SlideShare a Scribd company logo
1 of 15
Download to read offline
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES 
TABLE OF CONTENTS 
1.0 INTRODUCTION 
2.0 SUMMARY 
3.0 SOIL RESISTIVITY SURVEY 
4.0 DESIGN PARAMETERS 
5.0 CATHODIC PROTECTION DESIGN CALCULATIONS 
Page 2 of
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES 
0 
c: 
1.0 INTRODUCTION 
This report defines the design calculations and requirements of Cathodic Protection System 
for one No. 17" existing gas pipeline and three new LPG product pipelines. An impressed 
current cathodic protection system will be installed to supplement the' corrosion coating in 
providing corrosion control to the pipeline. The impressed current Cathodic Protection 
system for existing gas pipeline will be upgraded to suit the new requirement for existing 
gas pipeline as well as new LPG product pipelines. 
2.0 SUMMARY 
Cathodic protection is specified for the onshore section of the subject pipeline from Dinh 
Co to Thi Vai for new LPG pipeline and from Long Hi to Phu My for existing gas pipeline-length 
and other parameters are as given in Secsion 4.0 of this document. Both galvanic 
anode and impressed current cathodic protection systems were considered during this 
design. An impressed current cathodic protection system has been selected on a technical 
basis. The cathodic protection system has been designed in accordance with internationally 
accepted standards and compliance the codes and standards listed in section 1.2 o 
specification. A conservation design approach has been used including a 30 mA/m2 current 
density and 95% coating efficiency. For future addition a 20% spare output capacity has 
been provided ( NACE-1967). It has been determined that a single impressed current 
system required upgrading at the Phuoc Hoa LBV and at the Dinh Co Station would 
provide full cathodic protection of new LPG pipelines and existing gas pipelines. 
The soil resistivities at this location justified the installation of an effective surface anode 
groundbed. The groundbed will be located approximately 100 m from the pipeline and 
position perpendicularly to the pipeline in accordance with the --project specification 
(BS-7361 ). A rectifier will be used to energize the groundbed. They.415. VAC; three phases 
power supply to the rectifier will be provided from the415;volt switchboard. Elec€rical 
isolation of the pipeline will be provided by the installation of insulating flange sets 
Insulating flange set shall be provided with Explosion-proof surge diverters to prevent 
damage due to lightning or power surges. Test stations will be provided to monitor and 
adjust the cathodic protection system . Test station also have to be provided at following 
location 
• Both side of the major river or road crosing. 
• At all insulating joint. 
• At HT overhead line crossing. 
• At all vulnerable location where interferance is possible 
These test stations will be located at maximum intervals of 1.5 km. All cable connections to 
the pipeline will be made using the brassing thermit weld process. 
3.0 SOIL RESISTIVITY SURVEY 
Soil resistivity measurements have been previously carried out by others at 65 location 
along the pipeline ROW. According to the information included in the contract documents. 
this testing was performed using the Wenner 4-pin method at depth of 0.75, 1.5, and 
metres using a .M-416 instrument made in the Soviet Union. Test equipment must have 
maximum AC  DC ground current rejection feature. Soil resistivities are critical to the 
proper design of a cathodic protection system. They are used as a guide to determine the 
P9-CPS.05-01.0 Page of I
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL  JETTIES 
corrosiveness of the soil and also used to select ground locations and configurations. Soil 
resistivities are important regardless of whether and impressed current or a sacrificial anode 
cathodic protection system is utilized. It should be understood that this cathodic protection 
design has been based on the soil resistivities determined by others. Any inaccuracies in the 
reported resistivity values versus the actual resistivity values could have a significant impact on 
the effectiveness of the cathodic protection system. This can only be determined during 
commissioning of the system when the Contractor shall check the.soil resitivity inspection 
accordance with specification. 
4.0 
4.1 
4.1.1 
Y 
• 
DESIGN PARAMETERS 
The following sub-sections include parameters which have been used for design of the 
proposed cathodic protection system. 
GENERAL PIPELINE DETAILS 
These calculation for upgrading existing CP system for new LPG pipelines and existing gas 
pipeline will be done through two (2) cathodic protection system design. 
Portion 1: (CP Station at Dinh Co location ) 
Gas pipeline (Long Hai to Ba Ria) 
Length of pipeline 16.5 km a 
Pipeline diameter 406.4 mm 1 /17 
Pipeline number 1 
Coating Coal tar enamel 
LPG pipelines (Dinh Co to Ba Ria) 
Length of pipeline 7.5 km 
Pipeline diameter 168 mm C L 
Pipeline number 3 
Coating Polyethylene 
4.1.2 Portion 2: (CP Station at Phuoc Hoa location ) 
Gas pipeline (Ba Ria to Phu My) 
Length of pipeline 21.5 km 
Pipeline diameter 426 mm 
Pipeline number 
Coating Coal tar enamel 
LPG pipelines (Ba Ria to Thi Vai) 
Length of pipeline 17 km 
Pipeline diameter 168 mm 
Pipeline number 3 
P9-CPS.05-01.0 
Page 4 of I '
Rev. D /,(
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL  JETTIES 
Coating Polyethylene 
4.2 CATHODIC PROTECTION DESIGN LIFE 
In accordance with the contract documents, the impressed current cathodic protection 
system will have a design life of 30 years. The cathodic protection Contractor shall 
demonstrate the design life of his proposed CP system. 
4.3 ANODE TYPE 
1 T' 'um tubular anodes with a mixed metal oxide coating will be installed. These anodes 
have proven to have superior operating characteristics over silicon iron and graphite anodes. 
Titanium / mixed metal oxide anode are also of lighter weight and capable of significantly 
higher current outputs and longer life. 
4.4 COATING EFFICIENCY 
A common method to assess the pipe coating condition is to use a factor referred to 
percent bare. For a normal factory applied coaltar enamel coating system which would be 
inspected and repaired prior to back filling. of the pipe, a value of a approximately I to 2 
percent bare would be experienced immediately subsequent to construction. However, 
during the service life of the pipeline with expansion and contraction of the pipeline due to 
thermal effects, soil movement, water ingress through the coating etc, the condition of the 
coating will deteriorate. 
A conservative coating efficiency of 95% has been used for this cathodic protection design. 
This means that over the 30 year life, the cathodic protection system will have the capacity 
protect an average of 5% of the total surface area of the pipeline. 
4.5 CP CURRENT DENSITY 
The National Association of Corrosion Engineers (NACE) Recommended practice 
RP-0169-92 and DNV RP B401 specifies a current density of 10-30 mA/m2 for bare steel 
structures in soil. The soils along the proposed ROW for this pipeline are very aggressive 
with high moisture content, high salinity and low soil resistivity. Therefore, this design uses 
a 
conservative 30 mAIm2 current density. 
4.6 SOIL RESISTIVITY 
4.6.1 Dinh Co Location 
As mentioned in previous Section 3.0, soil resistivity testing along the pipeline ROW has 
been previously carried out by others. A review of this data indicates that points R-18 and 
R-19 are located relatively near Dinh Co: 
Depth (m) Soil Resistivity (ohm cm) 
R-18 
0.75 8000 
1.50 4200 
P9-CPS.05-01.0 Page 5 of 14 
.
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL  JETTIES 
3.00 1050 
R-19 
0.75 3600 
1.50 1300 
3.00 500 
The deep-well anode system will be installed for cathodic protection, The average resistivity 
value for the above two points at a 1.5m depth is 2750 ohm-cm and will be used t For 
groundbed design at Dinh Co. 
4.6.2 Phuoc Hoa Location 
Also mentioned in previous Section 3.0, soil resistivity testing along the pipeline ROW has 
been previously carried out by others. A review of this data indicates that points BH23 aid 
BH24 are located relatively near Ba Ria ( at Phuoc Hoa ) where the impressed current CP 
system will be located. The soil resistivity values reported at these locations are : 
Depth (m) Soil Resistivity (ohm ern) 
BH23 
0.75 1300 
1.50 1500 
3.00 1000 
BH24 
0.75 1500 
1.50 1500 
3.00 800 
