SlideShare a Scribd company logo
1 of 4
Download to read offline
Decision criterion for anticipation of the infrastructure in staged projects
Tito Livio M. Cardoso
São Paulo, Brazil, 24-Oct-2018
Projects that will be deployed in multiple stages always go through an important discussion to define the scope of
implementation of the first stage: anticipate or not, the investment in infrastructure for the following stages?
In general, the option to anticipate results in a total CapEx, of the two stages, smaller, for example, deploying in the first
stage all the earthworks and civil works for pump station, water treatment, drainage and secondary substations, leaving
to the next stage only the equipment and distribution lines. The same case occurs in the anticipation of the civilian base
of transporters, or construction of the mill building that will house the mills of the 2 stages, for example. In this option
the infra will be integrated, that is, 100% shared between the production lines at the end of the 2nd stage.
The alternative of not anticipating anything produces a non-integrated infra-scope, where each deployment stage
includes a complete infrastructure, with a smaller size that corresponds only to the need associated with the productive
capacity of a stage. This approach, while not minimizing and CapEx below the two stages, should produce a smaller
CapEx for the 1st stage and present greater layout flexibility since the non-shared structures need not be adjacent.
This decision on the option to adopt is decisive for the engineering project and different managers stand in a
controversial way on the subject. In recent work, a manager has asserted himself on the integrated infrastructure
option: "If it is known to have expansion, it is absurd to make a 'cast' project that makes the company spend more if it
wants to expand." Another manager has already achieved a significant CapEx reduction by eliminating all anticipation of
infra for the 2nd stage and argues that this decision maximizes the NPV of the project. Who's right?
Answer: It depends...
It depends on:
 Additional investment in Stage 1 to advance in integrated infrastructure option
 "Saving", i.e. the total cost reduction (along of the all stages) on the integrated infrastructure option
 When will be the construction of stage 2
t = 0 t = 6 years
CapEx in infra
= US$ 200 M
CapEx in infra
= US$ 200 M
Stage 1
Cap. Total:
15 MTPY
Stage 2
Cap. Total:
30 MTPY
t = 40 years
A) Example, without infrastructure
anticipation.
t = 0 t = 6 years
CapEx in infra
= US$ 240 M
CapEx in infra
= US$ 120 M
Stage 1
Cap. Total:
15 MTPY
Stage 2
Cap. Total:
30 MTPY
t = 40 years
B) Example, with infrastructure
anticipation.
The company can always carry out another investment with the capital that would be immobilized in the integrated
infra-option. This alternative investment may monetize more than the larger CapEx total difference in the non-
integrated option if sufficient time is given. That is, for the same project, the integrated option can add or disaggregate
value depending on the time interval between the implementation of each stage. Like any decision-making process in
industrial projects, we need to calculate the present value of each option to identify the one that maximizes value to our
particular case.
Next we will deduce a general rule that supports the decision between anticipating or not the investment in an
integrated infrastructure for projects implemented in two stages. Let's assume that the total OpEx will be approximately
the same, with or without integrated infrastructure.
1) Option model without integration, i.e., identical and individual infrastructures for each stage:
The total investment without integration, ITSI, is the investment bro to implement the individual infra of each stage, ITSI
= 2 x ISI. That is, we invested ISI in year zero (today) and asaving ISI in year N. If the 2nd stage will be implemented in
year N, the Present Value of this investment will be:
1
1
(1 )
SI N
VPI ISI
i
 
    
Where i is the annual interest rate that discounts the capital invested in year N.
2) Model integrated option, i.e., common infrastructure in anticipation of Stage 1:
The total investment with integration, ITCI, presents the saving  in relation to the non-integrated option:
ITCI = (1-) ITSI = 2 (1-) ISI
In practice  is between 20% and 40%. Investments in the infra stage 1 and 2 will no longer be the same. Integration
investment, ICI, in stage 1 is greater. Be  (0.5 to 1.0) as the ratio of the total integration with infrastructure
investment, ITCI is disbursed in the 1st stage, ie as is "d anticipates the" capex below common to both stages. What
remains for the stage 2 is the residual investment (1-) of the total with integration:
ICI (t=0) = . ITCI = 2 (1-) ISI  Integrated infrastructure investment in stage 1
ICI (t=N) = (1-) ITCI = 2 (1-) (1-) ISI  Integrated infrastructure investment in stage 2
The Present Value of this investment, VPICI, will be:
 
