SlideShare a Scribd company logo
1 of 37
PLANNING, ANALYSIS, DESIGN
AND ESTIMATION OF G+5
RESIDENTIAL APARTMENT
Guide by:
Dr.R. Saraswathi M.E.,Ph.D.,
Submitted by:
CHANDRU V (1901008)
DHINAKARAN M (1901012)
MATHAN KUMAR M (1901034)
YOGESHWARAN S (1901055)
Content
 Architectural plans
 Electrical Layout
 Plumbing Layout
 Design and Detailing of slab
 Manual 2D Frame Analysis
 Software 2D Frame Analysis
 Comparison of 2D Frame Analysis Results
2
3
Architectural plans
4
Design of one way slab:
1
Shorter span (lx) 1600mm
Longer span(ly) 4190mm
characteristic strength of concrete(fck) 20N/mm2
yield stress(fy) 415N/mm2
cover 20mm
dia of bar 10mm
live load 3KN/m2
breadth(b) 1m
wall thickness(wt) 230mm
modification factor 1.2
effective depth ratio 26
fos 1.5
2TYPE OF SLAB
ly/lx 2.62
one way
3THICKNESS OF SLAB
Calculated depth 75mm d 75mm
Assumed Depth D 150mm D 150
Effective depth d 125
Design of one way slab:
5
4EFFECTIVE LENGTH
leff1 clear span + effective depth 1725mm
leff2
c/c distance between
supports 1830mm
leff 1725mm Leff 1725mm
5LOAD CALCULATION
dead load
self weigth 3.75
Floor finish(FF) 1
total dl 4.75
factored dead load 7.125 F. DL 7.125KN/m2
live load 3
factored live load 4.5 F. LL 4.5KN/m2
Total load 11.625KN/m2
6CALCULATION OF BENDING MOMENT
Span BM end(+ve) 1.04KN
Support BM end(-ve) -0.98KN
Span BM mid (+ve) 0.82KN
Support BM mid (-ve) -1.09KN
Bending moment +ve 3.09KNm
Bending moment -ve 2.92KNm 3.09KNm
Design of one way slab:
6
7CHECK FOR EFFECTIVE DEPTH
dep required 50mm
dreq< dprov hence ok check for depth hence ok
8Ast CALCULATION
Ast required
Mu/(0.87*fy*) 8571.25c
Ast -125b
Ast^2 0.02075a
b^2-4ac 14913.59
SQRT(*b^2-4ac) 122.12
Ast 5954.73
69.37
min ast 180
max ast 6000
ast 180mm2
check hence ok check for ast hence ok
spacing 300mm
Design of one way slab:
7
Mu/(0.87*fy*) 8076.76c
Ast -125b Distribution steel:
Ast^2 0.02075a
b^2-4ac 14954.63 min ast 180
SQRT(*b^2-4ac) 122.29 Spacing 279
Ast 5958.77
65.32
min ast 180
max ast 6000
ast 180.00mm2
check hence ok % M20
spacing 300mm 0.15 0.28
Ast provided (∏/4*d^2*1000)/spacing 262mm2 0.17
0.32
check hence ok check for ast hence ok 0.25 0.48
9CHECK FOR SHEAR
Vu 10.03
Ʈv Vu/b*D 0.07
percentage of steel 100*ast/b*D 0.17
Ʈc 0.32
Ʈc max 2.8
check hence ok check for shear hence ok
Design of one way slab:
8
10CHECK FOR DEFLECTION
fs 165.58
kt 1.6
kc 1
kf 1
actual deflection 21.33
permissible deflection 41.6
check hence ok check for deflection hence ok
Provide
Provide 10mm dia bars at 300mm c/c distance along shorter direction at middle span as main reinforcemnet
& 10mm dia bars at 300mm c/c at supports.
Provide 8mm dia bars at 275 mm c/c distance as distribution steel along longer direction
Detailing of one way slab:
9
Design of two way slab:
10
DESIGN OF SLAB:(s4 one long edge discontinuous)
1BASIC DATA :
ly 6.63m fy 415.00N/mm2
lx 5.11m fck 20.00N/mm2
Thickness of support 230mm
Clear cover 20mm
2TYPE OF SLAB :
Span Ratio 1.30 LESS THAN 2
Therefore Design the slab as two way slab
3DEPTH :
Depth 110.00mm
Assumed depth 150mm
Effective Depth 124mm
4EFFECTIVE SPAN :
For lx
a)C/C between Supports 5.34m As per IS 456:2000
b)Clear Span + Eff. depth 5.23m
cl 22.2, pg-34
lxeff 5.23m
Design of two way slab:
11
4EFFECTIVE SPAN :
For lx
a)C/C between Supports 5.34m As per IS 456:2000
b)
Clear Span + Eff.
depth
5.23m
cl 22.2, pg-34
lxeff 5.23m
For ly
a)C/C between Supports 6.86m
b)
Clear Span + Eff.
depth
6.75m
lyeff 6.75m
5LOAD CALCULATION :
Dead Load 3.75kN/m As per IS 875-2 1987
Live Load 3kN/m cl 23.2.1, pg-37
Floor Finish 1kN/m
Total Load 7.75kN/m
Design of two way slab:
12
Design Load 7.75kN/m
Factored Load 11.625kN/m ly/lx Positive moment αx ly/lx Negative moment αx
1.2 0.0390 1.2 0.0520
6CALCULATION OF COEFFICIENTS : 1.29 0.0553 1.29 0.0565
lx/ly 1.29 1.3 0.0570 1.3 0.0570
Positive moment αx 0.0553
Negative moment αx 0.0565
Positive moment αy 0.028
Negative moment αy 0.0370
7CALCULATION OF BENDING MOMENTS :
Mux(+ve) 16.78KNm
Mux(-ve) 17.16KNm
Muy(+ve) 8.50KNm
Muy(-ve) 11.23KNm
7CHECK FOR DEPTH :
Mumax 17.16KNm
dreq 78.84mm
Check dreq < dprovided
If not
increase
thedepth
Design of two way slab:
13
8AREA OF REINFORCEMENT REQUIRED :
a)
AREA OF STEEL ALONG SHORTER DIRECTION (mid span)
Mu=0.87*fy*Ast*(d-(Ast*fy)/(b*fck))
Mu/(0.87*fy*) 46471.333c
Ast -124b
Ast^2 0.0207500a
b^2-4ac 11518.879
SQRT(*b^2-4ac) 107.326
Ast 5574.122
401.78
Ast minimum 180mm2
Ast required 401.78mm2
Spacing 195mm Using 10 mm dia
Provided Spacing 190mm
Ast provided 413mm2
Therefore provide 10 mm dia at 190 mm c/c in shorter direction mid span
Design of two way slab:
14
b)AREA OF STEEL ALONG SHORTER DIRECTION (edge)
Mu=0.87*fy*Ast*(d-(Ast*fy)/(b*fck))
Mu/(0.87*fy) 47519.621c
Ast -124b
Ast^2 0.0207500a
b^2-4ac 11431.871
SQRT(*b^2-4ac) 106.920