The average resistivity value for the above two points at a 1.5m depth is 1500 ohm-cnl _:d 
will be used for groundbed design at Phuoc Hoa. 
4.7 CATHODIC PROTECTION CRITERIA 
NACE Recommended Practice RP-0169-92 addresses cathodic protection criteria --Dr 
underground and submerged metallic piping systems. Applicable excerpts of this st.and=d 
relative to CP criteria for this project are as follows- 
A negative (cathodic) potential of at least 85OmV with the cathodic protecti'Dn 
applied. This potential is measured with respect to a saturated copper / copper ulfat.e 
reference electrode contacting the electrolyte. Voltage drops other than those across 
the structure to electrolyte boundary must be considered for valid interpretation of 
this voltage measurement. 
A negative polarized potential of at least 850 mV relative to a saturated copper / 
copper sulfate reference electrode. 
P9-CPS.05-01.0
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL  JETTIES 
A minimum of 100 mA of cathodic polarization between the structure surface and a 
stable reference electrode contacting the electrolyte. The formation or decay of 
polarization can be'measured to satisfy this criterion. 
5.0 CATHODIC PROTECTION DESIGN CALCULATIONS 
5.1 DINH CO LOCATION 
5.1.1 Pipeline Total Surface Area 
The onshore portion of Long Hai to Ba Ria gas pipeline and Dinh Co to Ba Ria LPG 
pipelines has a total surface area as follows: 
Sa = (Pi) (d) (1) 
Sa (3.1416)-[(0.406,x 16500) + (3 x 0.168 x 7500)] 
Sa = 32921 (m2) 
Where: Sa = Surface area (m2 ) 
Pi = 3.1416 
1 Length of pipeline (m) 
Diameter of pipeline (m) 
5.1.2 CATHODIC PROTECTION CURRENT REQUIREMENT 
The cathodic protection system will have a DC output capacity as follows: 
(Sa) (Id) (Cb) 
It 
It 
It = 
ZSF 
1000 
(32921) (30) (0.05) 
X1.1 
1000 
54.32 (A) 
Say 55 amperes 
Where: Sa Total surface area (m2 ) 
Id = CP current density (mA/m2 ) 
Cb = Coating breakdown factor (%) 
SF = Safety factor (1.1) 
5.1.3 CATHODIC PROTECTION ANODE REQUIREMENT 
Chosen output rating of 2 Ampere for each anode, the number of anodes: 
N = It/2 = 54.32/2 = 27.16 
No. of anodes based on current requirement 
Page 7 of 14 
m.1
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL  JETTIES 
N = 30 
Another, maximum anode current output for each anodeto be determined as follows : 
LogL= 3.3 - LogId 
Where : L = design life in years 
Id = Maximum anode current density (A/m2 ) 
For L = 3 0 years 
The anode has a dimension of 31.75mm dia x I000mm legth with a.total area of 0.1m2 
Therefore, Id =.66.5 A/m2 
Maximum current output of anode = 0.1m2 x 66.5 A/m2 =6.65A 
Hence 3 0 anodes will give 6.65 x3 0 = 199.5 A  Required 54.3 2 A 
noe wegt requ id re , W = 
W 
W = 
(0) (It)(y) 
Uf 
0.1 (54.32) (30) 
0.6 
271.6 kg 
Anodes No. required based on weight requirement : 
N W/Wa 
271.6 / 20 
13.6 
No. of anodes based on weight requirement, N = 14 
Where Q Anode consumption rate (kg/amp-year) 
It = Cathodic Protection current ( A ) 
Y = Design life of the system ( years ) 
Uf = Anode Utilization factor ( 0.6 for a conservative design ) 
Wa = Weight of individual anode ( kg ) 
Hence anode No. chosen is 30 
There are 20 canister anodes in existing groundbed at Dinh Co, so that 10 canister anodes 
which are the same existing anode specification will be required to add in this location. 
5.1.4 GROUNDBED RESISTANCE 
Installation of 30 canister anodes on 5 metre spacing in 2750 ohm-cm soil results in an 
estimated groundbed resistance of 0.5844 ohm as follows: 
Rn = RI + R2 ( NACE - 1967, page 95 ) 
Where Rl Anode to backfill resistance 
R2 Backfill to soil resistance 
Pb BLcr - 1+ 2La 
R1 
N.yLcrx6.28 
[In 
do S 
In(0.656N)]) { NACE - 1967 ) 
.- I + (2)(100) 
R1' = 50 Fn (8)(100) 
ln(0.656)(30)] 
(30)(100)(6.28) 3175 500 
Ri 0.0152 (ohm) 
Rev. D 
-
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL  JETTIES 
Where: Pb 
La = 
da = 
S = 
N 
Backfill resistivity (ohm-cm) 
Length of anode- excluding backfill (cm) 
Diameter of anode- excluding backfill (cm) 
Spacing of anodes (cm) 
Number of anodes.. 
Ps 8Lc -1 + 2Lc 
R2 
R2 
NxLcx6.28 
2750 
[In In(0.656N)J) (NACE - 196J ) 
do S 
(8) (150) (2) (150) 
-1 + in(0.656)(30)J 
(30)(150)(6.28) [in 76 500 
R2 = 0.5692 (ohm) 
Where: Ps Soil resistivity (ohm-cm) 
Lc Length of anode- including backfill (cm) 
dc Diameter of anode- including backfill (cm) 
S. Spacing of anodes (cm) 
Number of anodes. 
Hence Rn = 0.0152 + 0.5692 
0.5844 (ohm) 
5.1.5 TRANSFORMER RECTIFIER DC OUTPUT VOLTAGE 
It is estimated that the transformer rectifier will require a 45 volt output to achieve :Lie 
desired 54.32 ampere DC current output as follows: 
It.(Rn+Rc) + Bemf 
E 54.32x(0.5844 + 0.2) + 2 
E 44.6 volts 
Say 45 volts 
Where : E Rectifier DC output voltage (volts) 
It = Rectifier output current (amp) 
Rn = Total groundbed resistance (ohm) 
Rc Total cable resistance (0.2 ohm) 
Bemf = Dropped voltage between pipeline and ground (-2.0 volts) 
Note : Pipe to earth resistance (Rpe) has not been considered since the coating resistari :e is so 
high.( 1010 ohm-mz ) that all current will pass through 5% bare areas through r±e pipeline 
coating. 
Rev. D
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL  JETTIES 
5.1.6 TRANSFORMER RECTIFIER AC INPUT 
Actual DC power output required : Pd = 44.6 x 55.32 
2422.672 (W) 
DC power requirement including 20% overvoltage provision (20% spare Capacity ) 
= 1.2x44.6x54.32=2907.2 (W) 
Now, considering overall system P.F (power factor) = 0.8 
and Transformer Rectifier Unit efficiency (E.F) = 0.85 (85% ) 
For 3 phases, 415V, 50Hz supply input to Transformer Rectifier Unit : 
Input current 
2907.2 
Ip 
Ip = 
Jx415x0.8x0.85 
5.95 A 
Hence, AC power input ( including 20% spare capacity) is : 
43 x 415 x 5.95 x 0.8 
3420.23 Watt 
5.1.7 CHANGE IN EARTH POTENTIAL DUE TO FORCED DRAINAGE 
When CP current is injected into ground through anode bed, the current flow results in a 
potential gradient in the earth. _... 
The change in earth potential near the pipelines 
(Ps)(It) 
V = 
27r(r) 
(2750)(54.32) 
V 
Where : Ps 
It 
r 
5.2 PHUOC HOA LOCATION 
5.2.1 Pipeline Total Surface Area 
27zx10000 
2.38 Volts 
Soil resistivity ( ohm-cm ) 
Cathodic Protection current ( Ampere ) 
Distance between pipeline and anode bed (cm ) 
The onshore portion of Ba Ria to Phu My gas pipeline and Ba Ria to Thi Vai LPG pipelines 
has a total surface area as follows: 
Sa _ (Pi) (d) (1) 
Sa (3.1416) [(0.426 x 21.500)+ (3 x 0.168 x 17000)] 
Sa = 55691 (m2 ) 
P9-CPS.05-01.0 Page 10 of 14
G.U.P PHASE I1- LIQUID PIPELINES, TERMINAL  JETTIES 
Where: Sa Surface area (m2 ) 
Pi 3.1416 
I Length of pipeline (m) 
Diameter of pipeline (m) 
5.2.2 CATHODIC PROTECTION CURRENT REQUIREMENT 
The cathodic protection system will have a DC output capacity as follows: 
It = 91.89 A 
( ) * * 
(55691 ) * 30 * 0.05 
It = x 
Say 92 amperes 
Where: Sa Total surface area (m2 ) 
Id = CP current density (mA/m2 ) 
Cb = Coating breakdown factor (%) 
SF = Safety factor (1.1) 
5.2.3 CATHODIC PROTECTION ANODE REQUIREMENT 
Chosen output rating of 2 Ampere for each anode, the number of anodes: 
N = It/2 92/2 = 45.95 
No. of anodes based on current requirement 
N = 50 
Another, maximum anode current output for each anodeto be determined as follows : 
LogL=3.3 -Log Id 
Where : L = design life in years 
Id = Maximum anode current density ( A/m2 ) 
For L = 30 years 
The anode has a dimension of 31.75mm dia x 1000mm legth with a total area of 0.1m2 
Therefore, Id = 66.5 A/m2 
Maximum current output of anode = 0.1 m2 x 66.5 A/m2 = 6.65A 
Hence 50 anodes will give 6.65 x 50 = 332.5 A  Required 92 A 
(Q)(It)(Y) 
Anode weight required, W = 
W 
= 
Uf 
(0.1) (92) (30) 
0.6 
460 kg 
Page I 1-of 14- 
Rev. D 
xSF 
Sa Id Cb 
It 
1000 
= 
1.1 
1000
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL  JETTIES 
Anodes No. required based on weight requirement : 
N = W / Wa 
460 / 20 
23 
No. of anodes based on weight requirement, N = 23 
Where Q = Anode consumption rate (kg/amp-year ) 
It = Cathodic Protection current (A ) 
Y = Design life of the system ( years ) 
Uf = Anode Utilization factor ( 0.6 for a conservative design 
Wa = Weight of individual anode ( kg ) 
Hence anode No. chosen is 30 
There are 20 canister anodes in existing groundbed at Phuoc Hoa, so that 30 canister 
anodes which are the same existing anode specification will be required to add in this 
location. 
5.2.4 OROUNDDED RESISTANCE 
Installation of 50 canister anodes on 5 metre spacing in 1500 ohm-cm soil results in an 
estimated groundbed resistance of 0.19 ohm as follows: 
Rn = R1 + R2 
Where R1 = Anode to backfill resistance 
R2 Backfill to soil resistance 
R1= 
R1= 
 
