1. ContingencyPlanning
ProjectTitle:“Crush”shortfilm
Consider:1.Technical [camera, equipment, etc.],2. Organisational, 3. Logistical and 4. Personnel
Ideally4 or 5 for each
Pot. Problem Effecton Production Solution/Control PersonResponsible
Camera gets dropped The camera breaks Be careful Toni Gibson
Water getsinto the
camera if it rains
Camerabreaks Holdumbrellaover
camera
Toni Gibson
Unstable tripod Un evenfootage.
Cameracouldfall.
Make sure the tripodis
stable before putting
the camera on it.
Toni Gibson
Weather Rain,coulddamage
equipment
Schedule adifferent
day to film
Un predictable
SD card Loose footage Checkit before filming Toni Gibson
Battery Cameracouldgo dead “” Toni Gibson
Eye strain Coulddelaythe overall
outcome of the final
production
Have breaksin
betweenediting
Toni Gibson
Risk factors outside Slippingonthe mud
outside,slow
production
Be careful when
movingequipment
around
Everyone
Tripping hazards
outside
The ground isuneven Charactersshouldbe
careful whenrunning
around.
Everyone