Community and Partner Input  Adjacent landowner requirements  Partner agencies considerations  Complementary projects  Public access & amenities  Community Involvement:  Information sessions  Draft Environmental Assessment Review/Comment  Potential outreach portals (webpage, library, press, signage, info sheets, email updates)
  • 19. 19 FEMA Approval of Phase 1 Advancement to Phase 2  Final plans and specifications for construction  Construction
  • 20. 20
  • 21. 21 Thank You Lisa Baron Project Manager, USACE Lisa.a.baron@usace.army.mil 917-790-8306 Joanna Field Marine Resources Biologist Region 2, LIC joanna.field@dec.ny.gov 718-482-4057 Connect with us: Facebook: www.facebook.com/NYSDEC Twitter: twitter.com/NYSDEC Flickr: www.flickr.com/photos/nysdec

Editor's Notes

  1. New York Rising – we’re coordinating with the Howard Beach community’s priority projects to find efficiencies and achieve greater protection through combined efforts.