 
La 
2 *100 
R1 = 0.0094 Ohm 
 
Pb 
 
50 
Where: Pb 
La 
8 *100 
La = 
da = 
S = 
N = 
 
Backfill resistivity (ohm-cm) 
Length of anode- excluding backfill (cm) 
Diameter of anode- excluding backfill (cm) 
Spacing of anodes (cm) 
Number of anodes. 
 
− + 
× × 
(ln 0.656 ) 
2 
1 
8 
6.28 
N 
S 
da 
Ln 
N La 
 
 
− + 
× × 
(ln 0.656 * 50 ) 
500 
1 
3.175 
50 100 6.28 
Ln
R2= 
R2 = 
Lc 
2 *150 
8 *150 
R2= 0.196 (ohm) 
 
Lc 
Pb 
 
50 
Where:. Ps = Soil resistivity (ohm-cm) 
 
 
Lc = Length of anode- including backfill (cm) 
dc Diameter of anode- including backfill (cm) 
S Spacing of anodes (cm) 
Number of anodes. 
Hence Rn 0.0094 + 0.196 
0.2054 (ohm) 
5.2.5 TRANSFORMER RECTIFIER DC OUTPUT VOLTAGE 
 
It is estimated that the transformer rectifier will require a 42 volt output to achieve 
the desired 92mpere DC current output as follows: 
It.(Rn+Rc) + Bemf 
E 92 x (0.2054 + 0.2) + 2 
E 39.29 volts 
Say 42 volts 
Where.: E Rectifier DC output voltage (volts) 
it = Rectifier output current_ (amp) 
Rn _ Total groundbed resistance (ohm) 
Rc = Total cable resistance (0.2 ohm) 
Bemf = Dropped voltage between pipeline and ground (-2.0 
volts) 
Note : Pipe to earth resistance (Rpe ) has not been considered since the coating 
resistance 
is so high ( 1010 ohm-nag ) that all current will pass through 5% bare areas 
through the 
pipeline coating. 
5.2.6 TRANSFORMER RECTIFIER AC INPUT 
Actual DC power output required : Pdc = 39.29 x 92 
3614.68 ( W) 
 
