ROOFING ANALYSIS OF PRICES BQS458
CLAY ROOF TILES
NO OF TILES & LENGTH OF BATTEN
NAILS AND LABOR OUTPUT
CONCRETE ROOF TILES
ROOF COVERING
CORRUGATED ASBESTOS FREE CEMENT ROOFING SHEET
 Corrugated small sheet
 Corrugated small standard sheet
 Corrugated large sheet
 Corrugated large sheet Big Six
 Corrugated large angle sheet
STEEL ROOF SHEET
WASTAGE PERCENTAGE
TYPE OF ROOF SHEET
WIDTH
(mm)
SIDE LAPS
(mm)
NETT WIDTH
(mm)
WASTAGE RATE
%
Corrugated small sheet 738 98 640 28.00
Corrugated small standard sheet 762 114 648 30.43
Corrugated large sheet 1075 75 1000 19.67
Corrugated large sheet Big Six 1086 52 1034 17.03
Corrugated large angle sheet 1100 100 1000 22.33
FORMULAE TO CALCULATE PERCENTAGE OF LAPS AND
WASTAGE
Standard sheeting size = 2400mm long x 762mm wide
Head laps = 150mm
Side laps = 114mm
Sheet area = 2.40 x 0.762 = 1.8288 m2
Enclosure area = (2.40 – 0.15) x (0.762 – 0.114) = 1.458m2
Percentage laps = 1.8288m2 – 1.458m2 x 100 =25.43%
1.458m2
Percentage wastage = 5.00%
= 30.43%
Standard
length
Standard width
sides laps
Standard
length
Standard width
Head laps
sides laps
LABOUR OUTPUT TO FIX ASBESTOS FREE CEMENT & STEEL
ROOF SHEET
Maximum roof sheet
length (mm)
1 roofer and 1 unskilled labour(Hr/m2)
Small piece Large piece
1200 0.22 0.19
1800 0.2 0.17
2400 0.18 0.16
3000 0.17 0.15
END OF LECTURE

More Related Content

Similar to bumbung.pdf

Similar to bumbung.pdf (20)

Rubri New type MgO / Fiber cement board
Rubri New type MgO / Fiber cement board Rubri New type MgO / Fiber cement board
Rubri New type MgO / Fiber cement board
 
ACE305: Aircraft Components Design and Manufacture
ACE305: Aircraft Components Design and ManufactureACE305: Aircraft Components Design and Manufacture
ACE305: Aircraft Components Design and Manufacture
 
Standard plank for wood lamination on khaya ivorensis
Standard plank for wood lamination on khaya ivorensisStandard plank for wood lamination on khaya ivorensis
Standard plank for wood lamination on khaya ivorensis
 
phase 2ppt.pptx
phase 2ppt.pptxphase 2ppt.pptx
phase 2ppt.pptx
 
Taber Extrusions Sales Presentation
Taber Extrusions Sales PresentationTaber Extrusions Sales Presentation
Taber Extrusions Sales Presentation
 
Coates Hire - Trench Shoring Solutions
Coates Hire - Trench Shoring SolutionsCoates Hire - Trench Shoring Solutions
Coates Hire - Trench Shoring Solutions
 
2nd Presentation NAME 338
2nd Presentation NAME 3382nd Presentation NAME 338
2nd Presentation NAME 338
 
Attaching Cladding with Long Screws
Attaching Cladding with Long ScrewsAttaching Cladding with Long Screws
Attaching Cladding with Long Screws
 
Attaching Cladding with Long Screws
Attaching Cladding with Long ScrewsAttaching Cladding with Long Screws
Attaching Cladding with Long Screws
 
CATALOGE-PP AQUATECH.jpg
CATALOGE-PP AQUATECH.jpgCATALOGE-PP AQUATECH.jpg
CATALOGE-PP AQUATECH.jpg
 
NAME 338 , Presentation 1
NAME 338 , Presentation 1NAME 338 , Presentation 1
NAME 338 , Presentation 1
 
8 months work
8 months work8 months work
8 months work
 
Empire Series Enclosures
Empire Series EnclosuresEmpire Series Enclosures
Empire Series Enclosures
 
Presentation.pptx
Presentation.pptxPresentation.pptx
Presentation.pptx
 
2021 Product Catalogue.pdf
2021 Product Catalogue.pdf2021 Product Catalogue.pdf
2021 Product Catalogue.pdf
 
Street Lighting Polypipe Cable Duct
Street Lighting Polypipe Cable DuctStreet Lighting Polypipe Cable Duct
Street Lighting Polypipe Cable Duct
 