 
ISI
i
VPI
i
ICI
ICIVPI
NCI
N
Nt
tCI










 

1
)1(
)1(2
1
)(
)0(


3) Decision criterion on anticipation in integrated infra:
Whenever the present value of the integrated option is greater than the present value of the option without
anticipation, anticipating the infra destroys project value (reduces NPV and IRR).
since ISI is common to both sides of the inequality, it disappears, leaving only the three variables we cited before
deducing the criterion for decision making: the anticipated capital in the integrated option (), the saving in CapEx total
in the integrated option () and the time interval between the two stages (N).
An important, and somewhat obscure, conclusion of this deduction is that the decision criterion is independent of the
size of the investment or plant capacity, and is applicable to mega-projects for billions or small projects.
Example:
As a quick example of applying this criterion, suppose a project for plant deployment in 2 stages of the same capacity.
CapEx design is US$ 800 million being US$ 160 million on the shared infrastructure to be deployed in the 1st stage,
leaving only US$ 8 million in the 2nd stage deployment. The option without anticipation would result in the
implementation of independent infrastructure at an estimated cost of US$ 13 million in each stage. So, the option of
anticipating the infrastructure presents savings of US$ 20 million in total CapEx. The anticipation without option reduces
US$ 30 million of CapEx for Stage 1 but increases by US$ 5 million in Stage 2.
Applying the criterion presented for = 0.077 and = 0.667, calculated by the reported values, and adopting an
opportunity cost i = 10% per year (typical), we find that N = 4 years is the interval between the implementation of 2
stages that equals the present values of the two options. Conclusion:
 If N < 4 years, the option to anticipate the infra common to both stages is the one that reduces the VPI,
therefore, maximizes the NPV and IRR.
   
valoragreganãoAntecipar
1
)1(
)1(2
1
1
1 
















NN
CISI
ii
VPIVPI

 Anticipate does not add value
 If N> 4 years, it is best left to expand the infra at the time of the implementation of stage 2, because the
profitability of the capital not immobilized in the anticipation of the infra surpasses the economy that would be
obtained with the anticipation of the infra.
i = 10%
ALPHA = 0.077
BETA = 0.667
N
Without
Integration With integration
1+1/(1+i)N 2(1-)[+(1-)/(1+i)N
]
1 1,91 1,79
2 1,83 1,74
3 1,75 1,69
4 1,68 1,65
5 1,62 1,61
6 1,56 1,58
7 1,51 1,55
8 1,47 1,52
9 1,42 1,49
10 1,39 1,47
It is important to note that the time to when the best decision is by anticipating the scope of the next stage is very
sensitive to the relationship between the volume of capital anticipated and the savings that will be obtained with it.

More Related Content

Similar to Decision criterion for anticipation of the infrastructure in staged projects

Nummary Tactical Keynote (NTK) Nguyen Khanh Duy (ENG)
Nummary Tactical Keynote (NTK) Nguyen Khanh Duy (ENG)Nummary Tactical Keynote (NTK) Nguyen Khanh Duy (ENG)
Nummary Tactical Keynote (NTK) Nguyen Khanh Duy (ENG)Duy Khanh Nguyen
 
social cost benefit.pdf
social cost benefit.pdfsocial cost benefit.pdf
social cost benefit.pdfLalitbalani1
 
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...Robert Muir
 
Value Incremental Comprehension (VIC) nomograph to evaluate socio-economic ef...
Value Incremental Comprehension (VIC) nomograph to evaluate socio-economic ef...Value Incremental Comprehension (VIC) nomograph to evaluate socio-economic ef...
Value Incremental Comprehension (VIC) nomograph to evaluate socio-economic ef...Duy Khanh Nguyen
 
Sub project management
Sub   project managementSub   project management
Sub project managementsmumbahelp
 
Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]Hariharan Ponnusamy
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIALNat Rice
 