− + 
× × 
(ln 0.656 ) 
2 
1 
8 
6.28 
N 
S 
dc 
Ln 
N Lc 
 
 
− + 
× × 
(ln 0.656 * 50 ) 
500 
1 
3.175 
50 150 6.28 
Ln
DC power requirement including 20% overvoltage provision (20% spare Capacity) 
= 1.2x39.29x92=4337.6 (W) 
Now, considering overall system P.F ( power factor) = 0.8 
and Transformer Rectifier Unit efficiency (E.F) = 0.85 ( 85% ) 
For 3 phases, 415V, 50Hz supply input to Transformer 
Rectifier Unit : Input current 
IP= 
4337 .6 
3 x 415 x 0.8 x 
0.85 
Ip =8.875 A 
Hence, AC power input ( including 20% spare capacity) is : 
- _ 
3x415 x8.875 x0.8 = 5013W
: 
G.U.P PHASE II - LIQUID PIPELINES, TERMINAL  JETTIES 
5.2.7 CHANGE IN EARTH POTENTIAL DUE TO FORCED DRAINAGE 
When CP current is injected into ground through anode bed, the current flow results in a 
potential gradient in the earth. 
The change in earth potential near the pipelines 
(Ps)(It) 
2 r(r) 
(1500)(92) 
V = 
Where : Ps = 
It = 
r = 
2xl0000 
= 2.2 Volts 
Soil resistivity ( ohm-cm ) 
Cathodic Protection current ( Ampere ) 
Distance between pipeline and anode bed ( cm ) 
Page 14 of 14

More Related Content

Viewers also liked

Resume - CP2 Chris Stenzel
Resume - CP2 Chris StenzelResume - CP2 Chris Stenzel
Resume - CP2 Chris StenzelChris Stenzel
 
Certifcate of Fundamentals of corrosion and Cathodic Protection
Certifcate of Fundamentals of corrosion and Cathodic ProtectionCertifcate of Fundamentals of corrosion and Cathodic Protection
Certifcate of Fundamentals of corrosion and Cathodic ProtectionMuhammad Irfan
 
CorrosionCathProtBasicDesignSATX
CorrosionCathProtBasicDesignSATXCorrosionCathProtBasicDesignSATX
CorrosionCathProtBasicDesignSATXStanley Worcester
 
Cathodic Protection For Oil Wells
Cathodic Protection For Oil WellsCathodic Protection For Oil Wells
Cathodic Protection For Oil WellsAbinash Padhy
 
Cathodic protection fundamentals
Cathodic protection fundamentalsCathodic protection fundamentals
Cathodic protection fundamentalsAbinash Padhy
 
3 cp corrosion control
3 cp corrosion control3 cp corrosion control
3 cp corrosion controlhimanshu jain
 
Cathodic protection fundamentals
Cathodic protection fundamentalsCathodic protection fundamentals
Cathodic protection fundamentalsAbinash Padhy
 
(cathodic protection)
(cathodic protection) (cathodic protection)
(cathodic protection) Mohamed Safwat
 
IMPRESSED CURRENT CATHODIC PROTECTION
IMPRESSED CURRENT CATHODIC PROTECTIONIMPRESSED CURRENT CATHODIC PROTECTION
IMPRESSED CURRENT CATHODIC PROTECTIONSHAILESH SHUKLA
 

Viewers also liked (15)

Allan Borja CV
Allan Borja CVAllan Borja CV
Allan Borja CV
 
Cv english
Cv englishCv english
Cv english
 
jegu_ccna
jegu_ccnajegu_ccna
jegu_ccna
 
Resume - CP2 Chris Stenzel
Resume - CP2 Chris StenzelResume - CP2 Chris Stenzel
Resume - CP2 Chris Stenzel
 
UNFPA CP2 Evaluation report
UNFPA CP2 Evaluation reportUNFPA CP2 Evaluation report
UNFPA CP2 Evaluation report
 
Certifcate of Fundamentals of corrosion and Cathodic Protection
Certifcate of Fundamentals of corrosion and Cathodic ProtectionCertifcate of Fundamentals of corrosion and Cathodic Protection
Certifcate of Fundamentals of corrosion and Cathodic Protection
 
CorrosionCathProtBasicDesignSATX
CorrosionCathProtBasicDesignSATXCorrosionCathProtBasicDesignSATX
CorrosionCathProtBasicDesignSATX
 
Cathodic Protection For Oil Wells
Cathodic Protection For Oil WellsCathodic Protection For Oil Wells
Cathodic Protection For Oil Wells
 
Cathodic protection fundamentals
Cathodic protection fundamentalsCathodic protection fundamentals
Cathodic protection fundamentals
 
3 cp corrosion control
3 cp corrosion control3 cp corrosion control
3 cp corrosion control
 
Cathodic protection fundamentals
Cathodic protection fundamentalsCathodic protection fundamentals
Cathodic protection fundamentals
 
(cathodic protection)
(cathodic protection) (cathodic protection)
(cathodic protection)
 
IMPRESSED CURRENT CATHODIC PROTECTION
IMPRESSED CURRENT CATHODIC PROTECTIONIMPRESSED CURRENT CATHODIC PROTECTION
IMPRESSED CURRENT CATHODIC PROTECTION
 
cathodic protection
cathodic protectioncathodic protection
cathodic protection
 
Cathodic and anodic protection
Cathodic and anodic protectionCathodic and anodic protection
Cathodic and anodic protection
 

Similar to Thiết kế đường ống trên bờ

external & internal corrosion monitoring
external & internal corrosion monitoringexternal & internal corrosion monitoring
external & internal corrosion monitoringsair ali khan
 
20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-systemAdeoye Okunoye
 
20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-systemAdeoye Okunoye
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAli Osman Öncel
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Audubon Engineering Company
 
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdf
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdfStandards_Technical Seminar for Cathodic Protection to GOGC Design.pdf
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdfSergeRINAUDO1
 
Corrosion control
Corrosion controlCorrosion control
Corrosion controlDuy Vu
 
Shyam cable catalogue
Shyam cable catalogueShyam cable catalogue
Shyam cable catalogueuibsamit87
 
City gas distribution- Complete Overview
City gas distribution- Complete OverviewCity gas distribution- Complete Overview
City gas distribution- Complete OverviewUjjwal Rao
 
M 503 cathodic protection
M 503 cathodic protectionM 503 cathodic protection
M 503 cathodic protectionHedi Mohamed
 
Cathodic prevention of steel rebars in concrete the international outlook
Cathodic prevention of steel rebars in concrete the international outlookCathodic prevention of steel rebars in concrete the international outlook
Cathodic prevention of steel rebars in concrete the international outlookSimone Tremolada
 
Technical presentation on modern earthing
Technical presentation on modern earthingTechnical presentation on modern earthing
Technical presentation on modern earthingPankaj Chakraborty
 
Corrosion Assessment – Half-Cell Potential Method for reinforced concrete
Corrosion Assessment – Half-Cell Potential Method for reinforced concreteCorrosion Assessment – Half-Cell Potential Method for reinforced concrete
Corrosion Assessment – Half-Cell Potential Method for reinforced concreteYash Shah
 
Corrosion Control Project
Corrosion Control ProjectCorrosion Control Project
Corrosion Control ProjectDil Nawaz
 

Similar to Thiết kế đường ống trên bờ (20)

external & internal corrosion monitoring
external & internal corrosion monitoringexternal & internal corrosion monitoring
external & internal corrosion monitoring
 
SLIDES
SLIDESSLIDES
SLIDES
 
20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system
 
20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system20392769 design-calculation-cathodic-protection-impressed-cureent-system
20392769 design-calculation-cathodic-protection-impressed-cureent-system
 
MC _ CP Rev.0.pdf
MC _ CP Rev.0.pdfMC _ CP Rev.0.pdf
MC _ CP Rev.0.pdf
 
An Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara SeaAn Example for Borehole Seismology in Marmara Sea
An Example for Borehole Seismology in Marmara Sea
 