Ast 5564.336
411.57
Ast minimum 180mm2
Ast required 411.57mm2 Astreq < Astmin
Spacing 436mm Using 10 mm dia
Provided Spacing 300mm
Ast provided 262mm2
Therefore provide 10mm dia at 300mm c/c in shorter direction supports
Design of two way slab:
15
c)
AREA OF STEEL ALONG LONGER DIRECTION (mid span)
Mu=0.87*fy*Ast*(d-(Ast*fy)/(b*fck))
Mu/(0.87*fy*) 23541.029c
Ast -124b
Ast^2 0.0207500a
b^2-4ac 13422.095
SQRT(*b^2-4ac) 115.854
Ast 5779.609
196.29
Ast minimum 180mm2
Ast required 196.29mm2
Spacing 400mm Using 10 mm dia
Provided Spacing 300mm
Ast provided 262mm2
Therefore provide 10 mm dia at 300 mm c/c in longer direction mid span
Design of two way slab:
16
c)
AREA OF STEEL ALONG LONGER DIRECTION (edge)
Mu=0.87*fy*Ast*(d-(Ast*fy)/(b*fck))
Mu/(0.87*fy*) 31107.788c
Ast -124b
Ast^2 0.0207500a
b^2-4ac 12794.054
SQRT(*b^2-4ac) 113.111
Ast 5713.513
262.39
Ast minimum 180mm2
Ast required 262.39mm2
Spacing 299mm Using 10 mm dia
Provided Spacing 290mm
Ast provided 271mm2
Therefore provide 10 mm dia at 290 mm c/c in longer direction supports
Design of two way slab:
17
9CHECK FOR SHEAR :
Vu=W*Lx/2 29.70KN
τv=Vu/b*d 0.24N/mm2
For τc % M20
Pt 0.33% 0.25 0.28
τc 0.31 0.33 0.31
K 1.3 0.5 0.36
K*τc 0.39861N/mm2
For τcmax
τcmax 2.80N/mm2
τv < K*τc < τcmax Hence safe in shear.
10
CHECK FOR
DEFLECTION :
Permissible l/d=M*26 46.80
Actual l/d 34.07
Hence safe in deflection
Design of two way slab:
18
11Torsional Reinforcement
3/4 of Ast at midspan 301.34mm2
Use 8 mm bars
No of bars 6nos
Length of Reinforcement lx/5
1.02m
The Reinforcement mesh should beprovided at top and bottom
of the slab at corners
Mesh size is 1.05m X 1.05m
Detailing of two way slab:
19
Detailing of two way slab:
20
Reinforcement details:
21
Slab ly lx ly/lx End condition Reinforcement
S1 5.11 3.58 1.43 Two adjacen edges are discontinuous
provide 10 mm dia at 300 mm c/c in mid span of shorter direction
provide 10mm dia at 300mm c/c in supports of shorter direction
provide 10 mm dia at 300 mm c/c in mid span of longer direction
provide 10 mm dia at 300 mm c/c in supports of longer direction
S2 5.11 3.58 1.43 Two adjacen edges are discontinuous
provide 10 mm dia at 300 mm c/c in mid span of shorter direction
provide 10mm dia at 300mm c/c in supports of shorter direction
provide 10 mm dia at 300 mm c/c in mid span of longer direction
provide 10 mm dia at 300 mm c/c in supports of longer direction
S3 5.11 4.19 1.22 Interior panel
provide 10 mm dia at 300 mm c/c in mid span of shorter direction
provide 10mm dia at 300mm c/c in supports of shorter direction
provide 10 mm dia at 300 mm c/c in mid span of longer direction
provide 10 mm dia at 300 mm c/c in supports of longer direction
S4 6.63 5.11 1.30 one long edge discontinuous
provide 10 mm dia at 190 mm c/c in mid span of shorter direction
provide 10mm dia at 300mm c/c in supports of shorter direction
provide 10 mm dia at 300 mm c/c in mid span of longer direction
provide 10 mm dia at 290 mm c/c in supports of longer direction
S5 6.63 5.11 1.30 Interior panel
provide 10 mm dia at 300 mm c/c in mid span of shorter direction
provide 10mm dia at 300mm c/c in supports of shorter direction
provide 10 mm dia at 300 mm c/c in mid span of longer direction
provide 10 mm dia at 300 mm c/c in supports of longer direction
Reinforcement details:
22
S6 5.11 5.11 1.00 Two adjacen edges are discontinuous
provide 10 mm dia at 300 mm c/c in mid span of shorter direction
provide 10mm dia at 300mm c/c in supports of shorter direction
provide 10 mm dia at 300 mm c/c in mid span of longer direction
provide 10 mm dia at 230 mm c/c in supports of longer direction
S7 5.11 5.11 1.00 one short edge discontinuous
provide 10 mm dia at 300 mm c/c in mid span of shorter direction
provide 10mm dia at 300mm c/c in supports of shorter direction
provide 10 mm dia at 300 mm c/c in mid span of longer direction
provide 10 mm dia at 275 mm c/c in supports of longer direction
S8 4.19 2.25 1.86 Interior panel
provide 10 mm dia at 300 mm c/c in mid span of shorter direction
provide 10mm dia at 300mm c/c in supports of shorter direction
provide 10 mm dia at 300 mm c/c in mid span of longer direction
provide 10 mm dia at 300 mm c/c in supports of longer direction
S9 5.11 3.58 1.43 one long edge discontinuous
provide 10 mm dia at 300 mm c/c in mid span of shorter direction
provide 10mm dia at 300mm c/c in supports of shorter direction
provide 10 mm dia at 300 mm c/c in mid span of longer direction
provide 10 mm dia at 300 mm c/c in supports of longer direction
S10 4.19 1.6 2.62 End span continous
Provide 10mm dia bars at 300mm c/c distance along shorter direction at middle span as main
reinforcement
provide 10mm dia at 300mm c/c in supports
Provide 8mm dia bars at 275 mm c/c distance as distribution steel along longer direction