Chapter15 multipleprojectsandconstraints
Chapter15 multipleprojectsandconstraintsChapter15 multipleprojectsandconstraints
Chapter15 multipleprojectsandconstraintsAKSHAYA0000
 
Chap 18 risk management & capital budgeting
Chap 18   risk management & capital budgetingChap 18   risk management & capital budgeting
Chap 18 risk management & capital budgetingArindam Khan
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...IRJET Journal
 
Assignment 2 Property Development Finance 17704.pdf
Assignment 2 Property Development Finance 17704.pdfAssignment 2 Property Development Finance 17704.pdf
Assignment 2 Property Development Finance 17704.pdfLiz Adams
 
Project appraisal and Analysis
Project appraisal and AnalysisProject appraisal and Analysis
Project appraisal and AnalysisSuhail Hussain
 
Infrastructure investments in Japan - Ryuichi Kataoka, Japan
Infrastructure investments in Japan - Ryuichi Kataoka, JapanInfrastructure investments in Japan - Ryuichi Kataoka, Japan
Infrastructure investments in Japan - Ryuichi Kataoka, JapanOECD Governance
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Offssuserfe1b72
 

Similar to Decision criterion for anticipation of the infrastructure in staged projects (20)

Nummary Tactical Keynote (NTK) Nguyen Khanh Duy (ENG)
Nummary Tactical Keynote (NTK) Nguyen Khanh Duy (ENG)Nummary Tactical Keynote (NTK) Nguyen Khanh Duy (ENG)
Nummary Tactical Keynote (NTK) Nguyen Khanh Duy (ENG)
 
social cost benefit.pdf
social cost benefit.pdfsocial cost benefit.pdf
social cost benefit.pdf
 
Fm chapter five
Fm chapter fiveFm chapter five
Fm chapter five
 
Pm assignment
Pm assignmentPm assignment
Pm assignment
 
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
Grey and Green Infrastructure Benefit Cost, Return on Investment Analysis for...
 
Value Incremental Comprehension (VIC) nomograph to evaluate socio-economic ef...
Value Incremental Comprehension (VIC) nomograph to evaluate socio-economic ef...Value Incremental Comprehension (VIC) nomograph to evaluate socio-economic ef...
Value Incremental Comprehension (VIC) nomograph to evaluate socio-economic ef...
 
Sub project management
Sub   project managementSub   project management
Sub project management
 
Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]Production & Operation Management Chapter6[1]
Production & Operation Management Chapter6[1]
 
Chapter6[1]
Chapter6[1]Chapter6[1]
Chapter6[1]
 
2008glhy12a22
2008glhy12a222008glhy12a22
2008glhy12a22
 
Project appraisal
Project appraisalProject appraisal
Project appraisal
 
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
 
Chapter15 multipleprojectsandconstraints
Chapter15 multipleprojectsandconstraintsChapter15 multipleprojectsandconstraints
Chapter15 multipleprojectsandconstraints
 
Chap 18 risk management & capital budgeting
Chap 18   risk management & capital budgetingChap 18   risk management & capital budgeting
Chap 18 risk management & capital budgeting
 
project cba
project cbaproject cba
project cba
 
Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...Application of Earned Value Method and Delay Analysis on Construction Project...
Application of Earned Value Method and Delay Analysis on Construction Project...
 
Assignment 2 Property Development Finance 17704.pdf
Assignment 2 Property Development Finance 17704.pdfAssignment 2 Property Development Finance 17704.pdf
Assignment 2 Property Development Finance 17704.pdf
 
Project appraisal and Analysis
Project appraisal and AnalysisProject appraisal and Analysis
Project appraisal and Analysis
 
Infrastructure investments in Japan - Ryuichi Kataoka, Japan
Infrastructure investments in Japan - Ryuichi Kataoka, JapanInfrastructure investments in Japan - Ryuichi Kataoka, Japan
Infrastructure investments in Japan - Ryuichi Kataoka, Japan
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Off
 

More from Tito Livio M. Cardoso

Tito Cardoso - Resumo - EN Junho-2023
Tito Cardoso - Resumo - EN Junho-2023Tito Cardoso - Resumo - EN Junho-2023
Tito Cardoso - Resumo - EN Junho-2023Tito Livio M. Cardoso
 
