UPDATE ON
WHOLESALE WATER SALES
Presentation to the City Council
March 31, 2014
1
Existing Wholesale Customers
2
Existing Wholesale Customers
 Skokie
 Wholesale customer since 1944
 Current contract runs through February 28,
2017
 Current wholesale water rate is $1.02 per
thousand gallons
 Skokie’s water rate to their customers is $4.56
per thousand gallons
3
Existing Wholesale Customers
 Northwest Water Commission
 Executed Water Supply Contract in 1980
 Began providing water in 1985
 Current contract runs through February 28,
2035
 Current wholesale water rate is $0.64 per
thousand gallons
 Customer’s retail rate ranges from $3.48 to
$5.41 per thousand gallons
4
Existing + Potential Wholesale Customers
5
Other North Shore Water Plants
 Wilmette – wholesale supply to Glenview
 Winnetka – wholesale supply to Northfield
 Glencoe – retail only
 Northbrook – retail only
 Highland Park – wholesale supply to Deerfield and
Lincolnshire
 Highwood – retail only
 Lake Forest – retail only
 Lake Bluff – location of CLCJAWA
 North Chicago – retail only
 Waukegan – retail only
 Lake County Public Water District – wholesale supply to
Zion and Winthrop Harbor 6
Wholesale Water Studies Completed To Date
 2012 Transmission Main Study
 Lincolnwood, Niles, Park Ridge, Des Plaines,
Northwest Water Commission, and Northwest
Suburban Municipal Joint Action Water Agency
 2013 Cost of Service Study
 Existing 108 MGD Facility
 Facility expanded to 132 MDG
 Facility expanded to 214 MGD
 2014 Transmission Main Study
 Niles, Park Ridge, Morton Grove, and Glenview
7
2012 Transmission Main Study Findings
Estimated Construction Costs
8
Item
Route A
North
Open Cut
Route B
South
Open Cut
Route C
North
Tunnel
Route D
South
Tunnel
Transmission Main $169,011,400 $157,589,000 $233,553,600 $263,816,000
Lincolnwood
Connection
$ 17,836,500 $ 11,224,000 $ 17,836,500 $ 8,314,500
Niles Connection $ 13,167,500 $ 5,313,000 $ 14,547,500 $ 5,336,000
Park Ridge
Connection
$ 13,052,500 $ 5,324,500 $ 15,536,500 $ 5,324,500
Des Plaines
Connection
$ 19,872,000 $ 1,345,500 $ 20,895,500 $ 3,082,000
NWC Connection $ 2,311,500 $ 47,713,500 $ 48,817,500 $130,881,500
NSMJAWA
Connection
N/A N/A $135,907,000 $ 54,786,000
TOTAL $235,251,400 $228,509,500 $487,094,100 $471,540,500
2012 Transmission Main Study Findings
Projected Wholesale Rates
9
Route B – South Open Cut
Transmission
Main Debt
Service
Evanston
Wholesale
Rate (132
MGD Plant)
Total Rate
per 1,000
gallons
2015
Chicago
Water
Rate
Projected
Annual
Savings
Niles $0.99 $1.13 $2.12 $3.82 $2,308,000
Park Ridge $1.13 $1.13 $2.26 $3.82 $2,095,000
Des Plaines $1.18 $1.14 $2.32 $3.82 $3,269,000
Route D – South Tunnel
Transmission
Main Debt
Service
Evanston
Wholesale
Rate (214
MGD Plant)
Total Rate
per 1,000
gallons
2015
Chicago
Water
Rate
Projected
Annual
Savings
Niles $0.60 $2.14 $2.74 $3.82 $1,466,000
Park Ridge $0.68 $2.14 $2.82 $3.82 $1,343,000
Des Plaines $0.65 $2.24 $2.89 $3.82 $2,027,000
NSMJAWA $0.85 $2.13 $2.98 $3.82 $9,106,000
2012 Transmission Main Study Findings
Projected Wholesale Rates
 Build a transmission main from Evanston’s South
Standpipe to Lincolnwood’s reservoir.
 Lincolnwood’s rate includes costs for Evanston’s
distribution system as well as plant operation.
10
Projected Wholesale Water Rates for Lincolnwood in 2015
Scenario
Transmission
Main Debt
Service
Evanston
Wholesale
Rate
Total Rate
per 1,000
gallons
2015
Chicago
Water Rate
Projected
Annual
Savings
108 MGD Plant $0.45 $2.21 $2.66 $3.82 $741,000
132 MGD Plant $0.45 $2.39 $2.84 $3.82 $626,000
214 MGD Plant $0.45 $2.83 $3.28 $3.82 $345,000
Projected Savings for Lincolnwood
During a 30-Year Contract
 Significant savings potential for Lincolnwood.
 Assume 2% annual increase in Evanston’s
wholesale rate and in Chicago’s water rate.
11
Year
Evanston Wholesale
Rate + Debt Service
Chicago
Water Rate
Annual
Savings
2015 $2.66 $3.82 $741,000
2020 $2.90 $4.22 $843,000
2025 $3.15 $4.66 $965,000