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs) Cathodic Protection for Above Ground Storage Tanks (AGSTs)
Cathodic Protection for Above Ground Storage Tanks (AGSTs)
 
ملزمة
ملزمةملزمة
ملزمة
 
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdf
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdfStandards_Technical Seminar for Cathodic Protection to GOGC Design.pdf
Standards_Technical Seminar for Cathodic Protection to GOGC Design.pdf
 
Boiler Operation and Maintenance Experiences
Boiler Operation and Maintenance ExperiencesBoiler Operation and Maintenance Experiences
Boiler Operation and Maintenance Experiences
 
Corrosion control
Corrosion controlCorrosion control
Corrosion control
 
Shyam cable catalogue
Shyam cable catalogueShyam cable catalogue
Shyam cable catalogue
 
City gas distribution- Complete Overview
City gas distribution- Complete OverviewCity gas distribution- Complete Overview
City gas distribution- Complete Overview
 
KNPC Volume 3B.pdf
KNPC Volume 3B.pdfKNPC Volume 3B.pdf
KNPC Volume 3B.pdf
 
M 503 cathodic protection
M 503 cathodic protectionM 503 cathodic protection
M 503 cathodic protection
 
Cathodic prevention of steel rebars in concrete the international outlook
Cathodic prevention of steel rebars in concrete the international outlookCathodic prevention of steel rebars in concrete the international outlook
Cathodic prevention of steel rebars in concrete the international outlook
 
Technical presentation on modern earthing
Technical presentation on modern earthingTechnical presentation on modern earthing
Technical presentation on modern earthing
 
Corrosion Assessment – Half-Cell Potential Method for reinforced concrete
Corrosion Assessment – Half-Cell Potential Method for reinforced concreteCorrosion Assessment – Half-Cell Potential Method for reinforced concrete
Corrosion Assessment – Half-Cell Potential Method for reinforced concrete
 
Corrosion Control Project
Corrosion Control ProjectCorrosion Control Project
Corrosion Control Project
 
01_WP-CPL_0608_LR
01_WP-CPL_0608_LR01_WP-CPL_0608_LR
01_WP-CPL_0608_LR
 

More from Vcoi Vit

2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri31
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri312eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri31
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri31Vcoi Vit
 
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri14
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri142eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri14
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri14Vcoi Vit
 
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri13
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri132eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri13
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri13Vcoi Vit
 
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri052eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05Vcoi Vit
 
Giao trinh nuoi_trong_thuy_san46
Giao trinh nuoi_trong_thuy_san46Giao trinh nuoi_trong_thuy_san46
Giao trinh nuoi_trong_thuy_san46Vcoi Vit
 
Giao trinh nuoi_trong_thuy_san28
Giao trinh nuoi_trong_thuy_san28Giao trinh nuoi_trong_thuy_san28
Giao trinh nuoi_trong_thuy_san28Vcoi Vit
 
Giao trinh nuoi_trong_thuy_san23
Giao trinh nuoi_trong_thuy_san23Giao trinh nuoi_trong_thuy_san23
Giao trinh nuoi_trong_thuy_san23Vcoi Vit
 
Giao trinh nuoi_trong_thuy_san22
Giao trinh nuoi_trong_thuy_san22Giao trinh nuoi_trong_thuy_san22
Giao trinh nuoi_trong_thuy_san22Vcoi Vit
 
Giao trinh nuoi_trong_thuy_san21
Giao trinh nuoi_trong_thuy_san21Giao trinh nuoi_trong_thuy_san21
Giao trinh nuoi_trong_thuy_san21Vcoi Vit
 
Giao trinh nuoi_trong_thuy_san16
Giao trinh nuoi_trong_thuy_san16Giao trinh nuoi_trong_thuy_san16
Giao trinh nuoi_trong_thuy_san16Vcoi Vit
 
Giao trinh nuoi_trong_thuy_san05
Giao trinh nuoi_trong_thuy_san05Giao trinh nuoi_trong_thuy_san05
Giao trinh nuoi_trong_thuy_san05Vcoi Vit
 
Giao trinh nuoi_trong_thuy_san02
Giao trinh nuoi_trong_thuy_san02Giao trinh nuoi_trong_thuy_san02
Giao trinh nuoi_trong_thuy_san02Vcoi Vit
 
Giao trinh tong hop sv50
Giao trinh tong hop sv50Giao trinh tong hop sv50
Giao trinh tong hop sv50Vcoi Vit
 
Giao trinh tong hop sv49
Giao trinh tong hop sv49Giao trinh tong hop sv49
Giao trinh tong hop sv49Vcoi Vit
 
Giao trinh tong hop sv48
Giao trinh tong hop sv48Giao trinh tong hop sv48
Giao trinh tong hop sv48Vcoi Vit
 
Giao trinh tong hop sv47
Giao trinh tong hop sv47Giao trinh tong hop sv47
Giao trinh tong hop sv47Vcoi Vit
 
Giao trinh tong hop sv46
Giao trinh tong hop sv46Giao trinh tong hop sv46
Giao trinh tong hop sv46Vcoi Vit
 
Giao trinh tong hop sv45
Giao trinh tong hop sv45Giao trinh tong hop sv45
Giao trinh tong hop sv45Vcoi Vit
 
Giao trinh tong hop sv43
Giao trinh tong hop sv43Giao trinh tong hop sv43
Giao trinh tong hop sv43Vcoi Vit
 
Giao trinh tong hop sv41
Giao trinh tong hop sv41Giao trinh tong hop sv41
Giao trinh tong hop sv41Vcoi Vit
 

More from Vcoi Vit (20)

2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri31
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri312eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri31
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri31
 
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri14
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri142eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri14
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri14
 
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri13
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri132eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri13
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri13
 
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri052eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05
2eae0e86 e7c6-431d-aa08-b8f89ba71921 giaotrinhkinhtechinhtri05
 
Giao trinh nuoi_trong_thuy_san46
Giao trinh nuoi_trong_thuy_san46Giao trinh nuoi_trong_thuy_san46
Giao trinh nuoi_trong_thuy_san46
 
Giao trinh nuoi_trong_thuy_san28
Giao trinh nuoi_trong_thuy_san28Giao trinh nuoi_trong_thuy_san28
Giao trinh nuoi_trong_thuy_san28
 
Giao trinh nuoi_trong_thuy_san23
Giao trinh nuoi_trong_thuy_san23Giao trinh nuoi_trong_thuy_san23
Giao trinh nuoi_trong_thuy_san23
 
Giao trinh nuoi_trong_thuy_san22
Giao trinh nuoi_trong_thuy_san22Giao trinh nuoi_trong_thuy_san22
Giao trinh nuoi_trong_thuy_san22
 
Giao trinh nuoi_trong_thuy_san21
Giao trinh nuoi_trong_thuy_san21Giao trinh nuoi_trong_thuy_san21
Giao trinh nuoi_trong_thuy_san21
 
Giao trinh nuoi_trong_thuy_san16
Giao trinh nuoi_trong_thuy_san16Giao trinh nuoi_trong_thuy_san16
Giao trinh nuoi_trong_thuy_san16
 
Giao trinh nuoi_trong_thuy_san05
Giao trinh nuoi_trong_thuy_san05Giao trinh nuoi_trong_thuy_san05
Giao trinh nuoi_trong_thuy_san05
 
