A report released on the Wildcreek Golf Course showed it would be a suitable location for the Washoe County School District to build a high school.
The report from Wood Rodgers, a surveying and engineering firm, showed seven different configurations of how a 75-acre high school campus could fit onto the Wildcreek property.
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Sample Designs of Wildcreek High School
1. Tennis Courts
Fields
Potential School
Site
Wild Creek Feasibility Study - 1
November 9th, 2017
Fields
Fields
Below is a list of opportunities and issues associated with Scenario 1
Opportunities:
• E-W 104 Overhead power lines remain
• Option for partial Regulation Golf Course to remain
• Minimal grading for potential school site and fields
Issues:
• Orr Ditch modification in SW corner of site
• Potential school site adjacent to McCarran Blvd. - noise/traffic concern
• Potential school site near residential neighborhoods - noise/traffic concern
• Traffic modification needed at Wedekind Rd.
• Existing Clubhouse and Executive Golf Course removed
• SE fields located in wetlands (require addn. approval)
0 400’ 800’
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
2. Fields
Fields
Fields
Potential School
Site
Tennis Courts
0 400’ 800’
Wild Creek Feasibility Study - 2
November 9th, 2017
Below is a list of opportunities and issues associated with Scenario 2
Opportunities:
• Option for Executive Golf Course to remain
• Option for partial Regulation Golf Course to remain
• E-W 104 Overhead power lines remain
• Minimal grading for potential school site and fields
Issues:
• Orr Ditch modification along West side of site
• Potential school site placed in Emergency Water Release Drainage Area
• Existing Clubhouse removed
• Proposed school site near residential neighborhood - noise/traffic concern
• SE fields located in wetlands (require addn. approval)
Executive Golf Course
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
3. Fields
Fields
Fields
Fields
Potential School
Site
Tennis Courts
Existing Clubhouse and
Executive Golf Course
0 400’ 800’
Wild Creek Feasibility Study - 3
November 9th, 2017
Below is a list of issues and opportunities associated with Scenario 3
Opportunities:
• Option for Executive Golf Course and Clubhouse to remain
• Proposed school site away from McCarran Blvd
• Proposed school site out of Emergency Water Release Drainage Area
• Proposed school site away from residential neighborhoods
• Option for no Orr Ditch modification
Issues:
• Fields located in Emergency Water Release Drainage Area
• E-W 104 Power Line modification
• Some fields away from potential school site
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
4. Fields
Fields
Fields
Potential School
Site
Tennis Courts
Existing Clubhouse and
Executive Golf Course
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
0 400’ 800’
Wild Creek Feasibility Study - 4A
November 9th, 2017
Below is a list of opportunities and issues associated with Scenario 4A
Opportunities:
• Option for Executive Golf Course and Clubhouse to remain
• Proposed school site away from McCarran Blvd
• Proposed school site out of Emergency Water Release Drainage Area
• Option for no E-W 104 Power line modification
• Proximity of fields to potential school site
• Potential school site away from residential neighborhoods
Issues:
• Fields located in Emergency Water Release Drainage Area
• Orr Ditch modification along East side of site
5. 0 400’ 800’
Fields
FieldsFields
Potential School
Site
Tennis Courts
Existing Clubhouse and
Executive Golf Course
Wild Creek Feasibility Study - 4B
November 9th, 2017
Below is a list of opportunities and issues associated with Scenario 4B
Opportunities:
• Option for Executive Golf Course and Clubhouse to remain
• Proposed school site away from McCarran Blvd
• Proposed school site out of Emergency Water Release Drainage Area
• Option for no E-W 104 Power line modification
• Proximity of fields to potential school site
• Potential school site away from residential neighborhoods
Issues:
• Fields located in Emergency Water Release Drainage Area
• Orr Ditch modification along East side of site
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
6. Fields
Fields
Potential School
Site
Fields
Fields
Tennis
Courts
Existing Clubhouse and
Executive Golf Course
0 400’ 800’
Wild Creek Feasibility Study - 5
November 9th, 2017
Below is a list of opportunities and issues associated with Scenario 5
Opportunities:
• Option for Executive Golf Course and Clubhouse to remain
• Potential school site away from McCarran Blvd
• Minimal grading for potential school site
Issues:
• Potential school site/fields located in Emergency Water Release Drainage Area
• E-W 104 Power Line modification (fields)
• Orr Ditch modification along East side of site
• Potential school site near residential neighborhood
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area
7. Fields
Fields
Potential School
Site
Fields
Tennis Courts
Existing Clubhouse and
Executive Golf Course
0 400’ 800’
Wild Creek Feasibility Study - 6
November 9th, 2017
Below is a list of opportunities and issues associated with Scenario 6
Opportunities:
• Option for Executive Golf Course and Clubhouse to remain
• Potential school site away from McCarran Blvd
• Potential school site out of Emergency Water Release Drainage Area
• Potential school site away from residential neighborhoods
• Option for no Orr Ditch modification
• Option for no E-W 104 Power Line modification
Issues:
• Fields located in Emergency Water Release Drainage Area
Orr Ditch
E-W 104 Power Line
Road
Parking
Emergency Water Release
Drainage Area