2030 $3.44 $5.15 $1,093,000
2035 $3.29 $5.69 $1,533,000
2040 $3.64 $6.28 $1,687,000
2044 $3.94 $6.80 $1,827,000
Total projected savings over a 30-year contract $35,964,000
2014 Transmission Main Study
(modification of 2012 study)
 Revised customer set
 Niles and Park Ridge (included in 2012 study)
 Morton Grove and Glenview (new)
 Assumes all open cut construction
 Four scenarios
 1 – add Niles and Morton Grove
 2 – Scenario 1 + Park Ridge
 3 – Scenario 2 + Glenview (south alignment)
 4 – Scenario 2 + Glenview (north alignment)
12
2014 Transmission Main Study Findings
Estimated Construction Costs
13
Item Scenario 1 Scenario 2 Scenario 3 Scenario 4
Transmission Main $70,580,000 $79,100,000 $87,000,000 $85,900,000
Morton Grove
Connection
$ 330,000 $ 330,000 $ 330,000 $ 2,440,000
Niles Connection $ 7,490,000 $ 4,720,000 $ 5,410,000 $ 5,410,000
Park Ridge
Connection
N/A $14,030,000 $ 14,030,000 $14,030,000
Glenview
Connection
N/A N/A $36,540,000 $19,140,000
TOTAL $78,400,000 $98,180,000 $143,310,000 $126,920,000
2014 Transmission Main Study Findings
Projected Wholesale Rates
14
Scenario 1
Community
Transmission
Main Debt
Service
Evanston
Wholesale
Rate (108
MGD Plant)
Total Rate
per 1,000
gallons
2015
Chicago
Water
Rate
Projected
Annual
Savings
Morton Grove $2.07 $0.85 $2.92 $3.82 $1,153,000
Niles $2.27 $0.85 $3.12 $3.82 $1,280,000
Scenario 2
Community
Transmission
Main Debt
Service
Evanston
Wholesale
Rate (108
MGD Plant)
Total Rate
per 1,000
gallons
2015
Chicago
Water
Rate
Projected
Annual
Savings
Morton Grove $1.43 $0.80 $2.23 $3.82 $2,043,000
Niles $1.63 $0.80 $2.43 $3.82 $2,531,000
Park Ridge $2.05 $0.80 $2.85 $3.82 $1,748,000
Projected Savings for Potential Wholesale
Customers During a 30-Year Contract
 Assume 2% annual increase in Evanston’s
wholesale rate and in Chicago’s water rate.
15
Projected Annual Savings Under Scenario 2
Year Morton Grove Niles Park Ridge
2015 $2,043,000 $2,531,000 $1,748,000
2020 $2,381,000 $2,927,000 $2,113,000
2025 $2,900,000 $3,555,000 $2,697,000
2030 $3,526,000 $4,301,000 $3,391,000
2035 $6,160,000 $8,171,000 $7,870,000
2040 $6,480,000 $9,072,000 $8,739,000
2044 $7,449,000 $9,880,000 $9,517,000
30-year total $126,188,000 $161,612,000 $141,179,000
Alternate Scenarios for Future Consideration
 2012 and 2014 transmission main studies
assumed new wholesale customers would own
and maintain the transmission main
 Alternative is for Evanston to be the lead agency
for the transmission main
 Could evaluate alternate transmission main
route on Touhy Avenue to Niles and Morton
Grove.
16
Proposed Wholesale Water Rate Structure
AWWA M1 Method
 Appropriate rates will be charged to new wholesale
water customers to recover the capital cost of the
treatment facility expansion (if needed), as well as
operation and maintenance costs.
 American Water Works Association (AWWA) is the
industry standard for rate making
 Principles of Water Rates, Fees, and Charges,
Manual of Water Supply Practices (M1)
 Two Parts
 Demand Charge
 Quantity Charge 17
 NWC & NSMJAWA
 Currently have an RFQ for analysis of options for
Lake Michigan water treatment facility and
delivery system.
 Des Plaines
 Will likely become a member of the NWC
 Glenview
 Currently gets water from Wilmette
 Transmission main cost prohibits them from
coming to Evanston
 Leading study with Niles, Morton Grove and Park
Ridge to obtain water from Wilmette via Glenview18
Current Status Summary
 Niles, Morton Grove and Park Ridge
 Performing due diligence to determine if water supply
from Evanston or Wilmette is better option.
 Capital Cost to construct a new transmission main
while paying Chicago’s high water rate is a burden.
 Would probably be more interested if Evanston
became partner in transmission main construction.
 Lincolnwood
 Waiting to see if other communities come to
Evanston and how it would affect their water
rate.
19
Current Status Summary
UPDATE ON WHOLESALE WATER SALES
Questions?
20