Giao trinh nuoi_trong_thuy_san02
Giao trinh nuoi_trong_thuy_san02Giao trinh nuoi_trong_thuy_san02
Giao trinh nuoi_trong_thuy_san02
 
Giao trinh tong hop sv50
Giao trinh tong hop sv50Giao trinh tong hop sv50
Giao trinh tong hop sv50
 
Giao trinh tong hop sv49
Giao trinh tong hop sv49Giao trinh tong hop sv49
Giao trinh tong hop sv49
 
Giao trinh tong hop sv48
Giao trinh tong hop sv48Giao trinh tong hop sv48
Giao trinh tong hop sv48
 
Giao trinh tong hop sv47
Giao trinh tong hop sv47Giao trinh tong hop sv47
Giao trinh tong hop sv47
 
Giao trinh tong hop sv46
Giao trinh tong hop sv46Giao trinh tong hop sv46
Giao trinh tong hop sv46
 
Giao trinh tong hop sv45
Giao trinh tong hop sv45Giao trinh tong hop sv45
Giao trinh tong hop sv45
 
Giao trinh tong hop sv43
Giao trinh tong hop sv43Giao trinh tong hop sv43
Giao trinh tong hop sv43
 
Giao trinh tong hop sv41
Giao trinh tong hop sv41Giao trinh tong hop sv41
Giao trinh tong hop sv41
 