Tito Cardoso - Resumo - PT Junho-2023
Tito Cardoso - Resumo - PT Junho-2023Tito Cardoso - Resumo - PT Junho-2023
Tito Cardoso - Resumo - PT Junho-2023Tito Livio M. Cardoso
 
Probable Maximum Loss (PML) Evaluation
Probable Maximum Loss (PML) EvaluationProbable Maximum Loss (PML) Evaluation
Probable Maximum Loss (PML) EvaluationTito Livio M. Cardoso
 
Estimativa Parametrica de Custo de Transportador de Correia
Estimativa Parametrica de Custo de Transportador de CorreiaEstimativa Parametrica de Custo de Transportador de Correia
Estimativa Parametrica de Custo de Transportador de CorreiaTito Livio M. Cardoso
 
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...Tito Livio M. Cardoso
 
Certificado DIO Especialaista Inovação Digital AD0B801B.pdf
Certificado DIO Especialaista Inovação Digital AD0B801B.pdfCertificado DIO Especialaista Inovação Digital AD0B801B.pdf
Certificado DIO Especialaista Inovação Digital AD0B801B.pdfTito Livio M. Cardoso
 
Certificado DIO Front-End Angular 1E8E60C7.pdf
Certificado DIO Front-End Angular 1E8E60C7.pdfCertificado DIO Front-End Angular 1E8E60C7.pdf
Certificado DIO Front-End Angular 1E8E60C7.pdfTito Livio M. Cardoso
 
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdfCertificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdfTito Livio M. Cardoso
 
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...Tito Livio M. Cardoso
 
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...Tito Livio M. Cardoso
 
Desenvolvimento de projetos em baixa das commodities
Desenvolvimento de projetos em baixa das commoditiesDesenvolvimento de projetos em baixa das commodities
Desenvolvimento de projetos em baixa das commoditiesTito Livio M. Cardoso
 
Riscos relacionadas a extensao de cronogramas - Schedule extension related risks
Riscos relacionadas a extensao de cronogramas - Schedule extension related risksRiscos relacionadas a extensao de cronogramas - Schedule extension related risks
Riscos relacionadas a extensao de cronogramas - Schedule extension related risksTito Livio M. Cardoso
 
Otimização da configuração do banco de baterias para navio híbrido
Otimização da configuração do banco de baterias para navio híbridoOtimização da configuração do banco de baterias para navio híbrido
Otimização da configuração do banco de baterias para navio híbridoTito Livio M. Cardoso
 
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018Tito Livio M. Cardoso
 
Estratégia de Autofinanciamento de Projetos
Estratégia de Autofinanciamento de ProjetosEstratégia de Autofinanciamento de Projetos
Estratégia de Autofinanciamento de ProjetosTito Livio M. Cardoso
 
Critério de decisão para implantação da infraestrutura em projetos implantado...
Critério de decisão para implantação da infraestrutura em projetos implantado...Critério de decisão para implantação da infraestrutura em projetos implantado...
Critério de decisão para implantação da infraestrutura em projetos implantado...Tito Livio M. Cardoso
 
Analise de riscos da aplicação de novas tecnologias
Analise de riscos da aplicação de novas tecnologiasAnalise de riscos da aplicação de novas tecnologias
Analise de riscos da aplicação de novas tecnologiasTito Livio M. Cardoso
 
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...Tito Livio M. Cardoso
 

More from Tito Livio M. Cardoso (20)

Tito Cardoso - Resumo - EN Junho-2023
Tito Cardoso - Resumo - EN Junho-2023Tito Cardoso - Resumo - EN Junho-2023
Tito Cardoso - Resumo - EN Junho-2023
 
Tito Cardoso - Resumo - PT Junho-2023
Tito Cardoso - Resumo - PT Junho-2023Tito Cardoso - Resumo - PT Junho-2023
Tito Cardoso - Resumo - PT Junho-2023
 
Probable Maximum Loss (PML) Evaluation
Probable Maximum Loss (PML) EvaluationProbable Maximum Loss (PML) Evaluation
Probable Maximum Loss (PML) Evaluation
 
Estimativa Parametrica de Custo de Transportador de Correia
Estimativa Parametrica de Custo de Transportador de CorreiaEstimativa Parametrica de Custo de Transportador de Correia
Estimativa Parametrica de Custo de Transportador de Correia
 
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
Use of the Bowtie Tool to Develop Regulatory Standards Focusing on Process Sa...
 