S11 5.11 1.33 3.84 End span continous
Provide 10mm dia bars at 300mm c/c distance along shorter direction at middle span as main
reinforcement
provide 10mm dia at 300mm c/c in supports
Provide 8mm dia bars at 275 mm c/c distance as distribution steel along longer direction
Reinforcement details:
23
S12 7.16 1.6 4.48 End span continous
Provide 10mm dia bars at 300mm c/c distance along shorter direction at middle span as main
reinforcement
provide 10mm dia at 300mm c/c in supports
Provide 8mm dia bars at 275 mm c/c distance as distribution steel along longer direction
S13 15.32 1.6 9.58 End span continous
Provide 10mm dia bars at 300mm c/c distance along shorter direction at middle span as main
reinforcement
provide 10mm dia at 300mm c/c in supports
Provide 8mm dia bars at 275 mm c/c distance as distribution steel along longer direction
Manual 2D Frame Analysis
Selected Beam for Analysis
24
Manual 2D Frame Analysis
Substitute Frame for
Manual Analysis
25
Load Calculation:
26
Manual 2D Frame Analysis
S1b TRAPEZOIDAL LOAD TRAPEZOIDAL LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD
dead load (KN/m) live load (KN/m) (KN/m) (KN/m) (KN/m) (KN/m)
(wlx/2)*(1-0.5/k) (wlx/2)*(1-0.5/k) h*t*20 b*d*25*l
8.3 5.3 12.65 2.59 23.51 28.76
S1c TRAPEZOIDAL LOAD TRAPEZOIDAL LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD
dead load(KN/m) live load(KN/m) (KN/m) (KN/m) (KN/m) (KN/m)
(wlx/2)*(1-0.5/k) (wlx/2)*(1-0.5/k) h*t*20 b*d*25*l
8.2 5.2 12.65 2.59 23.44 28.62
S1a TRAPEZOIDAL LOAD TRAPEZOIDAL LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD
dead load(KN/m) live load(KN/m) (KN/m) (KN/m) (KN/m) (KN/m)
(wlx/2)*(1-0.5/k) (wlx/2)*(1-0.5/k) h*t*20 b*d*25*l
8.2 5.2 12.65 2.59 23.44 28.67
Manual 2D Frame Analysis
27
S1 TRAPEZOIDAL LOAD TRAPEZOIDAL LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD
dead load(KN/m) live load(KN/m) (KN/m) (KN/m) (KN/m) (KN/m)
(wlx/2)*(1-0.5/k) (wlx/2)*(1-0.5/k) h*t*20 b*d*25*l
9.6 5.6 12.65 2.59 24.83 30.40
S4
RECTANGULAR
LOAD
RECTANGULAR
LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD
dead load(KN/m) live load(KN/m) (KN/m) (KN/m) (KN/m) (KN/m)
Wlx/2 Wlx/2 h*t*20 b*d*25*l
4.7 4.5 12.65 2.59 19.98 24.48
S5 POINT LOAD POINT LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD
wl/2 (KN) wl/2 (KN) (KN/m) (KN/m)
DL LL h*t*20 b*d*25*l
11.9 9.4 12.65 2.59
Manual 2D Frame Analysis
Loading diagram
28
Manual 2D Frame Analysis
By Substitute Frame Method,
29
FIXED END MOMENTS:
DL TL
MAB -94.46kNm -115.645kNm
MBA 94.46kNm 115.64kNm
MBC -105.18kNm -128.72kNm
MCB 105.18kNm -105.18kNm
MCD -97.27kNm -244.24kNm
MDC 97.27kNm 244.24kNm
MDE -105.04kNm -128.53kNm
MED 105.04kNm 128.53kNm
MEF -94.46kNm -115.64kNm
MFE 94.46kNm 115.64kNm
Manual 2D Frame Analysis
Distribution Factor:
30
Joint Member Relative
Stiffness
Sum of
Stiffness
Distribution
factor
A
AB 0.196
0.821
0.238
AG 0.313 0.381
AH 0.313 0.381
B
BA 0.196
1.016
0.193
BI 0.313 0.307
BJ 0.313 0.307
BC 0.196 0.193
C
CB 0.196
1.020
0.192
CK 0.313 0.307
CL 0.313 0.307
CD 0.199 0.195
D
DC 0.199
1.020
0.195
DM 0.313 0.307
DN 0.313 0.307
DE 0.196 0.192
E
ED 0.196
1.016
0.193
EO 0.313 0.307
EP 0.313 0.307
EF 0.196 0.193
F
FE 0.196
0.821
0.238
FQ 0.313 0.381
FR 0.313 0.381
Manual 2D Frame Analysis
Calculation of final moment at Ends:
31
13.03 0.097
At A, 10.46 7.91
At span AB LL is added 13.03 -0.25
Joint A B C
Members AG AH AB BA BI BJ BC CB CK CL CD
D.F. 0.381 0.381 0.238 0.193 0.307 0.307 0.193 0.192 0.307 0.195 0.195
FEM -115.645 115.645 -105.185 105.185 -97.27
Balancing 44.035 44.035 27.575 -2.014 -3.216 -3.216 -2.014 -1.519 -2.426 -1.543 -1.54
C.O. -1.007 13.788 -0.759 -1.007 0.76
balancing 0.383 0.383 0.240 -2.508 -4.006 -4.006 -2.508 0.048 0.077 0.049 0.05
CO -1.254 0.120 0.024 -1.254 0.174
Balancing 0.48 0.478 0.299 -1.564 -13.028 -1.564 -1.564 0.121 0.121 0.121 0.12
Final moments 44.896 44.896 -89.791 123.466 -20.250 -8.786 -112.007 101.574 -2.228 -1.373 -97.713
Manual 2D Frame Analysis
32
0.69 4.05
-7.76 10.57
-1.79 -10.52
D E F
DC DM DN DE ED EO EP EF FE FQ FR
0.195 0.307 0.307 0.192 0.193 0.307 0.307 0.193 0.238 0.381 0.381
97.27 -105.04 105.04 -94.46 94.46
1.51 2.38 2.38 1.49 -2.04 -3.25 -3.25 -2.04 -22.53 -35.97 -35.97
-0.77 -1.02 0.75 -11.26 -1.02
0.35 0.55 0.55 0.34 2.03 3.23 3.23 2.03 0.24 0.39 0.39
0.024 1.013 0.172 0.121 1.013
-0.02 -0.02 -0.02 -0.02 -0.70 -0.70 -0.70 -0.70 -0.25 -0.39 -0.39
98.370 2.911 2.911 -103.224 105.246 -0.712 -0.712 -106.312 71.932 -35.975 -35.975
Software 2D Frame Analysis using
STAADPRO
Intermediate Frame Loading Diagram
33
Software 2D Frame Analysis using
STAADPRO
Bending Moment Diagram
34
Software 2D Frame Analysis using
STAADPRO
Substitute frame Loading Diagram
Software 2D Frame Analysis using
STAADPRO
Bending Moment Diagram
36
THANK
YOU
37