More Related Content

Viewers also liked

Pipeline Analysis Tool
Pipeline Analysis ToolPipeline Analysis Tool
Pipeline Analysis ToolTal Carmi
 
Sales pipeline development
Sales pipeline developmentSales pipeline development
Sales pipeline developmentSwayne Hill
 
Integrated sales pipeline management
Integrated sales pipeline managementIntegrated sales pipeline management
Integrated sales pipeline managementNamkee Chung
 
12 Tips for Building & Managing a Bigger Sales Pipeline
12 Tips for Building & Managing a Bigger Sales Pipeline12 Tips for Building & Managing a Bigger Sales Pipeline
12 Tips for Building & Managing a Bigger Sales PipelineHeinz Marketing Inc
 
Our Company Brochure
Our Company BrochureOur Company Brochure
Our Company Brochurekazrobo
 
Best Practices for Managing Inside Sales with Salesforce.com
Best Practices for Managing Inside Sales with Salesforce.comBest Practices for Managing Inside Sales with Salesforce.com
Best Practices for Managing Inside Sales with Salesforce.comShell Black
 
Is Your Marketing/Sales Pipeline Dysfunctional? Review the 6 Stages
Is Your Marketing/Sales Pipeline Dysfunctional? Review the 6 StagesIs Your Marketing/Sales Pipeline Dysfunctional? Review the 6 Stages
Is Your Marketing/Sales Pipeline Dysfunctional? Review the 6 StagesSurefire Local
 
Download editable sales funnel power point slides and ppt diagram templates
Download editable sales funnel power point slides and ppt diagram templates Download editable sales funnel power point slides and ppt diagram templates
Download editable sales funnel power point slides and ppt diagram templates SlideTeam.net
 
How to Own Your Sales Funnel
How to Own Your Sales FunnelHow to Own Your Sales Funnel
How to Own Your Sales FunnelTrada
 
The Definitive Guide to Sales Pipeline Management
The Definitive Guide to Sales Pipeline ManagementThe Definitive Guide to Sales Pipeline Management
The Definitive Guide to Sales Pipeline ManagementInsightSquared
 

Viewers also liked (10)

Pipeline Analysis Tool
Pipeline Analysis ToolPipeline Analysis Tool
Pipeline Analysis Tool
 
Sales pipeline development
Sales pipeline developmentSales pipeline development
Sales pipeline development
 
Integrated sales pipeline management
Integrated sales pipeline managementIntegrated sales pipeline management
Integrated sales pipeline management
 
12 Tips for Building & Managing a Bigger Sales Pipeline
12 Tips for Building & Managing a Bigger Sales Pipeline12 Tips for Building & Managing a Bigger Sales Pipeline
12 Tips for Building & Managing a Bigger Sales Pipeline
 
Our Company Brochure
Our Company BrochureOur Company Brochure
Our Company Brochure
 
Best Practices for Managing Inside Sales with Salesforce.com
Best Practices for Managing Inside Sales with Salesforce.comBest Practices for Managing Inside Sales with Salesforce.com
Best Practices for Managing Inside Sales with Salesforce.com
 
Is Your Marketing/Sales Pipeline Dysfunctional? Review the 6 Stages
Is Your Marketing/Sales Pipeline Dysfunctional? Review the 6 StagesIs Your Marketing/Sales Pipeline Dysfunctional? Review the 6 Stages
Is Your Marketing/Sales Pipeline Dysfunctional? Review the 6 Stages
 
Download editable sales funnel power point slides and ppt diagram templates
Download editable sales funnel power point slides and ppt diagram templates Download editable sales funnel power point slides and ppt diagram templates
Download editable sales funnel power point slides and ppt diagram templates
 
How to Own Your Sales Funnel
How to Own Your Sales FunnelHow to Own Your Sales Funnel
How to Own Your Sales Funnel
 
The Definitive Guide to Sales Pipeline Management
The Definitive Guide to Sales Pipeline ManagementThe Definitive Guide to Sales Pipeline Management
The Definitive Guide to Sales Pipeline Management
 

