2. Khi Solar One – East cavity boiler
Heavy lifting and installation of West cavity Lifting team
Aligning the structure for installation Installing bolts into flanges to secure the structure
3. Storage vessels for heated salt solution
Core drilling through 900mm of concrete for
installation of lateral flanges
Core Drilling for installation of elevated
walkway
Core drilling in gondola Core drilling on rope
4. Khi Solar One – Mirror field
Aiding on beam clamps 150 metres above
ground to perform Quality control on the
bolting on the flanges and to check the
torque values on the bolts
Installation of
lock nuts to M60
threaded bar and
tightening with
torque multiplier
5. Commissioning of East cavity