Startup of Factory After Lockdown
Process Wise Startup – First & Most important thing is to
adhere Guidelines issued by Ministry of Home affairs.
safety norms required as per factories act, guidelines ,
Government regulations , EOHS compliance & applicable
regulations in the regions where the location is.
Process Wise Startup -Office
 Ensure seating arrangement is cleaned properly.
 Ensure wiring of computer system is proper.
 Update/inline the system with server /Erp after
consultation with superiors.
 Download mails & arrange properly pending works .
 Reply each & every mail .
 Make list of work which was in progress when
lockdown started & start working on them
 Make list of work which was planned in following days
from lockdown starts & start working on them.
 Ensure Sufficient manpower is available in plant.
 Pl communicate with Employees .
 Make sure availability of PPE for COVID 19 & applicable PPE for
processes.
 Skill matrix & available employees to be reviewed.
 Communicate with department heads & arrange retraining of
employees incase of new process or new employee & wherever
required.
 Review the statutory & regulatory pending works during lockdown &
take on priority.
Process Wise Startup – HR
 Ensure availability of material which is supposed to received
during lockdown period.
 Review pending purchase requirements & po. Make action plan.
 Communicate with suppliers for availability of required material &
inventory at them.
 Review supplier evaluation & rating is completed after lockdown.
 Review if there any material which is need to be returned or
replaced.
 Review ISO / IATF/EOHS certification of suppliers are valid.
 Make sure that GRN are not pending & bills of accepted material
are
booked in the system.
Process Wise Startup – Purchase
 Tally stock of Raw material , Consumable & Maintenance related
material .
 Ensure shelf life of material is valid.
 Ensure there was no mix up in materials.
 Ensure all material is in good condition.
 Notify to Purchase for Material with less inventory .
 Status of material which was in transit when Lockdown started.
 Circulate Inventory sheet.
 Ensure Weighing balance working properly by self calibration.
 Ensure Material issue system & bar code is working properly.
 Ensure there is identification on every material
 Get checked first few charge before issue from Metallurgy
department
Process Wise Startup – Stores
 Material receipt during lock down is checked & ok for
use.
 Status of GRN pl complete pending GRN.
 Ensure Calibration of Instruments otherwise Notify to
calibration dept.
 Ensure Shelf life of chemicals prepared for testing.
 Check Sand for HTS & lump formation once again.
Process Wise Startup – Receiving Inspection
 Make schedules considering backlogs & customer demand.
 Communicate with Marketing for acceptance of schedules.
 Communicate dispatch dates of materials which is not packed to
marketing considering all situations happened due to lockdown.
 Plan number of resources required to complete the schedule in
agreement with production team.
Process Wise Startup – PPC
 Ensure availability of quality sand.
 Ensure machine condition ,air supply , Oiling & Lubrication of
machine.
 Check sand quality in Hoppers.
 Check heaters .
 Ensure pattern number as per plan & start production.
 Check shells for scratch hardness.
Process Wise Startup – Foundry
1) Shell Molding
Process Wise Startup – Foundry
1) Melting & Pouring
• Ensure availability of proper water pressure & Temp.
• Ensure Furnace Lining quality.
• Ensure weighing balance calibration.
• Ensure Temp stick working properly.
• Ensure Hydraulics of furnace working good.
• Ensure availability of trolleys.
• Ensure Vibrator is working
• Ensure all cranes are working.
• Ensure Centrifugal machines are running.
• Ensure availability of Laddles.
• Ensure availability of Fire Extinguishers, check there pressure
gauge.
• Check status of material produced during lock down start date.
Complet route card & production registers.
 Ensure Air pressure.