Brochure ENG (1)
Brochure ENG (1)Brochure ENG (1)
Brochure ENG (1)
 
NBC_Brochure(GB).pdf
NBC_Brochure(GB).pdfNBC_Brochure(GB).pdf
NBC_Brochure(GB).pdf
 
MDSI Series 30 Product Data Sheet
MDSI Series 30 Product Data SheetMDSI Series 30 Product Data Sheet
MDSI Series 30 Product Data Sheet
 
Productblad_aluland_Plates_ENG
Productblad_aluland_Plates_ENGProductblad_aluland_Plates_ENG
Productblad_aluland_Plates_ENG
 

More from Aisyah Asyikin (7)

Week 7_estimation in construction works.pdf
Week 7_estimation in construction works.pdfWeek 7_estimation in construction works.pdf
Week 7_estimation in construction works.pdf
 
ONG NOTES
ONG NOTESONG NOTES
ONG NOTES
 
Roofing.pptx
Roofing.pptxRoofing.pptx
Roofing.pptx
 
Week 7 - Woodworks.pdf
Week 7 - Woodworks.pdfWeek 7 - Woodworks.pdf
Week 7 - Woodworks.pdf
 
MAINTENANCE MANAGEMENT.ppt.pdf
MAINTENANCE MANAGEMENT.ppt.pdfMAINTENANCE MANAGEMENT.ppt.pdf
MAINTENANCE MANAGEMENT.ppt.pdf
 
OFFSHORE PLATFORM_1.ppt (1).pdf
OFFSHORE PLATFORM_1.ppt (1).pdfOFFSHORE PLATFORM_1.ppt (1).pdf
OFFSHORE PLATFORM_1.ppt (1).pdf
 
industrialised building systems_achah
industrialised building systems_achahindustrialised building systems_achah
industrialised building systems_achah
 

Recently uploaded

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
MayuraD1
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
AldoGarca30
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 

Recently uploaded (20)

Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
DeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakesDeepFakes presentation : brief idea of DeepFakes
DeepFakes presentation : brief idea of DeepFakes
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Computer Networks Basics of Network Devices
Computer Networks  Basics of Network DevicesComputer Networks  Basics of Network Devices
Computer Networks Basics of Network Devices
 
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
457503602-5-Gas-Well-Testing-and-Analysis-pptx.pptx
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...Basic Electronics for diploma students as per technical education Kerala Syll...
Basic Electronics for diploma students as per technical education Kerala Syll...
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Signal Processing and Linear System Analysis
Signal Processing and Linear System AnalysisSignal Processing and Linear System Analysis
Signal Processing and Linear System Analysis
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
1_Introduction + EAM Vocabulary + how to navigate in EAM.pdf
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 

bumbung.pdf

  • 1. ROOFING ANALYSIS OF PRICES BQS458
  • 3. NO OF TILES & LENGTH OF BATTEN
  • 4.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12. ROOF COVERING CORRUGATED ASBESTOS FREE CEMENT ROOFING SHEET  Corrugated small sheet  Corrugated small standard sheet  Corrugated large sheet  Corrugated large sheet Big Six  Corrugated large angle sheet STEEL ROOF SHEET
  • 13.
  • 14. WASTAGE PERCENTAGE TYPE OF ROOF SHEET WIDTH (mm) SIDE LAPS (mm) NETT WIDTH (mm) WASTAGE RATE % Corrugated small sheet 738 98 640 28.00 Corrugated small standard sheet 762 114 648 30.43 Corrugated large sheet 1075 75 1000 19.67 Corrugated large sheet Big Six 1086 52 1034 17.03 Corrugated large angle sheet 1100 100 1000 22.33
  • 15. FORMULAE TO CALCULATE PERCENTAGE OF LAPS AND WASTAGE Standard sheeting size = 2400mm long x 762mm wide Head laps = 150mm Side laps = 114mm Sheet area = 2.40 x 0.762 = 1.8288 m2 Enclosure area = (2.40 – 0.15) x (0.762 – 0.114) = 1.458m2 Percentage laps = 1.8288m2 – 1.458m2 x 100 =25.43% 1.458m2 Percentage wastage = 5.00% = 30.43%
  • 17. LABOUR OUTPUT TO FIX ASBESTOS FREE CEMENT & STEEL ROOF SHEET Maximum roof sheet length (mm) 1 roofer and 1 unskilled labour(Hr/m2) Small piece Large piece 1200 0.22 0.19 1800 0.2 0.17 2400 0.18 0.16 3000 0.17 0.15
  • 18.