More Related Content

Similar to phase 2ppt.pptx

Heron, vol 50, no 2 (2005)
Heron, vol 50, no 2 (2005)Heron, vol 50, no 2 (2005)
Heron, vol 50, no 2 (2005)Ab van den Bos
 
Bulb Flats Brochure
Bulb Flats BrochureBulb Flats Brochure
Bulb Flats BrochureMike Nielsen
 
Structural engineering and irrigation drawing.pptx
Structural engineering and irrigation drawing.pptxStructural engineering and irrigation drawing.pptx
Structural engineering and irrigation drawing.pptxSTRUCTURALDYNAMICS
 
onw way slab design
onw way slab designonw way slab design
onw way slab designPalak Patel
 
Clt mtb seminar_presentation_five
Clt mtb seminar_presentation_fiveClt mtb seminar_presentation_five
Clt mtb seminar_presentation_fiveFWPA
 
Lecture-7-Detailing-PHG-A1-Rev-10-2-Nov-16-Print.pptx
Lecture-7-Detailing-PHG-A1-Rev-10-2-Nov-16-Print.pptxLecture-7-Detailing-PHG-A1-Rev-10-2-Nov-16-Print.pptx
Lecture-7-Detailing-PHG-A1-Rev-10-2-Nov-16-Print.pptxAbelMulugeta8
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxRajeshKumar25548
 
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN Approved
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN ApprovedNexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN Approved
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN ApprovedThorne & Derrick International
 
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN Approved
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN ApprovedNexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN Approved
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN ApprovedThorne & Derrick International
 
A COMPARATIVE STUDY ON RIGID CONNECTION DESIGN OF FRAMED MULTI STOREYED STEEL...
A COMPARATIVE STUDY ON RIGID CONNECTION DESIGN OF FRAMED MULTI STOREYED STEEL...A COMPARATIVE STUDY ON RIGID CONNECTION DESIGN OF FRAMED MULTI STOREYED STEEL...
A COMPARATIVE STUDY ON RIGID CONNECTION DESIGN OF FRAMED MULTI STOREYED STEEL...IRJET Journal
 
IRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET Journal
 
Hospital Building(PPT).pptx
Hospital Building(PPT).pptxHospital Building(PPT).pptx
Hospital Building(PPT).pptxRajeshKumar25548
 
PVC Catalogue pdf of ACL Cables . Industriapower
PVC Catalogue pdf of ACL Cables . IndustriapowerPVC Catalogue pdf of ACL Cables . Industriapower
PVC Catalogue pdf of ACL Cables . Industriapowermbharindra
 
Ship design project &amp; presentation 3
Ship design project &amp;  presentation 3Ship design project &amp;  presentation 3
Ship design project &amp; presentation 3Kifayath Chowdhury
 
Design of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxDesign of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxSharpEyu
 
M2 cv-rc-d-005(anchor bolt details)
M2 cv-rc-d-005(anchor bolt details)M2 cv-rc-d-005(anchor bolt details)
M2 cv-rc-d-005(anchor bolt details)neeraj dubey
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumIRJET Journal
 
Design-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdfDesign-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdfAsifHameed33
 

Similar to phase 2ppt.pptx (20)

Heron, vol 50, no 2 (2005)
Heron, vol 50, no 2 (2005)Heron, vol 50, no 2 (2005)
Heron, vol 50, no 2 (2005)
 