 Ensure Alumina sand level
 Ensure Quenching oil level.
 Ensure all temp indicators are working.
 Ensure heating is not abnormal.
 Ensure cooling towers working.
 Ensure availability of binding wire & hooks, rods & fitures.
 Ensure crane is working.
 Ensure availability of Fire extinguishers.
 Ensure alarms & poka yoke are working.
 Check status of material heat treated during lockdown start,
check quality of material & if ok complete route card.
Process Wise Startup – Heat Treatment
 Check spectro, Microscope wiring.
 Ensure AC is working.
 Ensure availability of Argon gas cylinder.
 Start spectro with standard operating procedure.
 Ensure spectro & Micro polishing machine is working.
 Ensure quality of hardness testing ,check masters & if
ok offer for inspection.
 Ensure heat treated lots during Lock down start date
are checked for Hardness & micro.
Process Wise Startup – Metallurgy Lab
 Ensure Lubrication & oiling of machine is done.
 Ensure tools & grinding wheels ,grinding segments are properly fitted.
 Check auto feeder working before starting production.
 Ensure coolant level & concentration is correct.
 Ensure all required gauges & instruments are in good condition & calibrated before
use.
 Ensure control plans & family sheet is available on machine.
 Start machine as per guidelines in Work instruction.
 Check & then Fill up the machine checklist
 Ensure machine slides & guide ways are free.
 Ensure all pressure gauges are working.
 Ensure oil in Hydraulic system.
 In first off check 5 parts instead of 1 for first startup.
 If any abnormal noise or vibration is observed immediately stop the machine & inform
to supervisor & maintenance.
 Ensure status of WIP( parts on machine or for machining during lockdown start
.Check for quality involve quality person , if ok then only offer for process.
 Ensure Route cards are available & filled .
 Ensure ERP & Bar coding system functioning correctly.
Process Wise Startup – Machine Shop
 Ensure all Lights are illuminating properly.
 Ensure all Non confirming material is recorded & disposed off.
 Ensure MPI machines working properly.
 Check Media concentration of MPI , validate pie gauge & if shown ok then
start the inspection.
 Check shelf life & condition of Zyglo chemicals. Stir well before use.
 Recheck the Material in process during lock down.
 Ensure all gauges & instruments are in good condition & calibrated before
use.
 Recheck the material which was pending for packing during lockdown starts.
 Ensure Air dryer is working properly.
 Recheck unidentified parts & then take action accordingly.
 Ensure computer & UPS connections are proper before starting machine.
 Ensure calibration status of instruments & Gauges.
 Ensure AC working & humidity before starting inspection activity.
 Ensure UPS & computer connections of laser marking are proper.
Process Wise Startup – Final Inspection & Gauge Room
 Check status of material at laser marking .
 Ensure packed material in sample for good condition.
 Material proven for rust check with large sample size for
good condition.
 Check material which was in progress during lockdown for
rust & mix up.
 Check incomplete boxes for mix up.
 Ensure Packaging standard is followed as per customer
agreement on packed material during lock down starts &
startup after lockdown end.
Process Wise Startup – Oiling & Packing
 Review list of development parts.
 Categories the parts as per different stages during lockdown starts.
 Make a list of activities which are in progress when lockdown starts
or planned in the week & till Ist week of May.
 Review the above list & make action plan with responsibility & Target
date.
 Recheck & confirm the suitability of parts in development WIP for
further use.
 Make sure availability of Tooling & Gauges which are supposed to
come during lock down period.
 Update plans accordingly with new dates.
 Communicate with customer for samples which are due in lockdown
period & feedback of supplied parts which is to be received durig
lockdown.
Process Wise Startup – Development