Similar to Sp1 water sales update to council mar 31 2014

Apw1 utilities july 22 2013 ws presentation dds final 7.22.13
Apw1 utilities july 22 2013 ws presentation dds final 7.22.13Apw1 utilities july 22 2013 ws presentation dds final 7.22.13
Apw1 utilities july 22 2013 ws presentation dds final 7.22.13cityofevanston
 
Water sales update to council feb 11 2013
Water sales update to council feb 11 2013Water sales update to council feb 11 2013
Water sales update to council feb 11 2013cityofevanston
 
Municipal Budgets, Capital Improvements Planning & Public Funding
Municipal Budgets, Capital Improvements Planning & Public FundingMunicipal Budgets, Capital Improvements Planning & Public Funding
Municipal Budgets, Capital Improvements Planning & Public FundingShaun Wilson
 
WHCRWA 2011 Town Hall Meeting Nov 8, 2011
WHCRWA 2011 Town Hall Meeting Nov 8, 2011WHCRWA 2011 Town Hall Meeting Nov 8, 2011
WHCRWA 2011 Town Hall Meeting Nov 8, 2011The Texas Network, LLC
 
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...Texas Living Waters Project
 
Water Presentation - Jan 30, 2019
Water Presentation - Jan 30, 2019Water Presentation - Jan 30, 2019
Water Presentation - Jan 30, 2019Franklin Matters
 
DS-16-161 Water Reuse Master Plan
DS-16-161 Water Reuse Master PlanDS-16-161 Water Reuse Master Plan
DS-16-161 Water Reuse Master PlanCityofKilleen
 
The municipal partnering initiative 0810 longer
The municipal partnering initiative 0810 longerThe municipal partnering initiative 0810 longer
The municipal partnering initiative 0810 longerDr. Paul Davis
 
Public works presentation 9 30final
Public works presentation 9 30finalPublic works presentation 9 30final
Public works presentation 9 30finalCityofEvanston2
 
Lauren Fahnestock: One Water: Challenges and Opportunities for Water Infrastr...
Lauren Fahnestock: One Water: Challenges and Opportunities for Water Infrastr...Lauren Fahnestock: One Water: Challenges and Opportunities for Water Infrastr...
Lauren Fahnestock: One Water: Challenges and Opportunities for Water Infrastr...Econsult Solutions, Inc.
 
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...San Diego County Water Authority
 
Wastewater Treatment Plant Capacity Report 3-18-2015
Wastewater Treatment Plant Capacity Report 3-18-2015Wastewater Treatment Plant Capacity Report 3-18-2015
Wastewater Treatment Plant Capacity Report 3-18-2015JGNelson
 
Water Management at Rainbow Drive: In Buildotech
Water Management at Rainbow Drive: In BuildotechWater Management at Rainbow Drive: In Buildotech
Water Management at Rainbow Drive: In Buildotechbiomeshubha
 

Similar to Sp1 water sales update to council mar 31 2014 (20)

Apw1 utilities july 22 2013 ws presentation dds final 7.22.13
Apw1 utilities july 22 2013 ws presentation dds final 7.22.13Apw1 utilities july 22 2013 ws presentation dds final 7.22.13
Apw1 utilities july 22 2013 ws presentation dds final 7.22.13
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Water-Wastewater Impact Fees
Water-Wastewater Impact FeesWater-Wastewater Impact Fees
Water-Wastewater Impact Fees
 
Water sales update to council feb 11 2013
Water sales update to council feb 11 2013Water sales update to council feb 11 2013
Water sales update to council feb 11 2013
 
LSL replacement
LSL replacement LSL replacement
LSL replacement
 
Municipal Budgets, Capital Improvements Planning & Public Funding
Municipal Budgets, Capital Improvements Planning & Public FundingMunicipal Budgets, Capital Improvements Planning & Public Funding
Municipal Budgets, Capital Improvements Planning & Public Funding
 
WHCRWA 2011 Town Hall Meeting Nov 8, 2011
WHCRWA 2011 Town Hall Meeting Nov 8, 2011WHCRWA 2011 Town Hall Meeting Nov 8, 2011
WHCRWA 2011 Town Hall Meeting Nov 8, 2011
 
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...
Reducing Long-Term Rate Impacts Through Water Conservation, and Lessons Learn...
 