Analise de riscos das alternativas
Analise de riscos das alternativasAnalise de riscos das alternativas
Analise de riscos das alternativas
 
Certificado DIO Especialaista Inovação Digital AD0B801B.pdf
Certificado DIO Especialaista Inovação Digital AD0B801B.pdfCertificado DIO Especialaista Inovação Digital AD0B801B.pdf
Certificado DIO Especialaista Inovação Digital AD0B801B.pdf
 
Certificado DIO Front-End Angular 1E8E60C7.pdf
Certificado DIO Front-End Angular 1E8E60C7.pdfCertificado DIO Front-End Angular 1E8E60C7.pdf
Certificado DIO Front-End Angular 1E8E60C7.pdf
 
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdfCertificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
Certificado DIO Fullstack developer - Banco carrefour 7B553D75.pdf
 
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
Dinâmica das contratações governamentais: Propostas para eficiência e satisfa...
 
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
DYNAMICS OF GOVERNMENT CONTRACTING: PROPOSALS FOR EFFICIENCY AND SATISFACTION...
 
Desenvolvimento de projetos em baixa das commodities
Desenvolvimento de projetos em baixa das commoditiesDesenvolvimento de projetos em baixa das commodities
Desenvolvimento de projetos em baixa das commodities
 
Riscos relacionadas a extensao de cronogramas - Schedule extension related risks
Riscos relacionadas a extensao de cronogramas - Schedule extension related risksRiscos relacionadas a extensao de cronogramas - Schedule extension related risks
Riscos relacionadas a extensao de cronogramas - Schedule extension related risks
 
Leasing de equipamentos industriais
Leasing de equipamentos industriaisLeasing de equipamentos industriais
Leasing de equipamentos industriais
 
Otimização da configuração do banco de baterias para navio híbrido
Otimização da configuração do banco de baterias para navio híbridoOtimização da configuração do banco de baterias para navio híbrido
Otimização da configuração do banco de baterias para navio híbrido
 
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
Utilizing a Self-Financing Strategy for Projects - BRG Review 7-1-2018
 
Estratégia de Autofinanciamento de Projetos
Estratégia de Autofinanciamento de ProjetosEstratégia de Autofinanciamento de Projetos
Estratégia de Autofinanciamento de Projetos
 
Critério de decisão para implantação da infraestrutura em projetos implantado...
Critério de decisão para implantação da infraestrutura em projetos implantado...Critério de decisão para implantação da infraestrutura em projetos implantado...
Critério de decisão para implantação da infraestrutura em projetos implantado...
 
Analise de riscos da aplicação de novas tecnologias
Analise de riscos da aplicação de novas tecnologiasAnalise de riscos da aplicação de novas tecnologias
Analise de riscos da aplicação de novas tecnologias
 
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
Efeitos da incerteza na produtividade de serviços sobre o custo e prazo do pr...
 

Recently uploaded

Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...
Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...
Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...priyasharma62062
 
7 tips trading Deriv Accumulator Options
7 tips trading Deriv Accumulator Options7 tips trading Deriv Accumulator Options
7 tips trading Deriv Accumulator OptionsVince Stanzione
 
VIP Kalyan Call Girls 🌐 9920725232 🌐 Make Your Dreams Come True With Mumbai E...
VIP Kalyan Call Girls 🌐 9920725232 🌐 Make Your Dreams Come True With Mumbai E...VIP Kalyan Call Girls 🌐 9920725232 🌐 Make Your Dreams Come True With Mumbai E...
VIP Kalyan Call Girls 🌐 9920725232 🌐 Make Your Dreams Come True With Mumbai E...roshnidevijkn ( Why You Choose Us? ) Escorts
 