More Related Content

What's hot

Ernest Professional Industrial Engineering of Technology resume
Ernest Professional Industrial Engineering of Technology resumeErnest Professional Industrial Engineering of Technology resume
Ernest Professional Industrial Engineering of Technology resumeErnest Asare
 
Quality Assurance & Control In Your Supply Chain for Active Carbon
Quality Assurance & Control In Your Supply Chain for Active CarbonQuality Assurance & Control In Your Supply Chain for Active Carbon
Quality Assurance & Control In Your Supply Chain for Active CarbonADA-CS
 
Rene Contreras CV (eng)
Rene Contreras CV (eng)Rene Contreras CV (eng)
Rene Contreras CV (eng)Rene Contreras
 
Quality Assurance Presentation
Quality Assurance PresentationQuality Assurance Presentation
Quality Assurance PresentationADA-CS
 
Saturn Electronics Corp., PCB Manufacturer
Saturn Electronics Corp., PCB ManufacturerSaturn Electronics Corp., PCB Manufacturer
Saturn Electronics Corp., PCB ManufacturerDomestic PCB Fabrication
 
sandy resume planning.doc
sandy resume planning.docsandy resume planning.doc
sandy resume planning.docSandeep Rane
 
GMP (Good Manufacturing Practice)
GMP (Good Manufacturing Practice)GMP (Good Manufacturing Practice)
GMP (Good Manufacturing Practice)RAJESHWAR CHAVAN
 
Carol Sutton updated resume
Carol Sutton updated resume Carol Sutton updated resume
Carol Sutton updated resume Carol Sutton
 
Au production kaizen event - Anthony Guillen
Au production kaizen event - Anthony GuillenAu production kaizen event - Anthony Guillen
Au production kaizen event - Anthony GuillenAnthony Guillen
 
Investigation on Cycle Time Reduction in Production and Implementation of an ...
Investigation on Cycle Time Reduction in Production and Implementation of an ...Investigation on Cycle Time Reduction in Production and Implementation of an ...
Investigation on Cycle Time Reduction in Production and Implementation of an ...IRJET Journal
 
CURRICULUM VITAE - Victor Hugo Pelaez Hernandez - 15 Noviembre 2016
CURRICULUM VITAE - Victor Hugo Pelaez Hernandez - 15 Noviembre 2016CURRICULUM VITAE - Victor Hugo Pelaez Hernandez - 15 Noviembre 2016
CURRICULUM VITAE - Victor Hugo Pelaez Hernandez - 15 Noviembre 2016Victor Pelaez
 

What's hot (19)

Ernest Professional Industrial Engineering of Technology resume
Ernest Professional Industrial Engineering of Technology resumeErnest Professional Industrial Engineering of Technology resume
Ernest Professional Industrial Engineering of Technology resume
 
LESTER_ANTONY_FRANCIS ( Aug 2016)
LESTER_ANTONY_FRANCIS ( Aug 2016)LESTER_ANTONY_FRANCIS ( Aug 2016)
LESTER_ANTONY_FRANCIS ( Aug 2016)
 
Quality Assurance & Control In Your Supply Chain for Active Carbon
Quality Assurance & Control In Your Supply Chain for Active CarbonQuality Assurance & Control In Your Supply Chain for Active Carbon
Quality Assurance & Control In Your Supply Chain for Active Carbon
 
BadenhorstJC.updated
BadenhorstJC.updatedBadenhorstJC.updated
BadenhorstJC.updated
 
Rene Contreras CV (eng)
Rene Contreras CV (eng)Rene Contreras CV (eng)
Rene Contreras CV (eng)
 
Amr ZAKI
Amr ZAKIAmr ZAKI
Amr ZAKI
 
Quality Assurance Presentation
Quality Assurance PresentationQuality Assurance Presentation
Quality Assurance Presentation
 
Justin Ray Hernandez
Justin Ray HernandezJustin Ray Hernandez
Justin Ray Hernandez
 
CV Johan 3
CV Johan 3CV Johan 3
CV Johan 3
 
Steve Isaac CV
Steve Isaac  CVSteve Isaac  CV
Steve Isaac CV
 
Saturn Electronics Corp., PCB Manufacturer
Saturn Electronics Corp., PCB ManufacturerSaturn Electronics Corp., PCB Manufacturer
Saturn Electronics Corp., PCB Manufacturer
 
sandy resume planning.doc
sandy resume planning.docsandy resume planning.doc
sandy resume planning.doc
 
GMP (Good Manufacturing Practice)
GMP (Good Manufacturing Practice)GMP (Good Manufacturing Practice)
GMP (Good Manufacturing Practice)
 