Rc detailing-to-ec2
Rc detailing-to-ec2Rc detailing-to-ec2
Rc detailing-to-ec2
 
Bulb Flats Brochure
Bulb Flats BrochureBulb Flats Brochure
Bulb Flats Brochure
 
Two-Way Floor Slab
Two-Way Floor SlabTwo-Way Floor Slab
Two-Way Floor Slab
 
Structural engineering and irrigation drawing.pptx
Structural engineering and irrigation drawing.pptxStructural engineering and irrigation drawing.pptx
Structural engineering and irrigation drawing.pptx
 
onw way slab design
onw way slab designonw way slab design
onw way slab design
 
Clt mtb seminar_presentation_five
Clt mtb seminar_presentation_fiveClt mtb seminar_presentation_five
Clt mtb seminar_presentation_five
 
Lecture-7-Detailing-PHG-A1-Rev-10-2-Nov-16-Print.pptx
Lecture-7-Detailing-PHG-A1-Rev-10-2-Nov-16-Print.pptxLecture-7-Detailing-PHG-A1-Rev-10-2-Nov-16-Print.pptx
Lecture-7-Detailing-PHG-A1-Rev-10-2-Nov-16-Print.pptx
 
New Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptxNew Microsoft PowerPoint Presentation.pptx
New Microsoft PowerPoint Presentation.pptx
 
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN Approved
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN ApprovedNexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN Approved
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN Approved
 
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN Approved
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN ApprovedNexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN Approved
Nexans 11kV Single Core XLPE Cables (300mm2 Cu) UKPN Approved
 
A COMPARATIVE STUDY ON RIGID CONNECTION DESIGN OF FRAMED MULTI STOREYED STEEL...
A COMPARATIVE STUDY ON RIGID CONNECTION DESIGN OF FRAMED MULTI STOREYED STEEL...A COMPARATIVE STUDY ON RIGID CONNECTION DESIGN OF FRAMED MULTI STOREYED STEEL...
A COMPARATIVE STUDY ON RIGID CONNECTION DESIGN OF FRAMED MULTI STOREYED STEEL...
 
IRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line SystemIRJET- Design of the Support Structure for the Pipe Line System
IRJET- Design of the Support Structure for the Pipe Line System
 
Hospital Building(PPT).pptx
Hospital Building(PPT).pptxHospital Building(PPT).pptx
Hospital Building(PPT).pptx
 
PVC Catalogue pdf of ACL Cables . Industriapower
PVC Catalogue pdf of ACL Cables . IndustriapowerPVC Catalogue pdf of ACL Cables . Industriapower
PVC Catalogue pdf of ACL Cables . Industriapower
 
Ship design project &amp; presentation 3
Ship design project &amp;  presentation 3Ship design project &amp;  presentation 3
Ship design project &amp; presentation 3
 
Design of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptxDesign of composite steel and concrete structures.pptx
Design of composite steel and concrete structures.pptx
 
M2 cv-rc-d-005(anchor bolt details)
M2 cv-rc-d-005(anchor bolt details)M2 cv-rc-d-005(anchor bolt details)
M2 cv-rc-d-005(anchor bolt details)
 
Design of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an AuditoriumDesign of Steel Grillage Foundation for an Auditorium
Design of Steel Grillage Foundation for an Auditorium
 
Design-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdfDesign-Of-concrete-Structure MCQ.pdf
Design-Of-concrete-Structure MCQ.pdf
 