Thiết kế đường ống trên bờ

  • 1. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 SUMMARY 3.0 SOIL RESISTIVITY SURVEY 4.0 DESIGN PARAMETERS 5.0 CATHODIC PROTECTION DESIGN CALCULATIONS Page 2 of
  • 2. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL & JETTIES 0 c: 1.0 INTRODUCTION This report defines the design calculations and requirements of Cathodic Protection System for one No. 17" existing gas pipeline and three new LPG product pipelines. An impressed current cathodic protection system will be installed to supplement the' corrosion coating in providing corrosion control to the pipeline. The impressed current Cathodic Protection system for existing gas pipeline will be upgraded to suit the new requirement for existing gas pipeline as well as new LPG product pipelines. 2.0 SUMMARY Cathodic protection is specified for the onshore section of the subject pipeline from Dinh Co to Thi Vai for new LPG pipeline and from Long Hi to Phu My for existing gas pipeline-length and other parameters are as given in Secsion 4.0 of this document. Both galvanic anode and impressed current cathodic protection systems were considered during this design. An impressed current cathodic protection system has been selected on a technical basis. The cathodic protection system has been designed in accordance with internationally accepted standards and compliance the codes and standards listed in section 1.2 o specification. A conservation design approach has been used including a 30 mA/m2 current density and 95% coating efficiency. For future addition a 20% spare output capacity has been provided ( NACE-1967). It has been determined that a single impressed current system required upgrading at the Phuoc Hoa LBV and at the Dinh Co Station would provide full cathodic protection of new LPG pipelines and existing gas pipelines. The soil resistivities at this location justified the installation of an effective surface anode groundbed. The groundbed will be located approximately 100 m from the pipeline and position perpendicularly to the pipeline in accordance with the --project specification (BS-7361 ). A rectifier will be used to energize the groundbed. They.415. VAC; three phases power supply to the rectifier will be provided from the415;volt switchboard. Elec€rical isolation of the pipeline will be provided by the installation of insulating flange sets Insulating flange set shall be provided with Explosion-proof surge diverters to prevent damage due to lightning or power surges. Test stations will be provided to monitor and adjust the cathodic protection system . Test station also have to be provided at following location • Both side of the major river or road crosing. • At all insulating joint. • At HT overhead line crossing. • At all vulnerable location where interferance is possible These test stations will be located at maximum intervals of 1.5 km. All cable connections to the pipeline will be made using the brassing thermit weld process. 3.0 SOIL RESISTIVITY SURVEY Soil resistivity measurements have been previously carried out by others at 65 location along the pipeline ROW. According to the information included in the contract documents. this testing was performed using the Wenner 4-pin method at depth of 0.75, 1.5, and metres using a .M-416 instrument made in the Soviet Union. Test equipment must have maximum AC DC ground current rejection feature. Soil resistivities are critical to the proper design of a cathodic protection system. They are used as a guide to determine the P9-CPS.05-01.0 Page of I
  • 3. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL JETTIES corrosiveness of the soil and also used to select ground locations and configurations. Soil resistivities are important regardless of whether and impressed current or a sacrificial anode cathodic protection system is utilized. It should be understood that this cathodic protection design has been based on the soil resistivities determined by others. Any inaccuracies in the reported resistivity values versus the actual resistivity values could have a significant impact on the effectiveness of the cathodic protection system. This can only be determined during commissioning of the system when the Contractor shall check the.soil resitivity inspection accordance with specification. 4.0 4.1 4.1.1 Y • DESIGN PARAMETERS The following sub-sections include parameters which have been used for design of the proposed cathodic protection system. GENERAL PIPELINE DETAILS These calculation for upgrading existing CP system for new LPG pipelines and existing gas pipeline will be done through two (2) cathodic protection system design. Portion 1: (CP Station at Dinh Co location ) Gas pipeline (Long Hai to Ba Ria) Length of pipeline 16.5 km a Pipeline diameter 406.4 mm 1 /17 Pipeline number 1 Coating Coal tar enamel LPG pipelines (Dinh Co to Ba Ria) Length of pipeline 7.5 km Pipeline diameter 168 mm C L Pipeline number 3 Coating Polyethylene 4.1.2 Portion 2: (CP Station at Phuoc Hoa location ) Gas pipeline (Ba Ria to Phu My) Length of pipeline 21.5 km Pipeline diameter 426 mm Pipeline number Coating Coal tar enamel LPG pipelines (Ba Ria to Thi Vai) Length of pipeline 17 km Pipeline diameter 168 mm Pipeline number 3 P9-CPS.05-01.0 Page 4 of I '
  • 5. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL JETTIES Coating Polyethylene 4.2 CATHODIC PROTECTION DESIGN LIFE In accordance with the contract documents, the impressed current cathodic protection system will have a design life of 30 years. The cathodic protection Contractor shall demonstrate the design life of his proposed CP system. 4.3 ANODE TYPE 1 T' 'um tubular anodes with a mixed metal oxide coating will be installed. These anodes have proven to have superior operating characteristics over silicon iron and graphite anodes. Titanium / mixed metal oxide anode are also of lighter weight and capable of significantly higher current outputs and longer life. 4.4 COATING EFFICIENCY A common method to assess the pipe coating condition is to use a factor referred to percent bare. For a normal factory applied coaltar enamel coating system which would be inspected and repaired prior to back filling. of the pipe, a value of a approximately I to 2 percent bare would be experienced immediately subsequent to construction. However, during the service life of the pipeline with expansion and contraction of the pipeline due to thermal effects, soil movement, water ingress through the coating etc, the condition of the coating will deteriorate. A conservative coating efficiency of 95% has been used for this cathodic protection design. This means that over the 30 year life, the cathodic protection system will have the capacity protect an average of 5% of the total surface area of the pipeline. 4.5 CP CURRENT DENSITY The National Association of Corrosion Engineers (NACE) Recommended practice RP-0169-92 and DNV RP B401 specifies a current density of 10-30 mA/m2 for bare steel structures in soil. The soils along the proposed ROW for this pipeline are very aggressive with high moisture content, high salinity and low soil resistivity. Therefore, this design uses a conservative 30 mAIm2 current density. 4.6 SOIL RESISTIVITY 4.6.1 Dinh Co Location As mentioned in previous Section 3.0, soil resistivity testing along the pipeline ROW has been previously carried out by others. A review of this data indicates that points R-18 and R-19 are located relatively near Dinh Co: Depth (m) Soil Resistivity (ohm cm) R-18 0.75 8000 1.50 4200 P9-CPS.05-01.0 Page 5 of 14 .
  • 6. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL JETTIES 3.00 1050 R-19 0.75 3600 1.50 1300 3.00 500 The deep-well anode system will be installed for cathodic protection, The average resistivity value for the above two points at a 1.5m depth is 2750 ohm-cm and will be used t For groundbed design at Dinh Co. 4.6.2 Phuoc Hoa Location Also mentioned in previous Section 3.0, soil resistivity testing along the pipeline ROW has been previously carried out by others. A review of this data indicates that points BH23 aid BH24 are located relatively near Ba Ria ( at Phuoc Hoa ) where the impressed current CP system will be located. The soil resistivity values reported at these locations are : Depth (m) Soil Resistivity (ohm ern) BH23 0.75 1300 1.50 1500 3.00 1000 BH24 0.75 1500 1.50 1500 3.00 800 The average resistivity value for the above two points at a 1.5m depth is 1500 ohm-cnl _:d will be used for groundbed design at Phuoc Hoa. 4.7 CATHODIC PROTECTION CRITERIA NACE Recommended Practice RP-0169-92 addresses cathodic protection criteria --Dr underground and submerged metallic piping systems. Applicable excerpts of this st.and=d relative to CP criteria for this project are as follows- A negative (cathodic) potential of at least 85OmV with the cathodic protecti'Dn applied. This potential is measured with respect to a saturated copper / copper ulfat.e reference electrode contacting the electrolyte. Voltage drops other than those across the structure to electrolyte boundary must be considered for valid interpretation of this voltage measurement. A negative polarized potential of at least 850 mV relative to a saturated copper / copper sulfate reference electrode. P9-CPS.05-01.0