RESUME
RESUMERESUME
RESUME
 
Guidehaccpplan
GuidehaccpplanGuidehaccpplan
Guidehaccpplan
 
Carol Sutton updated resume
Carol Sutton updated resume Carol Sutton updated resume
Carol Sutton updated resume
 
Au production kaizen event - Anthony Guillen
Au production kaizen event - Anthony GuillenAu production kaizen event - Anthony Guillen
Au production kaizen event - Anthony Guillen
 
Investigation on Cycle Time Reduction in Production and Implementation of an ...
Investigation on Cycle Time Reduction in Production and Implementation of an ...Investigation on Cycle Time Reduction in Production and Implementation of an ...
Investigation on Cycle Time Reduction in Production and Implementation of an ...
 
CURRICULUM VITAE - Victor Hugo Pelaez Hernandez - 15 Noviembre 2016
CURRICULUM VITAE - Victor Hugo Pelaez Hernandez - 15 Noviembre 2016CURRICULUM VITAE - Victor Hugo Pelaez Hernandez - 15 Noviembre 2016
CURRICULUM VITAE - Victor Hugo Pelaez Hernandez - 15 Noviembre 2016
 

Similar to Manufacturing setup startup after lockdown thought by dhananjay

Documentation in Pharmaceutical Industry
Documentation in Pharmaceutical IndustryDocumentation in Pharmaceutical Industry
Documentation in Pharmaceutical IndustryPooja Harkal
 
Documentation in pharmaceutical industry
Documentation in pharmaceutical industryDocumentation in pharmaceutical industry
Documentation in pharmaceutical industryPooja Harkal
 
Production in quality assurance
Production  in quality assuranceProduction  in quality assurance
Production in quality assurancekalai vani
 
Sigma Test and Research Centre
Sigma Test and Research CentreSigma Test and Research Centre
Sigma Test and Research Centresigmatest2011
 
cGMP / Sai sasidhar.ch
cGMP / Sai sasidhar.chcGMP / Sai sasidhar.ch
cGMP / Sai sasidhar.chsai sasidhar
 
basicgmps-130524145222-phpapp02 (1).pdf
basicgmps-130524145222-phpapp02 (1).pdfbasicgmps-130524145222-phpapp02 (1).pdf
basicgmps-130524145222-phpapp02 (1).pdfSethuPathi64
 
Pharmaceutical plant layout
Pharmaceutical plant layoutPharmaceutical plant layout
Pharmaceutical plant layoutArchana Chavhan
 
equipmentsvalidation.pdf
equipmentsvalidation.pdfequipmentsvalidation.pdf
equipmentsvalidation.pdfpshashank0409
 
DOCUMENTS on quality of pharmaceutical products
DOCUMENTS on quality of pharmaceutical productsDOCUMENTS on quality of pharmaceutical products
DOCUMENTS on quality of pharmaceutical productsLINGESHMASSLEE007
 
Pilot plant scaleup.pptx
Pilot plant scaleup.pptxPilot plant scaleup.pptx
Pilot plant scaleup.pptxANANDGADAD2
 
EQUIPMENT VALIDATION : HOT AIR OVEN
EQUIPMENT VALIDATION : HOT AIR OVENEQUIPMENT VALIDATION : HOT AIR OVEN
EQUIPMENT VALIDATION : HOT AIR OVENSagar Savale
 

Similar to Manufacturing setup startup after lockdown thought by dhananjay (20)

Documentation in Pharmaceutical Industry
Documentation in Pharmaceutical IndustryDocumentation in Pharmaceutical Industry
Documentation in Pharmaceutical Industry
 
Documentation in pharmaceutical industry
Documentation in pharmaceutical industryDocumentation in pharmaceutical industry
Documentation in pharmaceutical industry
 
chinna terminal operator.
chinna terminal operator.chinna terminal operator.
chinna terminal operator.
 