WHCRWA Town Hall 2012 - Fall
WHCRWA Town Hall 2012 - FallWHCRWA Town Hall 2012 - Fall
WHCRWA Town Hall 2012 - Fall
 
Water Presentation - Jan 30, 2019
Water Presentation - Jan 30, 2019Water Presentation - Jan 30, 2019
Water Presentation - Jan 30, 2019
 
DS-16-161 Water Reuse Master Plan
DS-16-161 Water Reuse Master PlanDS-16-161 Water Reuse Master Plan
DS-16-161 Water Reuse Master Plan
 
The municipal partnering initiative 0810 longer
The municipal partnering initiative 0810 longerThe municipal partnering initiative 0810 longer
The municipal partnering initiative 0810 longer
 
Public works presentation 9 30final
Public works presentation 9 30finalPublic works presentation 9 30final
Public works presentation 9 30final
 
2014 Bond Sale and Re-funding
2014 Bond Sale and Re-funding2014 Bond Sale and Re-funding
2014 Bond Sale and Re-funding
 
Lauren Fahnestock: One Water: Challenges and Opportunities for Water Infrastr...
Lauren Fahnestock: One Water: Challenges and Opportunities for Water Infrastr...Lauren Fahnestock: One Water: Challenges and Opportunities for Water Infrastr...
Lauren Fahnestock: One Water: Challenges and Opportunities for Water Infrastr...
 
Palm Bay Utilities Update
Palm Bay Utilities UpdatePalm Bay Utilities Update
Palm Bay Utilities Update
 
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
Economic Analyses Conducted on the Bay Delta Conservation Plan - David Sung, ...
 
Water Reuse Coalition
Water Reuse CoalitionWater Reuse Coalition
Water Reuse Coalition
 
Wastewater Treatment Plant Capacity Report 3-18-2015
Wastewater Treatment Plant Capacity Report 3-18-2015Wastewater Treatment Plant Capacity Report 3-18-2015
Wastewater Treatment Plant Capacity Report 3-18-2015
 
Water Management at Rainbow Drive: In Buildotech
Water Management at Rainbow Drive: In BuildotechWater Management at Rainbow Drive: In Buildotech
Water Management at Rainbow Drive: In Buildotech
 

More from cityofevanston

SBA & City of Evanston Economic Injury Webinar - 4/1/2020
SBA & City of Evanston Economic Injury Webinar - 4/1/2020SBA & City of Evanston Economic Injury Webinar - 4/1/2020
SBA & City of Evanston Economic Injury Webinar - 4/1/2020cityofevanston
 
Zs city of evanston presentation 28 january 2015
Zs city of evanston presentation 28 january 2015Zs city of evanston presentation 28 january 2015
Zs city of evanston presentation 28 january 2015cityofevanston
 
Human services funding summit jan 27 2015 presentation
Human services funding summit jan 27 2015 presentationHuman services funding summit jan 27 2015 presentation
Human services funding summit jan 27 2015 presentationcityofevanston
 
Age friendlyhealth summit
Age friendlyhealth summitAge friendlyhealth summit
Age friendlyhealth summitcityofevanston
 
Divvy Community Meeting Presentation
Divvy Community Meeting PresentationDivvy Community Meeting Presentation
Divvy Community Meeting Presentationcityofevanston
 
Human services noyes ctr successes 2014
Human services noyes ctr successes 2014Human services noyes ctr successes 2014
Human services noyes ctr successes 2014cityofevanston
 
Leathers & Associates Penny Park Presentation
Leathers & Associates Penny Park PresentationLeathers & Associates Penny Park Presentation
Leathers & Associates Penny Park Presentationcityofevanston
 
Penny Park Renovations
Penny Park RenovationsPenny Park Renovations
Penny Park Renovationscityofevanston
 
Sheridan Road Improvement Project
Sheridan Road Improvement ProjectSheridan Road Improvement Project
Sheridan Road Improvement Projectcityofevanston
 
FY 2014 Second Quarter Financial Review
FY 2014 Second Quarter Financial ReviewFY 2014 Second Quarter Financial Review
FY 2014 Second Quarter Financial Reviewcityofevanston
 
SP1 Second Quarter Financial Review
SP1 Second Quarter Financial ReviewSP1 Second Quarter Financial Review
SP1 Second Quarter Financial Reviewcityofevanston
 
A5 Chicago Ave Project Plan
A5 Chicago Ave Project PlanA5 Chicago Ave Project Plan
A5 Chicago Ave Project Plancityofevanston
 
P1 Sports Dome Planned Development
P1 Sports Dome Planned DevelopmentP1 Sports Dome Planned Development
P1 Sports Dome Planned Developmentcityofevanston
 
Sheridan Road City Council Presentation
Sheridan Road City Council PresentationSheridan Road City Council Presentation
Sheridan Road City Council Presentationcityofevanston
 
Sp1 2013 street resurfacing presentation
Sp1 2013 street resurfacing presentationSp1 2013 street resurfacing presentation
Sp1 2013 street resurfacing presentationcityofevanston
 