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...priyasharma62062
 
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Call Girls Rajgurunagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Rajgurunagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Rajgurunagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Rajgurunagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...Call Girls in Nagpur High Profile
 
call girls in Sant Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
call girls in Sant Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️call girls in Sant Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
call girls in Sant Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Best VIP Call Girls Morni Hills Just Click Me 6367492432
Best VIP Call Girls Morni Hills Just Click Me 6367492432Best VIP Call Girls Morni Hills Just Click Me 6367492432
Best VIP Call Girls Morni Hills Just Click Me 6367492432motiram463
 
Webinar on E-Invoicing for Fintech Belgium
Webinar on E-Invoicing for Fintech BelgiumWebinar on E-Invoicing for Fintech Belgium
Webinar on E-Invoicing for Fintech BelgiumFinTech Belgium
 
Call Girls in New Friends Colony Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escort...
Call Girls in New Friends Colony Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escort...Call Girls in New Friends Colony Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escort...
Call Girls in New Friends Colony Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escort...Delhi Call girls
 
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...amitlee9823
 
Navi Mumbai Cooperetive Housewife Call Girls-9833754194-Natural Panvel Enjoye...
Navi Mumbai Cooperetive Housewife Call Girls-9833754194-Natural Panvel Enjoye...Navi Mumbai Cooperetive Housewife Call Girls-9833754194-Natural Panvel Enjoye...
Navi Mumbai Cooperetive Housewife Call Girls-9833754194-Natural Panvel Enjoye...priyasharma62062
 
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...Call Girls in Nagpur High Profile
 
Top Rated Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...
Top Rated  Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...Top Rated  Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...
Top Rated Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...Call Girls in Nagpur High Profile
 
Vasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbai
Vasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbaiVasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbai
Vasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbaipriyasharma62062
 
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...dipikadinghjn ( Why You Choose Us? ) Escorts
 

Recently uploaded (20)

Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...
Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...
Diva-Thane European Call Girls Number-9833754194-Diva Busty Professional Call...
 
7 tips trading Deriv Accumulator Options
7 tips trading Deriv Accumulator Options7 tips trading Deriv Accumulator Options
7 tips trading Deriv Accumulator Options
 
VIP Kalyan Call Girls 🌐 9920725232 🌐 Make Your Dreams Come True With Mumbai E...
VIP Kalyan Call Girls 🌐 9920725232 🌐 Make Your Dreams Come True With Mumbai E...VIP Kalyan Call Girls 🌐 9920725232 🌐 Make Your Dreams Come True With Mumbai E...
VIP Kalyan Call Girls 🌐 9920725232 🌐 Make Your Dreams Come True With Mumbai E...
 
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
 
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Koregaon Park Call Me 7737669865 Budget Friendly No Advance Booking
 
(Vedika) Low Rate Call Girls in Pune Call Now 8250077686 Pune Escorts 24x7
(Vedika) Low Rate Call Girls in Pune Call Now 8250077686 Pune Escorts 24x7(Vedika) Low Rate Call Girls in Pune Call Now 8250077686 Pune Escorts 24x7
(Vedika) Low Rate Call Girls in Pune Call Now 8250077686 Pune Escorts 24x7
 
Call Girls Rajgurunagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Rajgurunagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Rajgurunagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Rajgurunagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Shivane  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Shivane 6297143586 Call Hot Indian Gi...
 
call girls in Sant Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
call girls in Sant Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️call girls in Sant Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
call girls in Sant Nagar (DELHI) 🔝 >༒9953056974 🔝 genuine Escort Service 🔝✔️✔️
 
Best VIP Call Girls Morni Hills Just Click Me 6367492432
Best VIP Call Girls Morni Hills Just Click Me 6367492432Best VIP Call Girls Morni Hills Just Click Me 6367492432
Best VIP Call Girls Morni Hills Just Click Me 6367492432
 
From Luxury Escort Service Kamathipura : 9352852248 Make on-demand Arrangemen...
From Luxury Escort Service Kamathipura : 9352852248 Make on-demand Arrangemen...From Luxury Escort Service Kamathipura : 9352852248 Make on-demand Arrangemen...
From Luxury Escort Service Kamathipura : 9352852248 Make on-demand Arrangemen...
 