BMR And MFR
BMR And MFRBMR And MFR
BMR And MFR
 
Production in quality assurance
Production  in quality assuranceProduction  in quality assurance
Production in quality assurance
 
Sigma Test and Research Centre
Sigma Test and Research CentreSigma Test and Research Centre
Sigma Test and Research Centre
 
cGMP / Sai sasidhar.ch
cGMP / Sai sasidhar.chcGMP / Sai sasidhar.ch
cGMP / Sai sasidhar.ch
 
basicgmps-130524145222-phpapp02 (1).pdf
basicgmps-130524145222-phpapp02 (1).pdfbasicgmps-130524145222-phpapp02 (1).pdf
basicgmps-130524145222-phpapp02 (1).pdf
 
Basics of FDA GMP Training
Basics of FDA GMP TrainingBasics of FDA GMP Training
Basics of FDA GMP Training
 
Pharmaceutical plant layout
Pharmaceutical plant layoutPharmaceutical plant layout
Pharmaceutical plant layout
 
2. Ppt on GLP
2. Ppt on GLP2. Ppt on GLP
2. Ppt on GLP
 
Preformulation
PreformulationPreformulation
Preformulation
 
equipmentsvalidation.pdf
equipmentsvalidation.pdfequipmentsvalidation.pdf
equipmentsvalidation.pdf
 
DOCUMENTS on quality of pharmaceutical products
DOCUMENTS on quality of pharmaceutical productsDOCUMENTS on quality of pharmaceutical products
DOCUMENTS on quality of pharmaceutical products
 
Pilot plant scaleup.pptx
Pilot plant scaleup.pptxPilot plant scaleup.pptx
Pilot plant scaleup.pptx
 
EQUIPMENT VALIDATION : HOT AIR OVEN
EQUIPMENT VALIDATION : HOT AIR OVENEQUIPMENT VALIDATION : HOT AIR OVEN
EQUIPMENT VALIDATION : HOT AIR OVEN
 
Changeover Clearance
Changeover ClearanceChangeover Clearance
Changeover Clearance
 
Basic c gm ps
Basic c gm psBasic c gm ps
Basic c gm ps
 
BMR & MFR
BMR & MFRBMR & MFR
BMR & MFR
 
Gmp presentation
Gmp presentationGmp presentation
Gmp presentation
 

Recently uploaded

如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一
如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一
如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一ypfy7p5ld
 
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂Hot Call Girls In Sector 58 (Noida)
 
Innovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC TechnologyInnovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC Technologyquickpartslimitlessm
 
What Causes DPF Failure In VW Golf Cars & How Can They Be Prevented
What Causes DPF Failure In VW Golf Cars & How Can They Be PreventedWhat Causes DPF Failure In VW Golf Cars & How Can They Be Prevented
What Causes DPF Failure In VW Golf Cars & How Can They Be PreventedAutobahn Automotive Service
 
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样gfghbihg
 
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptx
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptxUNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptx
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptxDineshKumar4165
 
2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agency2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agencyHyundai Motor Group
 
Digamma / CertiCon Company Presentation
Digamma / CertiCon Company  PresentationDigamma / CertiCon Company  Presentation
Digamma / CertiCon Company PresentationMihajloManjak
 
John Deere 300 3029 4039 4045 6059 6068 Engine Operation and Service Manual
John Deere 300 3029 4039 4045 6059 6068 Engine Operation and Service ManualJohn Deere 300 3029 4039 4045 6059 6068 Engine Operation and Service Manual
John Deere 300 3029 4039 4045 6059 6068 Engine Operation and Service ManualExcavator
 
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证jjrehjwj11gg
 
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一fjjhfuubb
 
call girls in G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样umasea
 
定制(Plymouth文凭证书)普利茅斯大学毕业证毕业证成绩单学历认证原版一比一
定制(Plymouth文凭证书)普利茅斯大学毕业证毕业证成绩单学历认证原版一比一定制(Plymouth文凭证书)普利茅斯大学毕业证毕业证成绩单学历认证原版一比一
定制(Plymouth文凭证书)普利茅斯大学毕业证毕业证成绩单学历认证原版一比一fhhkjh
 