Presentation - japanese visitors
Presentation - japanese visitorsPresentation - japanese visitors
Presentation - japanese visitorscityofevanston
 
Evanston committee 3 5-2012
Evanston committee 3 5-2012Evanston committee 3 5-2012
Evanston committee 3 5-2012cityofevanston
 
A8 a10 chicago main intro of ordinances 2012 12/10
A8 a10 chicago main intro of ordinances 2012 12/10A8 a10 chicago main intro of ordinances 2012 12/10
A8 a10 chicago main intro of ordinances 2012 12/10cityofevanston
 
Council meeting 3.20.12 cross fit e-town
Council meeting 3.20.12  cross fit e-townCouncil meeting 3.20.12  cross fit e-town
Council meeting 3.20.12 cross fit e-towncityofevanston
 

More from cityofevanston (20)

SBA & City of Evanston Economic Injury Webinar - 4/1/2020
SBA & City of Evanston Economic Injury Webinar - 4/1/2020SBA & City of Evanston Economic Injury Webinar - 4/1/2020
SBA & City of Evanston Economic Injury Webinar - 4/1/2020
 
Zs city of evanston presentation 28 january 2015
Zs city of evanston presentation 28 january 2015Zs city of evanston presentation 28 january 2015
Zs city of evanston presentation 28 january 2015
 
Human services funding summit jan 27 2015 presentation
Human services funding summit jan 27 2015 presentationHuman services funding summit jan 27 2015 presentation
Human services funding summit jan 27 2015 presentation
 
Age friendlyhealth summit
Age friendlyhealth summitAge friendlyhealth summit
Age friendlyhealth summit
 
Divvy Community Meeting Presentation
Divvy Community Meeting PresentationDivvy Community Meeting Presentation
Divvy Community Meeting Presentation
 
Human services noyes ctr successes 2014
Human services noyes ctr successes 2014Human services noyes ctr successes 2014
Human services noyes ctr successes 2014
 
Hs cagngfrndlyupdte
Hs cagngfrndlyupdteHs cagngfrndlyupdte
Hs cagngfrndlyupdte
 
Leathers & Associates Penny Park Presentation
Leathers & Associates Penny Park PresentationLeathers & Associates Penny Park Presentation
Leathers & Associates Penny Park Presentation
 
Penny Park Renovations
Penny Park RenovationsPenny Park Renovations
Penny Park Renovations
 
Sheridan Road Improvement Project
Sheridan Road Improvement ProjectSheridan Road Improvement Project
Sheridan Road Improvement Project
 
FY 2014 Second Quarter Financial Review
FY 2014 Second Quarter Financial ReviewFY 2014 Second Quarter Financial Review
FY 2014 Second Quarter Financial Review
 
SP1 Second Quarter Financial Review
SP1 Second Quarter Financial ReviewSP1 Second Quarter Financial Review
SP1 Second Quarter Financial Review
 
A5 Chicago Ave Project Plan
A5 Chicago Ave Project PlanA5 Chicago Ave Project Plan
A5 Chicago Ave Project Plan
 
P1 Sports Dome Planned Development
P1 Sports Dome Planned DevelopmentP1 Sports Dome Planned Development
P1 Sports Dome Planned Development
 
Sheridan Road City Council Presentation
Sheridan Road City Council PresentationSheridan Road City Council Presentation
Sheridan Road City Council Presentation
 
Sp1 2013 street resurfacing presentation
Sp1 2013 street resurfacing presentationSp1 2013 street resurfacing presentation
Sp1 2013 street resurfacing presentation
 
Presentation - japanese visitors
Presentation - japanese visitorsPresentation - japanese visitors
Presentation - japanese visitors
 
Evanston committee 3 5-2012
Evanston committee 3 5-2012Evanston committee 3 5-2012
Evanston committee 3 5-2012
 
A8 a10 chicago main intro of ordinances 2012 12/10
A8 a10 chicago main intro of ordinances 2012 12/10A8 a10 chicago main intro of ordinances 2012 12/10
A8 a10 chicago main intro of ordinances 2012 12/10
 
Council meeting 3.20.12 cross fit e-town
Council meeting 3.20.12  cross fit e-townCouncil meeting 3.20.12  cross fit e-town
Council meeting 3.20.12 cross fit e-town
 