Webinar on E-Invoicing for Fintech Belgium
Webinar on E-Invoicing for Fintech BelgiumWebinar on E-Invoicing for Fintech Belgium
Webinar on E-Invoicing for Fintech Belgium
 
Call Girls in New Friends Colony Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escort...
Call Girls in New Friends Colony Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escort...Call Girls in New Friends Colony Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escort...
Call Girls in New Friends Colony Delhi 💯 Call Us 🔝9205541914 🔝( Delhi) Escort...
 
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
 
Navi Mumbai Cooperetive Housewife Call Girls-9833754194-Natural Panvel Enjoye...
Navi Mumbai Cooperetive Housewife Call Girls-9833754194-Natural Panvel Enjoye...Navi Mumbai Cooperetive Housewife Call Girls-9833754194-Natural Panvel Enjoye...
Navi Mumbai Cooperetive Housewife Call Girls-9833754194-Natural Panvel Enjoye...
 
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
 
Top Rated Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...
Top Rated  Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...Top Rated  Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...
Top Rated Pune Call Girls Viman Nagar ⟟ 6297143586 ⟟ Call Me For Genuine Sex...
 
Vasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbai
Vasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbaiVasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbai
Vasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbai
 
Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7
Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7
Call Girls in New Ashok Nagar, (delhi) call me [9953056974] escort service 24X7
 