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGER
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGERUNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGER
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGERDineshKumar4165
 
Dubai Call Girls Size E6 (O525547819) Call Girls In Dubai
Dubai Call Girls  Size E6 (O525547819) Call Girls In DubaiDubai Call Girls  Size E6 (O525547819) Call Girls In Dubai
Dubai Call Girls Size E6 (O525547819) Call Girls In Dubaikojalkojal131
 
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingWhat Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingEscondido German Auto
 
办理埃默里大学毕业证Emory毕业证原版一比一
办理埃默里大学毕业证Emory毕业证原版一比一办理埃默里大学毕业证Emory毕业证原版一比一
办理埃默里大学毕业证Emory毕业证原版一比一mkfnjj
 
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一meq5nzfnk
 

Recently uploaded (20)

如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一
如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一
如何办理(Flinders毕业证)查理斯特大学毕业证毕业证成绩单原版一比一
 
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂
꧁༒☬ 7042364481 (Call Girl) In Dwarka Delhi Escort Service In Delhi Ncr☬༒꧂
 
Innovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC TechnologyInnovating Manufacturing with CNC Technology
Innovating Manufacturing with CNC Technology
 
What Causes DPF Failure In VW Golf Cars & How Can They Be Prevented
What Causes DPF Failure In VW Golf Cars & How Can They Be PreventedWhat Causes DPF Failure In VW Golf Cars & How Can They Be Prevented
What Causes DPF Failure In VW Golf Cars & How Can They Be Prevented
 
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样
(办理学位证)(Toledo毕业证)托莱多大学毕业证成绩单修改留信学历认证原版一模一样
 
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptx
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptxUNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptx
UNIT-IV-STEERING, BRAKES AND SUSPENSION SYSTEMS.pptx
 
2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agency2024 TOP 10 most fuel-efficient vehicles according to the US agency
2024 TOP 10 most fuel-efficient vehicles according to the US agency
 
Digamma / CertiCon Company Presentation
Digamma / CertiCon Company  PresentationDigamma / CertiCon Company  Presentation
Digamma / CertiCon Company Presentation
 
John Deere 300 3029 4039 4045 6059 6068 Engine Operation and Service Manual
John Deere 300 3029 4039 4045 6059 6068 Engine Operation and Service ManualJohn Deere 300 3029 4039 4045 6059 6068 Engine Operation and Service Manual
John Deere 300 3029 4039 4045 6059 6068 Engine Operation and Service Manual
 
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
原版工艺美国普林斯顿大学毕业证Princeton毕业证成绩单修改留信学历认证
 
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一
定制昆士兰大学毕业证(本硕)UQ学位证书原版一比一
 
call girls in G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in  G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in  G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in G.T.B. Nagar (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
办理学位证(MLU文凭证书)哈勒 维滕贝格大学毕业证成绩单原版一模一样
 
定制(Plymouth文凭证书)普利茅斯大学毕业证毕业证成绩单学历认证原版一比一
定制(Plymouth文凭证书)普利茅斯大学毕业证毕业证成绩单学历认证原版一比一定制(Plymouth文凭证书)普利茅斯大学毕业证毕业证成绩单学历认证原版一比一
定制(Plymouth文凭证书)普利茅斯大学毕业证毕业证成绩单学历认证原版一比一
 
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGER
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGERUNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGER
UNIT-II-ENGINE AUXILIARY SYSTEMS &TURBOCHARGER
 
Call Girls In Kirti Nagar 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In Kirti Nagar 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICECall Girls In Kirti Nagar 📱  9999965857  🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
Call Girls In Kirti Nagar 📱 9999965857 🤩 Delhi 🫦 HOT AND SEXY VVIP 🍎 SERVICE
 