Recently uploaded

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

phase 2ppt.pptx

  • 1. PLANNING, ANALYSIS, DESIGN AND ESTIMATION OF G+5 RESIDENTIAL APARTMENT Guide by: Dr.R. Saraswathi M.E.,Ph.D., Submitted by: CHANDRU V (1901008) DHINAKARAN M (1901012) MATHAN KUMAR M (1901034) YOGESHWARAN S (1901055)
  • 2. Content  Architectural plans  Electrical Layout  Plumbing Layout  Design and Detailing of slab  Manual 2D Frame Analysis  Software 2D Frame Analysis  Comparison of 2D Frame Analysis Results 2
  • 4. 4 Design of one way slab: 1 Shorter span (lx) 1600mm Longer span(ly) 4190mm characteristic strength of concrete(fck) 20N/mm2 yield stress(fy) 415N/mm2 cover 20mm dia of bar 10mm live load 3KN/m2 breadth(b) 1m wall thickness(wt) 230mm modification factor 1.2 effective depth ratio 26 fos 1.5 2TYPE OF SLAB ly/lx 2.62 one way 3THICKNESS OF SLAB Calculated depth 75mm d 75mm Assumed Depth D 150mm D 150 Effective depth d 125
  • 5. Design of one way slab: 5 4EFFECTIVE LENGTH leff1 clear span + effective depth 1725mm leff2 c/c distance between supports 1830mm leff 1725mm Leff 1725mm 5LOAD CALCULATION dead load self weigth 3.75 Floor finish(FF) 1 total dl 4.75 factored dead load 7.125 F. DL 7.125KN/m2 live load 3 factored live load 4.5 F. LL 4.5KN/m2 Total load 11.625KN/m2 6CALCULATION OF BENDING MOMENT Span BM end(+ve) 1.04KN Support BM end(-ve) -0.98KN Span BM mid (+ve) 0.82KN Support BM mid (-ve) -1.09KN Bending moment +ve 3.09KNm Bending moment -ve 2.92KNm 3.09KNm
  • 6. Design of one way slab: 6 7CHECK FOR EFFECTIVE DEPTH dep required 50mm dreq< dprov hence ok check for depth hence ok 8Ast CALCULATION Ast required Mu/(0.87*fy*) 8571.25c Ast -125b Ast^2 0.02075a b^2-4ac 14913.59 SQRT(*b^2-4ac) 122.12 Ast 5954.73 69.37 min ast 180 max ast 6000 ast 180mm2 check hence ok check for ast hence ok spacing 300mm
  • 7. Design of one way slab: 7 Mu/(0.87*fy*) 8076.76c Ast -125b Distribution steel: Ast^2 0.02075a b^2-4ac 14954.63 min ast 180 SQRT(*b^2-4ac) 122.29 Spacing 279 Ast 5958.77 65.32 min ast 180 max ast 6000 ast 180.00mm2 check hence ok % M20 spacing 300mm 0.15 0.28 Ast provided (∏/4*d^2*1000)/spacing 262mm2 0.17 0.32 check hence ok check for ast hence ok 0.25 0.48 9CHECK FOR SHEAR Vu 10.03 Ʈv Vu/b*D 0.07 percentage of steel 100*ast/b*D 0.17 Ʈc 0.32 Ʈc max 2.8 check hence ok check for shear hence ok
  • 8. Design of one way slab: 8 10CHECK FOR DEFLECTION fs 165.58 kt 1.6 kc 1 kf 1 actual deflection 21.33 permissible deflection 41.6 check hence ok check for deflection hence ok Provide Provide 10mm dia bars at 300mm c/c distance along shorter direction at middle span as main reinforcemnet & 10mm dia bars at 300mm c/c at supports. Provide 8mm dia bars at 275 mm c/c distance as distribution steel along longer direction
  • 9. Detailing of one way slab: 9
  • 10. Design of two way slab: 10 DESIGN OF SLAB:(s4 one long edge discontinuous) 1BASIC DATA : ly 6.63m fy 415.00N/mm2 lx 5.11m fck 20.00N/mm2 Thickness of support 230mm Clear cover 20mm 2TYPE OF SLAB : Span Ratio 1.30 LESS THAN 2 Therefore Design the slab as two way slab 3DEPTH : Depth 110.00mm Assumed depth 150mm Effective Depth 124mm 4EFFECTIVE SPAN : For lx a)C/C between Supports 5.34m As per IS 456:2000 b)Clear Span + Eff. depth 5.23m cl 22.2, pg-34 lxeff 5.23m
  • 11. Design of two way slab: 11 4EFFECTIVE SPAN : For lx a)C/C between Supports 5.34m As per IS 456:2000 b) Clear Span + Eff. depth 5.23m cl 22.2, pg-34 lxeff 5.23m For ly a)C/C between Supports 6.86m b) Clear Span + Eff. depth 6.75m lyeff 6.75m 5LOAD CALCULATION : Dead Load 3.75kN/m As per IS 875-2 1987 Live Load 3kN/m cl 23.2.1, pg-37 Floor Finish 1kN/m Total Load 7.75kN/m
  • 12. Design of two way slab: 12 Design Load 7.75kN/m Factored Load 11.625kN/m ly/lx Positive moment αx ly/lx Negative moment αx 1.2 0.0390 1.2 0.0520 6CALCULATION OF COEFFICIENTS : 1.29 0.0553 1.29 0.0565 lx/ly 1.29 1.3 0.0570 1.3 0.0570 Positive moment αx 0.0553 Negative moment αx 0.0565 Positive moment αy 0.028 Negative moment αy 0.0370 7CALCULATION OF BENDING MOMENTS : Mux(+ve) 16.78KNm Mux(-ve) 17.16KNm Muy(+ve) 8.50KNm Muy(-ve) 11.23KNm 7CHECK FOR DEPTH : Mumax 17.16KNm dreq 78.84mm Check dreq < dprovided If not increase thedepth
  • 13. Design of two way slab: 13 8AREA OF REINFORCEMENT REQUIRED : a) AREA OF STEEL ALONG SHORTER DIRECTION (mid span) Mu=0.87*fy*Ast*(d-(Ast*fy)/(b*fck)) Mu/(0.87*fy*) 46471.333c Ast -124b Ast^2 0.0207500a b^2-4ac 11518.879 SQRT(*b^2-4ac) 107.326 Ast 5574.122 401.78 Ast minimum 180mm2 Ast required 401.78mm2 Spacing 195mm Using 10 mm dia Provided Spacing 190mm Ast provided 413mm2 Therefore provide 10 mm dia at 190 mm c/c in shorter direction mid span