  • 7. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL JETTIES A minimum of 100 mA of cathodic polarization between the structure surface and a stable reference electrode contacting the electrolyte. The formation or decay of polarization can be'measured to satisfy this criterion. 5.0 CATHODIC PROTECTION DESIGN CALCULATIONS 5.1 DINH CO LOCATION 5.1.1 Pipeline Total Surface Area The onshore portion of Long Hai to Ba Ria gas pipeline and Dinh Co to Ba Ria LPG pipelines has a total surface area as follows: Sa = (Pi) (d) (1) Sa (3.1416)-[(0.406,x 16500) + (3 x 0.168 x 7500)] Sa = 32921 (m2) Where: Sa = Surface area (m2 ) Pi = 3.1416 1 Length of pipeline (m) Diameter of pipeline (m) 5.1.2 CATHODIC PROTECTION CURRENT REQUIREMENT The cathodic protection system will have a DC output capacity as follows: (Sa) (Id) (Cb) It It It = ZSF 1000 (32921) (30) (0.05) X1.1 1000 54.32 (A) Say 55 amperes Where: Sa Total surface area (m2 ) Id = CP current density (mA/m2 ) Cb = Coating breakdown factor (%) SF = Safety factor (1.1) 5.1.3 CATHODIC PROTECTION ANODE REQUIREMENT Chosen output rating of 2 Ampere for each anode, the number of anodes: N = It/2 = 54.32/2 = 27.16 No. of anodes based on current requirement Page 7 of 14 m.1
  • 8. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL JETTIES N = 30 Another, maximum anode current output for each anodeto be determined as follows : LogL= 3.3 - LogId Where : L = design life in years Id = Maximum anode current density (A/m2 ) For L = 3 0 years The anode has a dimension of 31.75mm dia x I000mm legth with a.total area of 0.1m2 Therefore, Id =.66.5 A/m2 Maximum current output of anode = 0.1m2 x 66.5 A/m2 =6.65A Hence 3 0 anodes will give 6.65 x3 0 = 199.5 A Required 54.3 2 A noe wegt requ id re , W = W W = (0) (It)(y) Uf 0.1 (54.32) (30) 0.6 271.6 kg Anodes No. required based on weight requirement : N W/Wa 271.6 / 20 13.6 No. of anodes based on weight requirement, N = 14 Where Q Anode consumption rate (kg/amp-year) It = Cathodic Protection current ( A ) Y = Design life of the system ( years ) Uf = Anode Utilization factor ( 0.6 for a conservative design ) Wa = Weight of individual anode ( kg ) Hence anode No. chosen is 30 There are 20 canister anodes in existing groundbed at Dinh Co, so that 10 canister anodes which are the same existing anode specification will be required to add in this location. 5.1.4 GROUNDBED RESISTANCE Installation of 30 canister anodes on 5 metre spacing in 2750 ohm-cm soil results in an estimated groundbed resistance of 0.5844 ohm as follows: Rn = RI + R2 ( NACE - 1967, page 95 ) Where Rl Anode to backfill resistance R2 Backfill to soil resistance Pb BLcr - 1+ 2La R1 N.yLcrx6.28 [In do S In(0.656N)]) { NACE - 1967 ) .- I + (2)(100) R1' = 50 Fn (8)(100) ln(0.656)(30)] (30)(100)(6.28) 3175 500 Ri 0.0152 (ohm) Rev. D -
  • 9. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL JETTIES Where: Pb La = da = S = N Backfill resistivity (ohm-cm) Length of anode- excluding backfill (cm) Diameter of anode- excluding backfill (cm) Spacing of anodes (cm) Number of anodes.. Ps 8Lc -1 + 2Lc R2 R2 NxLcx6.28 2750 [In In(0.656N)J) (NACE - 196J ) do S (8) (150) (2) (150) -1 + in(0.656)(30)J (30)(150)(6.28) [in 76 500 R2 = 0.5692 (ohm) Where: Ps Soil resistivity (ohm-cm) Lc Length of anode- including backfill (cm) dc Diameter of anode- including backfill (cm) S. Spacing of anodes (cm) Number of anodes. Hence Rn = 0.0152 + 0.5692 0.5844 (ohm) 5.1.5 TRANSFORMER RECTIFIER DC OUTPUT VOLTAGE It is estimated that the transformer rectifier will require a 45 volt output to achieve :Lie desired 54.32 ampere DC current output as follows: It.(Rn+Rc) + Bemf E 54.32x(0.5844 + 0.2) + 2 E 44.6 volts Say 45 volts Where : E Rectifier DC output voltage (volts) It = Rectifier output current (amp) Rn = Total groundbed resistance (ohm) Rc Total cable resistance (0.2 ohm) Bemf = Dropped voltage between pipeline and ground (-2.0 volts) Note : Pipe to earth resistance (Rpe) has not been considered since the coating resistari :e is so high.( 1010 ohm-mz ) that all current will pass through 5% bare areas through r±e pipeline coating. Rev. D
  • 10. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL JETTIES 5.1.6 TRANSFORMER RECTIFIER AC INPUT Actual DC power output required : Pd = 44.6 x 55.32 2422.672 (W) DC power requirement including 20% overvoltage provision (20% spare Capacity ) = 1.2x44.6x54.32=2907.2 (W) Now, considering overall system P.F (power factor) = 0.8 and Transformer Rectifier Unit efficiency (E.F) = 0.85 (85% ) For 3 phases, 415V, 50Hz supply input to Transformer Rectifier Unit : Input current 2907.2 Ip Ip = Jx415x0.8x0.85 5.95 A Hence, AC power input ( including 20% spare capacity) is : 43 x 415 x 5.95 x 0.8 3420.23 Watt 5.1.7 CHANGE IN EARTH POTENTIAL DUE TO FORCED DRAINAGE When CP current is injected into ground through anode bed, the current flow results in a potential gradient in the earth. _... The change in earth potential near the pipelines (Ps)(It) V = 27r(r) (2750)(54.32) V Where : Ps It r 5.2 PHUOC HOA LOCATION 5.2.1 Pipeline Total Surface Area 27zx10000 2.38 Volts Soil resistivity ( ohm-cm ) Cathodic Protection current ( Ampere ) Distance between pipeline and anode bed (cm ) The onshore portion of Ba Ria to Phu My gas pipeline and Ba Ria to Thi Vai LPG pipelines has a total surface area as follows: Sa _ (Pi) (d) (1) Sa (3.1416) [(0.426 x 21.500)+ (3 x 0.168 x 17000)] Sa = 55691 (m2 ) P9-CPS.05-01.0 Page 10 of 14
  • 11. G.U.P PHASE I1- LIQUID PIPELINES, TERMINAL JETTIES Where: Sa Surface area (m2 ) Pi 3.1416 I Length of pipeline (m) Diameter of pipeline (m) 5.2.2 CATHODIC PROTECTION CURRENT REQUIREMENT The cathodic protection system will have a DC output capacity as follows: It = 91.89 A ( ) * * (55691 ) * 30 * 0.05 It = x Say 92 amperes Where: Sa Total surface area (m2 ) Id = CP current density (mA/m2 ) Cb = Coating breakdown factor (%) SF = Safety factor (1.1) 5.2.3 CATHODIC PROTECTION ANODE REQUIREMENT Chosen output rating of 2 Ampere for each anode, the number of anodes: N = It/2 92/2 = 45.95 No. of anodes based on current requirement N = 50 Another, maximum anode current output for each anodeto be determined as follows : LogL=3.3 -Log Id Where : L = design life in years Id = Maximum anode current density ( A/m2 ) For L = 30 years The anode has a dimension of 31.75mm dia x 1000mm legth with a total area of 0.1m2 Therefore, Id = 66.5 A/m2 Maximum current output of anode = 0.1 m2 x 66.5 A/m2 = 6.65A Hence 50 anodes will give 6.65 x 50 = 332.5 A Required 92 A (Q)(It)(Y) Anode weight required, W = W = Uf (0.1) (92) (30) 0.6 460 kg Page I 1-of 14- Rev. D xSF Sa Id Cb It 1000 = 1.1 1000
  • 12. G.U.P PHASE II - LIQUID PIPELINES, TERMINAL JETTIES Anodes No. required based on weight requirement : N = W / Wa 460 / 20 23 No. of anodes based on weight requirement, N = 23 Where Q = Anode consumption rate (kg/amp-year ) It = Cathodic Protection current (A ) Y = Design life of the system ( years ) Uf = Anode Utilization factor ( 0.6 for a conservative design Wa = Weight of individual anode ( kg ) Hence anode No. chosen is 30 There are 20 canister anodes in existing groundbed at Phuoc Hoa, so that 30 canister anodes which are the same existing anode specification will be required to add in this location. 5.2.4 OROUNDDED RESISTANCE Installation of 50 canister anodes on 5 metre spacing in 1500 ohm-cm soil results in an estimated groundbed resistance of 0.19 ohm as follows: Rn = R1 + R2 Where R1 = Anode to backfill resistance R2 Backfill to soil resistance R1= R1= La 2 *100 R1 = 0.0094 Ohm Pb 50 Where: Pb La 8 *100 La = da = S = N = Backfill resistivity (ohm-cm) Length of anode- excluding backfill (cm) Diameter of anode- excluding backfill (cm) Spacing of anodes (cm) Number of anodes. − + × × (ln 0.656 ) 2 1 8 6.28 N S da Ln N La − + × × (ln 0.656 * 50 ) 500 1 3.175 50 100 6.28 Ln
  • 13. R2= R2 = Lc 2 *150 8 *150 R2= 0.196 (ohm) Lc Pb 50 Where:. Ps = Soil resistivity (ohm-cm) Lc = Length of anode- including backfill (cm) dc Diameter of anode- including backfill (cm) S Spacing of anodes (cm) Number of anodes. Hence Rn 0.0094 + 0.196 0.2054 (ohm) 5.2.5 TRANSFORMER RECTIFIER DC OUTPUT VOLTAGE It is estimated that the transformer rectifier will require a 42 volt output to achieve the desired 92mpere DC current output as follows: It.(Rn+Rc) + Bemf E 92 x (0.2054 + 0.2) + 2 E 39.29 volts Say 42 volts Where.: E Rectifier DC output voltage (volts) it = Rectifier output current_ (amp) Rn _ Total groundbed resistance (ohm) Rc = Total cable resistance (0.2 ohm) Bemf = Dropped voltage between pipeline and ground (-2.0 volts) Note : Pipe to earth resistance (Rpe ) has not been considered since the coating resistance is so high ( 1010 ohm-nag ) that all current will pass through 5% bare areas through the pipeline coating. 5.2.6 TRANSFORMER RECTIFIER AC INPUT Actual DC power output required : Pdc = 39.29 x 92 3614.68 ( W) − + × × (ln 0.656 ) 2 1 8 6.28 N S dc Ln N Lc − + × × (ln 0.656 * 50 ) 500 1 3.175 50 150 6.28 Ln
  • 14. DC power requirement including 20% overvoltage provision (20% spare Capacity) = 1.2x39.29x92=4337.6 (W) Now, considering overall system P.F ( power factor) = 0.8 and Transformer Rectifier Unit efficiency (E.F) = 0.85 ( 85% ) For 3 phases, 415V, 50Hz supply input to Transformer Rectifier Unit : Input current IP= 4337 .6 3 x 415 x 0.8 x 0.85 Ip =8.875 A Hence, AC power input ( including 20% spare capacity) is : - _ 3x415 x8.875 x0.8 = 5013W
  • 15. : G.U.P PHASE II - LIQUID PIPELINES, TERMINAL JETTIES 5.2.7 CHANGE IN EARTH POTENTIAL DUE TO FORCED DRAINAGE When CP current is injected into ground through anode bed, the current flow results in a potential gradient in the earth. The change in earth potential near the pipelines (Ps)(It) 2 r(r) (1500)(92) V = Where : Ps = It = r = 2xl0000 = 2.2 Volts Soil resistivity ( ohm-cm ) Cathodic Protection current ( Ampere ) Distance between pipeline and anode bed ( cm ) Page 14 of 14