Dubai Call Girls Size E6 (O525547819) Call Girls In Dubai
Dubai Call Girls  Size E6 (O525547819) Call Girls In DubaiDubai Call Girls  Size E6 (O525547819) Call Girls In Dubai
Dubai Call Girls Size E6 (O525547819) Call Girls In Dubai
 
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop WorkingWhat Could Cause A VW Tiguan's Radiator Fan To Stop Working
What Could Cause A VW Tiguan's Radiator Fan To Stop Working
 
办理埃默里大学毕业证Emory毕业证原版一比一
办理埃默里大学毕业证Emory毕业证原版一比一办理埃默里大学毕业证Emory毕业证原版一比一
办理埃默里大学毕业证Emory毕业证原版一比一
 
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一
定制多伦多大学毕业证(UofT毕业证)成绩单(学位证)原版一比一
 

Manufacturing setup startup after lockdown thought by dhananjay

  • 1. Startup of Factory After Lockdown Process Wise Startup – First & Most important thing is to adhere Guidelines issued by Ministry of Home affairs. safety norms required as per factories act, guidelines , Government regulations , EOHS compliance & applicable regulations in the regions where the location is.
  • 2. Process Wise Startup -Office  Ensure seating arrangement is cleaned properly.  Ensure wiring of computer system is proper.  Update/inline the system with server /Erp after consultation with superiors.  Download mails & arrange properly pending works .  Reply each & every mail .  Make list of work which was in progress when lockdown started & start working on them  Make list of work which was planned in following days from lockdown starts & start working on them.
  • 3.  Ensure Sufficient manpower is available in plant.  Pl communicate with Employees .  Make sure availability of PPE for COVID 19 & applicable PPE for processes.  Skill matrix & available employees to be reviewed.  Communicate with department heads & arrange retraining of employees incase of new process or new employee & wherever required.  Review the statutory & regulatory pending works during lockdown & take on priority. Process Wise Startup – HR
  • 4.  Ensure availability of material which is supposed to received during lockdown period.  Review pending purchase requirements & po. Make action plan.  Communicate with suppliers for availability of required material & inventory at them.  Review supplier evaluation & rating is completed after lockdown.  Review if there any material which is need to be returned or replaced.  Review ISO / IATF/EOHS certification of suppliers are valid.  Make sure that GRN are not pending & bills of accepted material are booked in the system. Process Wise Startup – Purchase
  • 5.  Tally stock of Raw material , Consumable & Maintenance related material .  Ensure shelf life of material is valid.  Ensure there was no mix up in materials.  Ensure all material is in good condition.  Notify to Purchase for Material with less inventory .  Status of material which was in transit when Lockdown started.  Circulate Inventory sheet.  Ensure Weighing balance working properly by self calibration.  Ensure Material issue system & bar code is working properly.  Ensure there is identification on every material  Get checked first few charge before issue from Metallurgy department Process Wise Startup – Stores
  • 6.  Material receipt during lock down is checked & ok for use.  Status of GRN pl complete pending GRN.  Ensure Calibration of Instruments otherwise Notify to calibration dept.  Ensure Shelf life of chemicals prepared for testing.  Check Sand for HTS & lump formation once again. Process Wise Startup – Receiving Inspection
  • 7.  Make schedules considering backlogs & customer demand.  Communicate with Marketing for acceptance of schedules.  Communicate dispatch dates of materials which is not packed to marketing considering all situations happened due to lockdown.  Plan number of resources required to complete the schedule in agreement with production team. Process Wise Startup – PPC
  • 8.  Ensure availability of quality sand.  Ensure machine condition ,air supply , Oiling & Lubrication of machine.  Check sand quality in Hoppers.  Check heaters .  Ensure pattern number as per plan & start production.  Check shells for scratch hardness. Process Wise Startup – Foundry 1) Shell Molding
  • 9. Process Wise Startup – Foundry 1) Melting & Pouring • Ensure availability of proper water pressure & Temp. • Ensure Furnace Lining quality. • Ensure weighing balance calibration. • Ensure Temp stick working properly. • Ensure Hydraulics of furnace working good. • Ensure availability of trolleys. • Ensure Vibrator is working • Ensure all cranes are working. • Ensure Centrifugal machines are running. • Ensure availability of Laddles. • Ensure availability of Fire Extinguishers, check there pressure gauge. • Check status of material produced during lock down start date. Complet route card & production registers.