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
 

Decision criterion for anticipation of the infrastructure in staged projects

  • 1. Decision criterion for anticipation of the infrastructure in staged projects Tito Livio M. Cardoso São Paulo, Brazil, 24-Oct-2018 Projects that will be deployed in multiple stages always go through an important discussion to define the scope of implementation of the first stage: anticipate or not, the investment in infrastructure for the following stages? In general, the option to anticipate results in a total CapEx, of the two stages, smaller, for example, deploying in the first stage all the earthworks and civil works for pump station, water treatment, drainage and secondary substations, leaving to the next stage only the equipment and distribution lines. The same case occurs in the anticipation of the civilian base of transporters, or construction of the mill building that will house the mills of the 2 stages, for example. In this option the infra will be integrated, that is, 100% shared between the production lines at the end of the 2nd stage. The alternative of not anticipating anything produces a non-integrated infra-scope, where each deployment stage includes a complete infrastructure, with a smaller size that corresponds only to the need associated with the productive capacity of a stage. This approach, while not minimizing and CapEx below the two stages, should produce a smaller CapEx for the 1st stage and present greater layout flexibility since the non-shared structures need not be adjacent. This decision on the option to adopt is decisive for the engineering project and different managers stand in a controversial way on the subject. In recent work, a manager has asserted himself on the integrated infrastructure option: "If it is known to have expansion, it is absurd to make a 'cast' project that makes the company spend more if it wants to expand." Another manager has already achieved a significant CapEx reduction by eliminating all anticipation of infra for the 2nd stage and argues that this decision maximizes the NPV of the project. Who's right? Answer: It depends... It depends on:  Additional investment in Stage 1 to advance in integrated infrastructure option  "Saving", i.e. the total cost reduction (along of the all stages) on the integrated infrastructure option  When will be the construction of stage 2 t = 0 t = 6 years CapEx in infra = US$ 200 M CapEx in infra = US$ 200 M Stage 1 Cap. Total: 15 MTPY Stage 2 Cap. Total: 30 MTPY t = 40 years A) Example, without infrastructure anticipation. t = 0 t = 6 years CapEx in infra = US$ 240 M CapEx in infra = US$ 120 M Stage 1 Cap. Total: 15 MTPY Stage 2 Cap. Total: 30 MTPY t = 40 years B) Example, with infrastructure anticipation.
  • 2. The company can always carry out another investment with the capital that would be immobilized in the integrated infra-option. This alternative investment may monetize more than the larger CapEx total difference in the non- integrated option if sufficient time is given. That is, for the same project, the integrated option can add or disaggregate value depending on the time interval between the implementation of each stage. Like any decision-making process in industrial projects, we need to calculate the present value of each option to identify the one that maximizes value to our particular case. Next we will deduce a general rule that supports the decision between anticipating or not the investment in an integrated infrastructure for projects implemented in two stages. Let's assume that the total OpEx will be approximately the same, with or without integrated infrastructure. 1) Option model without integration, i.e., identical and individual infrastructures for each stage: The total investment without integration, ITSI, is the investment bro to implement the individual infra of each stage, ITSI = 2 x ISI. That is, we invested ISI in year zero (today) and asaving ISI in year N. If the 2nd stage will be implemented in year N, the Present Value of this investment will be: 1 1 (1 ) SI N VPI ISI i        Where i is the annual interest rate that discounts the capital invested in year N. 2) Model integrated option, i.e., common infrastructure in anticipation of Stage 1: The total investment with integration, ITCI, presents the saving  in relation to the non-integrated option: ITCI = (1-) ITSI = 2 (1-) ISI In practice  is between 20% and 40%. Investments in the infra stage 1 and 2 will no longer be the same. Integration investment, ICI, in stage 1 is greater. Be  (0.5 to 1.0) as the ratio of the total integration with infrastructure investment, ITCI is disbursed in the 1st stage, ie as is "d anticipates the" capex below common to both stages. What remains for the stage 2 is the residual investment (1-) of the total with integration: ICI (t=0) = . ITCI = 2 (1-) ISI  Integrated infrastructure investment in stage 1 ICI (t=N) = (1-) ITCI = 2 (1-) (1-) ISI  Integrated infrastructure investment in stage 2 The Present Value of this investment, VPICI, will be:
  • 3.     ISI i VPI i ICI ICIVPI NCI N Nt tCI              1 )1( )1(2 1 )( )0(   3) Decision criterion on anticipation in integrated infra: Whenever the present value of the integrated option is greater than the present value of the option without anticipation, anticipating the infra destroys project value (reduces NPV and IRR). since ISI is common to both sides of the inequality, it disappears, leaving only the three variables we cited before deducing the criterion for decision making: the anticipated capital in the integrated option (), the saving in CapEx total in the integrated option () and the time interval between the two stages (N). An important, and somewhat obscure, conclusion of this deduction is that the decision criterion is independent of the size of the investment or plant capacity, and is applicable to mega-projects for billions or small projects. Example: As a quick example of applying this criterion, suppose a project for plant deployment in 2 stages of the same capacity. CapEx design is US$ 800 million being US$ 160 million on the shared infrastructure to be deployed in the 1st stage, leaving only US$ 8 million in the 2nd stage deployment. The option without anticipation would result in the implementation of independent infrastructure at an estimated cost of US$ 13 million in each stage. So, the option of anticipating the infrastructure presents savings of US$ 20 million in total CapEx. The anticipation without option reduces US$ 30 million of CapEx for Stage 1 but increases by US$ 5 million in Stage 2. Applying the criterion presented for = 0.077 and = 0.667, calculated by the reported values, and adopting an opportunity cost i = 10% per year (typical), we find that N = 4 years is the interval between the implementation of 2 stages that equals the present values of the two options. Conclusion:  If N < 4 years, the option to anticipate the infra common to both stages is the one that reduces the VPI, therefore, maximizes the NPV and IRR.     valoragreganãoAntecipar 1 )1( )1(2 1 1 1                  NN CISI ii VPIVPI   Anticipate does not add value
  • 4.  If N> 4 years, it is best left to expand the infra at the time of the implementation of stage 2, because the profitability of the capital not immobilized in the anticipation of the infra surpasses the economy that would be obtained with the anticipation of the infra. i = 10% ALPHA = 0.077 BETA = 0.667 N Without Integration With integration 1+1/(1+i)N 2(1-)[+(1-)/(1+i)N ] 1 1,91 1,79 2 1,83 1,74 3 1,75 1,69 4 1,68 1,65 5 1,62 1,61 6 1,56 1,58 7 1,51 1,55 8 1,47 1,52 9 1,42 1,49 10 1,39 1,47 It is important to note that the time to when the best decision is by anticipating the scope of the next stage is very sensitive to the relationship between the volume of capital anticipated and the savings that will be obtained with it.