1. EMV ISS and POS ACQ
Production Plan
Updated 23 Sept 2016
2. Actions
Items Activity Teams Date By
1 ATM – No Impacts •ATM support team
•Cash loading team
•Security
NA Bong Ny/Senghuy
2 POS replacement
Merchants first
Branch later As Old App working
with new Host
•Card Center
•Branches
•Merchants
Nov-16 Theara
3 EMV Product Creation •Card Center Sep-16 Team
4 Wing integration – No Impacts •Wing and Card
Center
NA Team
5 User trainings and new processes • All Now Team
6 User guides •Card Center Nov-16 Ravy
7 User experiences •All Nov-16 Chanty/Monirouth