3. What is SMV???
Standard time of a average worker will take to do a job.
In idle environment in predetermined speed a general
operator needs time to do a process.
SMV=Standard Minute Value
SMV = Cycle time + allowances
Allowances = personal + machine+ bundle handling
Personal 2%
Machine O/L = 10%, SN = 3%, FL = 8%
Bundle = 2%
4. TARGET CALCULATION
TARGET FOR A LINE = M/P X W/H X 60 X 100%
SMV
SUPPOSE, LINE 25+26 (MIKE BOXER)
SMV=5.97, W/H=11,M/P=26
SO…. TARGET AT 100% EFF = (60/5.97) X 11 X 26
=2874 PCS
TARGET AT 55% EFF = 2874 X 0.55=1581 PCS
5. Output x SMV
Efficiency =
Total M/P x W/H x 60
X 100%
2000 x 7.07
Efficiency =
32 x 11 x 60
14140
=
21120
X
100%
= 0.6695 X 100%
= 66.95%
X
100%
Example
6. 1. If Manpower decrease Then efficiency increase.
2. If output Increase Then efficiency increase.
3. If Working Hour decrease with same output then efficiency increase.
3
7. Productivity is a measure of economic performance that compares the amount of goods and
services produced (output) with the amount of inputs used to produce those goods and services.
What do we mean by productivity?
8. productivity is the quantity of work produced by a team, business or individual. Efficiency,
on the other hand, refers to the resources used to produce that work.
9.
10. Line balancing is a production strategy that involves balancing operator and machine time to
match the production rate to the takt time.
What is meant by line balancing?
11.
12. What is Bottleneck in garments?
The lowest output point in the production line is called a bottleneck.
15. Line Feeding Activity
Next
Feeding
( Before
Two Days)
Pre Setting
( Before
one Days)
Today
Feeding
( QCO)
1st 30 hrs.
Production
Monitoring
Day to Day
Activity.
16. Next Feeding ( Before Two Days) Activity
Machine
(Attachment)
Manpower
Operator
Training
Skill
Allocation
17. Pre Setting ( Before one Days)
Running
Style
Status.
Setup
Feeding
Plan.
20. Today Feeding ( QCO)
Standard Method & Standard Workplace need to be ensure.
Set the operation according to skill allocation.
Make sure standard quality.
Calculate Total Feeding Time.
21. QCO
Quick Change Over (QCO) is a set of activities (preparation, changing and adjustment) which are being
carried out in between the production of two varieties to reduce changeover time and to reach the
optimum production running.
22. 1st 30 hrs. Production Monitoring
1.Check Hourly Production Achievement
2.Ensure the Product Quality
3.Check Capacity Study
4.Re-Balance the line .
23. Day to Day Activity.
1. To make Line Re-Balance
2. Proper manpower Allocation
3. Forecast according to plan
4. Operation improved
5. Efficiency Achieve.