Sp1 water sales update to council mar 31 2014

  • 1. UPDATE ON WHOLESALE WATER SALES Presentation to the City Council March 31, 2014 1
  • 3. Existing Wholesale Customers  Skokie  Wholesale customer since 1944  Current contract runs through February 28, 2017  Current wholesale water rate is $1.02 per thousand gallons  Skokie’s water rate to their customers is $4.56 per thousand gallons 3
  • 4. Existing Wholesale Customers  Northwest Water Commission  Executed Water Supply Contract in 1980  Began providing water in 1985  Current contract runs through February 28, 2035  Current wholesale water rate is $0.64 per thousand gallons  Customer’s retail rate ranges from $3.48 to $5.41 per thousand gallons 4
  • 5. Existing + Potential Wholesale Customers 5
  • 6. Other North Shore Water Plants  Wilmette – wholesale supply to Glenview  Winnetka – wholesale supply to Northfield  Glencoe – retail only  Northbrook – retail only  Highland Park – wholesale supply to Deerfield and Lincolnshire  Highwood – retail only  Lake Forest – retail only  Lake Bluff – location of CLCJAWA  North Chicago – retail only  Waukegan – retail only  Lake County Public Water District – wholesale supply to Zion and Winthrop Harbor 6
  • 7. Wholesale Water Studies Completed To Date  2012 Transmission Main Study  Lincolnwood, Niles, Park Ridge, Des Plaines, Northwest Water Commission, and Northwest Suburban Municipal Joint Action Water Agency  2013 Cost of Service Study  Existing 108 MGD Facility  Facility expanded to 132 MDG  Facility expanded to 214 MGD  2014 Transmission Main Study  Niles, Park Ridge, Morton Grove, and Glenview 7
  • 8. 2012 Transmission Main Study Findings Estimated Construction Costs 8 Item Route A North Open Cut Route B South Open Cut Route C North Tunnel Route D South Tunnel Transmission Main $169,011,400 $157,589,000 $233,553,600 $263,816,000 Lincolnwood Connection $ 17,836,500 $ 11,224,000 $ 17,836,500 $ 8,314,500 Niles Connection $ 13,167,500 $ 5,313,000 $ 14,547,500 $ 5,336,000 Park Ridge Connection $ 13,052,500 $ 5,324,500 $ 15,536,500 $ 5,324,500 Des Plaines Connection $ 19,872,000 $ 1,345,500 $ 20,895,500 $ 3,082,000 NWC Connection $ 2,311,500 $ 47,713,500 $ 48,817,500 $130,881,500 NSMJAWA Connection N/A N/A $135,907,000 $ 54,786,000 TOTAL $235,251,400 $228,509,500 $487,094,100 $471,540,500
  • 9. 2012 Transmission Main Study Findings Projected Wholesale Rates 9 Route B – South Open Cut Transmission Main Debt Service Evanston Wholesale Rate (132 MGD Plant) Total Rate per 1,000 gallons 2015 Chicago Water Rate Projected Annual Savings Niles $0.99 $1.13 $2.12 $3.82 $2,308,000 Park Ridge $1.13 $1.13 $2.26 $3.82 $2,095,000 Des Plaines $1.18 $1.14 $2.32 $3.82 $3,269,000 Route D – South Tunnel Transmission Main Debt Service Evanston Wholesale Rate (214 MGD Plant) Total Rate per 1,000 gallons 2015 Chicago Water Rate Projected Annual Savings Niles $0.60 $2.14 $2.74 $3.82 $1,466,000 Park Ridge $0.68 $2.14 $2.82 $3.82 $1,343,000 Des Plaines $0.65 $2.24 $2.89 $3.82 $2,027,000 NSMJAWA $0.85 $2.13 $2.98 $3.82 $9,106,000
  • 10. 2012 Transmission Main Study Findings Projected Wholesale Rates  Build a transmission main from Evanston’s South Standpipe to Lincolnwood’s reservoir.  Lincolnwood’s rate includes costs for Evanston’s distribution system as well as plant operation. 10 Projected Wholesale Water Rates for Lincolnwood in 2015 Scenario Transmission Main Debt Service Evanston Wholesale Rate Total Rate per 1,000 gallons 2015 Chicago Water Rate Projected Annual Savings 108 MGD Plant $0.45 $2.21 $2.66 $3.82 $741,000 132 MGD Plant $0.45 $2.39 $2.84 $3.82 $626,000 214 MGD Plant $0.45 $2.83 $3.28 $3.82 $345,000
  • 11. Projected Savings for Lincolnwood During a 30-Year Contract  Significant savings potential for Lincolnwood.  Assume 2% annual increase in Evanston’s wholesale rate and in Chicago’s water rate. 11 Year Evanston Wholesale Rate + Debt Service Chicago Water Rate Annual Savings 2015 $2.66 $3.82 $741,000 2020 $2.90 $4.22 $843,000 2025 $3.15 $4.66 $965,000 2030 $3.44 $5.15 $1,093,000 2035 $3.29 $5.69 $1,533,000 2040 $3.64 $6.28 $1,687,000 2044 $3.94 $6.80 $1,827,000 Total projected savings over a 30-year contract $35,964,000