  • 10.  Ensure Air pressure.  Ensure Alumina sand level  Ensure Quenching oil level.  Ensure all temp indicators are working.  Ensure heating is not abnormal.  Ensure cooling towers working.  Ensure availability of binding wire & hooks, rods & fitures.  Ensure crane is working.  Ensure availability of Fire extinguishers.  Ensure alarms & poka yoke are working.  Check status of material heat treated during lockdown start, check quality of material & if ok complete route card. Process Wise Startup – Heat Treatment
  • 11.  Check spectro, Microscope wiring.  Ensure AC is working.  Ensure availability of Argon gas cylinder.  Start spectro with standard operating procedure.  Ensure spectro & Micro polishing machine is working.  Ensure quality of hardness testing ,check masters & if ok offer for inspection.  Ensure heat treated lots during Lock down start date are checked for Hardness & micro. Process Wise Startup – Metallurgy Lab
  • 12.  Ensure Lubrication & oiling of machine is done.  Ensure tools & grinding wheels ,grinding segments are properly fitted.  Check auto feeder working before starting production.  Ensure coolant level & concentration is correct.  Ensure all required gauges & instruments are in good condition & calibrated before use.  Ensure control plans & family sheet is available on machine.  Start machine as per guidelines in Work instruction.  Check & then Fill up the machine checklist  Ensure machine slides & guide ways are free.  Ensure all pressure gauges are working.  Ensure oil in Hydraulic system.  In first off check 5 parts instead of 1 for first startup.  If any abnormal noise or vibration is observed immediately stop the machine & inform to supervisor & maintenance.  Ensure status of WIP( parts on machine or for machining during lockdown start .Check for quality involve quality person , if ok then only offer for process.  Ensure Route cards are available & filled .  Ensure ERP & Bar coding system functioning correctly. Process Wise Startup – Machine Shop
  • 13.  Ensure all Lights are illuminating properly.  Ensure all Non confirming material is recorded & disposed off.  Ensure MPI machines working properly.  Check Media concentration of MPI , validate pie gauge & if shown ok then start the inspection.  Check shelf life & condition of Zyglo chemicals. Stir well before use.  Recheck the Material in process during lock down.  Ensure all gauges & instruments are in good condition & calibrated before use.  Recheck the material which was pending for packing during lockdown starts.  Ensure Air dryer is working properly.  Recheck unidentified parts & then take action accordingly.  Ensure computer & UPS connections are proper before starting machine.  Ensure calibration status of instruments & Gauges.  Ensure AC working & humidity before starting inspection activity.  Ensure UPS & computer connections of laser marking are proper. Process Wise Startup – Final Inspection & Gauge Room
  • 14.  Check status of material at laser marking .  Ensure packed material in sample for good condition.  Material proven for rust check with large sample size for good condition.  Check material which was in progress during lockdown for rust & mix up.  Check incomplete boxes for mix up.  Ensure Packaging standard is followed as per customer agreement on packed material during lock down starts & startup after lockdown end. Process Wise Startup – Oiling & Packing
  • 15.  Review list of development parts.  Categories the parts as per different stages during lockdown starts.  Make a list of activities which are in progress when lockdown starts or planned in the week & till Ist week of May.  Review the above list & make action plan with responsibility & Target date.  Recheck & confirm the suitability of parts in development WIP for further use.  Make sure availability of Tooling & Gauges which are supposed to come during lock down period.  Update plans accordingly with new dates.  Communicate with customer for samples which are due in lockdown period & feedback of supplied parts which is to be received durig lockdown. Process Wise Startup – Development