  • 14. Design of two way slab: 14 b)AREA OF STEEL ALONG SHORTER DIRECTION (edge) Mu=0.87*fy*Ast*(d-(Ast*fy)/(b*fck)) Mu/(0.87*fy) 47519.621c Ast -124b Ast^2 0.0207500a b^2-4ac 11431.871 SQRT(*b^2-4ac) 106.920 Ast 5564.336 411.57 Ast minimum 180mm2 Ast required 411.57mm2 Astreq < Astmin Spacing 436mm Using 10 mm dia Provided Spacing 300mm Ast provided 262mm2 Therefore provide 10mm dia at 300mm c/c in shorter direction supports
  • 15. Design of two way slab: 15 c) AREA OF STEEL ALONG LONGER DIRECTION (mid span) Mu=0.87*fy*Ast*(d-(Ast*fy)/(b*fck)) Mu/(0.87*fy*) 23541.029c Ast -124b Ast^2 0.0207500a b^2-4ac 13422.095 SQRT(*b^2-4ac) 115.854 Ast 5779.609 196.29 Ast minimum 180mm2 Ast required 196.29mm2 Spacing 400mm Using 10 mm dia Provided Spacing 300mm Ast provided 262mm2 Therefore provide 10 mm dia at 300 mm c/c in longer direction mid span
  • 16. Design of two way slab: 16 c) AREA OF STEEL ALONG LONGER DIRECTION (edge) Mu=0.87*fy*Ast*(d-(Ast*fy)/(b*fck)) Mu/(0.87*fy*) 31107.788c Ast -124b Ast^2 0.0207500a b^2-4ac 12794.054 SQRT(*b^2-4ac) 113.111 Ast 5713.513 262.39 Ast minimum 180mm2 Ast required 262.39mm2 Spacing 299mm Using 10 mm dia Provided Spacing 290mm Ast provided 271mm2 Therefore provide 10 mm dia at 290 mm c/c in longer direction supports
  • 17. Design of two way slab: 17 9CHECK FOR SHEAR : Vu=W*Lx/2 29.70KN τv=Vu/b*d 0.24N/mm2 For τc % M20 Pt 0.33% 0.25 0.28 τc 0.31 0.33 0.31 K 1.3 0.5 0.36 K*τc 0.39861N/mm2 For τcmax τcmax 2.80N/mm2 τv < K*τc < τcmax Hence safe in shear. 10 CHECK FOR DEFLECTION : Permissible l/d=M*26 46.80 Actual l/d 34.07 Hence safe in deflection
  • 18. Design of two way slab: 18 11Torsional Reinforcement 3/4 of Ast at midspan 301.34mm2 Use 8 mm bars No of bars 6nos Length of Reinforcement lx/5 1.02m The Reinforcement mesh should beprovided at top and bottom of the slab at corners Mesh size is 1.05m X 1.05m
  • 19. Detailing of two way slab: 19
  • 20. Detailing of two way slab: 20
  • 21. Reinforcement details: 21 Slab ly lx ly/lx End condition Reinforcement S1 5.11 3.58 1.43 Two adjacen edges are discontinuous provide 10 mm dia at 300 mm c/c in mid span of shorter direction provide 10mm dia at 300mm c/c in supports of shorter direction provide 10 mm dia at 300 mm c/c in mid span of longer direction provide 10 mm dia at 300 mm c/c in supports of longer direction S2 5.11 3.58 1.43 Two adjacen edges are discontinuous provide 10 mm dia at 300 mm c/c in mid span of shorter direction provide 10mm dia at 300mm c/c in supports of shorter direction provide 10 mm dia at 300 mm c/c in mid span of longer direction provide 10 mm dia at 300 mm c/c in supports of longer direction S3 5.11 4.19 1.22 Interior panel provide 10 mm dia at 300 mm c/c in mid span of shorter direction provide 10mm dia at 300mm c/c in supports of shorter direction provide 10 mm dia at 300 mm c/c in mid span of longer direction provide 10 mm dia at 300 mm c/c in supports of longer direction S4 6.63 5.11 1.30 one long edge discontinuous provide 10 mm dia at 190 mm c/c in mid span of shorter direction provide 10mm dia at 300mm c/c in supports of shorter direction provide 10 mm dia at 300 mm c/c in mid span of longer direction provide 10 mm dia at 290 mm c/c in supports of longer direction S5 6.63 5.11 1.30 Interior panel provide 10 mm dia at 300 mm c/c in mid span of shorter direction provide 10mm dia at 300mm c/c in supports of shorter direction provide 10 mm dia at 300 mm c/c in mid span of longer direction provide 10 mm dia at 300 mm c/c in supports of longer direction
  • 22. Reinforcement details: 22 S6 5.11 5.11 1.00 Two adjacen edges are discontinuous provide 10 mm dia at 300 mm c/c in mid span of shorter direction provide 10mm dia at 300mm c/c in supports of shorter direction provide 10 mm dia at 300 mm c/c in mid span of longer direction provide 10 mm dia at 230 mm c/c in supports of longer direction S7 5.11 5.11 1.00 one short edge discontinuous provide 10 mm dia at 300 mm c/c in mid span of shorter direction provide 10mm dia at 300mm c/c in supports of shorter direction provide 10 mm dia at 300 mm c/c in mid span of longer direction provide 10 mm dia at 275 mm c/c in supports of longer direction S8 4.19 2.25 1.86 Interior panel provide 10 mm dia at 300 mm c/c in mid span of shorter direction provide 10mm dia at 300mm c/c in supports of shorter direction provide 10 mm dia at 300 mm c/c in mid span of longer direction provide 10 mm dia at 300 mm c/c in supports of longer direction S9 5.11 3.58 1.43 one long edge discontinuous provide 10 mm dia at 300 mm c/c in mid span of shorter direction provide 10mm dia at 300mm c/c in supports of shorter direction provide 10 mm dia at 300 mm c/c in mid span of longer direction provide 10 mm dia at 300 mm c/c in supports of longer direction S10 4.19 1.6 2.62 End span continous Provide 10mm dia bars at 300mm c/c distance along shorter direction at middle span as main reinforcement provide 10mm dia at 300mm c/c in supports Provide 8mm dia bars at 275 mm c/c distance as distribution steel along longer direction S11 5.11 1.33 3.84 End span continous Provide 10mm dia bars at 300mm c/c distance along shorter direction at middle span as main reinforcement provide 10mm dia at 300mm c/c in supports Provide 8mm dia bars at 275 mm c/c distance as distribution steel along longer direction