  • 12. 2014 Transmission Main Study (modification of 2012 study)  Revised customer set  Niles and Park Ridge (included in 2012 study)  Morton Grove and Glenview (new)  Assumes all open cut construction  Four scenarios  1 – add Niles and Morton Grove  2 – Scenario 1 + Park Ridge  3 – Scenario 2 + Glenview (south alignment)  4 – Scenario 2 + Glenview (north alignment) 12
  • 13. 2014 Transmission Main Study Findings Estimated Construction Costs 13 Item Scenario 1 Scenario 2 Scenario 3 Scenario 4 Transmission Main $70,580,000 $79,100,000 $87,000,000 $85,900,000 Morton Grove Connection $ 330,000 $ 330,000 $ 330,000 $ 2,440,000 Niles Connection $ 7,490,000 $ 4,720,000 $ 5,410,000 $ 5,410,000 Park Ridge Connection N/A $14,030,000 $ 14,030,000 $14,030,000 Glenview Connection N/A N/A $36,540,000 $19,140,000 TOTAL $78,400,000 $98,180,000 $143,310,000 $126,920,000
  • 14. 2014 Transmission Main Study Findings Projected Wholesale Rates 14 Scenario 1 Community Transmission Main Debt Service Evanston Wholesale Rate (108 MGD Plant) Total Rate per 1,000 gallons 2015 Chicago Water Rate Projected Annual Savings Morton Grove $2.07 $0.85 $2.92 $3.82 $1,153,000 Niles $2.27 $0.85 $3.12 $3.82 $1,280,000 Scenario 2 Community Transmission Main Debt Service Evanston Wholesale Rate (108 MGD Plant) Total Rate per 1,000 gallons 2015 Chicago Water Rate Projected Annual Savings Morton Grove $1.43 $0.80 $2.23 $3.82 $2,043,000 Niles $1.63 $0.80 $2.43 $3.82 $2,531,000 Park Ridge $2.05 $0.80 $2.85 $3.82 $1,748,000
  • 15. Projected Savings for Potential Wholesale Customers During a 30-Year Contract  Assume 2% annual increase in Evanston’s wholesale rate and in Chicago’s water rate. 15 Projected Annual Savings Under Scenario 2 Year Morton Grove Niles Park Ridge 2015 $2,043,000 $2,531,000 $1,748,000 2020 $2,381,000 $2,927,000 $2,113,000 2025 $2,900,000 $3,555,000 $2,697,000 2030 $3,526,000 $4,301,000 $3,391,000 2035 $6,160,000 $8,171,000 $7,870,000 2040 $6,480,000 $9,072,000 $8,739,000 2044 $7,449,000 $9,880,000 $9,517,000 30-year total $126,188,000 $161,612,000 $141,179,000
  • 16. Alternate Scenarios for Future Consideration  2012 and 2014 transmission main studies assumed new wholesale customers would own and maintain the transmission main  Alternative is for Evanston to be the lead agency for the transmission main  Could evaluate alternate transmission main route on Touhy Avenue to Niles and Morton Grove. 16
  • 17. Proposed Wholesale Water Rate Structure AWWA M1 Method  Appropriate rates will be charged to new wholesale water customers to recover the capital cost of the treatment facility expansion (if needed), as well as operation and maintenance costs.  American Water Works Association (AWWA) is the industry standard for rate making  Principles of Water Rates, Fees, and Charges, Manual of Water Supply Practices (M1)  Two Parts  Demand Charge  Quantity Charge 17
  • 18.  NWC & NSMJAWA  Currently have an RFQ for analysis of options for Lake Michigan water treatment facility and delivery system.  Des Plaines  Will likely become a member of the NWC  Glenview  Currently gets water from Wilmette  Transmission main cost prohibits them from coming to Evanston  Leading study with Niles, Morton Grove and Park Ridge to obtain water from Wilmette via Glenview18 Current Status Summary
  • 19.  Niles, Morton Grove and Park Ridge  Performing due diligence to determine if water supply from Evanston or Wilmette is better option.  Capital Cost to construct a new transmission main while paying Chicago’s high water rate is a burden.  Would probably be more interested if Evanston became partner in transmission main construction.  Lincolnwood  Waiting to see if other communities come to Evanston and how it would affect their water rate. 19 Current Status Summary
  • 20. UPDATE ON WHOLESALE WATER SALES Questions? 20