2. Kohinoor group established in 1961.
The founder of kohinoor group is Mr. Manohar Joshi Sir.
The chairman & managing director of kohinoor group is Mr. Unmesh Joshi sir.
Kohinoor group is divided into different sectors.
Such as education, hospitality, healthcare & real estate.
Kohinoor Planet Constructions Private Limited comes under the real estate sector.
Real estate sector is combination of constructions section, regulatory affairs section, & MEP
section.
Kohinoor business has grown into a well-diversified, multi-activity, multi-location group.
The Group believes in growing perpetually by empowering its students, employees,
customers, partners, associates, stakeholders and, most of all, society at large.
Kohinoor’s businesses are purported to fulfill important human needs – education,
comfortable living, gastronomic needs and healthcare.
Main office of kohinoor group is in Dadar .
3. Project Site name: -kohinoor city phase 2
Address:- kohinoor city, phase 2,kirol road, off LBS marg, Kurla (west).
developer : kohinoor group
Name of owner:- Mr.unmesh Joshi
Project architect: Shirke& associates.
Structural Consultant : mone& associates
Total Value of Project : 3oo Crores
Total area: 36 Acres (whole kohinoor city)
No of Block : 2blocks contains 12 buildings, each blocks contains 6 buildings.
No of Dwelling Unit: 415
Type of Structure : residential building, 2 basements+ ground floor+10
Date of Commencement :-30 june2010
Date of Endup:- 30 march 2018
AGM(constructions):- Mr. Santosh shingare sir
AGM(MEP):-Mr. Shailesh naik sir
Project manager(constructions):- Mr.Anil bhosle sir
Project manager(MEP):-Mr.Sunil mali sir
Building contains:- 2BHK,3BHK,Penthouse,& duplex.
First to seventh floors having 2BHK flats.
Eighth &ninth floor having 3BHK flat+ duplex +refuse area.
Tenth floor having penthouse.
Cost of 2BHK & 3BHK approx. 2crores to 4 crores.
Cost of duplex& penthouse approx. 5crores to 9crores.
Green building concept used in construction. Such as Solar panels, STP Plant etc.
13. Layout of Columns :-
Check the location of columns from
the datum location. If any
deficiency take place within
permissible limits, made
adjustments accordingly, otherwise
reconstruction of column is done.
Filling of Starters :-
Starters makes the actual
positions for const. of column.
made of mortar or lean
concrete. Thickness varies
from 4-6mm. Make the base
to shuttering
14. Reinforcement of Columns :-
Reinforcement is done as per
given in drawings. Check
should be made to the splice
length. As the lateral ties
spacing varies along the
length of column hence
spacing should be properly
maintained
Shuttering of columns :-
Shuttering is either made of wooden
or steel.(Preferably steel). Verticality
of shuttering could be checked by
using plumb bob and thread. Cover
block must be provided for better
finishing of column
15. Concreting and curing :-
Casting of column is done by
boom placer. Vibrator should
be used for compaction and
finishing purpose. Shuttering
of column is removed after 3
days. Curing of column ids
made by hanging the gunny
bags or sprinkling the water
at regular interval.
Checking the level of column :-
After the construction of column of
column the level and height is
checked by means of measuring
tape and total station. It gives
actual level of column and floors
construction.
16. Formwork of beam and slab :-
Formwork of main beam is first
laid on the column, then secondary
beam shuttering is placed. After it,
slab formwork is laid. Shuttering is
supported by tubular scaffolding
which can be adjusted later on