  • 23. Reinforcement details: 23 S12 7.16 1.6 4.48 End span continous Provide 10mm dia bars at 300mm c/c distance along shorter direction at middle span as main reinforcement provide 10mm dia at 300mm c/c in supports Provide 8mm dia bars at 275 mm c/c distance as distribution steel along longer direction S13 15.32 1.6 9.58 End span continous Provide 10mm dia bars at 300mm c/c distance along shorter direction at middle span as main reinforcement provide 10mm dia at 300mm c/c in supports Provide 8mm dia bars at 275 mm c/c distance as distribution steel along longer direction
  • 24. Manual 2D Frame Analysis Selected Beam for Analysis 24
  • 25. Manual 2D Frame Analysis Substitute Frame for Manual Analysis 25
  • 26. Load Calculation: 26 Manual 2D Frame Analysis S1b TRAPEZOIDAL LOAD TRAPEZOIDAL LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD dead load (KN/m) live load (KN/m) (KN/m) (KN/m) (KN/m) (KN/m) (wlx/2)*(1-0.5/k) (wlx/2)*(1-0.5/k) h*t*20 b*d*25*l 8.3 5.3 12.65 2.59 23.51 28.76 S1c TRAPEZOIDAL LOAD TRAPEZOIDAL LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD dead load(KN/m) live load(KN/m) (KN/m) (KN/m) (KN/m) (KN/m) (wlx/2)*(1-0.5/k) (wlx/2)*(1-0.5/k) h*t*20 b*d*25*l 8.2 5.2 12.65 2.59 23.44 28.62 S1a TRAPEZOIDAL LOAD TRAPEZOIDAL LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD dead load(KN/m) live load(KN/m) (KN/m) (KN/m) (KN/m) (KN/m) (wlx/2)*(1-0.5/k) (wlx/2)*(1-0.5/k) h*t*20 b*d*25*l 8.2 5.2 12.65 2.59 23.44 28.67
  • 27. Manual 2D Frame Analysis 27 S1 TRAPEZOIDAL LOAD TRAPEZOIDAL LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD dead load(KN/m) live load(KN/m) (KN/m) (KN/m) (KN/m) (KN/m) (wlx/2)*(1-0.5/k) (wlx/2)*(1-0.5/k) h*t*20 b*d*25*l 9.6 5.6 12.65 2.59 24.83 30.40 S4 RECTANGULAR LOAD RECTANGULAR LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD dead load(KN/m) live load(KN/m) (KN/m) (KN/m) (KN/m) (KN/m) Wlx/2 Wlx/2 h*t*20 b*d*25*l 4.7 4.5 12.65 2.59 19.98 24.48 S5 POINT LOAD POINT LOAD WALL LOAD SELFWEIGHT OF BEAM TOTAL DL TOTAL LOAD wl/2 (KN) wl/2 (KN) (KN/m) (KN/m) DL LL h*t*20 b*d*25*l 11.9 9.4 12.65 2.59
  • 28. Manual 2D Frame Analysis Loading diagram 28
  • 29. Manual 2D Frame Analysis By Substitute Frame Method, 29 FIXED END MOMENTS: DL TL MAB -94.46kNm -115.645kNm MBA 94.46kNm 115.64kNm MBC -105.18kNm -128.72kNm MCB 105.18kNm -105.18kNm MCD -97.27kNm -244.24kNm MDC 97.27kNm 244.24kNm MDE -105.04kNm -128.53kNm MED 105.04kNm 128.53kNm MEF -94.46kNm -115.64kNm MFE 94.46kNm 115.64kNm
  • 30. Manual 2D Frame Analysis Distribution Factor: 30 Joint Member Relative Stiffness Sum of Stiffness Distribution factor A AB 0.196 0.821 0.238 AG 0.313 0.381 AH 0.313 0.381 B BA 0.196 1.016 0.193 BI 0.313 0.307 BJ 0.313 0.307 BC 0.196 0.193 C CB 0.196 1.020 0.192 CK 0.313 0.307 CL 0.313 0.307 CD 0.199 0.195 D DC 0.199 1.020 0.195 DM 0.313 0.307 DN 0.313 0.307 DE 0.196 0.192 E ED 0.196 1.016 0.193 EO 0.313 0.307 EP 0.313 0.307 EF 0.196 0.193 F FE 0.196 0.821 0.238 FQ 0.313 0.381 FR 0.313 0.381
  • 31. Manual 2D Frame Analysis Calculation of final moment at Ends: 31 13.03 0.097 At A, 10.46 7.91 At span AB LL is added 13.03 -0.25 Joint A B C Members AG AH AB BA BI BJ BC CB CK CL CD D.F. 0.381 0.381 0.238 0.193 0.307 0.307 0.193 0.192 0.307 0.195 0.195 FEM -115.645 115.645 -105.185 105.185 -97.27 Balancing 44.035 44.035 27.575 -2.014 -3.216 -3.216 -2.014 -1.519 -2.426 -1.543 -1.54 C.O. -1.007 13.788 -0.759 -1.007 0.76 balancing 0.383 0.383 0.240 -2.508 -4.006 -4.006 -2.508 0.048 0.077 0.049 0.05 CO -1.254 0.120 0.024 -1.254 0.174 Balancing 0.48 0.478 0.299 -1.564 -13.028 -1.564 -1.564 0.121 0.121 0.121 0.12 Final moments 44.896 44.896 -89.791 123.466 -20.250 -8.786 -112.007 101.574 -2.228 -1.373 -97.713
  • 32. Manual 2D Frame Analysis 32 0.69 4.05 -7.76 10.57 -1.79 -10.52 D E F DC DM DN DE ED EO EP EF FE FQ FR 0.195 0.307 0.307 0.192 0.193 0.307 0.307 0.193 0.238 0.381 0.381 97.27 -105.04 105.04 -94.46 94.46 1.51 2.38 2.38 1.49 -2.04 -3.25 -3.25 -2.04 -22.53 -35.97 -35.97 -0.77 -1.02 0.75 -11.26 -1.02 0.35 0.55 0.55 0.34 2.03 3.23 3.23 2.03 0.24 0.39 0.39 0.024 1.013 0.172 0.121 1.013 -0.02 -0.02 -0.02 -0.02 -0.70 -0.70 -0.70 -0.70 -0.25 -0.39 -0.39 98.370 2.911 2.911 -103.224 105.246 -0.712 -0.712 -106.312 71.932 -35.975 -35.975
  • 33. Software 2D Frame Analysis using STAADPRO Intermediate Frame Loading Diagram 33
  • 34. Software 2D Frame Analysis using STAADPRO Bending Moment Diagram 34
  • 35. Software 2D Frame Analysis using STAADPRO Substitute frame Loading Diagram
  • 36. Software 2D Frame Analysis using STAADPRO Bending Moment Diagram 36